Saudi Aramco Inspection Checklist: In-Process Inspection of Intumescent Fireproofing Mat'ls SAIC-B-2007 15-Nov-17 Mech
Saudi Aramco Inspection Checklist: In-Process Inspection of Intumescent Fireproofing Mat'ls SAIC-B-2007 15-Nov-17 Mech
00 30-Jun-16
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
1. Use Section A for General Application Requirements.
2. Use Section B for Weather & Environmental checks during
work. 3. Use Section C for Quality Control
Note as referenced
checks during application. Production
work is in progress. Inspector monitors ongoing work & identifies
deficiencies early (SATR-B-2006 is used)
A General Requirements (Material & Data Sheet Instructions)
Metal surfaces are clean (no sand, dust, etc) before application.
SAES-H-001,
A1 Cleanliness (use white glove) shows all fines & dust are removed.
Para 8.4.3
SAES-H-001,
The substrate is free of any visible oil, grease, dirt, loose paint, loose rust,
A2 Para 6.1.1 (b)
or other surface contaminants (as applicable).
Substrate temperature is above 10°C & within the temperature limits listed SAES-H-001,Para
A4
by the manufacturer on the applicable Data Sheet. 6.1.1 (a)
The substrate temperature is less than 3°C above the dew point & within SAES-H-001,
A5
limits listed by the manufacturer on the applicable data sheet. Para 6.1.1.c
Contrasting colors (black & grey, etc) are used where multiple coat SAES-H-001,
A7
applications are performed (primer, intermediate & top coats) Para 9.3.1
Stripe coat by brush of all weld lines, edges, bolts, nuts & rivets applied SAES-H-001,
A8
prior to paint application. Maximum brush size is 125 mm. Para 9.3.6
The dry film thickness shall be within the minimum and maximumlimits SAES-H-001,
A9
allowed in the applicable APCS. Para 9.3.5.a
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Areas with defects (blisters, cracks, porous, below minimum dry film SAES-H-001,
A16
thickness, etc) are identified for repair. Identify defects by form. Para 9.3.5.e
SAES-H-100,
Finished coating dry film thickness is within minimum & maximum limits Section 8
A17
specified as checked in accordance with SSPC PA2 method. SAES-H-001,
Para 9.3.5
Repair Procedure for coatings strictly follows surface prep and SAES-H-001,
A18
application requirements in the manufacturer's technical data sheet. Para 9.5 & 9.6
SAES-H-001,
A19 Recoating intervals follow manufacturer's Technical Data Sheet.
Para 9.3.4
Application of intumescent mastics or other approved proprietary
SAES-B-006,Para
A20 fireproofing shall be performed only by personnel trained and certified by
8.2.2
the material manufacturer.
B Weather & Application Monitoring (*API Pub. 2218 as referenced in SAES-B-006 Para. 3.2)
SAES-H-001,
Overspray & wind protection (Plastic sheets, coverings, masking) are
B3 Para 6.1.1.d &
adequate for operations, especially during windy conditions.
9.2.d
C Quality Control
Drawings are checked & areas to be treated are easily identifiable & SAES-B-006,
C1
supported by drawings. Application limits are clearly identified. Para 8.4
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Adhesion strength of coating systems is not less than specified where
suspect coating applications result in rejection, NCR and the follow-up SAES-H-001,
C7
performance of an adhesion test to resolve any dispute. Para 9.3.5.d
REFERENCE DOCUMENTS:
1. SAES-B-006, Fireproofing for Plants, (20 November, 2011)
2. SAES-H-001, Coating Selection and Application Requirements for Industrial Plants and Equipemtent (5 April 2016)
3. SAES-H-102, Safety Requirements for Coating Applications (24 October 2012)
4. API Publication 2218 - Fireproofing Practices in Petroleum & Petrochemical Processing Plants Latest Edition
ATTACHMENTS: N/A
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date: