You are on page 1of 2

(Formerly R.D.

Suyat Masonry
and Carpentry Works)
To Engr. Earl Timothy Suarez
Vertical Engineering
MGS Construction, Inc.

QOUTATION PROPOSAL FOR:


Project Name : Vista Brent Hill (Painting Works)
Address : Yangco Rd, Upper General Luna, Baguio City
General Scope of Works : Interior Painting Works (21,500sqm)

Proposed Amount Php 340.00 per Sqm


Total Cost Php 7,310,000.00
Coverage Labor and Materials
Duration 150 Working days
Warranty 6 Months (Starts upon Completion of Painting Works)

QOUTATION BREAKDOWN
Lump Sum
Categories (PHP)
Direct Cost
Material Cost (MC) 4,623,655.92
Masonry/Dry Walls
 Flat Latex Paint by Boysen
 Semi-Gloss Latex Paint by Boysen
 Top Coat Latex Paint by Boysen
 Gasa Tape
 Walltek Skim Coat
 Penetrating Sealer
 Sand Paper #100
 Sand Paper #120
 Paint Brush (Assorted #1,2,3,4)
 Roller #4 with Pan
 Roller #7 with Pan
 Roller #9 with Pan
 Boral Joint Compound
6,241,935.49
Ceiling
 Flat Latex Paint by Boysen
 Top Coat Latex Paint by Boysen
 Gasa Tape by Boysen
 Walltek Skim Coat
 Sand Paper #100
 Sand Paper #120
 Paint Brush (Assorted #1,2,3,4)
 Roller #4 with Pan
 Roller #7 with Pan
 Roller #9 with Pan
 Boral Joint Compound
Labor Cost (35% of MC)
 Site Supervisor 1,618,279.57
 Painters
Indirect Cost
Overhead Miscellaneous
873,870.97
Contingency Cost
COVID Testing Requirements
Contractor’s Profit (10% of DC)
Tax (12% of LC) 194,193.54
TOTAL 7,310,000.00

SCOPE OF WORKS:
Walls
1. Preparation of Wall Surfaces
a. Cleaning of Surfaces
b. Filling-in gaps
c. Sanding
2. Application of Penetrating Sealer to Walls
3. Application of Primer
4. Sanding
5. Top Coating (2x)

Ceiling
1. Preparation of Ceiling Surfaces
a. Cleaning of Surfaces
b. Filling-in gaps
c. Sanding
2. Application of Primer
3. Sanding
4. Top Coating (2x)