Professional Documents
Culture Documents
Ste
el
Sh
ee
tP
ilin
g
Un
de
rgr
o
Th und
eH C
ag ar P
ue ark
4-12-03-1-E
Introduction 1.
This case study considers the an underground car park for more surface and 32 m wide below
design and construction of a multi- than 550 cars. ground. The deepest basement
storey car park in which steel sheet level is approximately 5.4 m below
piling was used as an integral part The car park is constructed partially ground level, whilst the top level is
of the load bearing structure. below ground level. The part approximately 5.4 m above ground
above ground consists of the level. The vertical distance between
The car park was built as an ground floor, first floor and roof each level is 2.7 m but the usable
extension of the head office of park. The underground part com- height is 2.2 m due to the thickness
Siemens Nederlands N.V. in The prises two levels of parking which of the floor members. (Fig. 1)
Hague and lies adjacent to the extend beneath the upper levels
railway linking The Hague to and the adjacent road. The design Vehicular access to each level is by
Amsterdam. The complex compris- is rectangular in shape, being means of two carousels, one at
es 12,000 m2 of office space and 138 m long by 16 m wide on the each end of the car park.
Fig. 4
EXISTING BUILDING
sand
precast prestressed stairwell entrance / exit
concrete beams
Fig. 5
sand concrete floor in situ
sand
solid sand
Fig. 1
3
Introduction 1.
This case study considers the an underground car park for more surface and 32 m wide below
design and construction of a multi- than 550 cars. ground. The deepest basement
storey car park in which steel sheet level is approximately 5.4 m below
piling was used as an integral part The car park is constructed partially ground level, whilst the top level is
of the load bearing structure. below ground level. The part approximately 5.4 m above ground
above ground consists of the level. The vertical distance between
The car park was built as an ground floor, first floor and roof each level is 2.7 m but the usable
extension of the head office of park. The underground part com- height is 2.2 m due to the thickness
Siemens Nederlands N.V. in The prises two levels of parking which of the floor members. (Fig. 1)
Hague and lies adjacent to the extend beneath the upper levels
railway linking The Hague to and the adjacent road. The design Vehicular access to each level is by
Amsterdam. The complex compris- is rectangular in shape, being means of two carousels, one at
es 12,000 m2 of office space and 138 m long by 16 m wide on the each end of the car park.
Fig. 4
EXISTING BUILDING
sand
precast prestressed stairwell entrance / exit
concrete beams
Fig. 5
sand concrete floor in situ
sand
solid sand
Fig. 1
3
2. Site conditions
the adjacent building. The results exceed 1.5 m3/h for this project.
were subsequently confirmed by Thus, it was necessary to ensure
clay that the car park was made as
soil analysis at the site location.
impermeable as possible. During
This consisted of a permeability
sand
the hydrogeological study an esti-
study and a geotechnical study of
mate was prepared of the expected
the excavation, together with a
seepage into the sheet pile sup-
bearing capacity study of both
clay ported excavation. It became
bearing and sheet piles. The apparent that to ensure that the
ground consists of a post glacial groundwater seepage remained
solid
sequence approximately 16 m below the stipulated levels it would
sand
thick, overlying a Pleistocene sand be necessary to take additional pre-
sequence. The post glacial cautionary measures.
sequence consists of the following:
Since the aquifer would be under
0 to 3.5 m An impermeable layer hydrostatic pressure, the design
with fine sand on top and clay needed to take into account the
and peat below. possibility of ground heave in the
3.5 to 7.5 m A permanent water lower impermeable layers.
bearing sand strata. The excavation was limited to 6 m
7.5 to 9.0 m A second imperme- below ground to provide sufficient
able, slightly cohesive layer. vertical stability.
9.0 to 13 m The second permanent Heavy drainage of the upper layers,
water bearing sand strata. which are prone to subsidence,
13 to 16 m Finally, an imperme- would result in subsidence of the
able clay which varies in thickness buildings adjacent to the car park.
So, for this reason, it would be
from 3.0 to 3.5 m.
necessary to use a steel sheet piling
cofferdam in the construction of
Below this post glacial layer, the
Fig. 2 the foundations.
pleistocene sequence consists of a
very compact sand. The ground
water level is 1.5 m below the
ground surface.
