You are on page 1of 6

IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 36, NO.

5, SEPTEMBER/OCTOBER 2000 1449

New Life for Old Thyristor Power Rectifiers Using


Contemporary Digital Control
Paul Buddingh, Member, IEEE, and Jack R. St. Mars, Member, IEEE

Abstract—This paper presents information on a control and


monitoring system retrofit of two unreliable 1978 14-MW recti-
fiers used in a sodium chlorate plant. Reasons for the upgrade and
expectations of the new system are discussed. Alternate solutions
considered and the rationale supporting the choices made are
reviewed. The paper summarizes the project from the initial in-
vestigation through the design process and selection of equipment.
Justification of the expenditure, issues of mating old and new
equipment, problems overcome during the implementation, and
the lessons learned are described. In closing, the suitability of this
approach for other rectifier installations is addressed.
Index Terms—Industrial power rectifier, upgrade.

I. INTRODUCTION
Fig. 1. Beauharnois rectifiers.

A PPROXIMATELY 20 power rectifier systems with ratings


of 8–34 MVA are operated and maintained in the North
American plants of CXY Chemicals. Seven manufacturers are II. EXISTING EQUIPMENT
represented and ages range up to 42 years. The dependability of The plant operates two 52-kA 275-Vdc output 13.8-kV input
1970s first-generation thyristor power rectifiers has been partic- industrial-type outdoor water-to-air cooled rectifiers, each sup-
ularly troublesome relative to the diode machines of the same plied with a close-coupled forced-air-cooled oil-insulated trans-
period and present-day thyristor rectifiers. The worst of these former (Fig. 1). The circuit design is ANSI 45/46 with inter-
older thyristor units require costly ongoing repairs. Production phase transformer. Two rectifier cabinets are attached to each
losses have been substantial with repeated failures and extended transformer, each containing a single-way three-phase thyristor
downtime, particularly during periods of full-load production. bank. As the two three-phase transformer windings supplying
To maintenance personnel fighting repeated battles to keep the the rectifier cabinets are phase shifted, the combined output of
equipment running, the effect on morale has been negative. De- the two cabinets is six-pulse. The single-way rectifiers consist
spite all this, convincing management to replace the equipment of two legs per phase with each leg containing 12 thyristors for
based on poor reliability alone is seldom successful due to the a total of 144 per rectifier system.
high capital cost and lengthy production outages. Controls were original first-generation electronic design
Increasing the plant’s product output was the key element in utilizing discrete analog components with gate drive and
obtaining funding for this project. isolator cards mounted in the power cabinet. Trigger amplifier,
This case study of the owner’s Beauharnois plant near Mon- gate drive, dc CT electronics, auxiliary relays, fan controls, and
treal, PQ, Canada, summarizes how increased output and reli- the majority of the control system were placed in the control
able production were achieved at a reasonable cost without re- cabinet at the end of the rectifier enclosure. Operator interface
placing the rectifiers. cards, meters, and an alarm panel were all located in the remote
operator control room located 300 ft from the rectifier.
Each 52-kA rectifier system powers a separate production
line, is controlled by its own HV circuit breaker, and is equipped
Paper PID 00–9, presented at the 1999 IEEE Petroleum and Chemical In- with its own alarm panel and control station.
dustry Technical Conference, San Diego, CA, September 13–15, and approved
for publication in the IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS by the
Petroleum and Chemical Industry Committee of the IEEE Industry Applications
Society. Manuscript submitted for review September 15, 1999 and released for
III. REASONS FOR UPGRADE
publication May 5, 2000.
P. Buddingh is with Universal Dynamics Ltd., Richmond, BC V6V 2X8
A. Control System Electronics
Canada (e-mail: pbuddingh@udl.com). Aging analog control electronics were particularly trouble-
J. R. St. Mars is with CXY Chemicals, North Vancouver, BC V7H 1S4
Canada. some. After some 20 years of operation, repeated failures of
Publisher Item Identifier S 0093-9994(00)07615-5. random components were typical of the final portion of the
0093–9994/00$10.00 © 2000 IEEE
1450 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 36, NO. 5, SEPTEMBER/OCTOBER 2000

