You are on page 1of 16

Sheet Piling

66, rue de Luxembourg


L - 4221 Esch-sur-Alzette (Luxembourg)
Tel.: (+352) 5313 3105
Fax: (+352) 5313 3290
E-mail: sheet-piling@arcelor.com
Internet: www.sheet-piling.arcelor.com

Ste
el
Sh
ee
tP
ilin
g

Un
de
rgr
o
Th und
eH C
ag ar P
ue ark

4-12-03-1-E
Introduction 1.
This case study considers the an underground car park for more surface and 32 m wide below
design and construction of a multi- than 550 cars. ground. The deepest basement
storey car park in which steel sheet level is approximately 5.4 m below
piling was used as an integral part The car park is constructed partially ground level, whilst the top level is
of the load bearing structure. below ground level. The part approximately 5.4 m above ground
above ground consists of the level. The vertical distance between
The car park was built as an ground floor, first floor and roof each level is 2.7 m but the usable
extension of the head office of park. The underground part com- height is 2.2 m due to the thickness
Siemens Nederlands N.V. in The prises two levels of parking which of the floor members. (Fig. 1)
Hague and lies adjacent to the extend beneath the upper levels
railway linking The Hague to and the adjacent road. The design Vehicular access to each level is by
Amsterdam. The complex compris- is rectangular in shape, being means of two carousels, one at
es 12,000 m2 of office space and 138 m long by 16 m wide on the each end of the car park.

Fig. 4

EXISTING BUILDING

precast concrete column

sand
precast prestressed stairwell entrance / exit
concrete beams

average height of the water


Fig. 5
precast prestressed
in situ concrete colum concrete beams
clay/peat in sheet pile

Fig. 5
sand concrete floor in situ

clay permanent drainage ground water level

sand

clay sheet pile precast concrete sheet pile


pile foundatoin
clay impermeable to water

solid sand
Fig. 1

3
Introduction 1.
This case study considers the an underground car park for more surface and 32 m wide below
design and construction of a multi- than 550 cars. ground. The deepest basement
storey car park in which steel sheet level is approximately 5.4 m below
piling was used as an integral part The car park is constructed partially ground level, whilst the top level is
of the load bearing structure. below ground level. The part approximately 5.4 m above ground
above ground consists of the level. The vertical distance between
The car park was built as an ground floor, first floor and roof each level is 2.7 m but the usable
extension of the head office of park. The underground part com- height is 2.2 m due to the thickness
Siemens Nederlands N.V. in The prises two levels of parking which of the floor members. (Fig. 1)
Hague and lies adjacent to the extend beneath the upper levels
railway linking The Hague to and the adjacent road. The design Vehicular access to each level is by
Amsterdam. The complex compris- is rectangular in shape, being means of two carousels, one at
es 12,000 m2 of office space and 138 m long by 16 m wide on the each end of the car park.

Fig. 4

EXISTING BUILDING

precast concrete column

sand
precast prestressed stairwell entrance / exit
concrete beams

average height of the water


Fig. 5
precast prestressed
in situ concrete colum concrete beams
clay/peat in sheet pile

Fig. 5
sand concrete floor in situ

clay permanent drainage ground water level

sand

clay sheet pile precast concrete sheet pile


pile foundatoin
clay impermeable to water

solid sand
Fig. 1

3
2. Site conditions

Cone resistance in MPa


Cone resistance in MPa Friction value (%)
2.2. Ground conditions (Fig. 2) 2.3. Groundwater drainage
TYPE OF SOIL
The nature and the characteristics The aquifer below the deepest
sand of the soils are of great impor- impermeable clay is used as a
tance when designing a founda- drinking water reservoir for The
clay/
peat tion. During the initial design Hague and must not be affected by
process the ground conditions drainage. The regional and local
were determined on the basis of authorities have stipulated that
earlier soil analysis carried out for drainage of groundwater must not
sand

