Water Proofing

Details
Category: Carpentry

Task / Description Slow Ave Fast  Units


 Asphalt coatings, horizontal surfaces 3.5 4.2 5.8  m2/hr
 Asphalt coatings, vertical surfaces 1.2 1.7 2.2  m2/hr
 Bituminous Brushed application, 2 coats 4.8 5.0 6.3  m2/hr
 Bituminous Brushed application, 3 coats 3.3 3.5 4.4  m2/hr
 Bituminous Sheets, horizontal surfaces 3.8 4.0 4.8  m2/hr
 Bituminous Sheets, vertical surfaces 3.3 3.5 4.2  m2/hr
 Polythene Sheets, horizontal surfaces - 20.0 -  m2/hr
 Bentonite Sheets, horizontal surfaces 18.7 25.0 31.3  m2/hr
 Bentonite Sheets, vertical surfaces 11.2 15.0 17.3  m2/hr
 Epoxy Based application, 1 coat - 75.0 -  m2/hr
 Epoxy Based application, 2 coat - 38.0 -  m2/hr