You are on page 1of 19

Domestic Water Booster Pump Calculation

Green Oasis (Strip Mall) Project

Pump Schedule given as follows

Flow in Head in
S.No. Building Location Quantity Unit Remarks
GPM Metre
1 Thumama A Part A 70 50 1 Duty + 1 Standby Set

2 Thumama A Part B 65 60 1 Duty + 1 Standby Set

3 Thumama B Part A 60 50 1 Duty + 1 Standby Set

4 Thumama B Part B 70 50 1 Duty + 1 Standby Set

5 Shahaba Part A 70 60 1 Duty + 1 Standby Set

6 Shahaba Part B 75 60 1 Duty + 1 Standby Set

7 Shahaba Part C 70 50 1 Duty + 1 Standby Set


Project: The Green Oasis Mall - Thumama A ( Part - A )
Subject: Water Supply Demand load selection by using Fixture units As per UPC System
Occupancy: Private
Fixture / Trim Quantity Demand
Total Demand
S.No. Fixture Weight in
Basement Ground Mezzanine First Second Roof Total Qty in Fixture Units
Fixture Units
European Water
1 9 19 6 34 3 102
Closet
2 Perenial Spray 9 19 6 34 1 34
3 Lavatory 9 18 6 33 1 33
4 Kitchen Sink 14 6 20 2 40
5 Hose Bibb 8 4 3 15 1 15
Total Demand in Fixture Units 224

Selected Demand As Per UPC Chart 18-2 for 224 Fixture Unit will be 70 Gallons/Minute

Project: The Green Oasis Mall - Thumama A ( Part - B )


Subject: Water Supply Demand load selection by using Fixture units As per UPC System
Occupancy: Private
Fixture / Trim Quantity Demand
Total Demand
S.No. Fixture Weight in
Basement Ground Mezzanine First Second Roof Total Qty in Fixture Units
Fixture Units
European Water
1 6 4 16 5 31 3 93
Closet
2 Perenial Spray 6 4 16 5 31 1 31

3 Lavatory 6 4 15 5 30 1 30

4 Kitchen Sink 1 11 4 16 2 32

5 Hose Bibb 7 3 10 1 10

Total Demand in Fixture Units 196

Selected Demand As Per UPC Chart 18-2 for 196Fixture Unit will be 65 Gallons/Minute
Project: The Green Oasis Mall - Thumama B ( Part - A )
Subject: Water Supply Demand load selection by using Fixture units As per UPC System
Occupancy: Private
Fixture / Trim Quantity Demand
Total Demand
S.No. Fixture Weight in
in Fixture Units
Basement Ground First Second Roof Total Qty Fixture Units
European Water
1 6 16 4 26 3 78
Closet
2 Perenial Spray 6 16 4 26 1 26

3 Lavatory 6 16 4 26 1 26

4 Kitchen Sink 10 4 14 2 28

5 Hose Bibb 8 2 10 1 10

Total Demand in Fixture Units 168

Selected Demand As Per UPC Chart 18-2 for 168 Fixture Unit will be 60 Gallons/Minute
Project: The Green Oasis Mall - Thumama B ( Part - B )
Subject: Water Supply Demand load selection by using Fixture units As per UPC System
Occupancy: Private
Fixture / Trim Quantity Demand
Total Demand in
S.No. Fixture Weight in
Fixture Units
Basement Ground Mezanine First Second Roof Total Qty Fixture Units
European Water
1 7 8 19 5 39 3 117
Closet
2 Perenial Spray 7 8 19 5 39 1 39

3 Lavatory 7 7 18 5 37 1 37

4 Kitchen Sink 10 4 14 2 28

5 Hose Bibb 5 3 8 1 8

Total Demand in Fixture Units 229

Selected Demand As Per UPC Chart 18-2 for 229 Fixture Unit will be 70 Gallons/Minute
Project: The Green Oasis Mall - Shahaba ( Part - A )
Subject: Water Supply Demand load selection by using Fixture units As per UPC System
Occupancy: Private
Fixture / Trim Quantity Demand
Total Demand in
S.No. Fixture Weight in
Basement Ground Mezanine First Second Roof Total Qty Fixture Units
Fixture Units
European Water
1 10 2 24 8 44 3 132
Closet
2 Perenial Spray 10 2 24 8 44 1 44