the adjacent building. The results exceed 1.5 m3/h for this project.
were subsequently confirmed by Thus, it was necessary to ensure
clay that the car park was made as
soil analysis at the site location.
impermeable as possible. During
This consisted of a permeability
sand
the hydrogeological study an esti-
study and a geotechnical study of
mate was prepared of the expected
the excavation, together with a
seepage into the sheet pile sup-
bearing capacity study of both
clay ported excavation. It became
bearing and sheet piles. The apparent that to ensure that the
ground consists of a post glacial groundwater seepage remained
solid
sequence approximately 16 m below the stipulated levels it would
sand
thick, overlying a Pleistocene sand be necessary to take additional pre-
sequence. The post glacial cautionary measures.
sequence consists of the following:
Since the aquifer would be under
0 to 3.5 m An impermeable layer hydrostatic pressure, the design
with fine sand on top and clay needed to take into account the
and peat below. possibility of ground heave in the
3.5 to 7.5 m A permanent water lower impermeable layers.
bearing sand strata. The excavation was limited to 6 m
7.5 to 9.0 m A second imperme- below ground to provide sufficient
able, slightly cohesive layer. vertical stability.
9.0 to 13 m The second permanent Heavy drainage of the upper layers,
water bearing sand strata. which are prone to subsidence,
13 to 16 m Finally, an imperme- would result in subsidence of the
able clay which varies in thickness buildings adjacent to the car park.
So, for this reason, it would be
from 3.0 to 3.5 m.
necessary to use a steel sheet piling
cofferdam in the construction of
Below this post glacial layer, the
Fig. 2 the foundations.
pleistocene sequence consists of a
very compact sand. The ground
water level is 1.5 m below the
ground surface.

2.1. Location driving the piles and when dig- Existing public road
Since existing buildings were close ging and draining the excavation. A public road existed on the site
to the proposed site it was neces- It was necessary to phase the pil- before construction started and
sary to take measures to limit the ing work and use low vibration once the car park was completed
noise during pile installation. installation methods together the road would be re-installed on
with an extremely rigid piling sys- the top of the underground part
Railway embankment tem in order to minimise the of the car park. The road was not
The design requirements specified effects on the railway. in use during the construction
that the subsidence of the rails phase but would be used for
had to be minimised as far as pos- Finally, it was necessary to include access on completion. The design,
sible. Special care was taken with measures to avoid increased corro- therefore, had to take account of
regard to subsidence of the rail- sion of the piles as a result of any the normal urban traffic load
way embankment during the con- stray currents in the ground coming expected to use this road.
struction phase, particularly when from the adjacent electric railway.

4 5
2. Site conditions

Cone resistance in MPa


Cone resistance in MPa Friction value (%)
2.2. Ground conditions (Fig. 2) 2.3. Groundwater drainage
TYPE OF SOIL
The nature and the characteristics The aquifer below the deepest
sand of the soils are of great impor- impermeable clay is used as a
tance when designing a founda- drinking water reservoir for The
clay/
peat tion. During the initial design Hague and must not be affected by
process the ground conditions drainage. The regional and local
were determined on the basis of authorities have stipulated that
earlier soil analysis carried out for drainage of groundwater must not
sand

the adjacent building. The results exceed 1.5 m3/h for this project.
were subsequently confirmed by Thus, it was necessary to ensure
clay that the car park was made as
soil analysis at the site location.
impermeable as possible. During
This consisted of a permeability
sand
the hydrogeological study an esti-
study and a geotechnical study of
mate was prepared of the expected
the excavation, together with a
seepage into the sheet pile sup-
bearing capacity study of both
clay ported excavation. It became
bearing and sheet piles. The apparent that to ensure that the
ground consists of a post glacial groundwater seepage remained
solid
sequence approximately 16 m below the stipulated levels it would
sand
thick, overlying a Pleistocene sand be necessary to take additional pre-
sequence. The post glacial cautionary measures.
sequence consists of the following:
Since the aquifer would be under
0 to 3.5 m An impermeable layer hydrostatic pressure, the design
with fine sand on top and clay needed to take into account the
and peat below. possibility of ground heave in the
3.5 to 7.5 m A permanent water lower impermeable layers.
bearing sand strata. The excavation was limited to 6 m
7.5 to 9.0 m A second imperme- below ground to provide sufficient
able, slightly cohesive layer. vertical stability.
9.0 to 13 m The second permanent Heavy drainage of the upper layers,
water bearing sand strata. which are prone to subsidence,
13 to 16 m Finally, an imperme- would result in subsidence of the
able clay which varies in thickness buildings adjacent to the car park.
So, for this reason, it would be
from 3.0 to 3.5 m.
necessary to use a steel sheet piling
cofferdam in the construction of
Below this post glacial layer, the
Fig. 2 the foundations.
pleistocene sequence consists of a
very compact sand. The ground
water level is 1.5 m below the
ground surface.

2.1. Location driving the piles and when dig- Existing public road
Since existing buildings were close ging and draining the excavation. A public road existed on the site
to the proposed site it was neces- It was necessary to phase the pil- before construction started and
sary to take measures to limit the ing work and use low vibration once the car park was completed
noise during pile installation. installation methods together the road would be re-installed on
with an extremely rigid piling sys- the top of the underground part
Railway embankment tem in order to minimise the of the car park. The road was not
The design requirements specified effects on the railway. in use during the construction
that the subsidence of the rails phase but would be used for
had to be minimised as far as pos- Finally, it was necessary to include access on completion. The design,
sible. Special care was taken with measures to avoid increased corro- therefore, had to take account of
regard to subsidence of the rail- sion of the piles as a result of any the normal urban traffic load
way embankment during the con- stray currents in the ground coming expected to use this road.
struction phase, particularly when from the adjacent electric railway.

