You are on page 1of 6

SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.

00 30-Jun-16

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Pre-Test Inspection of Pressure Vessels (All Applications,


SAIC-A-2025 15-Nov-17 MECH-
Including In-situ Testing of New Fin Fan Coolers)
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A Test Package Verification:

Test Diagram is submitted showing the following:


A) Limits of equipment to be tested incl. test manifold & equipment
included in the test.
A1 GI 2.102 Para
B) Test pressure of the system
5.1.2
C) Relief valve setting
D) Safety Instruction Sheet

• Hydrostatic testing for new vessels (field fabricated) shall be conducted


as per 32-SAMSS-004 and the original construction code.
Pneumatic test, when approved (refer to paragraph 5.4), shall be
conducted per UG-100 of ASME SEC VIII D1, or T-4 of ASME SEC VIII SAES-A-004,
A2 D2, whichever is applicable. Appendix F Item 3
• Pressure testing of small vessels shall be per the appropriate standard
as specified in 32-SAMSS-036.
• Hydrostatic testing for existing vessels shall be conducted per SAES-D-
008, Section 14.

A3 Procedure has been approved & meets the detailed requirements of GI 2.102 Para
SAIC-A-2001 (Review Procedure - Pressure Testing) 5.1.2

Verify drawing conformance of pressure vessel construction. Check all


32-SAMSS-004
nozzles, supports, attachments (orientation & dimension)
A4 Section 20
Systematically complete, verify & accept all drawings incl. details in
accordance with NMR-7919-1

Verify complete code construction incl. support attachments. Repairs 32-SAMSS-004,


A5
& Pick-up (ID/OD) are accepted. ASME VIII, UG-99 (a) Section 16.1.1

If block valves are used for blocking or isolating hydro test sections, the
differential pressure across the valve seat shall not exceed the seat test SAES-L-150 Para
A6
pressure during the strength test and shall not exceed the rated seat 5.10
pressure during the tightness test.

The hydrotest pressure of all internally coated vessels, tanks or piping SAES-A-004,
shall be reviewed against the coating limitations as per SAES-H-001. On Appendix F Item
A7
completing the hydrostatic test, the pressure should be reduced gradually 17
to prevent decompression failure of the internal coating.

Weld Summary Record (SAEP-1160 Welding Database) was verified to


SAEP-1160 Para
indicate completion/acceptance of all weld joints, repairs, modifications &
A8 5.1 & SAES-W-
any applicable weld inspection reqmts (visual, NDE).
010, Section 16
Verify SAIC-W-2008 & SATR-W-2008 details as applicable

All required inspection & testing (RT, MT, PT, PWHT, PMI) has been
completed & inspection control sheet has been signed by SA. (ASME 32-SAMSS-004,
A9
VIII, UG-99, Para. A-2) Para 14.1.3
As applicable, an SAEP-1160 Welding Database is reviewed

Saudi Aramco: Company General Use


Safety Instruction Sheet (SIS) for vessels/equipment is complete & SAES-A-005,
A10
approved. Verify correct test pressure for system/equipment. Para. 4.2

Test Pressure at top of vessel is verified against the SIS and conforms
to the following ASME Section VIII code, as applicable:
Test pressure measured at the top of the vessel shall be:
16.3.11.1(a) For Division 1 vessels per UG-99(b):
PT=1.3 MAWP (S/ST)
16.3.11.1(b) For Division 2 vessels per 8.2.1:
SAES-A-004,
Greater of:
Appendix F &
i) PT = 1.43 MAWP
A11 32-
ii) PT = 1.25 MAWP (ST/ S)
SAMSS-004,
Where,
Section 16.3.11
PT is the minimum test pressure
S is the allowable stress at design temperature
ST is the allowable stress at test temperature
ST/S is the lowest ratio for the pressure boundary
materials, excluding bolting materials, of which
the vessel is constructed.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.00 30-Jun-16

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Pre-Test Inspection of Pressure Vessels (All Applications,


SAIC-A-2025 15-Nov-17 MECH-
Including In-situ Testing of New Fin Fan Coolers)
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

B Field Verification/Pre-Test Inspection of Vessel

SAES-A-004
B1 Vents shall be provided at all high points in the tested system as needed Para 5.14.1

Temporary supports shall be installed prior to hydrostatic testing, and


flushing of the piping if they were determined to be required per
SAES-A-004,
B3 SAES-L-150. These supports shall not be removed until after the system
Para.5.15.2
has been fully drained. The structural support system for stacked
equipment shall be verified for hydrostatic loads prior to testing.

All threaded joints and faying surfaces shall be seal welded by a


continuous fillet weld (required weep holes shall be left unwelded). SAES-W-010,
B4
Connections or attachments designed for periodic removal may be Para. 11.15.1
exempted from seal welding.