3 Lavatory 10 2 23 8 43 1 43

4 Kitchen Sink 8 8 2 16

5 Hose Bibb 15 3 4 22 1 22

Total Demand in Fixture Units 257

Selected Demand As Per UPC Chart 18-2 for 257 Fixture Unit will be 70 Gallons/Minute
Project: The Green Oasis Mall - Shahaba ( Part - B )
Subject: Water Supply Demand load selection by using Fixture units As per UPC System
Occupancy: Private
Fixture / Trim Quantity Demand
Total Demand in
S.No. Fixture Weight in
Basement Ground Mezanine First Second Roof Total Qty Fixture Units
Fixture Units
European Water
1 10 3 23 8 44 3 132
Closet
2 Perenial Spray 10 3 23 8 44 1 44

3 Lavatory 10 3 22 8 43 1 43

4 Kitchen Sink 19 8 27 2 54

5 Hose Bibb 10 3 3 16 1 16

Total Demand in Fixture Units 289

Selected Demand As Per UPC Chart 18-2 for 289 Fixture Unit will be 75 Gallons/Minute
Project: The Green Oasis Mall - Shahaba ( Part - C )
Subject: Water Supply Demand load selection by using Fixture units As per UPC System
Occupancy: Private
Fixture / Trim Quantity Demand
Total Demand in
S.No. Fixture Weight in
Basement Ground Mezanine First Second Roof Total Qty Fixture Units
Fixture Units
European Water
1 8 0 19 6 33 3 99
Closet
2 Perenial Spray 8 0 19 6 33 1 33
3 Lavatory 8 0 18 6 32 1 32
4 Kitchen Sink 15 6 21 2 42
5 Hose Bibb 8 3 2 13 1 13
Total Demand in Fixture Units 219

Selected Demand As Per UPC Chart 18-2 for 219 Fixture Unit will be 70 Gallons/Minute
Project: The Green Oasis Mall - Thumama A ( Part - A )
Subject: Water Booster Pump Head Selection

Pipe Length Friction Loss / Total Friction


S.No. Section Item Fixture Unit GPM Pipe Size
in Feet 100 Ft Loss in Feet

1 AB Pipe 224 70 65mm 12 1.5 0.18


2 BC Pipe 224 70 65mm 12 1.5 0.18
3 CD Pipe 216 70 65mm 6 1.5 0.09
4 DE Pipe 158 60 50mm 5 3 0.15
5 EF Pipe 129 50 50mm 1 2.2 0.022
6 FG Pipe 104 45 50mm 48 2 0.96
7 GH Pipe 79 40 50mm 44 1.4 0.616
8 HI Pipe 54 30 50mm 31 1 0.31
9 IJ Pipe 29 23 32mm 39 6 2.34
10 JK Pipe 29 23 32mm 40 6 2.4
11 KL Pipe 14 15 32mm 15 2.5 0.375
12 LM Pipe 1 1 20mm 5 0.1 0.005
13 MN Pipe 1 1 20mm 4 0.1 0.004
Total friction loss in Feet 8
Friction Loss in Total Friction
S.No. Section Item Fixture Unit GPM Size Quantity
Feet Loss in Feet
1 A1 Flexible 224 70 65mm 1 2.5 2.5
2 A2 Check Valve 224 70 65mm 1 25 25
3 A3 Gate Valve 224 70 65mm 1 2.8 2.8
4 B Elbow 45 deg 224 70 65mm 1 5 5
5 C Elbow 45 deg 224 70 65mm 1 5 5
6 C Tee 224 70 65mm 1 2.5 2.5
7 D Tee 216 70 65mm 1 2.5 2.5
8 E Tee 158 60 50mm 1 2 2
9 F Tee 129 50 50mm 1 2 2
10 G Tee 104 45 50mm 1 2 2
11 H Tee 79 40 50mm 1 2 2
12 I Tee 54 30 50mm 1 2 2
13 J Elbow 29 23 32mm 1 4 4
14 K Tee 29 23 32mm 1 1.2 1.2
15 L Tee 14 15 32mm 1 1.2 1.2
16 M Elbow 1 1 20mm 1 2 2
Total friction loss in Feet 64
Grand Total friction loss in Feet 71 Feet
19 Metres
''Say 20 metres
Total Head Loss = Total Friction Loss + Static Head
= 20+20
= 40 m
= 4 bar
Considering 10% Safety Factor
= 4.5 bar
Say = 5 bar
Project: The Green Oasis Mall - Thumama A ( Part -B )
Subject: Water Booster Pump Head Selection