2.1. Location driving the piles and when dig- Existing public road
Since existing buildings were close ging and draining the excavation. A public road existed on the site
to the proposed site it was neces- It was necessary to phase the pil- before construction started and
sary to take measures to limit the ing work and use low vibration once the car park was completed
noise during pile installation. installation methods together the road would be re-installed on
with an extremely rigid piling sys- the top of the underground part
Railway embankment tem in order to minimise the of the car park. The road was not
The design requirements specified effects on the railway. in use during the construction
that the subsidence of the rails phase but would be used for
had to be minimised as far as pos- Finally, it was necessary to include access on completion. The design,
sible. Special care was taken with measures to avoid increased corro- therefore, had to take account of
regard to subsidence of the rail- sion of the piles as a result of any the normal urban traffic load
way embankment during the con- stray currents in the ground coming expected to use this road.
struction phase, particularly when from the adjacent electric railway.
4 5
2. Site conditions
the adjacent building. The results exceed 1.5 m3/h for this project.
were subsequently confirmed by Thus, it was necessary to ensure
clay that the car park was made as
soil analysis at the site location.
impermeable as possible. During
This consisted of a permeability
sand
the hydrogeological study an esti-
study and a geotechnical study of
mate was prepared of the expected
the excavation, together with a
seepage into the sheet pile sup-
bearing capacity study of both
clay ported excavation. It became
bearing and sheet piles. The apparent that to ensure that the
ground consists of a post glacial groundwater seepage remained
solid
sequence approximately 16 m below the stipulated levels it would
sand
thick, overlying a Pleistocene sand be necessary to take additional pre-
sequence. The post glacial cautionary measures.
sequence consists of the following:
Since the aquifer would be under
0 to 3.5 m An impermeable layer hydrostatic pressure, the design
with fine sand on top and clay needed to take into account the
and peat below. possibility of ground heave in the
3.5 to 7.5 m A permanent water lower impermeable layers.
bearing sand strata. The excavation was limited to 6 m
7.5 to 9.0 m A second imperme- below ground to provide sufficient
able, slightly cohesive layer. vertical stability.
9.0 to 13 m The second permanent Heavy drainage of the upper layers,
water bearing sand strata. which are prone to subsidence,
13 to 16 m Finally, an imperme- would result in subsidence of the
able clay which varies in thickness buildings adjacent to the car park.
So, for this reason, it would be
from 3.0 to 3.5 m.
necessary to use a steel sheet piling
cofferdam in the construction of
Below this post glacial layer, the
Fig. 2 the foundations.
pleistocene sequence consists of a
very compact sand. The ground
water level is 1.5 m below the
ground surface.
2.1. Location driving the piles and when dig- Existing public road
Since existing buildings were close ging and draining the excavation. A public road existed on the site
to the proposed site it was neces- It was necessary to phase the pil- before construction started and
sary to take measures to limit the ing work and use low vibration once the car park was completed
noise during pile installation. installation methods together the road would be re-installed on
with an extremely rigid piling sys- the top of the underground part
Railway embankment tem in order to minimise the of the car park. The road was not
The design requirements specified effects on the railway. in use during the construction
that the subsidence of the rails phase but would be used for
had to be minimised as far as pos- Finally, it was necessary to include access on completion. The design,
sible. Special care was taken with measures to avoid increased corro- therefore, had to take account of
regard to subsidence of the rail- sion of the piles as a result of any the normal urban traffic load
way embankment during the con- stray currents in the ground coming expected to use this road.
struction phase, particularly when from the adjacent electric railway.
4 5
3. Design considerations
Two alternative designs were con- with only one level below ground considered as a viable option. This a slight amount of leakage along torted due to water pressure in a water inflow than expected. This
sidered when designing the car was not an attractive proposition structure consists of a car park sup- the interface between the piles flood situation. would only become apparent dur-
park. A closed concrete structure because of the increased floor ported on all sides by steel sheet and the clay, a permanent ing excavation and could originate
and the chosen option, an open area needed. piling that had been driven drainage system has been installed When comparing the two alterna- from the piling interlocks or from
steel piling structure. (Fig. 3) through the clay into the sand. In approximately 0.5 m below the tives on the basis of cost and the pile to clay interface. If need-
Both of these concrete solutions the middle, a separate system of deepest car park level. speed of construction, the open ed, the remedial measures fore-
3.1. Closed concrete structure would also require extensive use bearing piles is also driven into the structure, employing steel sheet seen are grouting behind the piles
A conventional closed concrete of sheet piling in the form of tem- dense sand. The floor for the deepest level was piling, proved to be approximately or into the floor.
structure would consist of a con- porary cofferdams. designed as a thin concrete strut. 15% cheaper than the convention-
crete basement cast in-situ. The In this case, the clay layer and the This floor has a series of openings al concrete option.