Fig. 2. Control cabinet prior to removal of old controls. Fig. 3. Original power section.

bathtub-shaped reliability curve often used to describe elec- matching of components, and made uniform load-sharing inher-
tronic components (Fig. 2). The manufacturer was no longer ently difficult. One solution utilized was the purposely designed
in business and replacement parts were not readily available. bus and balancing reactor design.
Detailed drawings of existing components had degraded over On occasion, replacement of up to 24 thyristors per leg and
time; reverse engineering and outsourcing of replacement an equal number of fuses was required, a costly repair, not to
cards were costly and time consuming. Many repairs required mention the downtime required to complete the repairs.
specialized knowledge, not available locally. As the accuracy and precision of the gating (firing) signals
Automatic load control was inoperable. The operators simply strongly affect current sharing and the rectifier’s total output ca-
adjusted potentiometers in response to process changes. De- pability, the unreliability of the aging control components fos-
mand control consisted of an audible warning that signaled the tered power section component failures.
operator to reduce load via the potentiometer. Investigation of the rectifier repair history established a close
Similarly, the integrity of the fuse/thyristor failure monitoring correlation between each case of multiple thyristor failure and
system was questionable at best, making identification of failed an electronic control system problem.
components a laborious process. When faced with failures or
impending problems, the electricians had to shut down the rec- C. Maintenance Expertise
tifier and manually check the condition of cards, and up to 144
In the past, plant personnel have lacked technical insight into
fuses and thyristors. Furthermore, without a first-out thyristor
equipment operation and preventive maintenance. With the re-
alarm, the operator would not know that load needed to be re-
cent emphasis on improving reliability and plant production
duced to protect the remaining thyristors. This greatly increased
levels, maintenance electricians have become quite adept at re-
the probability of cascade failures and rectifier outages.
pairing the electronics with the limited resources available. Nev-
B. Repeated Failures of Power Thyristors ertheless, the frustrations of recurring failures with no solution
in sight were counterproductive to the morale of those trying to
Over the years, the makeup of fuses and thyristors had be- keep the equipment operating.
come a mix of manufactures with unmatched characteristics. As
well, both the integrity of the fuses due to aging and of the con- IV. EXPECTATIONS OF UPGRADE
nections due to varying assembly methods had degraded. As a
result, thermal and current-sharing problems arose among the The needs for the rectifier upgrade were established as fol-
24 thyristors per phase (Fig. 3). It is noted that equal current lows.
sharing is critical for continued operation of the thyristors. If 1) 105% of full-load rating of the rectifier must be achieved
one thyristor conducts much more than its rated current, it will with reliability. On occasion, the plant had operated at
eventually fail by overheating. As thyristors fail, the remainder 105%, but at the expense of rectifier failures.
are forced to share the load and additional thyristors are stressed, 2) Good operating reliability must be achieved. This was
creating a cascade effect. Massive paralleling was a technolog- defined as reducing or eliminating unscheduled outages
ical necessity at the time of manufacture and demanded careful to the point where production levels were unaffected.
BUDDINGH AND ST. MARS: NEW LIFE FOR OLD THYRISTOR POWER RECTIFIERS 1451