4 5
3. Design considerations

Two alternative designs were con- with only one level below ground considered as a viable option. This a slight amount of leakage along torted due to water pressure in a water inflow than expected. This
sidered when designing the car was not an attractive proposition structure consists of a car park sup- the interface between the piles flood situation. would only become apparent dur-
park. A closed concrete structure because of the increased floor ported on all sides by steel sheet and the clay, a permanent ing excavation and could originate
and the chosen option, an open area needed. piling that had been driven drainage system has been installed When comparing the two alterna- from the piling interlocks or from
steel piling structure. (Fig. 3) through the clay into the sand. In approximately 0.5 m below the tives on the basis of cost and the pile to clay interface. If need-
Both of these concrete solutions the middle, a separate system of deepest car park level. speed of construction, the open ed, the remedial measures fore-
3.1. Closed concrete structure would also require extensive use bearing piles is also driven into the structure, employing steel sheet seen are grouting behind the piles
A conventional closed concrete of sheet piling in the form of tem- dense sand. The floor for the deepest level was piling, proved to be approximately or into the floor.
structure would consist of a con- porary cofferdams. designed as a thin concrete strut. 15% cheaper than the convention-
crete basement cast in-situ. The In this case, the clay layer and the This floor has a series of openings al concrete option.
thick concrete floor would be set on 3.2. Open structure constructed piling form a near watertight seal in it, in the form of small pave-
concrete bearing piles and provision using steel sheet piling to the basement of the garage ment sections set on sand. These The clients’ design consultants had
would be made at the bottom of Since an impermeable clay layer and have sufficient vertical stabili- allow water to pass through in the recommended that consideration
the structure to prevent lifting. 3.5 m thick exists above the very ty to resist heave due to hydraulic event of the car park flooding and be given to remedial measures
A variant of the same structure dense sand, an open structure was uplift. As there is the possibility of prevent the floor becoming dis- needed in the event of higher

air duct air duct

EXISTING BUILDING

precast prestressed concrete beams precast prestressed concrete beams

stairwell stairwell

precast prestressed concrete beams precast prestressed concrete beams

air flue air flue


Fig. 1

Fig. 3

6 7
3. Design considerations

Two alternative designs were con- with only one level below ground considered as a viable option. This a slight amount of leakage along torted due to water pressure in a water inflow than expected. This
sidered when designing the car was not an attractive proposition structure consists of a car park sup- the interface between the piles flood situation. would only become apparent dur-
park. A closed concrete structure because of the increased floor ported on all sides by steel sheet and the clay, a permanent ing excavation and could originate
and the chosen option, an open area needed. piling that had been driven drainage system has been installed When comparing the two alterna- from the piling interlocks or from
steel piling structure. (Fig. 3) through the clay into the sand. In approximately 0.5 m below the tives on the basis of cost and the pile to clay interface. If need-
Both of these concrete solutions the middle, a separate system of deepest car park level. speed of construction, the open ed, the remedial measures fore-
3.1. Closed concrete structure would also require extensive use bearing piles is also driven into the structure, employing steel sheet seen are grouting behind the piles
A conventional closed concrete of sheet piling in the form of tem- dense sand. The floor for the deepest level was piling, proved to be approximately or into the floor.
structure would consist of a con- porary cofferdams. designed as a thin concrete strut. 15% cheaper than the convention-
crete basement cast in-situ. The In this case, the clay layer and the This floor has a series of openings al concrete option.
thick concrete floor would be set on 3.2. Open structure constructed piling form a near watertight seal in it, in the form of small pave-
concrete bearing piles and provision using steel sheet piling to the basement of the garage ment sections set on sand. These The clients’ design consultants had
would be made at the bottom of Since an impermeable clay layer and have sufficient vertical stabili- allow water to pass through in the recommended that consideration
the structure to prevent lifting. 3.5 m thick exists above the very ty to resist heave due to hydraulic event of the car park flooding and be given to remedial measures
A variant of the same structure dense sand, an open structure was uplift. As there is the possibility of prevent the floor becoming dis- needed in the event of higher

air duct air duct

EXISTING BUILDING

precast prestressed concrete beams precast prestressed concrete beams

stairwell stairwell

precast prestressed concrete beams precast prestressed concrete beams

air flue air flue


Fig. 1

Fig. 3

6 7
4. Loads to be considered

Horizontal loads
precast concrete
column
The horizontal loads on the structure variable traffic load

include:
• Wind load on the superstructure in air flue

accordance with NEN 3850.