thick concrete floor would be set on 3.2. Open structure constructed piling form a near watertight seal in it, in the form of small pave-
concrete bearing piles and provision using steel sheet piling to the basement of the garage ment sections set on sand. These The clients’ design consultants had
would be made at the bottom of Since an impermeable clay layer and have sufficient vertical stabili- allow water to pass through in the recommended that consideration
the structure to prevent lifting. 3.5 m thick exists above the very ty to resist heave due to hydraulic event of the car park flooding and be given to remedial measures
A variant of the same structure dense sand, an open structure was uplift. As there is the possibility of prevent the floor becoming dis- needed in the event of higher
EXISTING BUILDING
stairwell stairwell
Fig. 3
6 7
3. Design considerations
Two alternative designs were con- with only one level below ground considered as a viable option. This a slight amount of leakage along torted due to water pressure in a water inflow than expected. This
sidered when designing the car was not an attractive proposition structure consists of a car park sup- the interface between the piles flood situation. would only become apparent dur-
park. A closed concrete structure because of the increased floor ported on all sides by steel sheet and the clay, a permanent ing excavation and could originate
and the chosen option, an open area needed. piling that had been driven drainage system has been installed When comparing the two alterna- from the piling interlocks or from
steel piling structure. (Fig. 3) through the clay into the sand. In approximately 0.5 m below the tives on the basis of cost and the pile to clay interface. If need-
Both of these concrete solutions the middle, a separate system of deepest car park level. speed of construction, the open ed, the remedial measures fore-
3.1. Closed concrete structure would also require extensive use bearing piles is also driven into the structure, employing steel sheet seen are grouting behind the piles
A conventional closed concrete of sheet piling in the form of tem- dense sand. The floor for the deepest level was piling, proved to be approximately or into the floor.
structure would consist of a con- porary cofferdams. designed as a thin concrete strut. 15% cheaper than the convention-
crete basement cast in-situ. The In this case, the clay layer and the This floor has a series of openings al concrete option.
thick concrete floor would be set on 3.2. Open structure constructed piling form a near watertight seal in it, in the form of small pave-
concrete bearing piles and provision using steel sheet piling to the basement of the garage ment sections set on sand. These The clients’ design consultants had
would be made at the bottom of Since an impermeable clay layer and have sufficient vertical stabili- allow water to pass through in the recommended that consideration
the structure to prevent lifting. 3.5 m thick exists above the very ty to resist heave due to hydraulic event of the car park flooding and be given to remedial measures
A variant of the same structure dense sand, an open structure was uplift. As there is the possibility of prevent the floor becoming dis- needed in the event of higher
EXISTING BUILDING
stairwell stairwell
Fig. 3
6 7
4. Loads to be considered
Horizontal loads
precast concrete
column
The horizontal loads on the structure variable traffic load
include:
• Wind load on the superstructure in air flue
Load transmission Fig. 6 - Sheet pile bending at Y16 due to wind load Fig. 7 - Sheet pile bending at Y12 due to variable traffic load
air flue
precast prestressed
concrete beam
8 9
4. Loads to be considered
Horizontal loads
precast concrete
column
The horizontal loads on the structure variable traffic load
include:
• Wind load on the superstructure in air flue
Load transmission Fig. 6 - Sheet pile bending at Y16 due to wind load Fig. 7 - Sheet pile bending at Y12 due to variable traffic load
air flue
precast prestressed
concrete beam
8 9
5. Calculations Specific aspects 6.
The main calculations used in the The bending stress in the steel Deflection of the sheet piling due 6.1. Surface treatment By welding on rods in certain 6.5. Ventilation provisions
design of the steel sheet piling This falls into two parts: to the soil loading on the railway The exposed parts of the steel spots, it was possible to perform a The ventilation of the under-
The sheet piling serves as both the • The localised bending in the side sheet piling were treated with a controlling measurement after- ground part of the garage was
support to the ground and the piles due to the connection of the The deflection of the sheet piling layer of zinc-rich primer, then a wards. The location of the garage dealt with in two ways:
vertical loads from the structure floor members and the transmis- due to soil loading has been calcu- coat of epoxy primer and finally a was so favourable that no risk of • On the office side of the struc-
above. sion of the vertical load. lated using a programme which is coat of epoxy paint. corrosion due to stray currents ture, 5 ventilation shafts were
The profile chosen was the PU 16 • The bending moment due to the based on bi-linear ground springs was found. formed using sheet piling. Each
type of sheet piling (in steel quali- ground pressure. against the sheet piling. 6.2. Fire protection shaft was 2.5 m x 2.5 m and
ty PAE 250 in accordance with 6.4. Impermeability extended down to the under-
No specific measures were taken
Euronorm quality Fe340 B). Bending of the railway side wall The railway load has been calcu- with respect to fire protection of A sealing product was applied to ground levels from ground level.
