painting work Date:-26.03.

2019
S.N. Description No. Unit Qty. Total Qty. Unit Rate
Constants & Ratecorrected
Material for 100.00 sqm

1.00 sqm 0.13 12.50 Ltr 93.00


Wood
1 Primer(8sqm /ltr)

sqm Ltr
2 Oilpaint(11sqm/ltr) 1.00 0.09 9.09 238.00

Tarrpentine(100ml/k Ltr
3 g) 1.09 85.00

sqm 71.43 kg
4 Lambi(1.4sqm/kg) 1.00 0.71 50.00
8 Wastage @ 3%
9 Harware @ 2%
Total Material

Labour
1 Labour for above 40% of toal 100.00 sqm 48.96
2 20% Extra for night work 100.00 sqm 9.79
3
4
5

Total Labour

Add for Profit @ 15%


Total Amount for100 Sqm
Total Amount for 1.00 Sqm
SAY/SFT 14.00
Amount

1162.50

2163.64

92.73

3571.43

209.71
144.000
7344.001

4896.00
979.20

5875.20

1982.88
15202.082
152.02
14.13