Professional Documents
Culture Documents
(LIP 2021)
MAP SHOWING THE SOURCE OF MATERIAL TO THE POINT OF REFERENCE (PROJECT SITE) L= 13.5 KM
MAP SHOWING DPWH QUEZON II DEO OFFICE TO THE POINT OF REFERENCE (PROJECT SITE) L= 5.6 KM
Prepared by:
Project : LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Appropriation : P 5,000,000.00
Multipurpose/Facilities, Construction of Multi-Purpose Building (Barangay Hall), Source of Fund : GAA 2021 ( LIP )
Barangay Isabang, Lucena City, Quezon Target Start Date :
Project ID : Total Project Duration : 240 CD
Location : Lucena City, Quezon
Project Description : Construction of Multi - Purpose Building (Barangay Hall)
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.85% 70,950.55 1.85% 70,950.55
Part II Other General Requirements 10.94% 419,637.46 10.94% 419,637.46
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
Part A Earthworks 0.80% 31,021.97 0.80% 31,021.97
Part B Plain and Reinforced Concrete Works (PLS. SEE FORM POW-2015-01C-00) 31.16% 1,194,960.78 31.16% 1,194,960.78
Part C Finishing and Other Civil Works 47.47% 1,820,039.61 47.47% 1,820,039.61
Part D Electrical Works 7.77% 297,819.10 7.77% 297,819.10
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
JIM PAUL K. ABRIL FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Engineer II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
4/90
Republic of the Philippines
Department of Public Works and Highways
Quezon II District Engineering Office
Lucena City
Date:
EXECUTIVE SUMMARY
Project ID :
LOCAL PROGRAM, Local Infrastructure Program, Buildings
And Other Structures, Multipurpose/Facilities,
Project Name :
Construction of Multi-Purpose Building (Barangay Hall),
Barangay Isabang, Lucena City, Quezon
Location of Project : Lucena City, Quezon
2. Project Category : Multi-Purpose Building
3. Source of Fund : LIP 2021
4. Action Recommended: For Aproval
5. Implementing Office : DPWH Quezon II District Engineering Office
6. Reviewing Offices : DPWH Quezon II District Engineering Office
7. Appropriation : ₱ 5,000,000.00
8. ABC : ₱ 4,950,000.00
9. Project Duration : 240 C.D.
10. Mode Implementation: By Contract
PREPARED BY:
SUBMITTED BY:
Stair
Page 6 of 90
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures,
Multipurpose/Facilities, Construction of Multi-Purpose Building (Barangay Hall),
Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
Columns
Suspended Slab
Beams/Girders
Unit Weight
BAR Ø LENGTH QUANTITY PCS. FOR 6m No. Of Footing WEIGHT
(kg/m)
16mm Ø 1.50 10.00 3.00 1.578 10.00 284.04 kg
F-1
16mm Ø 2.00 10.00 4.00 1.578 10.00 378.72 kg
16mm Ø 1.50 7.00 2.00 1.578 2.00 37.87 kg
F-2
16mm Ø 1.50 7.00 2.00 1.578 2.00 37.87 kg
WF-1 (T) 12mm Ø 13.00 3.00 7.00 0.888 1.00 37.30 kg
WF-1 (H) 12mm Ø 0.40 32.00 3.00 0.888 1.00 15.98 kg
sub-total: 870.96
Page 7 of 90
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures,
Multipurpose/Facilities, Construction of Multi-Purpose Building (Barangay Hall),
Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
Unit Weight
BAR Ø LENGTH QUANTITY PCS. FOR 6m No. Of Beam WEIGHT
(kg/m)
16mm Ø 44.25 8 59.00 1.578 1 558.61 kg
FTB-1
10mm Ø 1.10 254 47.00 0.616 1 172.11 kg
sub-total: 803.79 kgs.
Unit Weight
BAR Ø LENGTH QUANTITY PCS. FOR 6m No. of Column WEIGHT
(kg/m)
Vertical Bars 20mm 9.00 12 18.00 2.466 12 3195.94 kg
C-1
Ties 10mm 1.20 51 11.00 0.616 12 487.87 kg
Vertical Bars 16mm 2.50 6 3.00 1.578 6 170.42 kg
PC-1
Ties 10mm 0.60 7 1.00 0.616 6 22.18 kg
Vertical Bars 16mm 1.00 6 1.00 1.578 3 28.40 kg
PC-2
Ties 10mm 0.80 16 3.00 0.616 3 33.26 kg
Unit Weight
BAR Ø NO. OF BARS LENGTH PCS. FOR 6m NO. OF BEAM WEIGHT
(kg/m)
Main Bar 20mm 9 62.5 94.00 2.466 1 1390.82 kg
B-1
Stirrups 10mm 418 1.2 84.00 0.616 1 308.99 kg
Main Bar 20mm 7 13 16.00 2.466 1 236.74 kg
B-2
Stirrups 10mm 88 1 15.00 0.616 1 54.21 kg
Main Bar 16mm 6 3.7 4.00 1.578 1 37.87 kg
B-3
Stirrups 10mm 26 0.9 4.00 0.616 1 14.41 kg
Main Bar 16mm 8 54.75 73.00 1.578 1 691.16 kg
RB-1
Stirrups 10mm 366 1.20 74.00 0.616 1 270.55 kg
Main Bar 16mm 6 73.90 74.00 1.579 1 700.13 kg
RB-2
Stirrups 10mm 494 0.90 75.00 0.616 1 273.87 kg
Main Bar 12 mm 4 47.00 32.00 0.888 1 166.94 kg
LRB-1
Stirrups 10mm 245 0.50 21.00 0.616 1 75.46 kg
total: 4,643.27 kgs.
LENGTH
Unit Weight
BAR Ø NO. OF BARS (including PCS. FOR 6m Quantity WEIGHT
(kg/m)
splicing)
Short Direction 10mm 35 8 47.00 0.616 1 173.71 kg
SLAB (BOT)
Long Direction 10mm 25 10 42.00 0.616 1 154.00 kg
Short Direction 10mm 70 8 94.00 0.616 1 347.42 kg
SLAB (TOP)
Long Direction 10mm 50 10 84.00 0.616 1 308.00 kg
Short Direction 10mm 15 3.3 9.00 0.616 1 33.26 kg
CORRIDOR
Long Direction 10mm 10 2.1 4.00 0.616 1 12.94 kg
total: 1,132.26 kgs.
LENGTH
Unit Weight
BAR Ø NO. OF BARS (including PCS. FOR 6m Quantity WEIGHT
(kg/m)
splicing)
Short Direction 10mm 35 8 47.00 0.616 1 173.71 kg
SOF
Long Direction 10mm 25 10 42.00 0.616 1 154.00 kg
Short Direction 10mm 15 3.3 9.00 0.616 1 33.26 kg
CORRIDOR
Long Direction 10mm 10 2.1 4.00 0.616 1 12.94 kg
Short Direction 10mm 15 2.9 8.00 0.616 1 26.80 kg
RAMP
Long Direction 10mm 10 2.1 4.00 0.616 1 12.94 kg
Page 8 of 90
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures,
Multipurpose/Facilities, Construction of Multi-Purpose Building (Barangay Hall),
Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
STAIR
QUANTITY: 156.59 kgs.