• Soil pressure against the substructure.
concrete
• Lateral pressure from the railway
column column
embankment.
concrete
column sheet pile
Vertical loads
sheet pile
The vertical loads consist of:
• Self weight.
• Live load on the floors in the garage.
• Live load on the garage roof.

Load transmission Fig. 6 - Sheet pile bending at Y16 due to wind load Fig. 7 - Sheet pile bending at Y12 due to variable traffic load

These loads are transmitted to the


foundations in the following way:

4.1. Vertical load transmission


concrete column
On the railway side (Y16) (in situ)
On the central axis 4.2. Horizontal load transmission The load bearing system
The vertical load of the superstructure
column reinforcement A double row of columns on the Horizontal load transmission of the lower structure
is transmitted through the floor beams
onto precast concrete columns which central axis of the structure is of the superstructure (Fig. 6) The sheet piling supports the
are sited at 7.2 m centres. The columns supported on bearing piles, which The design of the structure is such ground pressures in both the con-
in turn rest on a capping beam cast are founded in the dense sand that the horizontal wind load is struction and working phases of
onto the sheet piling which redistrib- 18 m below the surface level. not transmitted directly to the the structure. During the tempo-
utes the point loads of the columns sheet piling, but is transmitted to rary stages, ground anchors and
into the sheet pile wall. (Fig. 4) On the office side (Y12) the ground floor and the base- wallings were used for support,
air flue
The vertical load due to traffic on ment floor beneath it, forming where as the floors of the com-
The underground floors of the car park the office side of the garage is together with the in-situ concrete pleted structure supported the
are supported directly by beams that transmitted to the supporting columns a stiff frame and so walls in the long term.
bear directly onto the sheet piling. The sheet pile sheet piling as an evenly distrib- absorbing this additional moment.
deepest floor of the car park is found- uted load. The roof comprises
ed directly on the subsoil and is not 16 m long girders which rest on a
supported by the sheet piling. capping beam cast onto the sheet
piling. The basement floors are
constructed adopting the same
Fig. 4 - Vertical load transmission method used on the railway side
of the building. (Fig. 5+7)

air flue

precast prestressed
concrete beam

in situ casted concrete beam with


reinforcing bars welded to steel
Fig. 5 - Steel sheet pile/concrete connection sheet pile; Anchorage

8 9
4. Loads to be considered

Horizontal loads
precast concrete
column
The horizontal loads on the structure variable traffic load

include:
• Wind load on the superstructure in air flue

accordance with NEN 3850.


• Soil pressure against the substructure.
concrete
• Lateral pressure from the railway
column column
embankment.
concrete
column sheet pile
Vertical loads
sheet pile
The vertical loads consist of:
• Self weight.
• Live load on the floors in the garage.
• Live load on the garage roof.

Load transmission Fig. 6 - Sheet pile bending at Y16 due to wind load Fig. 7 - Sheet pile bending at Y12 due to variable traffic load

These loads are transmitted to the


foundations in the following way:

4.1. Vertical load transmission


concrete column
On the railway side (Y16) (in situ)
On the central axis 4.2. Horizontal load transmission The load bearing system
The vertical load of the superstructure
column reinforcement A double row of columns on the Horizontal load transmission of the lower structure
is transmitted through the floor beams
onto precast concrete columns which central axis of the structure is of the superstructure (Fig. 6) The sheet piling supports the
are sited at 7.2 m centres. The columns supported on bearing piles, which The design of the structure is such ground pressures in both the con-
in turn rest on a capping beam cast are founded in the dense sand that the horizontal wind load is struction and working phases of
onto the sheet piling which redistrib- 18 m below the surface level. not transmitted directly to the the structure. During the tempo-
utes the point loads of the columns sheet piling, but is transmitted to rary stages, ground anchors and
into the sheet pile wall. (Fig. 4) On the office side (Y12) the ground floor and the base- wallings were used for support,
air flue
The vertical load due to traffic on ment floor beneath it, forming where as the floors of the com-
The underground floors of the car park the office side of the garage is together with the in-situ concrete pleted structure supported the
are supported directly by beams that transmitted to the supporting columns a stiff frame and so walls in the long term.
bear directly onto the sheet piling. The sheet pile sheet piling as an evenly distrib- absorbing this additional moment.
deepest floor of the car park is found- uted load. The roof comprises
ed directly on the subsoil and is not 16 m long girders which rest on a
supported by the sheet piling. capping beam cast onto the sheet
piling. The basement floors are
constructed adopting the same
Fig. 4 - Vertical load transmission method used on the railway side
of the building. (Fig. 5+7)

air flue

precast prestressed
concrete beam

in situ casted concrete beam with


reinforcing bars welded to steel
Fig. 5 - Steel sheet pile/concrete connection sheet pile; Anchorage