Weld Summary Record was verified to indicate completion of all weld SAES-W-010,
B5
joints & applicable weld inspection reqmts (visual and NDE). Para. 15.2

No acceptance of pressure testing shall be made prior to postweld heat 32-SAMSS-004,


B6
treatment. Section 16.3.4

Prior to final inspection and ressure testing, the inside and outside of the
32-SAMSS-004,
B7 vessel shall be thoroughly cleaned of all slag, scale, dirt, grit, weld spatter,
Section 16.2.9
paint, oil, etc.

Vessel Trim (associated piping) receives a strength test except in Utility


services and less when a service test can be conducted. SAES-L-150,
B8
Note: Vessel Trim piping pressure tests are often Para. 5.3
overlooked
B9 Sampling piping systems are pressure tested as an integral part of the
SAES-L-150,
New equipment to which it is connected.
Para. 5.6

All welded attachments provide with telltale holes shall be pneumatically


32-SAMSS-004,
tested at minimum 70 kPa (10 psi) prior to heat treatment and vessel
B10 Section 16.3.5,
pressure testing. Telltale holes must not be plugged during the vessel
16.3.6
pressure test.

The use of shellacs, glues, lead, etc., on gaskets during testing is


32-SAMSS-004,
B11 prohibited. No paint or primer shall be applied to a vessel prior to
Section 16.3.7
hydrostatic testing.

Hydrostatic pressure testing shall be performed with gaskets and


bolting identical to those required in service and as specified on the 32-SAMSS-004,
B12
data sheet. These gaskets may be used as service gaskets if the bolted Section 16.3.9
joint is not disassembled after completion of hydrostatic pressure testing.

B13 Metal temperature shall monitor throughout pressure vessel during 32-SAMSS-004,
New pressure test as per 32-SAMSS-004 Section 16.3.13

Vertical vessels tested in horizontal position are supported such that


32-SAMSS-004,
B14 primary stresses in any part of the vessel do not exceed 90% of minimum
Section 16.3.14
specified yield strength of the vessel material.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.00 30-Jun-16

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Pre-Test Inspection of Pressure Vessels (All Applications,


SAIC-A-2025 15-Nov-17 MECH-
Including In-situ Testing of New Fin Fan Coolers)
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Horizontal vessels shall be tested while resting on their permanent 32-SAMSS-004,


B15
support saddles without additional supports or cribbing. Section 16.3.15

Equipment or parts that are cladded shall be hydrotested with water 32-SAMSS-031,
B16
having chloride content not greater than 50 ppm. Para. 10.2.1

Fin fan exchangers shall be strength tested as specified below:


a) New fabricated fin fan coolers to be strength tested in accordance with
32-SAMSS-011.
b) Modified or repaired fin fan coolers shall be strength tested in SAES-A-004,
B17 accordance with the Safety Instruction Sheet (SIS). Appendix F
c) In-situ pressure testing shall be conducted in reference to Appendix G. Item 4
This is applicable to new and repaired or modified fin fan coolers that
passed the shop strength test then transported to site.

Jacketed Vessel exams & hydrotest sequence are planned and detailed in
design & during hydrotesting (per test procedure).
A) Inner vessel construction &
hydrotesting is completed prior to installation and hydrotesting of outer
SCH Q, (Project
B18 jacket . B) Construction
Specific)
sequence allows 100% visual inspection of welds during hydrotest. Jacket
design & installation is carefully planned.
[Reference: ASME VIII, UG-99 sect. (e)]

REMARKS:

REFERENCE DOCUMENTS:
1. SAES-A-004, General Requirements for Pressure Testing, 7 Jan 2016)
2. SAES-A-005, Safety Instruction Sheet, (21 March 2010)
3. SAES-D-008, Repairs, Alterations, and Re-rating of Process Equipment (30 June 2012)
5. SAEP-1160, Tracking and Reporting of Welding, NDT and Pressure Testing for Capital Projects. (10 July 2011)
6. SAES-W-010, Welding Requirements for Pressure Vessels (15 May 2016)
7. 32-SAMSS-031, Manufacture of Clad Vessels and Heat Exchangers. (2 Nov, 2011)
8. 32-SAMSS-004, Manufacture of Pressure Vessels (30 June 2014)
9. ASME Section VIII, Division 1 - Rules for Construction of Pressure Vessels (Latest Edition)
10. ASME Section VIII, Division 2 - Rules for Construction of Pressure Vessels, Alternative Rules (Latest Edition)

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use


BER

ACTOR

RE-INSP DATE

Saudi Aramco: Company General Use


BER

ACTOR

RE-INSP DATE

Work Verified

Work Verified

Work Verified

YES N = NO F = FAILED

Saudi Aramco: Company General Use

You might also like