3) The upgrade must provide the knowledge, documenta- The operator interface consisted of a partially functional
tion, and continuing parts supply to undertake any needed alarm panel, broken trend recorders, and worn manual poten-
troubleshooting in house. tiometer that all needed replacement.
4) Outside technical support must be readily available.
5) A new system must fit into the existing control cabinet; C. General Improvements
the firing and fuse monitoring equipment must mate up to The local attitude and level of interest in implementing an
the columns in the power cabinets. The operator interface engineered solution were excellent. Knowledge of fundamental
must be compatible with the old control panel. aspects of maintaining a power rectifier system was lacking.
6) The plant downtime to install the new equipment should Education was required in the following areas:
be limited to ten days per rectifier. 1) importance of and frequency of monitoring the dissolved
7) One rectifier per production line must be kept operating gases in the rectifier transformer oil and monitoring tem-
during the upgrade of the other. peratures of the rectifier power cabinet components;
The following “want” list evolved. 2) correct methods for installing replacement thyristors and
1) A digital control system was desirable for its stable oper- fuses;
ation and ability to deliver precise thyristor firing timing, 3) importance of matching fuses and thyristors mounted in
a serious shortcoming with the existing controls. the same leg.
2) Implementation of the control system in software with
user-friendly programmable parameters was needed. The D. Gaining Corporate Approval
software should include online diagnostics to allow plan- Approval for the expenditure hinged on the payback of a pro-
ning for scheduled repair outages. duction improvement. The compelling question was whether the
3) The control system would automatically monitor the con- system was capable of additional output. Evaluation of the trans-
dition of the thyristor fuses and be set to alarm, reduce formers and cooling system history indicated that overheating of
load, and trip the system based on the number of thyristor the system was not a serious problem. New, precise control of
circuit failures. thyristor firing and careful matching, installation, and thermal
4) Troublesome auxiliary relays, meters, and interface de- monitoring of components would provide better balance and
vices would be replaced with a digital graphical interface improved operating temperatures. A first-out or high-tempera-
displaying metering, alarm, and control information. ture alarm and automatic cutback in case of a thyristor failure
would likely allow 105% output without impacting long-term
reliability.
V. CONSIDERATIONS
Early in the project cycle, the restrictions on available capital VI. SELECTION OF NEW EQUIPMENT
meant a creative approach would be required to meet the expec- With the viability of the rectifier power section, auxiliaries
tations of the plant. and, particularly, the transformers reasonably assured, the next
The need to examine the feasibility of a partial retrofit be- step was deciding what type of system to select and how to im-
came evident in the early stages of the project. Several essential plement it.
questions required answers to ensure a successful result.
A. Upgrade Options
A. What Is Reusable? 1) Replace complete rectifier/transformer systems.
2) Retain transformers and replace rectifiers.
The major unknown at the beginning of the project was the
3) Replace the control, firing, and fuse monitoring electronic
continued viability of the rectifier transformers. The condition
systems.
of these costly units was a major criterion for a successful
4) Replace power section fuses and thyristors in addition to
retrofit. Current and past dissolved gas analysis reports and
the electronics.
an internal inspection helped to confirm the integrity of the
Options 1) and 2) were too expensive. Option 3) was nec-
transformers.
essary; option 4) was desirable, but optional. Implementing
The power section of the rectifier was in surprisingly good
a power section upgrade at a later date would be possible by
condition despite the repeated thyristor failures. The thyristors
careful selection of an equipment vendor at this time.
and fuses, although unmatched, were of a style in current usage
Next was the selection of the most appropriate system
and commonly available.
from the marketplace. After going out for quotations, choices
Auxiliary components of the rectifier, including the cabinets,
included custom-designed systems as proposed from several
heat exchangers, plumbing, and fans were also in satisfactory
engineering companies or adapting a system from an estab-
condition.
lished rectifier manufacturer.
The rationale for the selection included the following:
B. What Should Be Replaced?
1) experience with similar system at other company-owned
The operating history of the plant clearly indicated the neces- plants;
sity of replacing the control electronics with something main- 2) proven reliability;
tainable. 3) vendor support;
1452 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 36, NO. 5, SEPTEMBER/OCTOBER 2000

4) ease of reconfiguring, maintaining, and troubleshooting;


5) availability of local support;
6) compatibility with a possible future upgrade of the power
section.
The owner had purchased several new rectifiers from the
same manufacturer in the past several years at competitive
prices, with positive results. Accordingly, it was decided
to order a semi-custom equipment package from the same
manufacturer. In this instance the term “semi-custom” refers
to the vendor’s standard equipment packaged in a custom
arrangement designed to fit into the existing rectifier design.
The owner elected to purchase new controls, gate drive and
fuse monitoring systems. A remote digital operator interface
completed the system.