Unit Weight
BAR Ø NO. OF BARS LENGTH PCS. FOR 6m Quantity WEIGHT
(kg/m)
Main Bar 16mm 7 4.00 5.00 1.578 1 47.34 kg
Stinger Inc. Temp Bar 12mm 20 1.40 5.00 0.888 1 24.86 kg
Landing Nosing Bar 10mm 17 1.00 3.00 0.616 1 11.09 kg
Chair Bar 10mm 7 1.00 2.00 0.616 17 73.30 kg
total: 156.59 kgs.
COLUMN
QTY. WIDTH (m.) DEPTH(m.) HEIGHT AREA UNIT
C-1 12.00 0.35 0.35 7.50 126.00 sq.m
PC-1 6.00 0.15 0.20 1.00 4.20 sq.m
PC-2 3.00 0.20 0.20 2.50 6.00 sq.m
BEAMS
QUANTITY LENGTH WIDTH DEPTH AREA UNIT
B-1 1.00 52.5 0.30 0.40 57.75 sq.m
B-2 1.00 13.5 0.25 0.35 12.83 sq.m
B-3 1.00 2.4 0.20 0.30 1.92 sq.m
RB-1 1.00 39 0.25 0.40 40.95 sq.m
RB-2 1.00 66.28 0.20 0.30 53.02 sq.m
LRB-1 1.00 36.6 0.15 0.20 20.13 sq.m
1046(2)a1 CHB Non Load Bearing (Inc. Reinforcing Steel ) 100mm thk.
Page 9 of 90
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures,
Multipurpose/Facilities, Construction of Multi-Purpose Building (Barangay Hall),
Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
1046(2)a2 CHB Non Load Bearing (Inc. Reinforcing Steel ) 150mm thk.
Page 10 of 90
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures,
Multipurpose/Facilities, Construction of Multi-Purpose Building (Barangay Hall),
Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
AREA
4" CHB 248.18
6" CHB 278.20
Moldings 55.00
TOTAL: 581.38 SQ.M.
AREA
Interior
1st Floor (CR) 4.00
Second Floor 63.00
Eaves 34.30
AREA
Ground Floor ( toilet ) 11.25
Second Floor ( toilet ) 11.25
Ground Floor Slab 74.00
Second Floor Slab 53.50
Stair 6.50
TOTAL: 156.50 SQ.M.
AREA
Ground Floor ( toilet ) 3.50
Second Floor ( toilet ) 3.50
TOTAL: 7.00
AREA UNIT
WALLS 221.650 sq.m.
COLUMNS 80.640 sq.m.
BEAMS 82.440 sq.m.
CEILING 55.000 sq.m.
Page 11 of 90
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures,
Multipurpose/Facilities, Construction of Multi-Purpose Building (Barangay Hall),
Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
1014(1)b1 Prepainted Metal Sheets (above 0.427mm) Corrugated Type Long Span
QUANTITY: 116.28 sq. m.
QUANTITY: 678.60 kg
QUANTITY: 1,183.78 kg
Page 12 of 90
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures,
Multipurpose/Facilities, Construction of Multi-Purpose Building (Barangay Hall),
Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
Page 13 of 90
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 1.57% 1.00 l.s 54,462.07 12,888.48 - 67,350.55 67,350.55 10% 6,735.06 3,704.28 77,789.89
A.1.1 (3) Construction of Field Office for the Engineer
As Evaluated 1.57% 1.00 l.s 54,462.07 12,888.48 - 67,350.55 67,350.55 10% 6,735.06 3,704.28 77,789.89
As Submitted 0.08% 240.00 each 3,600.00 - - 15.00 3,600.00 10% 360.00 198.00 4,158.00
A.1.4 (1) Provision of Progress Photographs
As Evaluated 0.08% 240.00 each 3,600.00 - - 15.00 3,600.00 10% 360.00 198.00 4,158.00
As Submitted 58,062.07 12,888.48 - 70,950.55 7,095.06 3,902.28 81,947.89
TOTAL OF PART I
As Evaluated 58,062.07 12,888.48 - 70,950.55 7,095.06 3,902.28 81,947.89
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.44% 1.00 l.s. 21,825.00 - - 21,825.00 21,825.00 0% - - 21,825.00
B.3 Permits and Clearances
As Evaluated 0.44% 1.00 l.s. 21,825.00 - - 21,825.00 21,825.00 0% - - 21,825.00
As Submitted 0.10% 1.00 ea. 2,560.00 1,165.16 - 3,725.16 3,725.16 25% 931.29 232.82 4,889.27
B.5 Project Billboard / Signboard
As Evaluated 0.10% 1.00 ea. 2,560.00 1,165.16 - 3,725.16 3,725.16 25% 931.29 232.82 4,889.27
As Submitted 8.61% 1.00 l.s. 87,242.58 254,400.00 27,444.72 369,087.30 369,087.30 10% 36,908.73 20,299.80 426,295.83
B.7 (2) Occupational Safety and Health Program
As Evaluated 8.61% 1.00 l.s. 87,242.58 254,400.00 27,444.72 369,087.30 369,087.30 10% 36,908.73 20,299.80 426,295.83
As Submitted 0.53% 1.00 l.s. - - 25,000.00 25,000.00 25,000.00 0% - 1,250.00 26,250.00
B.9 Mobilization / Demobilization
As Evaluated 0.53% 1.00 l.s. - - 25,000.00 25,000.00 25,000.00 0% - 1,250.00 26,250.00
As Submitted 111,627.58 255,565.16 52,444.72 419,637.46 37,840.02 21,782.62 479,260.10
TOTAL OF PART II
As Evaluated 111,627.58 255,565.16 52,444.72 419,637.46 37,840.02 21,782.62 479,260.10
(Project ID)
(Project Component ID - Description)
PART
CIVIL,
III MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.32% 51.76 m3 - 709.73 11,398.65 233.93 12,108.38 25% 3,027.10 756.77 15,892.25
803(1)a Structure Excavation (Common Soil)
As Evaluated 0.32% 51.76 m3 - 709.73 11,398.65 233.93 12,108.38 25% 3,027.10 756.77 15,892.25
As Submitted 0.21% 51.13 m3 - 1,424.85 6,611.04 157.18 8,035.89 25% 2,008.97 502.24 10,547.10
804(1)a Embankment From Structure Excavation
As Evaluated 0.21% 51.13 m3 - 1,424.85 6,611.04 157.18 8,035.89 25% 2,008.97 502.24 10,547.10
As Submitted 0.29% 35.25 m
3
9,466.58 982.41 428.71 308.59 10,877.70 25% 2,719.43 679.86 14,276.99
804(1)b Embankment from Borrow
As Evaluated 0.29% 35.25 m3 9,466.58 982.41 428.71 308.59 10,877.70 25% 2,719.43 679.86 14,276.99
As Submitted 9,466.58 3,116.99 18,438.40 31,021.97 7,755.50 1,938.87 40,716.34
TOTAL OF PART A
As Evaluated 9,466.58 3,116.99 18,438.40 31,021.97 7,755.50 1,938.87 40,716.34
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 10.25% 56.94 m3 238,878.48 101,195.03 46,392.39 6,787.25 386,465.90 25% 96,616.48 24,154.12 507,236.50
900(1)c1 Structural Concrete (Class A, 28 days)
As Evaluated 10.25% 56.94 m3 238,878.48 101,195.03 46,392.39 6,787.25 386,465.90 25% 96,616.48 24,154.12 507,236.50
As Submitted 16.56% 12393.76 kgs 503,620.44 87,392.91 33,418.80 50.38 624,432.15 25% 156,108.04 39,027.01 819,567.20