on line Y 16 (Fig. 8) lated as an additional horizontal the steel since the exposed sur- the interlocks at the factory and The top of each shaft is protected
Stresses as a result of vertical load The sheet piling showed little or load using the Culmann method. faces were backed by saturated the piles were driven into pre- with a grill
The stresses in the sheet piling no bending due to the vertical or The ground pressure coefficients soil, which would act as good drilled holes filled with bentonite • On the railway side, mechanical
resulting from vertical loads com- floor connection loads transmitted have been based on assumed fail- thermal conductor. cement slurry, down to the clay ventilation was provided via small
prise a normal compressive stress to it. ure surfaces. In use, the steel stress in the sheet layer. This pre-drilling was carried vertical ducts made as part of the
and a local bending stress where piling is very low at 40 N/mm2, out to reduce the vibration and vertical columns. (Fig. 10)
the capping beams are formed at Bending of the office side sheet which is approximately half of the subsidence effects on the sur-
the top of the piling and where piling line Y12, due to vertical maximum value. rounding ground and structures.
the underground floors are fixed load (Fig. 9) However it was thought that pil-
to the walls. A slight decrease in the yield point ing into bentonite cement slurry
The ground floor caused major
of the steel due to the effects of would have a beneficial effect on
bending moments at the head of
Normal vertical force temperature would not affect the sealing the interlocks. Once the
the sheet piling. During the con-
bearing capacity of the sheet pil- excavation was complete the
This consists of the vertical compo- struction phase this was due to
ing significantly. sheet piling wall was grouted to
nent of the ground anchor force the load of the garage roof and,
complete the sealing process.
in the temporary case and the in the permanent condition, from
load of the structure and its con- the heavier load from traffic on 6.3. Corrosion of steel sheet piling
tents in the permanent case. the road on top of the garage by stray electrical currents
roof. In view of the location of the
garage, with its steel sheet piling
close to an electrified railway line,
a study of the possible effects of
stray currents was undertaken.
Stray currents occur as a result of
using the rails as the return for
the electricity used by the trains.
The voltage of these stray currents
depends on the proximity of sub-
stations and the type of ground.
The corrosion effects can be min-
imised by ensuring good conduc-
tivity between the individual piles
and by welding on steel rods at
certain points to act as electrical
earth pathways, which lead the
stray current back to the rails.
Soil pressure (kN/M2) Bending moment (kNM) Displacements [MM] Soil pressure (kN/M2) Bending moment (kNM) Displacements [MM]
gauche gauche
droite droite
Fig. 8 - Sheet pile bending at Y16 due to soil and Fig. 9 - Sheet pile bending at Y12 due to soil and
water pressure water pressure Fig. 10 - Ventilation shaft
10 11
5. Calculations Specific aspects 6.
The main calculations used in the The bending stress in the steel Deflection of the sheet piling due 6.1. Surface treatment By welding on rods in certain 6.5. Ventilation provisions
design of the steel sheet piling This falls into two parts: to the soil loading on the railway The exposed parts of the steel spots, it was possible to perform a The ventilation of the under-
The sheet piling serves as both the • The localised bending in the side sheet piling were treated with a controlling measurement after- ground part of the garage was
support to the ground and the piles due to the connection of the The deflection of the sheet piling layer of zinc-rich primer, then a wards. The location of the garage dealt with in two ways:
vertical loads from the structure floor members and the transmis- due to soil loading has been calcu- coat of epoxy primer and finally a was so favourable that no risk of • On the office side of the struc-
above. sion of the vertical load. lated using a programme which is coat of epoxy paint. corrosion due to stray currents ture, 5 ventilation shafts were
The profile chosen was the PU 16 • The bending moment due to the based on bi-linear ground springs was found. formed using sheet piling. Each
type of sheet piling (in steel quali- ground pressure. against the sheet piling. 6.2. Fire protection shaft was 2.5 m x 2.5 m and
ty PAE 250 in accordance with 6.4. Impermeability extended down to the under-
No specific measures were taken
Euronorm quality Fe340 B). Bending of the railway side wall The railway load has been calcu- with respect to fire protection of A sealing product was applied to ground levels from ground level.
