Quality 

Control in Civil Works 2021‐04‐09

Module 1
Unit. II.  Quality Dimensions

Agenda
• Review

• Historical Evolution of Quality

• Quality Process

• Quality in the project Life Cycle

I Semester 2021 Dr. Milagros Pinto‐Nunez© 2

Class Notes 1
Quality Control in Civil Works 2021‐04‐09

Identify the main 
Review concepts of 
participants of a 
technical 
Construction 
specifications.
project.

Learning  Define and discuss 
the relevant 
Discuss the 
dimensions of 
Objectives concepts of Quality 
Control.
quality.

Identify the role of 
the Civil Engineer 
within the Quality 
Management.

I Semester 2021

1‐Review

Dr. Milagros Pinto‐Nunez© I Semester 2021 4

Class Notes 2
Quality Control in Civil Works 2021‐04‐09

• Quality in the construction of civil works is


defined as customer satisfaction with the
result or service provided by a certain
product/service.
• In construction, expectations are based on
Quality  technical documents (tender documents)
such as construction plans, designs,
Control in  specifications, contract.
Civil Works • In manufacturing “Control” means
“systematic planning, coordinating, and
directing of all manufacturing activities and
influences to ensure having goods made on
time, of adequate quality, and at reasonable
cost.” (Merriam‐Webster, 2021)

I Semester 2021 Dr. Milagros Pinto‐Nunez© 6

QC of Project: Planning, 
drawings, calculations.

Quality 
Control Phases QC of Materials

QC of Construction Methods

Class Notes 3
Quality Control in Civil Works 2021‐04‐09

Prof. Milagros Pinto N.

 Exterior urbanization,   Paintings.
earthworks, landfills.  Lifting devices.
 Slabs and pavements.
 Electrical regulation (low, 
Elements that   Foundations. medium and high voltage).
 Concrete and steel  Heating, air conditioning
undergo QC in  elements. and hot water.
construction   Metallic structures.  Sanitary systemPhotovoltaic
and thermosolar
 Wooden structures.
projects plates.Indoor water supply
 Blocks or other elements for facilities.
enclosures and partitions
(Alternative Systems)  Oil installations for own use.

 Coating materials and   Refrigeration plants and 


mortars. facilities.
 Fire protection.
 Waterproofing and thermal
insulation materials.  ETC.

9/4/2021 10

10

Responsibilities of Civil Engineer – Panama
Design – Build – Inspect ‐ Consultant

Roads,  Buildings,  Dams,  Tunnels, 

Bridges,  Ports,  Airports,  Railways, 

Water 
Sewers,  Aqueducts,  treatment  and Etc.
plants
I Semester 2021 Dr. Milagros Pinto‐Nunez© 11

11

Class Notes 4
Quality Control in Civil Works 2021‐04‐09

Dr. Milagros Pinto‐Nunez©

Responsibilities of Civil Engineer ‐ Consultant
• In the role of consultant,  Civil Engineer faces a series of responsibilities, inherent to 
the study and design of a project. 

• These responsibilities are:

• Search, investigate and analyze the location and characteristics of the site and also 
verify its feasibility for construction purposes.

• Organize, direct and develop the detailed engineering design, according to the 
clients' requirements.

• Assess the potential risks and challenges of the project.
I Semester 2021 12

12
Dr. Milagros Pinto‐Nunez©

Responsibilities of Civil Engineer 
Prime Contractor
• The Contractor is in charge of directing the execution of the project, in accordance with the plans and 
technical specifications. 
• In addition, She/He must ensure the quality and the best use of materials, equipment, tools and human 
resources within the work.
• The responsibilities are:
• Coordinate and execute all the necessary activities before construction (cleaning, declaration of 
permits, temporary installations, etc.).
• Manage and monitor the financial and legal information of the project.
• Know and enforce the requirements established in the work contract.