Pipe Length Friction Loss / Total Friction


S.No. Section Item Fixture Unit GPM Pipe Size
in Feet 100 Ft Loss in Feet

1 AB Pipe 196 65 65mm 12 1.3 0.156


2 BC Pipe 196 65 65mm 7 1.3 0.091
3 CD Pipe 196 65 65mm 4 1.3 0.052
4 DE Pipe 196 65 65mm 5 1.3 0.065
5 EF Pipe 188 65 65mm 8 1.3 0.104
6 FG Pipe 173 60 50mm 1 3 0.03
7 GH Pipe 139 50 50mm 30 2.2 0.66
8 HI Pipe 124 45 50mm 31 2 0.62
9 IJ Pipe 104 45 50mm 47 2 0.94
10 JK Pipe 55 30 40mm 45 3.5 1.575
11 KL Pipe 30 23 32mm 40 6 2.4
12 LM Pipe 30 23 32mm 40 6 2.4
13 MN Pipe 14 15 32mm 15 2.5 0.375
14 NO Pipe 1 1 20mm 5 0.1 0.005
15 OP Pipe 1 1 20mm 4 0.1 0.004
Total friction loss in Feet 9
Friction Loss in Total Friction
S.No. Section Item Fixture Unit GPM Size Quantity
Feet Loss in Feet
1 A1 Flexible 196 65 65mm 1 2.5 2.5
2 A2 Check Valve 196 65 65mm 1 25 25
4 A3 Gate Valve 196 65 65mm 1 2.8 2.8
5 B Elbow 196 65 65mm 1 8 8
6 C Elbow 45 deg 196 65 65mm 1 5 5
7 D Elbow 45 deg 196 65 65mm 1 5 5
8 D Tee 196 65 65mm 1 2.5 2.5
9 E Elbow 196 65 65mm 1 8 8
10 F Tee 188 65 65mm 1 2.5 2.5
11 G Tee 173 60 50mm 1 2 2
12 H Tee 139 50 50mm 1 2 2
13 I Elbow 124 45 50mm 1 7 7
14 J Tee 104 45 50mm 1 2 2
15 K Tee 55 30 40mm 1 1.5 1.5
16 L Elbow 30 23 32mm 1 4 4
17 M Tee 30 23 32mm 1 1.2 1.2
18 N Tee 14 15 32mm 1 1.2 1.2
19 O Elbow 1 1 20mm 1 2 2
Total friction loss in Feet 84
Grand Total friction loss in Feet 94 Feet
28 Metres
''Say 30 metres
Total Head Loss = Total Friction Loss + Static Head
= 30+20
= 50 m
= 5 bar
Considering 10% Safety Factor
= 5.5 bar
Say = 6 bar
Project: The Green Oasis Mall - Thumama B ( Part - A )
Subject: Water Booster Pump Head Selection