902(1)a Reinforcing Steel (Deformed) Grade 40
As Evaluated 16.56% 12393.76 kgs 503,620.44 87,392.91 33,418.80 50.38 624,432.15 25% 156,108.04 39,027.01 819,567.20
As Submitted 4.88% 395.74 m2 78,191.79 97,710.04 8,160.90 465.11 184,062.73 25% 46,015.68 11,503.92 241,582.33
903(2) Formworks and Falseworks
As Evaluated 4.88% 395.74 m2 78,191.79 97,710.04 8,160.90 465.11 184,062.73 25% 46,015.68 11,503.92 241,582.33
As Submitted 820,690.71 286,297.98 87,972.09 1,194,960.78 298,740.20 74,685.05 1,568,386.03
TOTAL OF PART B
As Evaluated 820,690.71 286,297.98 87,972.09 1,194,960.78 298,740.20 74,685.05 1,568,386.03
14/90
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART C FINISHINGS AND OTHER CIVIL WORKS
C.1 Termite Control Works
As Submitted 1.00% 120.00 liter 30,600.00 6,473.11 647.31 314.34 37,720.42 25% 9,430.11 2,357.53 49,508.06
1000(1) Soil Poisoning
As Evaluated 1.00% 120.00 liter 30,600.00 6,473.11 647.31 314.34 37,720.42 25% 9,430.11 2,357.53 49,508.06
As Submitted 30,600.00 6,473.11 647.31 37,720.42 9,430.11 2,357.53 49,508.06
Sub - Total C.1
As Evaluated 30,600.00 6,473.11 647.31 37,720.42 9,430.11 2,357.53 49,508.06
C.2. Masonry Works
As Submitted 2.22% 124.09 m2 63,138.38 13,712.51 6,951.25 675.33 83,802.14 25% 20,950.54 5,237.63 109,990.31
1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm
As Evaluated 2.22% 124.09 m
2
63,138.38 13,712.51 6,951.25 675.33 83,802.14 25% 20,950.54 5,237.63 109,990.31
As Submitted 3.66% 139.10 m2 110,106.16 18,488.93 9,372.54 991.86 137,967.63 25% 34,491.91 8,622.98 181,082.52
1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm
As Evaluated 3.66% 139.10 m2 110,106.16 18,488.93 9,372.54 991.86 137,967.63 25% 34,491.91 8,622.98 181,082.52
As Submitted 173,244.54 32,201.44 16,323.79 221,769.77 55,442.45 13,860.61 291,072.83
Sub - Total C.2
As Evaluated 173,244.54 32,201.44 16,323.79 221,769.77 55,442.45 13,860.61 291,072.83
C.3 Doors & Windows
As Submitted 3.14% 17.10 sq.m. 109,440.00 8,006.90 800.69 6,915.06 118,247.59 25% 29,561.90 7,390.47 155,199.96
1008 (1)b Aluminum Glass Windows ( Casement Type )
As Evaluated 3.14% 17.10 sq.m. 109,440.00 8,006.90 800.69 6,915.06 118,247.59 25% 29,561.90 7,390.47 155,199.96
As Submitted 0.32% 1.50 sq.m. 11,175.00 693.60 69.36 7,958.64 11,937.96 25% 2,984.49 746.12 15,668.57
1008 (1)c Aluminum Glass Windows ( Awning Type )
As Evaluated 0.32% 1.50 sq.m. 11,175.00 693.60 69.36 7,958.64 11,937.96 25% 2,984.49 746.12 15,668.57
As Submitted 0.67% 8.00 set 21,000.00 3,745.92 374.59 3,140.06 25,120.51 25% 6,280.13 1,570.03 32,970.67
1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions)
As Evaluated 0.67% 8.00 set 21,000.00 3,745.92 374.59 3,140.06 25,120.51 25% 6,280.13 1,570.03 32,970.67
As Submitted 0.41% 10.20 m2 7,140.00 7,462.58 746.26 1,504.79 15,348.84 25% 3,837.21 959.30 20,145.35
1010(2)a Doors (Flush)
As Evaluated 0.41% 10.20 m2 7,140.00 7,462.58 746.26 1,504.79 15,348.84 25% 3,837.21 959.30 20,145.35
As Submitted 1.30% 6.80 m2 44,200.00 4,422.27 442.23 7,215.37 49,064.50 25% 12,266.13 3,066.53 64,397.16
1010(2)b Door (Wood Panel)
As Evaluated 1.30% 6.80 m2 44,200.00 4,422.27 442.23 7,215.37 49,064.50 25% 12,266.13 3,066.53 64,397.16
As Submitted 1.14% 8.20 m2 38,950.00 3,839.57 383.96 5,265.06 43,173.53 25% 10,793.38 2,698.35 56,665.26
1007(1)a Aluminum Framed Glass Door (Sliding Type)
As Evaluated 1.14% 8.20 m2 38,950.00 3,839.57 383.96 5,265.06 43,173.53 25% 10,793.38 2,698.35 56,665.26
As Submitted 1.36% 6.30 m2 48,195.00 2,949.91 294.99 8,165.06 51,439.90 25% 12,859.98 3,214.99 67,514.87
1007(1)b Aluminum Framed Glass Door (Swing Type) 2
As Evaluated 1.36% 6.30 m 48,195.00 2,949.91 294.99 8,165.06 51,439.90 25% 12,859.98 3,214.99 67,514.87
As Submitted 0.17% 1.00 l.s 6,320.00 - - 6,320.00 6,320.00 25% 1,580.00 395.00 8,295.00
1004 (2) Finishing Hardware
As Evaluated 0.17% 1.00 l.s 6,320.00 - - 6,320.00 6,320.00 25% 1,580.00 395.00 8,295.00
As Submitted 286,420.00 31,120.75 3,112.08 320,652.83 80,163.22 20,040.79 420,856.84
Sub-Total C.3
As Evaluated 286,420.00 31,120.75 3,112.08 320,652.83 80,163.22 20,040.79 420,856.84
C.4 Finishing Works
As Submitted 2.94% 581.38 m2 67,943.77 39,154.41 3,915.44 190.95 111,013.62 25% 27,753.41 6,938.35 145,705.38
1027(1) Cement Plaster Finish
As Evaluated 2.94% 581.38 m2 67,943.77 39,154.41 3,915.44 190.95 111,013.62 25% 27,753.41 6,938.35 145,705.38
As Submitted 1.72% 1.00 l.s 31,344.60 14,620.40 18,920.04 64,885.04 64,885.04 25% 16,221.26 4,055.32 85,161.62
1051(6) Railings
As Evaluated 1.72% 1.00 l.s. 31,344.60 14,620.40 18,920.04 64,885.04 64,885.04 25% 16,221.26 4,055.32 85,161.62
As Submitted 2.05% 101.30 m2 51,094.71 23,739.08 2,373.91 762.17 77,207.70 25% 19,301.93 4,825.48 101,335.11
1003 (1)a1 Ceiling (4.5mm Fiber Cement Board, Metal Frame)
As Evaluated 2.05% 101.30 m2 51,094.71 23,739.08 2,373.91 762.17 77,207.70 25% 19,301.93 4,825.48 101,335.11
As Submitted 0.49% 110.00 m2 12,127.50 5,762.93 576.29 167.88 18,466.72 25% 4,616.68 1,154.17 24,237.57
1038(1) Reflective Insulation
As Evaluated 0.49% 110.00 m2 12,127.50 5,762.93 576.29 167.88 18,466.72 25% 4,616.68 1,154.17 24,237.57
As Submitted 6.58% 156.50 m
2
152,266.76 87,098.84 8,709.88 1,585.15 248,075.48 25% 62,018.87 15,504.72 325,599.07
1018 (1) Glazed Tiles and Trims
As Evaluated 6.58% 156.50 m2 152,266.76 87,098.84 8,709.88 1,585.15 248,075.48 25% 62,018.87 15,504.72 325,599.07
