OHTL Relocation Plan (April 18 2021)
OHTL Relocation Plan (April 18 2021)
24 Half Moon BSP ~ Dhahran South BSP 380 kV OHT CKT A (Portion III ) 28-Jan-21 17-Feb-21
20-Aug-21 1-Oct-21 15-Nov-21 21-Dec-21 36.00
25 Half Moon BSP ~ Dhahran South BSP 380 kV OHT CKT B (Portion III ) 19-Feb-21 11-Mar-21
30 Dismantling of Existing Dhahran Central 230/69 kV S/S August 2021 December 2021
380, 230 & 69 kV OHTL's Relocation Plan from Ajyal District
Date: March 8, 2021
Dependency / Remarks
Completed
Completed
OHTL dismantled except 1 tower to be removed once the new MAD tower installed
Simultaneous D/C Outage is required to complete the activity. Depending the completion of
Midra and NSIF 69kV lines dismantling.
Simultaneous D/C Outage is required so that work can be finished safely than single circuit
outages
Depending in completing 230 kV & 69kV OHTL need to be dismantled [S. No. 15-20 above]
Simultaneous D/C Outage is required to complete the activity as both circuits are in the same
tower so that work can be finished quickly and safely than single circuit outages
Simultaneous D/C Outage is required to complete the activity as both circuits are in the same
tower so that work can be finished quickly and safely than single circuit outages
Depending on the relocation of all 230 & 69 kV OHTL to New Dhahran Central S/S