ጥቅምት 2010
1 Introduction
The government of Ethiopia has planned and allocated budget to expand the electricity access
of the country to 90% within the growth and transformation year’s period (i.e. from 2008 to
2012 E.C). In past two years the number of electrified villages is 993 (398 in 2008 and 595 in
2009 budget year) . UEAP has planned to electrify 618 rural towns and villages in 2010 budget
year.
As per the instruction of the Ministry of Water and Energy and EEU , UEAP is expanding the
scope of distribution network construction to resolve the gap between Electric Access coverage
and the no.of connected EEU customers by including KWH meter installation in electrified
villages and in planned villages within the budget year.
61,800 service cable installation and Single phase KWH meter installation to households
and service centers within the newly electrified villages by Government/EEU budget
410,000 service cable installation and KWH meter installation for towns under the
densification project financed by World bank and AfDB.
Therefore this document is prepared to propose an affordable flat-rate cost for meter
connection for the community in rural villages. The proposal was prepared for installation,
transportation and material cost per house hold /service center. The category factors are
applicable on construction cost based on the village environmental condition.
2 Objective
The main objective of this document is to :-
Provide affordable meter connection cost by applying flat-rate cost which gives an
opportunity to the community to have unified cost within the range up to 25mt from
nearby LV Pole.
Provide a cost of meter connection for households >25mt from nearby pole which
requires additional pole and other related costs.(optional)
Provide Cost for Outsourcing purpose of the Service cable installation.(optional)
3 Scope
To set flat-rate cost for:
Service cable connection and KWH Meter installation total cost (for customer )
UEAP woreda coordination office mobilize all resources needed for installation of meter
connection (like materials, vehicles, tools …etc) to site technician/Mounter with average
distance of 100km.
The Meter installation is as per standard and all necessary materials are considered.
The construction unit consists of minimum one technician/Mounter and one daily laborer
is assumed to execute the installation within one hour (i.e 8 KWH meters per day)
One pickup will travel per day 50km for site activity
Once the materials are transported the material will be properly secured within the village
until all installation work is completed.
Price
Unit price Unit price
No. Description (in Birr) (in USD) Remark
Note:-
Although the customer pays fixed price the cable length to be installed is as per the actual length.
Detail price analysis is attached with the report.
Annex 1. Labour cost Detail
Annex 4 Summary