As Submitted 0.18% 7.00 m2 3,751.31 2,727.06 272.71 964.44 6,751.08 25% 1,687.77 421.94 8,860.79
1018 (2) Unglazed Tiles
As Evaluated 0.18% 7.00 m2 3,751.31 2,727.06 272.71 964.44 6,751.08 25% 1,687.77 421.94 8,860.79
As Submitted 318,528.65 173,102.72 34,768.27 526,399.64 131,599.92 32,899.98 690,899.54
Sub-Total C.4
As Evaluated 318,528.65 173,102.72 34,768.27 526,399.64 131,599.92 32,899.98 690,899.54
C.5 Painting Works
As Submitted 3.11% 439.73 m2 46,263.99 64,564.93 6,456.49 266.72 117,285.41 25% 29,321.35 7,330.34 153,937.10
1032(1)a Painting Works (Masonry/Concrete)
As Evaluated 3.11% 439.73 m2 46,263.99 64,564.93 6,456.49 266.72 117,285.41 25% 29,321.35 7,330.34 153,937.10
As Submitted 0.90% 121.46 m2 12,039.12 19,815.33 1,981.53 278.58 33,835.98 25% 8,459.00 2,114.75 44,409.73
1032(1)b Painting Works (Wood)
As Evaluated 0.90% 121.46 m2 12,039.12 19,815.33 1,981.53 278.58 33,835.98 25% 8,459.00 2,114.75 44,409.73
As Submitted 1.35% 190.08 m2 18,661.10 29,304.63 2,930.46 267.76 50,896.19 25% 12,724.05 3,181.01 66,801.25
1032(1)c Painting Works (Steel)
As Evaluated 1.35% 190.08 m2 18,661.10 29,304.63 2,930.46 267.76 50,896.19 25% 12,724.05 3,181.01 66,801.25
As Submitted 76,964.21 113,684.89 11,368.48 202,017.58 50,504.40 12,626.10 265,148.08
Sub-Total C.5
As Evaluated 76,964.21 113,684.89 11,368.48 202,017.58 50,504.40 12,626.10 265,148.08
15/90
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
C.6 Roof Framing and Roofing Works
Prepainted Metal Sheets, Long Span, Corrugated type, As Submitted 2.06% 116.28 m2 59,644.66 16,315.61 1,631.56 667.28 77,591.83 25% 19,397.96 4,849.49 101,839.28
1014(1)b1
0.427 mm thk As Evaluated 2.06% 116.28 m2 59,644.66 16,315.61 1,631.56 667.28 77,591.83 25% 19,397.96 4,849.49 101,839.28
Fabricated Metal Roofing Accessory (Ridge/Hip Roll, gauge As Submitted 0.07% 12.00 l.m 2,493.63 280.94 28.09 233.56 2,802.66 25% 700.67 175.17 3,678.50
1013(2)a1
26) As Evaluated 0.07% 12.00 l.m 2,493.63 280.94 28.09 233.56 2,802.66 25% 700.67 175.17 3,678.50
As Submitted 0.81% 26.40 l.m 29,326.57 1,236.15 123.62 1,162.36 30,686.34 25% 7,671.59 1,917.90 40,275.83
1013(2)b1 Fabricated Metal Roofing Accessory (Gutters, gauge 24)
As Evaluated 0.81% 26.40 l.m 29,326.57 1,236.15 123.62 1,162.36 30,686.34 25% 7,671.59 1,917.90 40,275.83
As Submitted 0.29% 50.60 l.m 9,746.07 1,184.65 118.46 218.36 11,049.18 25% 2,762.30 690.57 14,502.05
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, gauge 26)
As Evaluated 0.29% 50.60 l.m 9,746.07 1,184.65 118.46 218.36 11,049.18 25% 2,762.30 690.57 14,502.05
As Submitted 1.40% 678.60 kg 45,612.61 4,491.49 2,881.03 78.08 52,985.13 25% 13,246.28 3,311.57 69,542.98
1047(2)a Structural Steel (Trusses)
As Evaluated 1.40% 678.60 kg 45,612.61 4,491.49 2,881.03 78.08 52,985.13 25% 13,246.28 3,311.57 69,542.98
As Submitted 2.23% 1183.78 kg 65,255.87 7,999.71 11,034.53 71.20 84,290.11 25% 21,072.53 5,268.13 110,630.77
1047(2)b Structural Steel (Purlins)
As Evaluated 2.23% 1183.78 kg 65,255.87 7,999.71 11,034.53 71.20 84,290.11 25% 21,072.53 5,268.13 110,630.77
As Submitted 0.15% 40.00 each 4,200.00 1,337.83 133.78 141.79 5,671.61 25% 1,417.90 354.48 7,443.99
1047(3)a Metal Structure Accessories (Bolts)
As Evaluated 0.15% 40.00 each 4,200.00 1,337.83 133.78 141.79 5,671.61 25% 1,417.90 354.48 7,443.99
As Submitted 0.08% 8.00 each 1,600.00 1,174.40 117.44 361.48 2,891.84 25% 722.96 180.74 3,795.54
1047(3)c Metal Structure Accessories (Turn Buckle)
As Evaluated 0.08% 8.00 each 1,600.00 1,174.40 117.44 361.48 2,891.84 25% 722.96 180.74 3,795.54
As Submitted 0.12% 71.96 kg 3,005.24 1,296.44 129.64 61.58 4,431.32 25% 1,107.83 276.96 5,816.11
1047(4) Metal Structure Accessories (Cross Bracing)
As Evaluated 0.12% 71.96 kg 3,005.24 1,296.44 129.64 61.58 4,431.32 25% 1,107.83 276.96 5,816.11
As Submitted 0.36% 159.88 kg 10,374.61 2,879.32 287.93 84.70 13,541.86 25% 3,385.47 846.37 17,773.70
1047(6) Metal Structure Accessories (Steel Plates)
As Evaluated 0.36% 159.88 kg 10,374.61 2,879.32 287.93 84.70 13,541.86 25% 3,385.47 846.37 17,773.70
As Submitted 0.08% 42.63 kg 2,074.70 768.03 76.80 68.49 2,919.53 25% 729.88 182.47 3,831.88
1047(7)b Metal Structure Accessories (Sag Rods)
As Evaluated 0.08% 42.63 kg 2,074.70 768.03 76.80 68.49 2,919.53 25% 729.88 182.47 3,831.88
As Submitted 233,333.96 38,964.57 16,562.88 288,861.41 72,215.37 18,053.85 379,130.63
Sub-Total C.6
As Evaluated 233,333.96 38,964.57 16,562.88 288,861.41 72,215.37 18,053.85 379,130.63
C.7 Plumbing / Sanitary Works
As Submitted 0.80% 8.00 ea. 28,149.35 1,872.96 187.30 3,776.20 30,209.61 25% 7,552.40 1,888.10 39,650.11
1001(5)a Catch Basin (Concrete)
As Evaluated 0.80% 8.00 ea. 28,149.35 1,872.96 187.30 3,776.20 30,209.61 25% 7,552.40 1,888.10 39,650.11
As Submitted 1.08% 1.00 l.s 30,469.95 9,364.80 936.48 40,771.23 40,771.23 25% 10,192.81 2,548.20 53,512.24
1001(8) Sewer Line Works
As Evaluated 1.08% 1.00 l.s 30,469.95 9,364.80 936.48 40,771.23 40,771.23 25% 10,192.81 2,548.20 53,512.24
As Submitted 1.08% 1.00 l.s 30,254.70 9,364.80 936.48 40,555.98 40,555.98 25% 10,139.00 2,534.75 53,229.73
1001(9) Storm Drainage & Downspout
As Evaluated 1.08% 1.00 l.s 30,254.70 9,364.80 936.48 40,555.98 40,555.98 25% 10,139.00 2,534.75 53,229.73
As Submitted 0.97% 1.00 l.s 23,816.51 11,516.40 1,151.64 36,484.55 36,484.55 25% 9,121.14 2,280.28 47,885.97
1001(11) Septic Vault ( CHB )
As Evaluated 0.97% 1.00 l.s 23,816.51 11,516.40 1,151.64 36,484.55 36,484.55 25% 9,121.14 2,280.28 47,885.97