8 9
5. Calculations Specific aspects 6.
The main calculations used in the The bending stress in the steel Deflection of the sheet piling due 6.1. Surface treatment By welding on rods in certain 6.5. Ventilation provisions
design of the steel sheet piling This falls into two parts: to the soil loading on the railway The exposed parts of the steel spots, it was possible to perform a The ventilation of the under-
The sheet piling serves as both the • The localised bending in the side sheet piling were treated with a controlling measurement after- ground part of the garage was
support to the ground and the piles due to the connection of the The deflection of the sheet piling layer of zinc-rich primer, then a wards. The location of the garage dealt with in two ways:
vertical loads from the structure floor members and the transmis- due to soil loading has been calcu- coat of epoxy primer and finally a was so favourable that no risk of • On the office side of the struc-
above. sion of the vertical load. lated using a programme which is coat of epoxy paint. corrosion due to stray currents ture, 5 ventilation shafts were
The profile chosen was the PU 16 • The bending moment due to the based on bi-linear ground springs was found. formed using sheet piling. Each
type of sheet piling (in steel quali- ground pressure. against the sheet piling. 6.2. Fire protection shaft was 2.5 m x 2.5 m and
ty PAE 250 in accordance with 6.4. Impermeability extended down to the under-
No specific measures were taken
Euronorm quality Fe340 B). Bending of the railway side wall The railway load has been calcu- with respect to fire protection of A sealing product was applied to ground levels from ground level.
on line Y 16 (Fig. 8) lated as an additional horizontal the steel since the exposed sur- the interlocks at the factory and The top of each shaft is protected
Stresses as a result of vertical load The sheet piling showed little or load using the Culmann method. faces were backed by saturated the piles were driven into pre- with a grill
The stresses in the sheet piling no bending due to the vertical or The ground pressure coefficients soil, which would act as good drilled holes filled with bentonite • On the railway side, mechanical
resulting from vertical loads com- floor connection loads transmitted have been based on assumed fail- thermal conductor. cement slurry, down to the clay ventilation was provided via small
prise a normal compressive stress to it. ure surfaces. In use, the steel stress in the sheet layer. This pre-drilling was carried vertical ducts made as part of the
and a local bending stress where piling is very low at 40 N/mm2, out to reduce the vibration and vertical columns. (Fig. 10)
the capping beams are formed at Bending of the office side sheet which is approximately half of the subsidence effects on the sur-
the top of the piling and where piling line Y12, due to vertical maximum value. rounding ground and structures.
the underground floors are fixed load (Fig. 9) However it was thought that pil-
to the walls. A slight decrease in the yield point ing into bentonite cement slurry
The ground floor caused major
of the steel due to the effects of would have a beneficial effect on
bending moments at the head of
Normal vertical force temperature would not affect the sealing the interlocks. Once the
the sheet piling. During the con-
bearing capacity of the sheet pil- excavation was complete the
This consists of the vertical compo- struction phase this was due to
ing significantly. sheet piling wall was grouted to
nent of the ground anchor force the load of the garage roof and,
complete the sealing process.
in the temporary case and the in the permanent condition, from
load of the structure and its con- the heavier load from traffic on 6.3. Corrosion of steel sheet piling
tents in the permanent case. the road on top of the garage by stray electrical currents
roof. In view of the location of the
garage, with its steel sheet piling
close to an electrified railway line,
a study of the possible effects of
stray currents was undertaken.
Stray currents occur as a result of
using the rails as the return for
the electricity used by the trains.
The voltage of these stray currents
depends on the proximity of sub-
stations and the type of ground.
The corrosion effects can be min-
imised by ensuring good conduc-
tivity between the individual piles
and by welding on steel rods at
certain points to act as electrical
earth pathways, which lead the
stray current back to the rails.