Pipe Length Friction Loss / Total Friction


S.No. Section Item Fixture Unit GPM Pipe Size
in Feet 100 Ft Loss in Feet

1 AB Pipe 168 60 65mm 8.25 1 0.0825


2 BC Pipe 168 60 65mm 4 1 0.04
3 CD Pipe 168 60 65mm 9 1 0.09
4 DE Pipe 168 60 65mm 4 1 0.04
5 EF Pipe 168 60 65mm 5 1 0.05
6 FG Pipe 52 30 50mm 42 0.9 0.378
7 GH Pipe 52 30 50mm 64 0.9 0.576
8 HI Pipe 28 17 32mm 40 2 0.8
9 IJ Pipe 28 17 32mm 32.34 2 0.6468
10 JK Pipe 14 17 25mm 14.5 2 0.29
11 KL Pipe 1 1 20mm 3.3 1 0.033
Total friction loss in Feet 3
Friction Loss in Total Friction
S.No. Section Item Fixture Unit GPM Size Quantity
Feet Loss in Feet
1 A1 Flexible 168 60 65mm 1 2.5 2.5
2 A2 Check Valve 168 60 65mm 1 25 25
4 A3 Gate Valve 168 60 65mm 1 2.8 2.8
5 B Elbow 90 deg 168 60 65mm 1 8 8
5 C Elbow 90 deg 168 60 65mm 1 8 8
8 D Elbow 45 deg 168 60 65mm 1 5 5
10 E Elbow 45 deg 168 60 65mm 1 5 5
12 F Tee 168 35 50mm 1 2 2
14 G Tee 76 35 50mm 1 2 2
16 H Elbow 52 30 50mm 1 7 7
18 I Elbow 28 17 32mm 1 4 4
20 J Tee 28 17 32mm 1 1.2 1.2
22 K Tee 14 17 25mm 1 1.2 1.2
24 L Elbow 1 1 25mm 1 2.5 2.5
Total friction loss in Feet 76
Grand Total friction loss in Feet 79 Feet
23 Metres
''Say 25 metres
Total Head Loss = Total Friction Loss + Static Head
= 25+20
= 45 m
= 4.5 bar
Considering 10% Safety Factor
= 5 bar
Project: The Green Oasis Mall - Thumama B ( Part -B )
Subject: Water Booster Pump Head Selection

Pipe Length Friction Loss / Total Friction


S.No. Section Item Fixture Unit GPM Pipe Size
in Feet 100 Ft Loss in Feet

1 AB Pipe 229 70 65mm 12 1.5 0.18


2 BC Pipe 229 70 65mm 10.5 1.5 0.1575
3 CD Pipe 224 70 65mm 3.62 1.5 0.0543
4 DE Pipe 118 50 50mm 52.5 2.4 1.26
5 EF Pipe 94 40 50mm 1 1 0.01
6 FG Pipe 70 35 50mm 57 1.2 0.684
7 GH Pipe 46 30 50mm 27.5 0.9 0.2475
8 HI Pipe 20 15 32mm 40 2.5 1
9 IJ Pipe 20 15 32mm 14.5 2.5 0.3625
10 JK Pipe 15 10 32mm 14.5 1.2 0.174
11 KL Pipe 15 10 32mm 19 1.2 0.228
12 LM Pipe 8 8 25mm 19 1.8 0.342
13 MN Pipe 1 1 20mm 3.3 0.2 0.0066
14 NO Pipe 1 1 20mm 3.3 0.2 0.0066
15 OP Pipe 1 1 20mm 16.5 0.2 0.033
Total friction loss in Feet 5
Friction Loss in Total Friction
S.No. Section Item Fixture Unit GPM Size Quantity
Feet Loss in Feet
1 A1 Flexible 229 70 65mm 1 2.5 2.5
2 A2 Check Valve 229 70 65mm 1 25 25
4 A3 Gate Valve 229 70 65mm 1 2.8 2.8
5 B Elbow 45 deg 229 70 65mm 1 5 5
6 C Elbow 45 deg 229 70 65mm 1 5 5
7 C Tee 229 70 65mm 1 2.5 2.5
8 D Tee 224 70 65mm 1 2.5 2.5
9 E Tee 118 50 50mm 1 2 2
10 F Tee 94 40 50mm 1 2 2
11 G Tee 70 35 50mm 1 2 2
12 H Tee 46 30 50mm 1 2 2
13 I Elbow 20 15 32mm 1 4 4
14 J Tee 20 15 32mm 1 1.2 1.2
15 K ---N/A--- 15 10 32mm 1 0
16 L Tee 15 10 32mm 1 1.2 1.2
17 M Tee 8 8 25mm 1 0.9 0.9
18 N Elbow 1 1 25mm 1 3 3
19 O Elbow 1 1 25mm 1 3 3
Total friction loss in Feet 67
Grand Total friction loss in Feet 71 Feet
22 Metres
''Say 25 metres
Total Head Loss = Total Friction Loss + Static Head
= 25+20
= 45 m
= 4.5 bar
Considering 10% Safety Factor
= 5 bar
Project: The Green Oasis Mall - Shahaba ( Part - A )
Subject: Water Booster Pump Head Selection