B. New System
The new equipment consists of controls, gate drive panels,
fuse monitoring circuits and a remote digital operator interface.
The control panel mounts on a wall within the control cab-
inet. The heart of the system is an industrial 486 PC running an
RMX operating system. RMX is a real-time operating system Fig. 4. New main control panel.
that is designed to improve reliability for industrial automation
applications. Control system program changes are accessible by
a laptop computer that modifies “sequencer” software, a soft
PLC-type ladder logic. A keypad is available for normal control
functions in local mode.
Each rectifier control is provided with a current regulator of
the proportional and integral (PI) type designed to control two
six-pulse rectifiers. Each three-pulse side of a rectifier uses the
controls for a six-pulse system due to uncertainties in the orig-
inal design to acquire optimum control and balance. The sides
are designated “A” and “B.”
The current regulator operates with a fast inner feedback loop
and a slower outer loop. The regulator has a direct input to sup-
press firing signals. By going directly to the regulator, a very fast
method of stopping firing under fault or emergency conditions
results. In fact, the manufacturer’s tests indicate this action will Fig. 5. New gate drive/fuse monitor panels.
stop firing faster than the primary 15-kV breaker can open if a
tripping signal occurs.
The annunciator is equipped with 160 programmable and A CRT mounted in a shielded box recessed into the control
128 predefined points for faults and alarms. Diagnostics include console displays control, metering, and alarm information to the
predefined and programmable annunciator messages displayed operator.
on an LCD display. I/O consists of digital and analog inputs 1) Main Control Panel (Fig. 4): The supplier built their stan-
and outputs. Up to 20 “meters” and 16 “status lights” can be dard PC-based control system on a custom two-piece flat
programmed and displayed in graphical format on the display. panel approximately 7.5-ft high by 4.5-ft wide and 16.5-in
Firing uses a 120-electrical-degree pulse train to eliminate depth, designed to fit on a vacant wall of the walk-in con-
thyristor turn-on failure. For electrical immunity, fiber optics trol cabinet. CPU, firing interface, I/O, metering, protec-
are used to transmit the firing signals. tion, and the fiber-optic gating signals and control inter-
The control system is shielded and equipped with an LCD face attach to this panel.
display and minimizes the effects of the surrounding magnetic 2) Gate Drive and Protection Assembly (Fig. 5): Gate drive,
field and EMI/RFI. fuse monitor, and protection panels for each leg attach at
The gate drive, fuse monitor, and protection circuits for each floor level behind a clear acrylic cover. Pilot fuses mi-
leg (total of six per rectifier) are mounted on panels attached to croswitches and gate leads fasten on vertical glass fiber
the base of the columns in the power cabinet. columns replacing the old columns which supported the
A fiber-optic serial interface connects the control system to gate protection cards (Fig. 2).
the remote digital input panel, where a keypad is mounted for 3) Operator Interface (Fig. 6): The operator interface con-
operator input signals. The remote digital input panel is mounted sists of a main breaker close/trip switch, E-stop, keypad,
behind the existing operator control console. and computer CRT monitor. The single CRT displays in
BUDDINGH AND ST. MARS: NEW LIFE FOR OLD THYRISTOR POWER RECTIFIERS 1453

must extend from the phase reference supply through the


control to the gate on each thyristor. Measuring each gating
signal for the correct 1-A dc pulse of 120 electrical degrees
assures the correct signal to each thyristor. Synchronization
was confirmed using a dummy load. Finally, the rectifiers were
operated with the process load; first in “test mode” to determine
the feedback scaling, polarity, and load time constant, then
switching to automatic and fine-tuning step response and gain.
The first rectifier was equipped and commissioned within the
scheduled time. The second unit took 15 days or half the time
of the first.