Soil pressure (kN/M2) Bending moment (kNM) Displacements [MM] Soil pressure (kN/M2) Bending moment (kNM) Displacements [MM]
gauche gauche
droite droite

Fig. 8 - Sheet pile bending at Y16 due to soil and Fig. 9 - Sheet pile bending at Y12 due to soil and
water pressure water pressure Fig. 10 - Ventilation shaft

10 11
5. Calculations Specific aspects 6.
The main calculations used in the The bending stress in the steel Deflection of the sheet piling due 6.1. Surface treatment By welding on rods in certain 6.5. Ventilation provisions
design of the steel sheet piling This falls into two parts: to the soil loading on the railway The exposed parts of the steel spots, it was possible to perform a The ventilation of the under-
The sheet piling serves as both the • The localised bending in the side sheet piling were treated with a controlling measurement after- ground part of the garage was
support to the ground and the piles due to the connection of the The deflection of the sheet piling layer of zinc-rich primer, then a wards. The location of the garage dealt with in two ways:
vertical loads from the structure floor members and the transmis- due to soil loading has been calcu- coat of epoxy primer and finally a was so favourable that no risk of • On the office side of the struc-
above. sion of the vertical load. lated using a programme which is coat of epoxy paint. corrosion due to stray currents ture, 5 ventilation shafts were
The profile chosen was the PU 16 • The bending moment due to the based on bi-linear ground springs was found. formed using sheet piling. Each
type of sheet piling (in steel quali- ground pressure. against the sheet piling. 6.2. Fire protection shaft was 2.5 m x 2.5 m and
ty PAE 250 in accordance with 6.4. Impermeability extended down to the under-
No specific measures were taken
Euronorm quality Fe340 B). Bending of the railway side wall The railway load has been calcu- with respect to fire protection of A sealing product was applied to ground levels from ground level.
on line Y 16 (Fig. 8) lated as an additional horizontal the steel since the exposed sur- the interlocks at the factory and The top of each shaft is protected
Stresses as a result of vertical load The sheet piling showed little or load using the Culmann method. faces were backed by saturated the piles were driven into pre- with a grill
The stresses in the sheet piling no bending due to the vertical or The ground pressure coefficients soil, which would act as good drilled holes filled with bentonite • On the railway side, mechanical
resulting from vertical loads com- floor connection loads transmitted have been based on assumed fail- thermal conductor. cement slurry, down to the clay ventilation was provided via small
prise a normal compressive stress to it. ure surfaces. In use, the steel stress in the sheet layer. This pre-drilling was carried vertical ducts made as part of the
and a local bending stress where piling is very low at 40 N/mm2, out to reduce the vibration and vertical columns. (Fig. 10)
the capping beams are formed at Bending of the office side sheet which is approximately half of the subsidence effects on the sur-
the top of the piling and where piling line Y12, due to vertical maximum value. rounding ground and structures.
the underground floors are fixed load (Fig. 9) However it was thought that pil-
to the walls. A slight decrease in the yield point ing into bentonite cement slurry
The ground floor caused major
of the steel due to the effects of would have a beneficial effect on
bending moments at the head of
Normal vertical force temperature would not affect the sealing the interlocks. Once the
the sheet piling. During the con-
bearing capacity of the sheet pil- excavation was complete the
This consists of the vertical compo- struction phase this was due to
ing significantly. sheet piling wall was grouted to
nent of the ground anchor force the load of the garage roof and,
complete the sealing process.
in the temporary case and the in the permanent condition, from
load of the structure and its con- the heavier load from traffic on 6.3. Corrosion of steel sheet piling
tents in the permanent case. the road on top of the garage by stray electrical currents
roof. In view of the location of the
garage, with its steel sheet piling
close to an electrified railway line,
a study of the possible effects of
stray currents was undertaken.
Stray currents occur as a result of
using the rails as the return for
the electricity used by the trains.
The voltage of these stray currents
depends on the proximity of sub-
stations and the type of ground.
The corrosion effects can be min-
imised by ensuring good conduc-
tivity between the individual piles
and by welding on steel rods at
certain points to act as electrical
earth pathways, which lead the
stray current back to the rails.

Soil pressure (kN/M2) Bending moment (kNM) Displacements [MM] Soil pressure (kN/M2) Bending moment (kNM) Displacements [MM]
gauche gauche
droite droite

Fig. 8 - Sheet pile bending at Y16 due to soil and Fig. 9 - Sheet pile bending at Y12 due to soil and
water pressure water pressure Fig. 10 - Ventilation shaft

10 11
Evaluation 8.
8.1. Impermeability
The requirements stipulated with
regard to permanent drainage