Pipe Length Friction Loss / Total Friction


S.No. Section Item Fixture Unit GPM Pipe Size
in Feet 100 Ft Loss in Feet

1 AB Pipe 257 70 65mm 12 1.4 0.168


2 BC Pipe 257 70 65mm 12 1.4 0.168
3 CD Pipe 242 70 65mm 5 1.4 0.07
4 DE Pipe 196 65 65mm 5 1.3 0.065
5 EF Pipe 172 60 65mm 27 1.2 0.324
6 FG Pipe 158 60 65mm 21 1.2 0.252
7 GH Pipe 131 50 65mm 43 0.8 0.344
8 HI Pipe 107 45 65mm 2 0.7 0.014
9 IJ Pipe 78 40 65mm 60 0.5 0.3
10 JK Pipe 53 30 50mm 60 0.7 0.42
11 KL Pipe 29 23 32mm 40 5 2
12 LM Pipe 29 23 32mm 27 5 1.35
13 MN Pipe 14 15 32mm 14 2.5 0.35
14 NO Pipe 1 1 20mm 5 0.1 0.005
15 OP Pipe 1 1 20mm 4 0.1 0.004
Total friction loss in Feet 6
Friction Loss in Total Friction
S.No. Section Item Fixture Unit GPM Size Quantity
Feet Loss in Feet
1 A1 Flexible 257 70 65mm 1 2.5 2.5
2 A2 Check Valve 257 70 65mm 1 25 25
3 A3 Gate Valve 257 70 65mm 1 2.8 2.8
4 B Elbow 257 70 65mm 1 8 8
5 C Elbow 257 70 65mm 1 8 8
6 D Elbow 45 deg 196 65 65mm 1 5 5
7 D Tee 196 65 65mm 1 2.5 2.5
8 E Elbow 172 60 65mm 1 8 8
9 F Tee 158 60 65mm 1 2.5 2.5
10 G Tee 131 50 65mm 1 2.5 2.5
11 H Tee 107 45 65mm 1 2.5 2.5
12 I Tee 78 40 65mm 1 2.5 2.5
13 J Elbow 53 30 50mm 1 7 7
14 K Tee 29 23 32mm 1 1.2 1.2
15 L Elbow 29 23 32mm 1 4 4
16 M Tee 14 15 32mm 1 1.2 1.2
17 N Tee 1 1 32mm 1 1.2 1.2
18 O Elbow 1 1 20mm 1 2.5 2.5
Total friction loss in Feet 89
Grand Total friction loss in Feet 95 Feet
27 Metres
''Say 30 metres
Total Head Loss = Total Friction Loss + Static Head
= 30+20
= 50 m
= 5 bar
Considering 10% Safety Factor
= 5.5 bar
Say = 6 bar
Project: The Green Oasis Mall - Shahaba ( Part -B )
Subject: Water Booster Pump Head Selection