on line Y 16 (Fig. 8) lated as an additional horizontal the steel since the exposed sur- the interlocks at the factory and The top of each shaft is protected
Stresses as a result of vertical load The sheet piling showed little or load using the Culmann method. faces were backed by saturated the piles were driven into pre- with a grill
The stresses in the sheet piling no bending due to the vertical or The ground pressure coefficients soil, which would act as good drilled holes filled with bentonite • On the railway side, mechanical
resulting from vertical loads com- floor connection loads transmitted have been based on assumed fail- thermal conductor. cement slurry, down to the clay ventilation was provided via small
prise a normal compressive stress to it. ure surfaces. In use, the steel stress in the sheet layer. This pre-drilling was carried vertical ducts made as part of the
and a local bending stress where piling is very low at 40 N/mm2, out to reduce the vibration and vertical columns. (Fig. 10)
the capping beams are formed at Bending of the office side sheet which is approximately half of the subsidence effects on the sur-
the top of the piling and where piling line Y12, due to vertical maximum value. rounding ground and structures.
the underground floors are fixed load (Fig. 9) However it was thought that pil-
to the walls. A slight decrease in the yield point ing into bentonite cement slurry
The ground floor caused major
of the steel due to the effects of would have a beneficial effect on
bending moments at the head of
Normal vertical force temperature would not affect the sealing the interlocks. Once the
the sheet piling. During the con-
bearing capacity of the sheet pil- excavation was complete the
This consists of the vertical compo- struction phase this was due to
ing significantly. sheet piling wall was grouted to
nent of the ground anchor force the load of the garage roof and,
complete the sealing process.
in the temporary case and the in the permanent condition, from
load of the structure and its con- the heavier load from traffic on 6.3. Corrosion of steel sheet piling
tents in the permanent case. the road on top of the garage by stray electrical currents
roof. In view of the location of the
garage, with its steel sheet piling
close to an electrified railway line,
a study of the possible effects of
stray currents was undertaken.
Stray currents occur as a result of
using the rails as the return for
the electricity used by the trains.
The voltage of these stray currents
depends on the proximity of sub-
stations and the type of ground.
The corrosion effects can be min-
imised by ensuring good conduc-
tivity between the individual piles
and by welding on steel rods at
certain points to act as electrical
earth pathways, which lead the
stray current back to the rails.
Soil pressure (kN/M2) Bending moment (kNM) Displacements [MM] Soil pressure (kN/M2) Bending moment (kNM) Displacements [MM]
gauche gauche
droite droite
Fig. 8 - Sheet pile bending at Y16 due to soil and Fig. 9 - Sheet pile bending at Y12 due to soil and
water pressure water pressure Fig. 10 - Ventilation shaft
10 11
Evaluation 8.
8.1. Impermeability
The requirements stipulated with
regard to permanent drainage
12 13
Evaluation 8.
8.1. Impermeability
The requirements stipulated with
regard to permanent drainage
12 13
1 2 3 4 5
6 7 8 9 10
11 12 13
References of underground car parks 10.
Court Münster D picture 1
Congress Centre Amsterdam NL picture 2
House for dentistry Münster D picture 3
Malieveld Den Haag NL picture 4
KLM Amstelveen NL picture 5
City hall Rouen F picture 6
Münsterstrasse Düsseldorf D picture 7
Marketsquare Coesfeld D picture 8
World Trade Center Amsterdam NL picture 9
Haute ville Rouen F picture 10
Royal Christiana Hotel Oslo N picture 11
VROM Den Haag NL picture 12
Zwolsestraat Scheveningen NL picture 13
14 15
1 2 3 4 5
6 7 8 9 10
11 12 13
References of underground car parks 10.
Court Münster D picture 1
Congress Centre Amsterdam NL picture 2
House for dentistry Münster D picture 3
Malieveld Den Haag NL picture 4
KLM Amstelveen NL picture 5
City hall Rouen F picture 6
Münsterstrasse Düsseldorf D picture 7
Marketsquare Coesfeld D picture 8
World Trade Center Amsterdam NL picture 9
Haute ville Rouen F picture 10
Royal Christiana Hotel Oslo N picture 11
VROM Den Haag NL picture 12
Zwolsestraat Scheveningen NL picture 13
14 15
Sheet Piling
66, rue de Luxembourg
L - 4221 Esch-sur-Alzette (Luxembourg)
Tel.: (+352) 5313 3105
Fax: (+352) 5313 3290
E-mail: sheet-piling@arcelor.com
Internet: www.sheet-piling.arcelor.com
Ste
el
Sh
ee
tP
ilin
g
Un
de
rgr
o
Th und
eH C
ag ar P
ue ark
4-12-03-1-E