VIII. REFLECTIONS AND COMMENTS


One of the more perplexing problems that surfaced during
commissioning affected the fiber-optic firing circuits. Discon-
necting the fiber-optic connections one sunny day to complete a
test, the power supplies to the gating circuit were inadvertently
left on. Suddenly, one member of the team smelled the distinc-
tive odor of smoking electrical parts. Sunlight shining through
an open rectifier door had turned on the gating circuits via the
open optical connection. The gating circuits designed for a 1/3
Fig. 6. Installation complete. duty cycle had failed when turned fully on for several minutes.
Fortunately, damage was limited to several power resistors.
graphical format all metering, alarm, and control infor- Limitations of field test equipment prevented the testing of
mation. It replaces numerous chart recorders, panel me- the short length [7.6 m (25 ft)] of fiber-optic cables used to de-
ters, and a panel alarm. A VGA display extender ampli- liver gating pulses to the thyristors. On startup, several of the
fies VGA signal from the LCD display in the rectifier con- cables were found to be defective, likely from lack of care in
trol cabinet and displays an identical image on the remote handling when they were removed and repulled into the con-
CRT through a multiconductor coaxial cable. The keypad trol box. As the cable size and connector type were an older
connects to the remote digital input panel I/O card and a standard, connectors were in short supply. Accordingly, repairs
fiber-optic modem transmits the signals to the main con- involved both the retermination of existing and installation of
trol system located in the rectifier. replacement cables.
The VGA extender system used to transmit graphical images
to the operators control console from the main control resulted
VII. INSTALLATION
in a low-cost solution without the expense of a separate
The list of direct participants included the project manager, human–machine interface (HMI) system. Actual operator
consultant, installation contractor, plant project engineer, plant inputs were accomplished with a very robust keypad/digital
maintenance electricians, and process and production staff. To I/O/fiber-optic modem system. With the plant expecting to
upgrade one rectifier while keeping the second in service re- install a distributed control system (DCS) system the following
quired a concerted effort by all members of the team. Control year, switching the graphics over to the DCS is under consid-
systems of the two believed to be independent rectifiers turned eration.
out to be interconnected, requiring a methodical procedure to The original control used a number of auxiliary relays and
decommission and install the new equipment. switches to interface control, alarms, and monitoring signals.
The original schedule called for the installation during The new system eliminated most of these devices. Nevertheless,
a period of low production demand. A relatively leisurely corrosion and wear in the few that remained caused most of
schedule was called for with an installation contract based on a the startup difficulties. In retrospect, replacing all these devices
three-week cycle for each rectifier, two five-day weeks to install would have resulted in a smoother startup.
the equipment, and one week to start up and commission each Benefits of the new control system include better balance,
system. Typically, when the installation period approached, slightly cooler transformers, and greatly reduced thyristor fail-
production demands changed and the careful scheduling ures due to tighter control.
became redundant. The plant has adopted a structured procedure to procure, in-
Several meetings later, it was decided to use the original stall, and monitor thyristors and fuses to help ensure current bal-
schedule for the first rectifier and speed up the work on the ance and minimize future thyristor failures. Matching sets of
second unit once all the difficulties were discovered and thyristors and fuses for each leg was critical for the planned in-
resolved. crease in output.
Commissioning consisted of wiring checkout, preliminary Digital control and the use of fiber optics improved the accu-
system checks, and correct phasing tests. The phasing checks racy and precision of firing. Matching of components and en-
1454 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 36, NO. 5, SEPTEMBER/OCTOBER 2000