I Semester 2021 13

13

Class Notes 5
Quality Control in Civil Works 2021‐04‐09

Dr. Milagros Pinto‐Nunez©

Responsibilities of Civil Engineer 
Prime Contractor
• Carry out control, billing and monitoring procedures for all project activities (recurring taxes, 
contracted basic services, supply of materials, payroll, insurance, among others).
• Updating, monitoring, adaptation and compliance with the work schedule.
• Review and supervise As‐Built plans.
• Supervise and guarantee the quality of materials and equipment.
• Coordinate and interact constantly with subcontractors and department heads in the project 
(periodic follow‐up and progress meetings)

I Semester 2021 14

14

Evolution of 
Quality
Review PDF document in Moodle

Dr. Milagros Pinto‐Nunez© I Semester 2021 15

15

Class Notes 6
Quality Control in Civil Works 2021‐04‐09

5‐Step Construction Quality Control Process

1. Define and Share the Acceptance Criteria 
– The definition of “done”.
Some of the standards that might be incorporated into the 
acceptance criteria include:
• No visible defects
• Complies with minimum code standards
• Meets all manufacturers’ specifications
• Conforms to the customer’s contract specifications
• Specific organizational preferences
• Project‐specific quality standards
• Industry common practices

Dr. Milagros Pinto‐Nunez© I Semester 2021 17

17

5‐Step Construction Quality Control Process

2‐ Create an Inspection Plan

The inspection process allows you to determine 
whether a specific task was completed to the 
specifications. 
It’s how you know you have met the acceptance 
criteria that were defined in the first step. 
The team needs to know what will be inspected, 
when inspections will happen, and who is 
responsible for doing them. 
In some cases, this might be third‐party inspectors. This Photo by Unknown Author is licensed under CC BY

Dr. Milagros Pinto‐Nunez© I Semester 2021 18

18

Class Notes 7
Quality Control in Civil Works 2021‐04‐09

5‐Step Construction Quality Control Process

3‐ Use Checklists to Conduct 
Inspections

• Quality inspection checklists can help you stay


organized and ensure that all critical items are
verified. However, not all checklists are equally
effective and they are not always properly used.
• One of the many benefits of using checklists is
that they can be shared with the team before the
This Photo by Unknown Author is licensed under CC BY project starts and prior to each work task to
communicate critical requirements.
Dr. Milagros Pinto‐Nunez© I Semester 2021 19

19

5‐Step of Construction Quality Control Process

4‐ Correct Deficiencies and Verify Acceptance 
Criteria
• When deficiencies have been identified through the inspection 
process, subs and crews must correct them. The process is to:
• Physically mark the issue or area to prevent coverup
• Take a picture to clearly identify the issue and show how it’s marked in 
the field
• Correct the issue
• Document the correction
Dr. Milagros Pinto‐Nunez© I Semester 2021 20

20

Class Notes 8
Quality Control in Civil Works 2021‐04‐09

5‐Step of Construction Quality Control Process

5. Prevent Future Deficiencies


• The final step closes the loop. Learn why the deficiency happened and
adjust the quality control process so it doesn’t happen again.
• Make sure the item is included in the acceptance criteria and
communicated to all parties.
• Add to your checklist system and include it in your inspection plan.
• Success is when you don’t see the issue again and you are that much closer
to achieving first time quality with zero defects.

Dr. Milagros Pinto‐Nunez© I Semester 2021 21

21
Dr. Milagros Pinto‐Nunez©

Q
U
A
Remember L
I
T
Y

I Semester 2021 27

27

Class Notes 9
Quality Control in Civil Works 2021‐04‐09

Example of WBS
Name of The 
Project

Construction

Foundations Slab Column Beams Ceilings

Dr. Milagros Pinto‐Nunez© I Semester 2021 28

28
Dr. Milagros Pinto‐Nunez©

Discussion…

• In a hypothetical scenario, you are an inspector required to check the


reinforcement of a footing. According to the drawings, the
reinforcement is #5, but you realized that the footing has #7 bars. You
are in the middle of the inspection, and the mixer has just arrived at
the construction site. What would you do? Do you allow to pour the
concrete in the footing with #7 reinforcement?
• En  un  escenario  hipotético,  usted  es  un  inspector  que  debe  verificar  el 
refuerzo de una zapata. Según los dibujos, el refuerzo es el #5, pero se 
dio  cuenta  de  que  la  zapata  tiene  barras  #7.  Está  en  medio  de  la 
inspección  y  “la  tula”  acaba  de  llegar  al  sitio  de  construcción.  ¿Qué 
harías? ¿Permite verter el concreto en la zapata con refuerzo #7?
I Semester 2021 29

29

Class Notes 10
Quality Control in Civil Works 2021‐04‐09

https://youtu.be/74JNl5n‐YdI

Case Study

After watching the following 
video:
Indicate the failures in the 
Quality Management system 
(QA and QC)
I Semester 2021 30

30

Class Notes 11