Professional Documents
Culture Documents
Coventry University
School of Energy, Construction and Environment
MSc BRIDGE ENGINEERING MODULE
Introduction:
This example is based on the lecture notes for steel composite bridge design 1
Brief:
To design a simply supported steel-concrete composite multi beam bridge. Span 37.5m,
width between parapets 19.81m. The bridge forms part of a slip road to a new motorway in
the midlands. Loads will be standard UK loads with 45 units of HB.
Girder Spacing
The bridge is 19.81m wide, other bridges on the scheme have a 1.25m cantilever overhang,
a similar overhang will be used giving 17.31m between girders. The girders will be lifted in
pairs in pairs for stability during the construction stage:
For the steelwork the wider spaced girder is likely to be the most economic. Thegirder
spacing is at the upper end of the range (figure 8) and there is heavymotorway traffic and so
a 225mm slab is used. The bridge arrangement is shown in figure E1.
Durability
Reinforced soil abutments are used on most bridges on the scheme, a semi integral type is
used with these rather than a fully integral bridge. This avoids the use of joints but requires
bearings at each end. The bridge is over a river, it is away from the coast and there are no
pollution issues. A weathering steel bridge is proposed with a 1.5mm allowance for corrosion
to exposed faces.
From figure 20 the weight of steel is estimated to be 200 kg/m2 and so a pair of girders will
weigh:
(37.5 +1) x 19.81 x 200 / 3 = 50,085 kg or 50 tonnes.
Girder depth
From table 3 span to depth ratios of 18 to 20 are recommended.
S/D = 18 = 37.5 / 18 = 2.08m.
Allowing for the deck slab a 1.78m deep web for the girder is chosen.
Where l= 0.5 x y= 0.5 x 0.577y/m3= 0.5 x 175, (m3 is safety factor from BS, EC3 will be
different)
Hence, tw = 0.014m
Allowing additional thickness for corrosion a 1780 x 20mm web plate is used.
dw / tw = 1780 / (20-3) =105 this is well within the limits for webs in table 1
From figure 15 with d/t =105 and 1= 0.5y, = a/dw = 2.5,
Af1 = 0.0261 m2
hf/ tf = (950-20)x0.5 / 30 = 15.5 this is within the limits for tension flanges in table 1
As a first estimate a secondary flange size Af2 = 0.6 Af1 can be used
This is only required for construction and so no reduction for corrosion is required.
Bracing layout
For bracing the maximum spacing is 20 times the top flange width (figure 8)
S1 = 20 x 0.6 = 12m
Note as the bridge has a skew but that the bracing will be perpendicular to the beams the
actual spacing will vary and may be up to 10m (see layout on figure E2). The web stiffeners
will be placed at bracing spacing, as the stiffener spacing required is less than 10m
intermediate stiffeners will be required.
b eff = the spacing of the girders or 0.2 times the span whichever is the smaller.
b eff = 3.46m
Steelwork tonnage
6 x 39.5 x {(0.95x0.03)+(0.6x0.025)+(1.78x0.02)} x 7.85 x1.10 = 162 tonnes
Figure E3
Figure E4