As Submitted 0.64% 1.00 l.s 13,984.99 9,321.28 932.13 24,238.40 24,238.40 25% 6,059.60 1,514.90 31,812.90
1002 (24) Cold Water Lines
As Evaluated 0.64% 1.00 l.s 13,984.99 9,321.28 932.13 24,238.40 24,238.40 25% 6,059.60 1,514.90 31,812.90
As Submitted 1.34% 1.00 l.s 43,273.40 6,440.72 644.07 50,358.19 50,358.19 25% 12,589.55 3,147.39 66,095.13
1002 (4) Plumbing Fixtures
As Evaluated 1.34% 1.00 l.s 43,273.40 6,440.72 644.07 50,358.19 50,358.19 25% 12,589.55 3,147.39 66,095.13
As Submitted 169,948.90 47,880.96 4,788.10 222,617.96 55,654.50 13,913.62 292,186.08
Sub-Total C.7
As Evaluated 169,948.90 47,880.96 4,788.10 222,617.96 55,654.50 13,913.62 292,186.08
As Submitted 1,289,040.26 443,428.44 87,570.91 1,820,039.61 455,009.97 113,752.48 2,388,802.06
TOTAL OF PART C
As Evaluated 1,289,040.26 443,428.44 87,570.91 1,820,039.61 455,009.97 113,752.48 2,388,802.06
16/90
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART D ELECTRICAL
Conduits, Boxes & Fittings (Conduit Works/Conduit As Submitted 0.52% 1.00 l.s. 13,529.00 5,618.88 561.89 19,709.77 19,709.77 25% 4,927.44 1,231.86 25,869.07
1100(10)
Rough-in) As Evaluated 0.52% 1.00 l.s. 13,529.00 5,618.88 561.89 19,709.77 19,709.77 25% 4,927.44 1,231.86 25,869.07
As Submitted 1.81% 1.00 l.s. 55,765.00 11,237.76 1,123.78 68,126.54 68,126.54 25% 17,031.64 4,257.91 89,416.09
1101(33) Wires and Wiring Devices
As Evaluated 1.81% 1.00 l.s. 55,765.00 11,237.76 1,123.78 68,126.54 68,126.54 25% 17,031.64 4,257.91 89,416.09
As Submitted 0.42% 1.00 l.s. 15,000.00 593.76 59.38 15,653.14 15,653.14 25% 3,913.29 978.32 20,544.75
1102 (1) Panelboard with Main & Branch Breakers
As Evaluated 0.42% 1.00 l.s. 15,000.00 593.76 59.38 15,653.14 15,653.14 25% 3,913.29 978.32 20,544.75
As Submitted 1.27% 1.00 l.s. 41,600.00 5,618.88 561.89 47,780.77 47,780.77 25% 11,945.19 2,986.30 62,712.26
1103(1) Lighting Fixtures and Lamps
As Evaluated 1.27% 1.00 l.s. 41,600.00 5,618.88 561.89 47,780.77 47,780.77 25% 11,945.19 2,986.30 62,712.26
As Submitted 3.89% 1.00 l.s. 128,605.42 16,312.24 1,631.22 146,548.88 146,548.88 25% 36,637.22 9,159.31 192,345.41
1200(13)a Airconditioning ( Split type )
As Evaluated 3.89% 1.00 l.s. 128,605.42 16,312.24 1,631.22 146,548.88 146,548.88 25% 36,637.22 9,159.31 192,345.41
As Submitted 254,499.42 39,381.52 3,938.16 297,819.10 74,454.78 18,613.70 390,887.58
TOTAL OF PART D
As Evaluated 254,499.42 39,381.52 3,938.16 297,819.10 74,454.78 18,613.70 390,887.58
As Submitted 2,373,696.97 772,224.93 197,919.56 3,343,841.46 835,960.45 208,990.10 4,388,792.01
TOTAL OF PART III
As Evaluated 2,373,696.97 772,224.93 197,919.56 3,343,841.46 835,960.45 208,990.10 4,388,792.01
As Submitted 2,543,386.62 1,040,678.57 250,364.28 3,834,429.47 880,895.53 234,675.00 4,950,000.00
GRAND TOTAL
As Evaluated 2,543,386.62 1,040,678.57 250,364.28 3,834,429.47 880,895.53 234,675.00 4,950,000.00
17/90
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QTY. TOTAL MARK-UP % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT 5% VAT
As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated % COST As Submitted As Evaluated As Submitted As Evaluated
A.1.4 (1) Provision of Progress Photographs 240.00 240.00 l.s 3,600.00 3,600.00 15.00 15.00 10% 1.50 0.83 17.33 17.33 0.09% 0.09%
B.3 Permits and Clearances 1.00 1.00 l.s. 21,825.00 21,825.00 21,825.00 21,825.00 0% - - 21,825.00 21,825.00 0.57% 0.57%
B.5 Project Billboard / Signboard 1.00 1.00 ea. 3,725.16 3,725.16 3,725.16 3,725.16 25% 931.29 232.82 4,889.27 4,889.27 0.10% 0.10%
B.7 (2) Occupational Safety and Health Program 1.00 1.00 l.s. 369,087.30 369,087.30 369,087.30 369,087.30 10% 36,908.73 20,299.80 426,295.84 426,295.84 9.63% 9.63%
B.9 Mobilization / Demobilization 1.00 1.00 l.s. 25,000.00 25,000.00 25,000.00 25,000.00 0% - 1,250.00 26,250.00 26,250.00 0.65% 0.65%
Project ID
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
803(1)a Structure Excavation (Common Soil) 51.76 51.76 m3 12,108.38 12,108.38 233.93 233.93 25% 58.48 14.62 307.04 307.04 0.32% 0.32%
804(1)a Embankment From Structure Excavation 51.13 51.13 m3 8,035.89 8,035.89 157.18 157.18 25% 39.30 9.82 206.30 206.30 0.21% 0.21%
804(1)b Embankment from Borrow 35.25 35.25 m 3 10,877.70 10,877.70 308.59 308.59 25% 77.15 19.29 405.02 405.02 0.28% 0.28%
TOTAL OF PART A 31,021.97 31,021.97 0.81% 0.81%
PART B PLAIN AND REINFORCED CONCRETE WORKS
900(1)c1 Structural Concrete (Class A, 28 days) 56.94 56.94 m3 386,465.90 386,465.90 6,787.25 6,787.25 25% 1,696.81 424.20 8,908.26 8,908.26 10.08% 10.08%
902(1)a Reinforcing Steel (Deformed) Grade 40 12,393.76 12,393.76 kgs 624,432.15 624,432.15 50.38 50.38 25% 12.60 3.15 66.13 66.13 16.28% 16.28%
903(2) Formworks and Falseworks 395.74 395.74 m 2 184,062.73 184,062.73 465.11 465.11 25% 116.28 29.07 610.46 610.46 4.80% 4.80%
TOTAL OF PART B 1,194,960.78 1,194,960.78 31.16% 31.16%
18/90
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QTY. TOTAL MARK-UP % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT 5% VAT
As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated % COST As Submitted As Evaluated As Submitted As Evaluated
1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm 139.10 139.10 m2 137,967.63 137,967.63 991.86 991.86 25% 247.96 61.99 1,301.82 1,301.82 3.60% 3.60%
Sub-Total C.2 221,769.77 221,769.77 5.79% 5.79%
C.3 Doors & Windows
1008 (1)b Aluminum Glass Windows ( Casement Type ) 17.10 17.10 sq.m. 118,247.59 118,247.59 6,915.06 6,915.06 25% 1,728.77 432.19 9,076.02 9,076.02 3.08% 3.08%