Pipe Length Friction Loss / Total Friction


S.No. Section Item Fixture Unit GPM Pipe Size
in Feet 100 Ft Loss in Feet

1 AB Pipe 289 75 65mm 12 1.7 0.204


2 BC Pipe 289 75 65mm 12 1.7 0.204
3 CD Pipe 279 75 65mm 5 1.7 0.085
4 DE Pipe 204 65 65mm 5 1.4 0.07
5 EF Pipe 180 60 65mm 27 1.2 0.324
6 FG Pipe 152 50 65mm 21 0.8 0.168
7 GH Pipe 127 45 50mm 43 2 0.86
8 HI Pipe 103 45 50mm 2 2 0.04
9 IJ Pipe 78 40 50mm 60 1.5 0.9
10 JK Pipe 53 30 50mm 60 1 0.6
11 KL Pipe 29 23 32mm 40 6 2.4
12 LM Pipe 29 23 32mm 27 6 1.62
13 MN Pipe 15 15 32mm 14 2.5 0.35
14 NO Pipe 1 1 20mm 5 0.1 0.005
15 OP Pipe 1 1 20mm 4 0.1 0.004
Total friction loss in Feet 8
Friction Loss in Total Friction
S.No. Section Item Fixture Unit GPM Size Quantity
Feet Loss in Feet
1 A1 Flexible 289 75 65mm 1 2.5 2.5
2 A2 Check Valve 289 75 65mm 1 25 25
4 A3 Gate Valve 289 75 65mm 1 2.8 2.8
5 B Elbow 289 75 65mm 1 8 8
6 C Elbow 45 deg 289 75 65mm 1 5 5
7 C Tee 289 75 65mm 1 2.5 2.5
8 D Tee 279 75 65mm 1 2.5 2.5
9 E Tee 204 65 65mm 1 2.5 2.5
10 F Tee 180 60 65mm 1 2.5 2.5
11 G Tee 152 65 65mm 1 2.5 2.5
12 H Tee 127 45 50mm 1 2 2
13 I Tee 103 45 50mm 1 2 2
14 J Tee 78 40 50mm 1 2 2
15 K Elbow 53 30 50mm 1 7 7
16 L Elbow 29 23 32mm 1 4 4
17 M Tee 29 23 32mm 1 1.2 1.2
18 N Tee 15 15 32mm 1 1.2 1.2
19 O Elbow 1 1 20mm 1 2.5 2.5
Total friction loss in Feet 78
Grand Total friction loss in Feet 86 Feet
26 Metres
''Say 30 metres
Total Head Loss = Total Friction Loss + Static Head
= 30+20
= 50 m
= 5 bar
Considering 10% Safety Factor
= 5.5 bar
Say = 6 bar
Project: The Green Oasis Mall - Shahaba ( Part -C )
Subject: Water Booster Pump Head Selection

Pipe Length Friction Loss / Total Friction


S.No. Section Item Fixture Unit GPM Pipe Size
in Feet 100 Ft Loss in Feet

1 AB Pipe 219 70 65mm 12 1.4 0.168


2 BC Pipe 219 70 65mm 12 1.4 0.168
3 CD Pipe 211 70 65mm 5 1.4 0.07
4 DE Pipe 105 45 50mm 38 1.9 0.722
5 EF Pipe 80 40 50mm 39 1.5 0.585
6 FG Pipe 53 30 50mm 58 0.1 0.058
7 GH Pipe 29 23 32mm 40 6 2.4
8 HI Pipe 29 23 32mm 27 6 1.62
9 IJ Pipe 15 15 32mm 14 2.5 0.35
10 JK Pipe 1 1 20mm 5 0.1 0.005
11 KL Pipe 1 1 20mm 4 0.1 0.004
Total friction loss in Feet 6
Friction Loss in Total Friction
S.No. Section Item Fixture Unit GPM Size Quantity
Feet Loss in Feet
1 A1 Flexible 219 70 65mm 1 2.5 2.5
2 A2 Check Valve 219 70 65mm 1 25 25
4 A3 Gate Valve 219 70 65mm 1 2.8 2.8
5 B Elbow 219 70 65mm 1 8 8
6 C Elbow 45 deg 219 70 65mm 1 5 5
7 C Tee 219 70 65mm 1 2.5 2.5
8 D Tee 211 70 65mm 1 2.5 2.5
9 E Tee 105 45 50mm 1 2 2
10 F Tee 80 40 50mm 1 2 2
11 G Elbow 53 30 50mm 1 7 7
12 H Elbow 29 23 32mm 1 4 4
13 I Tee 29 23 32mm 1 1.2 1.2
14 J Tee 15 15 32mm 1 1.2 1.2
15 K Elbow 1 1 20mm 1 2.5 2.5
Total friction loss in Feet 68
Grand Total friction loss in Feet 74 Feet
23 Metres
''Say 25 metres
Total Head Loss = Total Friction Loss + Static Head
= 25+20
= 45 m
= 4.5 bar
Considering 10% Safety Factor
= 5 bar
Say = 5 bar
Project: The Green Oasis Mall - Thumama B ( Part - A )
Subject: Plumbing Fixture Qty for Demand Selection