suring proper operation of the cooling systems all contributed The continued reliable operation of the rectifiers will depend
to additional output through incremental improvements. on closely monitoring temperatures and transformer dissolved
On the final day of commissioning, the rectifiers reached full gas levels. Summer 1999 ambient temperatures at the plant will
load and the load was increased to 105% the following day. The approach 100 F (40 C) and will provide valuable information
rectifiers have run constantly since that time, except for one con- on the ability to run at extended output year round.
trol card that failed due to infant mortality.
REFERENCES
IX. SUITABILITY FOR OTHER APPLICATIONS
[1] R. Bernadelli et al., “Control modernization of SCR rectifiers with con-
This application is suitable for similar thyristor rectifiers tinuous device current monitoring,” in Conf. Rec. IEEE PCIC, vol. PCIC
when seeking improved reliability with limited funds. To help 97-19, 1997, pp. 183–190.
[2] R. L. Doughty et al., “Optimum electrical system design for a modern
assure a successful outcome, the following considerations are Chlor-Alkali plant,” Conf. Rec. IEEE PCIC, vol. PCIC 88-51, pp.
applicable. 139–150, 1988.
[3] Power Converter Handbook, Canadian General Electric Co. Ltd., 1976.
1) The condition of the rectifier transformers is critical. A [4] USA Standard Practices and Requirements for Semiconductor Power
rewind or major repair is costly and time consuming. Rectifiers, IEEE Std. 34.2, 1968.
Usually custom-built, with a complex configuration, [5] Megaverter Instruction Book, vol. MI-7805, Oxymetal Industries Corp..
these transformers are very difficult to source with
suitable specifications on the “used” market.
2) A history of dissolved gas analysis, preferably with an
internal inspection, is very helpful during the decision-
Paul Buddingh (S’89–M’90) received the B.Eng.
making process. Records from the original manufacturer degree in electrical engineering from Lakehead
can provide valuable design information in order to eval- University, Thunder Bay, ON, Canada.
uate the transformers additional output capacity. Following graduation, he spent several years
working out of Toronto, ON, Canada, as an electrical
3) Condition of the enclosure, cooling systems, balancing consulting engineer working in heavy industry,
reactors, maintenance history, operating environment, primarily in the electrochemical field. In 1991, he
and the original rectifier design constraints are all im- co-founded Mirus International, where he applied
a new magnetic approach to solving zero-sequence
portant considerations. In some cases, it may actually be harmonic problems in low-voltage systems. In 1997,
less expensive to replace the rectifier and/or transformer. he joined Universal Dynamics Ltd., Vancouver,
4) In order to sustain the intended long-term operation of a BC, Canada, where his work is centered on designing high-reliability power
systems, power conversion issues, and resolving power system problems for a
retrofit, emphasize the need for plant stakeholders to take number of industrial clients. He has authored a previous paper for the Petroleum
ownership and understand the importance of performing and Chemical Industry Committee of the IEEE Industry Applications Society.
preventive maintenance, stocking sufficient spare parts, Mr. Buddingh is a Registered Professional Engineer in the Provinces of On-
tario and British Columbia, Canada.
and maintaining technical support contacts.

X. CONCLUSION
The feasibility study was completed in the summer of 1997,
and the upgrade was completed in the fall of 1998. Jack St. Mars (M’88) is a native of Vancouver, BC,
To date, plant operation has proven that reliable performance Canada. He received the Diploma of Technology in
Electrical Power Engineering from British Columbia
and increased output are achievable on a problematic early-de- Institute of Technology, Vancouver, BC, Canada, in
sign thyristor power rectifier. 1971.
By installing up-to-date digital controls supported by the im- Following graduation, he worked in commercial
electrical consulting for one year. In 1972, he began
plementation of practical preventive maintenance methods, a his career in the electrochemical industry with
successful retrofit has met the requirements of the project. Hooker Chemicals, which later became CXY Chem-
Lower capital requirement of the upgrade versus replacement icals, North Vancouver, BC, Canada. He is currently
responsible for providing electrical engineering
made the difference between corporate approval and having to support for the maintenance and upgrade of power distribution, rectifier, and
stay on the path of reactive repairs and extended downtime. harmonic filter systems at seven company-owned electrochemical plants.

You might also like