1008 (1)c Aluminum Glass Windows ( Awning Type ) 1.50 1.50 sq.m. 11,937.96 11,937.96 7,958.64 7,958.64 25% 1,989.66 497.42 10,445.72 10,445.72 0.31% 0.31%
1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions) 8.00 8.00 set 25,120.51 25,120.51 3,140.06 3,140.06 25% 785.02 196.25 4,121.33 4,121.33 0.66% 0.66%
1010(2)a Doors (Flush) 10.20 10.20 m2 15,348.84 15,348.84 1,504.79 1,504.79 25% 376.20 94.05 1,975.03 1,975.03 0.40% 0.40%
1010(2)b Door (Wood Panel) 6.80 6.80 m2 49,064.50 49,064.50 7,215.37 7,215.37 25% 1,803.84 450.96 9,470.17 9,470.17 1.28% 1.28%
1007(1)a Aluminum Framed Glass Door (Sliding Type) 8.20 8.20 m2 43,173.53 43,173.53 5,265.06 5,265.06 25% 1,316.27 329.07 6,910.40 6,910.40 1.13% 1.13%
1007(1)b Aluminum Framed Glass Door (Swing Type) 6.30 6.30 m2 51,439.90 51,439.90 8,165.06 8,165.06 25% 2,041.27 510.32 10,716.65 10,716.65 1.34% 1.34%
1004 (2) Finishing Hardware 1.00 1.00 l.s 6,320.00 6,320.00 6,320.00 6,320.00 25% 1,580.00 395.00 8,295.00 8,295.00 0.16% 0.16%
Sub-Total C.3 320,652.83 320,652.83 8.36% 8.36%
C.4 Finishing Works
1027(1) Cement Plaster Finish 581.38 581.38 m2 111,013.62 111,013.62 190.95 190.95 25% 47.74 11.93 250.62 250.62 2.90% 2.90%
1051(6) Railings 1.00 1.00 l.s 64,885.04 64,885.04 64,885.04 64,885.04 25% 16,221.26 4,055.32 85,161.62 85,161.62 1.69% 1.69%
1003 (1)a1 Ceiling (4.5mm Fiber Cement Board, Metal Frame) 101.30 101.30 m2 77,207.70 77,207.70 762.17 762.17 25% 190.54 47.64 1,000.35 1,000.35 2.01% 2.01%
1038(1) Reflective Insulation 110.00 110.00 m2 18,466.72 18,466.72 167.88 167.88 25% 41.97 10.49 220.34 220.34 0.48% 0.48%
1018 (1) Glazed Tiles and Trims 156.50 156.50 m2 248,075.48 248,075.48 1,585.15 1,585.15 25% 396.29 99.07 2,080.51 2,080.51 6.47% 6.47%
1018 (2) Unglazed Tiles 7.00 7.00 m2 6,751.08 6,751.08 964.44 964.44 25% 241.11 60.28 1,265.83 1,265.83 0.18% 0.18%
Sub-Total C.4 526,399.64 526,399.64 13.73% 13.73%
C.5 Painting Works
1032(1)a Painting Works (Masonry/Concrete) 439.73 439.73 m2 117,285.41 117,285.41 266.72 266.72 25% 66.68 16.67 350.07 350.07 3.06% 3.06%
1032(1)b Painting Works (Wood) 121.46 121.46 m2 33,835.98 33,835.98 278.58 278.58 25% 69.64 17.41 365.63 365.63 0.88% 0.88%
1032(1)c Painting Works (Steel) 190.08 190.08 m 2 50,896.19 50,896.19 267.76 267.76 25% 66.94 16.74 351.44 351.44 1.33% 1.33%
Sub-Total C.5 202,017.58 202,017.58 5.27% 5.27%
19/90
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QTY. TOTAL MARK-UP % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT 5% VAT
As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated % COST As Submitted As Evaluated As Submitted As Evaluated
FACILITIES
C.6 Roof Framing FOR THE
and Roofing ENGINEER
Works
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated type, 0.427 mm thk 116.28 116.28 m2 77,591.83 77,591.83 667.28 667.28 25% 166.82 41.71 875.81 875.81 2.02% 2.02%
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Roll, gauge 26) 12.00 12.00 l.m 2,802.66 2,802.66 233.56 233.56 25% 58.39 14.60 306.54 306.54 0.07% 0.07%
1013(2)b1 Fabricated Metal Roofing Accessory (Gutters, gauge 24) 26.40 26.40 l.m 30,686.34 30,686.34 1,162.36 1,162.36 25% 290.59 72.65 1,525.60 1,525.60 0.80% 0.80%
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, gauge 26) 50.60 50.60 l.m 11,049.18 11,049.18 218.36 218.36 25% 54.59 13.65 286.60 286.60 0.29% 0.29%
1047(2)a Structural Steel (Trusses) 678.60 678.60 kg 52,985.13 52,985.13 78.08 78.08 25% 19.52 4.88 102.48 102.48 1.38% 1.38%
1047(2)b Structural Steel (Purlins) 1,183.78 1,183.78 kg 84,290.11 84,290.11 71.20 71.20 25% 17.80 4.45 93.46 93.46 2.20% 2.20%
1047(3)a Metal Structure Accessories (Bolts) 40.00 40.00 each 5,671.61 5,671.61 141.79 141.79 25% 35.45 8.86 186.10 186.10 0.15% 0.15%
1047(3)c Metal Structure Accessories (Turn Buckle) 8.00 8.00 each 2,891.84 2,891.84 361.48 361.48 25% 90.37 22.59 474.44 474.44 0.08% 0.08%
1047(4) Metal Structure Accessories (Cross Bracing) 71.96 71.96 kg 4,431.32 4,431.32 61.58 61.58 25% 15.40 3.85 80.82 80.82 0.12% 0.12%
1047(6) Metal Structure Accessories (Steel Plates) 159.88 159.88 kg 13,541.86 13,541.86 84.70 84.70 25% 21.18 5.29 111.17 111.17 0.35% 0.35%
1047(7)b Metal Structure Accessories (Sag Rods) 42.63 42.63 kg 2,919.53 2,919.53 68.49 68.49 25% 17.12 4.28 89.89 89.89 0.08% 0.08%
Sub-Total C.6 288,861.41 288,861.41 7.53% 7.53%
C.7 Plumbing / Sanitary Works
1001(5)a Catch Basin (Concrete) 8.00 8.00 ea. 30,209.61 30,209.61 3,776.20 3,776.20 25% 944.05 236.01 4,956.26 4,956.26 0.79% 0.79%
1001(8) Sewer Line Works 1.00 1.00 l.s 40,771.23 40,771.23 40,771.23 40,771.23 25% 10,192.81 2,548.20 53,512.24 53,512.24 1.06% 1.06%
1001(9) Storm Drainage & Downspout 1.00 1.00 l.s 40,555.98 40,555.98 40,555.98 40,555.98 25% 10,139.00 2,534.75 53,229.72 53,229.72 1.06% 1.06%
1001(9) Septic Vault ( CHB ) 1.00 1.00 l.s 36,484.55 36,484.55 36,484.55 36,484.55 25% 9,121.14 2,280.28 47,885.97 47,885.97 0.95% 0.95%
1002 (24) Cold Water Lines 1.00 1.00 l.s 24,238.40 24,238.40 24,238.40 24,238.40 25% 6,059.60 1,514.90 31,812.90 31,812.90 0.63% 0.63%
1002 (4) Plumbing Fixtures 1.00 1.00 l.s 50,358.19 50,358.19 50,358.19 50,358.19 25% 12,589.55 3,147.39 66,095.13 66,095.13 1.31% 1.31%
1100(10) Conduits, Boxes & Fittings (Conduit Works/ConduitRough-in) 1.00 1.00 l.s. 19,709.77 19,709.77 19,709.77 19,709.77 25% 4,927.44 1,231.86 25,869.07 25,869.07 0.51% 0.51%
