Sanvira On dated 1/4/2020

1 Metric ton=27m2
Sanvira Project status for painting

Volume Dry Film Theoretical Practical Painted Surface Volume Area Covered Consumption Actual
Product & Shade Thickness in Spreading Loss Factor Spreading Paint used
Solids % microns (µm) Rate m²/L Rate m²/L tonnage Area estimated per litre diifference consumption

HEMPADUR MASTIC 45880 80 100 8.0 50% 4.0 244.0 6588 m² 1647L 1800L 3.66 0.34 54.25

HEMPTHANE 55610 67 50 13.4 50% 6.7 244.0 6588 m² 824L 740L 8.90 -2.20 33.56

Total Dry Film Thickness 150 Total Value 6588 m²

Seby Joseph 99852923 Page 1 of 3 Hempel Oman/ JOSE/18530449/RUSTAQ


Hempel (Oman) L.L.C.,
Sanvira On dated 5/6/2020
1 Metric ton=27m2
Sanvira Project status for painting

Volume Dry Film Theoretical Practical Painted Surface Volume Area Covered Consumption Actual
Product & Shade Thickness in Spreading Loss Factor Spreading Paint used Unit Rate
Solids % microns (µm) Rate m²/L Rate m²/L tonnage Area estimated per litre diifference consumption

HEMPADUR MASTIC 45880 80 100 8.0 50% 4.0 289.4 7813 m² 1953L 1604L 4.87 -0.87 39.12 1.000

HEMPTHANE HS 55610 67 50 13.4 50% 6.7 289.4 7813 m² 1166L 880L 8.88 -2.18 33.75 37.500

Thineer 8080 N/A N/A N/A 20% N/A 289.4 7813 m² 391L 254L 0.600

Thineer 8050 N/A N/A N/A 20% N/A 289.4 7813 m² 233L 600L 0.600

Total Dry Film Thickness 150 Total Value 7813 m²

Seby Joseph 99852923 Page 2 of 3 Hempel Oman/ JOSE/18530449/RUSTAQ


Hempel (Oman) L.L.C.,
COST COST AS Actual
OMR ACTUAL Saving

1953.180 1604.000 349.180

43727.910 33000.000 10727.910


5.80%discount=38 Actual

234.382 152.400 81.982

139.929 360.000 -220.071

Total 10939.001