Suyat Masonry
and Carpentry Works)
To Engr. Earl Timothy Suarez
Vertical Engineering
MGS Construction, Inc.
QOUTATION BREAKDOWN
Lump Sum
Categories (PHP)
Direct Cost
Material Cost (MC) 4,623,655.92
Masonry/Dry Walls
Flat Latex Paint by Boysen
Semi-Gloss Latex Paint by Boysen
Top Coat Latex Paint by Boysen
Gasa Tape
Walltek Skim Coat
Penetrating Sealer
Sand Paper #100
Sand Paper #120
Paint Brush (Assorted #1,2,3,4)
Roller #4 with Pan
Roller #7 with Pan
Roller #9 with Pan
Boral Joint Compound
6,241,935.49
Ceiling
Flat Latex Paint by Boysen
Top Coat Latex Paint by Boysen
Gasa Tape by Boysen
Walltek Skim Coat
Sand Paper #100
Sand Paper #120
Paint Brush (Assorted #1,2,3,4)
Roller #4 with Pan
Roller #7 with Pan
Roller #9 with Pan
Boral Joint Compound
Labor Cost (35% of MC)
Site Supervisor 1,618,279.57
Painters
Indirect Cost
Overhead Miscellaneous
873,870.97
Contingency Cost
COVID Testing Requirements
Contractor’s Profit (10% of DC)
Tax (12% of LC) 194,193.54
TOTAL 7,310,000.00
SCOPE OF WORKS:
Walls
1. Preparation of Wall Surfaces
a. Cleaning of Surfaces
b. Filling-in gaps
c. Sanding
2. Application of Penetrating Sealer to Walls
3. Application of Primer
4. Sanding
5. Top Coating (2x)
Ceiling
1. Preparation of Ceiling Surfaces
a. Cleaning of Surfaces
b. Filling-in gaps
c. Sanding
2. Application of Primer
3. Sanding
4. Top Coating (2x)