1101(33) Wires and Wiring Devices 1.00 1.00 l.s. 68,126.54 68,126.54 68,126.54 68,126.54 25% 17,031.63 4,257.91 89,416.08 89,416.08 1.78% 1.78%
1102 (1) Panelboard with Main & Branch Breakers 1.00 1.00 l.s. 15,653.14 15,653.14 15,653.14 15,653.14 25% 3,913.28 978.32 20,544.74 20,544.74 0.41% 0.41%
1103(1) Lighting Fixtures and Lamps 1.00 1.00 l.s. 47,780.77 47,780.77 47,780.77 47,780.77 25% 11,945.19 2,986.30 62,712.26 62,712.26 1.25% 1.25%
1200(13)a Airconditioning ( Split type ) 1.00 1.00 l.s. 146,548.88 146,548.88 146,548.88 146,548.88 25% 36,637.22 9,159.31 192,345.41 192,345.41 3.82% 3.82%
20/90
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02A-00
(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND
PART III
SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 51.76 m
3 12,108.38 25% 3,027.10 756.77 3,783.87 15,892.25 307.04
803(1)a Structure Excavation (Common Soil)
As Evaluated 51.76 m3 12,108.38 25% 3,027.10 756.77 3,783.87 15,892.25 307.04
As Submitted 51.13 m
3 8,035.89 25% 2,008.97 502.24 2,511.21 10,547.10 206.30
804(1)a Embankment From Structure Excavation
As Evaluated 51.13 m3 8,035.89 25% 2,008.97 502.24 2,511.21 10,547.10 206.30
As Submitted 35.25 m
3 10,877.70 25% 2,719.43 679.86 3,399.29 14,276.99 405.02
804(1)b Embankment from Borrow
As Evaluated 35.25 m3 10,877.70 25% 2,719.43 679.86 3,399.29 14,276.99 405.02
As Submitted 31,021.97 7,755.50 1,938.87 9,694.37 40,716.34
TOTAL OF PART A
As Evaluated 31,021.97 7,755.50 1,938.87 9,694.37 40,716.34
Page 21 of 90
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02A-00
Page 22 of 90
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02A-00
Page 23 of 90
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02A-00
Page 24 of 90
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02A-00
Conduits, Boxes & Fittings (Conduit Works/Conduit As Submitted 1.00 l.s. 19,709.77 25% 4,927.44 1,231.86 6,159.30 25,869.07 25,869.07
1100(10)
Rough-in)
As Evaluated 1.00 l.s. 19,709.77 25% 4,927.44 1,231.86 6,159.30 25,869.07 25,869.07
As Submitted 1.00 l.s. 68,126.54 25% 17,031.64 4,257.91 21,289.55 89,416.09 89,416.08
1101(33) Wires and Wiring Devices
As Evaluated 1.00 l.s. 68,126.54 25% 17,031.64 4,257.91 21,289.55 89,416.09 89,416.08
As Submitted 1.00 l.s. 15,653.14 25% 3,913.29 978.32 4,891.61 20,544.75 20,544.74
1102 (1) Panelboard with Main & Branch Breakers
As Evaluated 1.00 l.s. 15,653.14 25% 3,913.29 978.32 4,891.61 20,544.75 20,544.74
As Submitted 1.00 l.s. 47,780.77 25% 11,945.19 2,986.30 14,931.49 62,712.26 62,712.26
1103(1) Lighting Fixtures and Lamps
As Evaluated 1.00 l.s. 47,780.77 25% 11,945.19 2,986.30 14,931.49 62,712.26 62,712.26
As Submitted 1.00 l.s. 146,548.88 25% 36,637.22 9,159.31 45,796.53 192,345.41 -
1200(13)a Airconditioning ( Split type )
As Evaluated 1.00 l.s. 146,548.88 25% 36,637.22 9,159.31 45,796.53 192,345.41 -
As Submitted 297,819.10 74,454.78 18,613.70 93,068.48 390,887.58
TOTAL OF PART D
As Evaluated 297,819.10 74,454.78 18,613.70 93,068.48 390,887.58
As Submitted 3,343,841.46 835,960.45 208,990.10 1,044,950.55 4,388,792.01
TOTAL OF PART III
As Evaluated 3,343,841.46 835,960.45 208,990.10 1,044,950.55 4,388,792.01
As Submitted 3,834,429.47 880,895.53 234,675.00 1,115,570.53 4,950,000.00
TOTAL OF (Project ID)
As Evaluated 3,834,429.47 880,895.53 234,675.00 1,115,570.53 4,950,000.00
Page 25 of 90
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02-00
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND
PART III
SANITARY/PLUMBING WORKS
As Submitted 31,021.97 25.00% 7,755.50 1,938.87 9,694.37 40,716.34
PART A EARTHWORKS
As Evaluated 31,021.97 25.00% 7,755.50 1,938.87 9,694.37 40,716.34
As Submitted 1,194,960.78 25.00% 298,740.20 74,685.05 373,425.25 1,568,386.03
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Evaluated 1,194,960.78 25.00% 298,740.20 74,685.05 373,425.25 1,568,386.03
As Submitted 1,820,039.61 25.00% 455,009.97 113,752.48 568,762.45 2,388,802.06
PART C FINISHING
As Evaluated 1,820,039.61 25.00% 455,009.97 113,752.48 568,762.45 2,388,802.06
As Submitted 297,819.10 25.00% 74,454.78 18,613.70 93,068.48 390,887.58
PART D ELECTRICAL WORKS
As Evaluated 297,819.10 25.00% 74,454.78 18,613.70 93,068.48 390,887.58
As Submitted 3,343,841.46 835,960.45 208,990.10 1,044,950.55 4,388,792.01
Total of Part III
As Evaluated 3,343,841.46 835,960.45 208,990.10 1,044,950.55 4,388,792.01
As Submitted 3,834,429.47 880,895.53 234,675.00 1,115,570.53 4,950,000.00
TOTAL OF (Project ID)
As Evaluated 3,834,429.47 880,895.53 234,675.00 1,115,570.53 4,950,000.00
As Submitted 3,834,429.47 880,895.53 234,675.00 1,115,570.53 4,950,000.00
TOTAL
As Evaluated 3,834,429.47 880,895.53 234,675.00 1,115,570.53 4,950,000.00
JIM PAUL K. ABRIL FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Engineer II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
26/90
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Lucena City, Quezon
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Plate Compactor ( 400-500 Gasoline Engine) 5 Hp 1 31
2 One Bagger Mixer 4-6 ft3/min 1 32
3 Bar Bender (25 mm Maximum Rebar Ø) Three Phase 1 33
4 Bar Cutter (25 mm Maximum Rebar Ø (Grade 40), Single Phase 1 34
5 Welding Machine (Electric Driven/DC Output) 500Amp 1 35
6 Backhoe 0.8 cu.m. 1 36
7 Dump Truck 12 cu.yd. 1 37
8 38
9 39
10 40
11 41
12 42
13 43
14 44
15 45
16 46
17 47
18 48
19 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL 7 SUB-TOTAL
TOTAL 7
27/27
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
A.1 Labor
