You are on page 1of 2

1.2.

Dumpling Method of Basement Ex Sections


3. Basement & waterproofing method Dumpling Method of Basement What the Basement Illustrated diagram – External External tanking is the process of Material Use in Upper Floor const.
4.5 External tanking method-Base.Exc. Excavation Basement is a story below the tanking method - Basement sealing the outside of a building or Timber, Steel, Precast Concrete,
6. Material use in upper floor Constru. ground level of a building. Basement substructure in order to protect it R.C.C. floors
6.7. Single joist timber floor A series of retaining walls are are constructed to increase the floor from water ingress, flooding, and
8. Foundation Diagram-Low rise completed in the trench, section by area of the building without other water damage. Plan of Single joisted timber floor
building in a slope ground section around the site perimeter increasing the foot print or ground
9.Types Pile Foundati. (material used) leaving the center Dumpling. used to the building Advantages
/ Cross Section For steel piles When walls are completed, 1. Protects the concrete from
10. Advantages & Disadvan. Steel Pile/ excavate at the center of the Basement waterproofing method aggression
Material used upper floor construction dumpling until expose the section of Dense monolithic concrete, Tanking 2. Protects the r/f from aggression
11. Advantages & Disadvantages pre- the wall. techniques, Drained cavity system elements
cast Concrete floors Then the wall side is supported by
12. Annotated steel roof truss shoring. Use of Basement
diagram span up to 10m Again excavation continues section Boiler, A/C system, Car Park
13.14 Truss Design to daylight in to by section until all is completed.
building (30) 1 2 3 4 5 6 7
Truss Design to daylight into 15. Different formwork & False

Annotated steel roof truss diagram span up to


Foundation Diagram-Low rise Types of pile foundations according Advantages of Steel Pile Advantages pre-cast Concrete floors building work / Good Properties formwork
building in a slope ground to their material used in Eliminate need of formwork, No 16. Different types of scaffoldings
construction Bearing capacity is high, Can take up curing time, can use soon after 17. Annotated Diagram Typical
lateral loads, can resist impacts, completed, Good quality control in Cantilever scaffold
Stepped Timber Piles, Concrete Piles (Cast in- Handling & driving is easy, cannot factory production 18. Basic types of shoring used in
Footing situ, Precast), Steel piles, Composite attack by insects. Construction work/ Situations that
Piles Disadvantages underpinning is required in
Disadvantages of Steel Pile Less flexible in designs, High degree building / Advantages of mass fill
Cross Section For steel piles Corrosion can be affected, Cost will of site accuracy is required, Openings conc. Underpinning
be high for anti-corrosive paintings. such as stair wells are to be done with 19. Diagram of Mass fill concrete
cast in-situ concrete. underpinning
Material used in upper floor 20. Diagram of typical suspended
construction ceiling grid work
Timber, Reinforced cast in-situ 21. Bentonite & It use the in

10m
concrete, Precast concrete, Steel. trench excavation

12
8 9 10 11 13 14 22. Dewatering methods
Diagram of Mass fill concrete

Diagram of typical suspended ceiling grid work


Different formwork & Falsework Different types of scaffoldings Annotated Diagram Typical Basic types of shoring used in underpinning Bentonite & It use the in trench Temporary Dewatering
Formwork is a mould used to support Single Scaffold, Double or Independ Cantilever scaffold Construction work excavation methods
fresh concrete and retain its shape Scaffold, Cantilever scaffold, Suspend Ranking shore, Horizontal or flying Bentonite available in powdered Simple sump pumping, Jetted
and size until it attains sufficient scaffold, Truss-out scaffold, Mobile shore, Vertical or dead shore form, when add water to pump, Well point system
strength to support itself Scaffolds bentonite powder a viscus fluid
Situations that underpinning is which have gel property. When Permanent Dewatering methods
Good Properties of formwork required in building the clay particles are mixed with Thin grouting membranes,
It should strong enough to resist the Uneven settlements, Increase in bentonite, increase the stability Contiguous or secant piling,
pressure and weight and loadings, Lowering of adjacent of excavation side walls. Diaphragm walls, grouting
superimposed loads, It should strong ground methods, Ground freezing
enough to retain shape without
excessive deformations, It should be Advantages of mass fill conc.
economic in cost, It should be able to Underpinning
easily fixed and remove Construction is simple, Low-cost
labor, Continuity of structures are

20
15 16 17 good 18 19 21 22
23. Diagram Contiguous/Secant Pile Friction Pile/Floating Pile 29. Methods used to overcome
24. Internal tanking method-Baseme. Disadvantages of Internal Tanking Classify piles according to their the problem of lateral forces
25. Disadvantages of Internal This will not give protection to the functions acting on high-rise building
Tanking / Name Column foundation main structure, by high hydrostatic End bearing pile, Friction pile, 30. North Light & Monitor truss
suitable for a medium-rise building / pressure waterproofing layer can be Batter pile, Under reamed Pile Advantages & Disadvantages (13)
Classify piles according to ground forced away 31. Functions of Upper floors
effect when they are driving into the 32. Steps to reduce the cost of
ground Name Column foundation suitable formwork
26. Isolated Pad (column) footing for a medium-rise building 33.34. Suitable shoring method
27. Classify piles according to their Isolated Pad Footing that can be used in the
functions construction of a new door
28. Friction Pile/Floating Pile Dia. Classify piles according to ground opening in an existing wall (Dead
(pile type suitable for ground which effect when they are driving into the Shoring)
cannot found firm strata ground 35. Building weak & Cannot take
Considerable economical depth) Displacement and Non-Displacement structural loads. firm strata not
piles available shallow depth
23 24 25 26 27 28 underneath of existing foundation
Rigid Frames – Rigid jointed frames North Light Functions of Upper floors Steps to reduce the cost of formwork Suitable shoring method that can be Needle and Pile underpinning
with moment resisting connections Ad – Good rain water run off Provide a level surface with sufficient Formwork should designed provide used in the construction of a new
between beams and columns Dis – Amount of daylight depend on strength to support to dead loads sufficient strength and rigidity, But door opening in an existing wall
orientation and imposed loads, Reduce heat loss should not over designed, Should be Dead Shoring
from lower floors as required, fabricated modular sizes to allow
Monitor Truss Provide required degree of sound more re-use, working drawings Dead shoring is placed vertically to
Ad – Light not affected by the insulation, Provide required degree should be prepared before support the wall during removing of
orientation of fire resistance fabrication, The components to be the lower part of the wall to
Shear Walls – are vertical elements of Dis – Poor rain water runoff pre-fabricated on the ground, Select introduce door opening
the horizontal force-resisting system economical and re-useable materials,
Nut and bolt systems are to be used,
Forms to be removes as soon as
possible, Forms should cleaned and
oiled after each use.

29 30 31 32 33 34 35

You might also like