Professional Documents
Culture Documents
00 30-Jun-16
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A3 Procedure has been approved & meets the detailed requirements of GI 2.102 Para
SAIC-A-2001 (Review Procedure - Pressure Testing) 5.1.2
If block valves are used for blocking or isolating hydro test sections, the
differential pressure across the valve seat shall not exceed the seat test SAES-L-150 Para
A6
pressure during the strength test and shall not exceed the rated seat 5.10
pressure during the tightness test.
The hydrotest pressure of all internally coated vessels, tanks or piping SAES-A-004,
shall be reviewed against the coating limitations as per SAES-H-001. On Appendix F Item
A7
completing the hydrostatic test, the pressure should be reduced gradually 17
to prevent decompression failure of the internal coating.
All required inspection & testing (RT, MT, PT, PWHT, PMI) has been
completed & inspection control sheet has been signed by SA. (ASME 32-SAMSS-004,
A9
VIII, UG-99, Para. A-2) Para 14.1.3
As applicable, an SAEP-1160 Welding Database is reviewed
Test Pressure at top of vessel is verified against the SIS and conforms
to the following ASME Section VIII code, as applicable:
Test pressure measured at the top of the vessel shall be:
16.3.11.1(a) For Division 1 vessels per UG-99(b):
PT=1.3 MAWP (S/ST)
16.3.11.1(b) For Division 2 vessels per 8.2.1:
SAES-A-004,
Greater of:
Appendix F &
i) PT = 1.43 MAWP
A11 32-
ii) PT = 1.25 MAWP (ST/ S)
SAMSS-004,
Where,
Section 16.3.11
PT is the minimum test pressure
S is the allowable stress at design temperature
ST is the allowable stress at test temperature
ST/S is the lowest ratio for the pressure boundary
materials, excluding bolting materials, of which
the vessel is constructed.
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
SAES-A-004
B1 Vents shall be provided at all high points in the tested system as needed Para 5.14.1
Weld Summary Record was verified to indicate completion of all weld SAES-W-010,
B5
joints & applicable weld inspection reqmts (visual and NDE). Para. 15.2
Prior to final inspection and ressure testing, the inside and outside of the
32-SAMSS-004,
B7 vessel shall be thoroughly cleaned of all slag, scale, dirt, grit, weld spatter,
Section 16.2.9
paint, oil, etc.
B13 Metal temperature shall monitor throughout pressure vessel during 32-SAMSS-004,
New pressure test as per 32-SAMSS-004 Section 16.3.13
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Equipment or parts that are cladded shall be hydrotested with water 32-SAMSS-031,
B16
having chloride content not greater than 50 ppm. Para. 10.2.1
Jacketed Vessel exams & hydrotest sequence are planned and detailed in
design & during hydrotesting (per test procedure).
A) Inner vessel construction &
hydrotesting is completed prior to installation and hydrotesting of outer
SCH Q, (Project
B18 jacket . B) Construction
Specific)
sequence allows 100% visual inspection of welds during hydrotest. Jacket
design & installation is carefully planned.
[Reference: ASME VIII, UG-99 sect. (e)]
REMARKS:
REFERENCE DOCUMENTS:
1. SAES-A-004, General Requirements for Pressure Testing, 7 Jan 2016)
2. SAES-A-005, Safety Instruction Sheet, (21 March 2010)
3. SAES-D-008, Repairs, Alterations, and Re-rating of Process Equipment (30 June 2012)
5. SAEP-1160, Tracking and Reporting of Welding, NDT and Pressure Testing for Capital Projects. (10 July 2011)
6. SAES-W-010, Welding Requirements for Pressure Vessels (15 May 2016)
7. 32-SAMSS-031, Manufacture of Clad Vessels and Heat Exchangers. (2 Nov, 2011)
8. 32-SAMSS-004, Manufacture of Pressure Vessels (30 June 2014)
9. ASME Section VIII, Division 1 - Rules for Construction of Pressure Vessels (Latest Edition)
10. ASME Section VIII, Division 2 - Rules for Construction of Pressure Vessels, Alternative Rules (Latest Edition)
ACTOR
RE-INSP DATE
ACTOR
RE-INSP DATE
Work Verified
Work Verified
Work Verified
YES N = NO F = FAILED