7. Phasing of excavation construction


were amply met. However, some
moisture had entered the structure
near the sheet piling interlocks
which made surface treatment less
easy. This seepage was virtually
1st Phase: Pre-Drilling of Bentonite sheet piling. The centre interlocks 4th Phase: Excavation to lower
stopped by means of grout injec-
Cement filled holes of the paired piles have been ground anchor level
tion.
Holes of 30 cm ø were drilled at treated with a bituminous sealing The excavation was then taken The source of the moisture was
1.2 m spacing (driving width of product. down to the lower anchor level. In believed to be due to capilliary
the paired piles) and filled with a order to reduce the possibility of action along the inside of the inter-
bentonite mix prior to driving the 3rd Phase: Excavation to first subsidence a supporting berm was locks from the water bearing
ground anchor level left against the sheet piling adja-
piles. The pre-drilling was neces- aquifer; as the sealing product had
sary to reduce the ground vibra- During construction, before the cent to the railway until the piles
been applied on the outside (land-
tions in order to minimise the car park levels were constructed it on the central axis had been driv-
side and waterside) of the locks the
potential for subsidence during was necessary to support the pil- en. Once the piles on the central
ground water could only seep out
ing by temporary ground anchors axis had been driven, the tempo-
pile driving and to improve the into the garage.
and steel walling on the inside. rary berm was removed and the
quality of the sheet pile installa- The impermeability of the piling
On the side adjacent to the rail- lower row of ground anchors was
tion. may have been further improved
way, to ensure that track subsi- installed, these having a length of
by applying a sealing product inside
dence was kept to a minimum, 2 14 m.
2nd Phase: Pile Driving the entire sheet piling interlock.
rows of temporary ground
The piling was driven using a pil- anchors were used. The positions 5th Phase: Completion
8.2. Drainage during construction
ing hammer with an impact ener- of the anchors correspond to the of excavation
gy of 120 kN/m per blow. The pil- Once the excavation had been to the direct surroundings. The firmed that no significant subsi-
ground floor and the first base- The excavation is completed and
ing was driven in crimped pairs pumped dry, further drainage was only exception to this was whilst dence was measured during the
ment floor. The third phase of the drained to the base level.
between the pre-drilled holes such minimal because of the imperme- driving the short stretch of piling installation of the ground to the
work involved drainage and exca-
that each free lock that had not ability of the sheet piling. No immediately adjacent to the exist- final level.
vation to the top anchor level and
influence on the surroundings has ing office block.
been previously treated was installation of the ground anchors.
been observed since the excava- 8.5. Maintenance
placed in a bentonite hole. The In each row, the anchors lay alter-
tion has been drained. 8.4. Subsidence of the railway The drainage pipes are positioned
composition of the bentonite nately at an angle of 20 degrees
embankment below the ground water level
cement mixture was such that it and 27 degrees to the horizontal.
8.3. Inconvenience on the sur- The vertical and horizontal move- which will reduce the risk of
was considered to be extremely The top row of anchors had a
roundings ments of the railway were meas- blockage due to drying out.
watertight with respect to the length of 20 m.
As a noise screen was used around ured at regular intervals during Maintenance is limited to periodic
the piling hammer during driving, the various stages of construction. purging of the drainage pipes to
minimal inconvenience was caused Measurements taken later con- facilitate the flow of water.

Parties involved in this project 9.


Management: Bouwkundig Design Consultant: Aronsohn Piling Subcontractor: van Splunder
Adviesbureau Derks b.v., Leiden Raadgevende Ingenieurs b.v., Funderingstechniek b.v., Rotterdam
Rotterdam and Visser & Smit Bouw b.v.,
Architect: de Jong, Hoogveld, Papendrecht
de Kat architecten, Utrecht Contractor:
DURA BOUW b.v., Rotterdam Soil Analysis: Grondmechanica
Delft, Delft
reinforcing bars welded to steel sheet pile
supporting the in situ casted concrete beams

12 13
Evaluation 8.
8.1. Impermeability
The requirements stipulated with
regard to permanent drainage

