Definition Fix % Earthing

25%
Earth Grid, Earth Cable/Tape, External Ducting, 50%
Cable Containment; 1st Fix
Piping, Concealed Conduit/Trunking 75%
100%
25%
Manholes/Pit, Wiring Work, Earth Bars; 50%
Water Tanks/Pumps, Exposed Trunking, Gas 2nd Fix
Cylinders 75%
100%
25%
Final Fittings, LV Boards, Feeder Pillar, Complete
Grounding; 50%
Pipe Fittings, Floor Traps, AC units, Control 3rd Fix
75%
Panels, Fire Extinguisher, Sensors
100%
25%
50%
O&M, Pre-T&C, Final T&C, T&C Report T&C
75%
100%
Lightning Electrical ACMV Fire
Cold Water Sanitary