Item no./Description : B.7(2) Construction Safety and Health (PPE, Safety Personnel, Disinfection)
Unit of Measurement : lot
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
A.1 Labor
a. Safety Practitioner/Officer (Part Time) 1 1920.0 62.50 120,000.00
b. Health Personnel (Full Time First Aider) 1 1920.0 35.00 67,200.00
c. Sanitation Aide 1 1920.0 35.00 67,200.00
B.1 Equipment
Antiseptics
a. Sanitizing Solution lit 110 100.00 11,000.00
b. Ethyl Alcohol lit 36 185.00 6,660.00
c. Disinfectant Spray can 18 1,000.00 18,000.00
d. Liquid Hand Soap lit 18 200.00 3,600.00
Item no./Description : B.7(2) Construction Safety and Health (PPE, Safety Personnel, Disinfection)
Unit of Measurement : lot
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
Part A - Earthworks
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Part A - Earthworks
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
3
a. Embankment Materials m 1.25 214.84 268.56
(w/ 25% Shrinkage Factor)
Part A - Earthworks
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
PART B - Plain and Reinforced Concrete Works
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
a. 1.22m x 2.44m x 19mm thick Penolic Board - 5 uses sheet 0.347 1,450.00 100.63
b. Good Lumber - 4 uses bd ft 4.727 60.00 70.91
c. CWN kg 0.208 80.00 16.64
d. Consumables (5% of Material Cost) 9.41
a. 1.22m x 2.44m x 19mm thick Penolic Board - 5 uses sheet 0.347 1,450.00 100.63
b. Good Lumber - 4 uses bd ft 4.727 60.00 70.91
c. CWN kg 0.208 80.00 16.64
d. Consumables (5% of Material Cost) 9.41
B.1 Equipment
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Item No./Description : 1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm
Unit of Measurement : m2
Output per hour : 3.825
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Item No./Description : 1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm
2
Unit of Measurement : m
Output per hour : 3.18
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
A.1 Labor
B.1 Equipment
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay San Andres, Candelaria, Quezon
A.1 Labor
B.1 Equipment
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Item No./Description : 1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions)
Unit of Measurement : set
Output : 1
A.1 Labor
B.1 Equipment
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
A.1 Labor
B.1 Equipment
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
A.1 Labor
B.1 Equipment
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
(Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)
(Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
A.1 Labor
B.1 Equipment
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
PART C - Finishing
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Item No./Description : 1003 (1)a1 Ceiling (4.5mm Fiber Cement Board, Metal Frame)
Unit of Measurement : m2
Output per hour : 1.243
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
A.1 Labor
B.1 Equipment
F.1 Materials
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Item No./Description : 1014(1)b1 Prepainted Metal Sheets (above 0.427mm) Corrugated Type Long Span
Unit of Measurement : m2
Output per hour : 2.076
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Item No./Description : 1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Roll, gauge 26)
Unit of Measurement : m
Output per hour : 10
B.1 Equipment
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Item No./Description : 1013(2)b1 Fabricated Metal Roofing Accessory (Gutters, gauge 24)
Unit of Measurement : m
Output per hour : 5
B.1 Equipment
F.1 Materials
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Item No./Description : 1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, gauge 26)
Unit of Measurement : m
Output per hour : 10
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Fabrication
a. Construction Foreman 1 1.00 102.73 102.73
b. Skilled Laborer 2 1.00 74.22 148.44
c. Unskilled Laborer 2 1.00 57.17 114.34
Erection
a. Skilled Laborer 3 0.50 74.22 111.33
b. Unskilled Laborer 3 0.50 57.17 85.76
Fabrication
a. Construction Foreman 1 1.00 102.73 102.73
b. Skilled Laborer 2 1.00 74.22 148.44
c. Unskilled Laborer 2 1.00 57.17 114.34
Erection
a. Skilled Laborer 3 0.50 74.22 111.33
b. Unskilled Laborer 3 0.50 57.17 85.76
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
a. Water Closet complete w/ fittings & accs. sets 2.00 7,500.00 15,000.00
b. Wall Hung Lavatory, complete w/ fittings & accs. sets 2.00 4,600.00 9,200.00
c.S.S. Floor Drain 4'x4'' pcs 4.00 250.00 1,000.00
d. Kitchen Faucet pcs 1.00 1,500.00 1,500.00
e. Bidet Sprayer Set with T-Adapter Valve pcs 2.00 1,000.00 2,000.00
f. Faucet, Hose Bibb, Brass 12mm dia. pcs 2.00 250.00 500.00
g. Kitchen Sink set 1.00 5,100.00 5,100.00
h. Mirror ft2 1.44 700.00 1,008.00
i. Urinal set 2.00 3,100.00 6,200.00
j. Consumables (5% of Materials) 1,765.40
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings And Other Structures, Multipurpose/Facilities,
Construction of Multi-Purpose Building (Barangay Hall), Barangay Isabang, Lucena City, Quezon
Item No./Description : 1102 (1) Panelboard with Main & Branch Breakers
Unit of Measurement : l.s.
Output per hour : 1
Panelboard with Main & Branch Breakers set 1.00 15,000.00 15,000.00
Br.: 4-30AT,50AF,2P,240V
1-100AT,120AF,2P,240V
Panelboard with Main & Branch Breakers set 1.00 15,000.00 15,000.00
Br.: 4-30AT,50AF,2P,240V
1-100AT,120AF,2P,240V