7. Phasing of excavation construction


were amply met. However, some
moisture had entered the structure
near the sheet piling interlocks
which made surface treatment less
easy. This seepage was virtually
1st Phase: Pre-Drilling of Bentonite sheet piling. The centre interlocks 4th Phase: Excavation to lower
stopped by means of grout injec-
Cement filled holes of the paired piles have been ground anchor level
tion.
Holes of 30 cm ø were drilled at treated with a bituminous sealing The excavation was then taken The source of the moisture was
1.2 m spacing (driving width of product. down to the lower anchor level. In believed to be due to capilliary
the paired piles) and filled with a order to reduce the possibility of action along the inside of the inter-
bentonite mix prior to driving the 3rd Phase: Excavation to first subsidence a supporting berm was locks from the water bearing
ground anchor level left against the sheet piling adja-
piles. The pre-drilling was neces- aquifer; as the sealing product had
sary to reduce the ground vibra- During construction, before the cent to the railway until the piles
been applied on the outside (land-
tions in order to minimise the car park levels were constructed it on the central axis had been driv-
side and waterside) of the locks the
potential for subsidence during was necessary to support the pil- en. Once the piles on the central
ground water could only seep out
ing by temporary ground anchors axis had been driven, the tempo-
pile driving and to improve the into the garage.
and steel walling on the inside. rary berm was removed and the
quality of the sheet pile installa- The impermeability of the piling
On the side adjacent to the rail- lower row of ground anchors was
tion. may have been further improved
way, to ensure that track subsi- installed, these having a length of
by applying a sealing product inside
dence was kept to a minimum, 2 14 m.
2nd Phase: Pile Driving the entire sheet piling interlock.
rows of temporary ground
The piling was driven using a pil- anchors were used. The positions 5th Phase: Completion
8.2. Drainage during construction
ing hammer with an impact ener- of the anchors correspond to the of excavation
gy of 120 kN/m per blow. The pil- Once the excavation had been to the direct surroundings. The firmed that no significant subsi-
ground floor and the first base- The excavation is completed and
ing was driven in crimped pairs pumped dry, further drainage was only exception to this was whilst dence was measured during the
ment floor. The third phase of the drained to the base level.
between the pre-drilled holes such minimal because of the imperme- driving the short stretch of piling installation of the ground to the
work involved drainage and exca-
that each free lock that had not ability of the sheet piling. No immediately adjacent to the exist- final level.
vation to the top anchor level and
influence on the surroundings has ing office block.
been previously treated was installation of the ground anchors.
been observed since the excava- 8.5. Maintenance
placed in a bentonite hole. The In each row, the anchors lay alter-
tion has been drained. 8.4. Subsidence of the railway The drainage pipes are positioned
composition of the bentonite nately at an angle of 20 degrees
embankment below the ground water level
cement mixture was such that it and 27 degrees to the horizontal.
8.3. Inconvenience on the sur- The vertical and horizontal move- which will reduce the risk of
was considered to be extremely The top row of anchors had a
roundings ments of the railway were meas- blockage due to drying out.
watertight with respect to the length of 20 m.
As a noise screen was used around ured at regular intervals during Maintenance is limited to periodic
the piling hammer during driving, the various stages of construction. purging of the drainage pipes to
minimal inconvenience was caused Measurements taken later con- facilitate the flow of water.

Parties involved in this project 9.


Management: Bouwkundig Design Consultant: Aronsohn Piling Subcontractor: van Splunder
Adviesbureau Derks b.v., Leiden Raadgevende Ingenieurs b.v., Funderingstechniek b.v., Rotterdam
Rotterdam and Visser & Smit Bouw b.v.,
Architect: de Jong, Hoogveld, Papendrecht
de Kat architecten, Utrecht Contractor:
DURA BOUW b.v., Rotterdam Soil Analysis: Grondmechanica
Delft, Delft
reinforcing bars welded to steel sheet pile
supporting the in situ casted concrete beams

12 13
1 2 3 4 5

6 7 8 9 10

11 12 13
References of underground car parks 10.
Court Münster D picture 1
Congress Centre Amsterdam NL picture 2
House for dentistry Münster D picture 3
Malieveld Den Haag NL picture 4
KLM Amstelveen NL picture 5
City hall Rouen F picture 6
Münsterstrasse Düsseldorf D picture 7
Marketsquare Coesfeld D picture 8
World Trade Center Amsterdam NL picture 9
Haute ville Rouen F picture 10
Royal Christiana Hotel Oslo N picture 11
VROM Den Haag NL picture 12
Zwolsestraat Scheveningen NL picture 13

14 15
1 2 3 4 5

6 7 8 9 10

11 12 13
References of underground car parks 10.
Court Münster D picture 1
Congress Centre Amsterdam NL picture 2
House for dentistry Münster D picture 3
Malieveld Den Haag NL picture 4
KLM Amstelveen NL picture 5
City hall Rouen F picture 6
Münsterstrasse Düsseldorf D picture 7
Marketsquare Coesfeld D picture 8
World Trade Center Amsterdam NL picture 9
Haute ville Rouen F picture 10
Royal Christiana Hotel Oslo N picture 11
VROM Den Haag NL picture 12
Zwolsestraat Scheveningen NL picture 13

14 15
Sheet Piling
66, rue de Luxembourg
L - 4221 Esch-sur-Alzette (Luxembourg)
Tel.: (+352) 5313 3105
Fax: (+352) 5313 3290
E-mail: sheet-piling@arcelor.com
Internet: www.sheet-piling.arcelor.com

Ste
el
Sh
ee
tP
ilin
g

Un
de
rgr
o
Th und
eH C
ag ar P
ue ark

4-12-03-1-E

You might also like