Fixture Total Fixture


S.No. Location Item Qty
Unit Unit
1 Basement Hose Bib 8 3
2 Ground Floor WC 6 3
3 Ground Floor Lav 6 1.5
4 Ground Floor Perenial Spray 6 3
5 First Floor WC 10 3
6 First Floor Lav 10 1.5
7 First Floor Perenial Spray 10 3
8 First Floor Kitchen Sink 10 3
Public Area
9 First Floor WC 6 5

Public Area
10 Lav 6 3
First Floor
Public Area
11 Perenial Spray 6 5
First Floor
12 Second Floor WC 4 3
13 Second Floor Lav 4 1.5
14 Second Floor Perenial Spray 4 3
15 Second Floor Kitchen Sink 4 3
16 Roof Floor Hose Bib 2 3
Project: The Green Oasis Mall - Thumama B ( Part - B )
Subject: Plumbing Fixture Qty for Demand Selection

Fixture Total Fixture


S.No. Location Item Qty
Unit Unit
1 Basement Hose Bib 5 3
2 Ground Floor WC 7 3
3 Ground Floor Lav 7 1.5
4 Ground Floor Perenial Spray 7 3
Public Areas -
5 WC 8 5
Mezanine Floor
Public Areas -
6 Mezanine Floor Lav 7 3

Public Areas -
7 Mezanine Floor Perenial Spray 8 5

8 First Floor WC 11 3
9 First Floor Lav 11 1.5
10 First Floor Perenial Spray 11 3
11 First Floor Kitchen Sink 10 3
Public Area First
12 Floor WC 8 5

Public Area First


13 Lav 7 3
Floor

14 Public Area First Perenial Spray 8 5


Floor
15 Second Floor WC 5 3
16 Second Floor Lav 5 1.5
17 Second Floor Perenial Spray 5 3
18 Second Floor Kitchen Sink 4 3
19 Roof Floor Hose Bib 3 3
Project: The Green Oasis Mall - Thumama B ( Part - B )
Subject: Water Supply Demand load selection by using Fixture units As per UPC System

Fixture / Trim Quantity Demand


Total Demand in
S.No. Fixture Weight in
Basement Ground Mezanine First Second Roof Total Qty Fixture Units Fixture Units
European Water
1 7 16 11 5 39 3 117
Closet
2 Perenial Spray 7 16 11 5 1 3 3

3 Lavatory 7 16 11 5 1 1.5 1.5

4 Kitchen Sink 10 4 2 3 6

5 Hose Bibb 5 3 1 3 3

Total Demand in Fixture Units 130.5

Selected Selected
Demand Demand
As Per UPC
As Per
Chart
UPC
18-2
Chart
for 168
18-1Fixture
for 440.5
Unit
Fixture 60
will beUnit will 115
Gallons/Minute
be Gallons/Minute

19

19 1

18 1

1
Total Demand in Fixture Units

Selected Demand As Per UPC Chart 18-2 for 229 Fixture Unit will be 70 Gallons/Minute
Project: The Green Oasis Mall - Thumama A ( Part - A )
Subject: Water Supply Demand load selection by using Fixture units As per UPC System
Occupancy: Private
Fixture / Trim Quantity Demand
Total Demand
S.No. Fixture Weight in
Basement Ground Mezzanine First Second Roof Total Qty in Fixture Units
Fixture Units
European Water
1 6 5 12 3 26 3 78
Closet
2 Perenial Spray 6 5 12 3 26 1 26
3 Lavatory 6 5 12 3 26 1 26
4 Kitchen Sink 9 3 12 2 24
5 Hose Bibb 8 3 2 13 1 13
Total Demand in Fixture Units 167

Selected Demand As Per UPC Chart 18-2 for 167 Fixture Unit will be 60 Gallons/Minute

Project: The Green Oasis Mall - Thumama A ( Part - B )


Subject: Water Supply Demand load selection by using Fixture units As per UPC System
Occupancy: Private
Fixture / Trim Quantity Demand
Total Demand
S.No. Fixture Weight in
Basement Ground Mezzanine First Second Roof Total Qty in Fixture Units
Fixture Units
European Water
1 7 6 16 5 34 3 102
Closet
2 Perenial Spray 7 6 16 5 34 1 34

3 Lavatory 7 6 15 5 33 1 33

4 Kitchen Sink 11 4 15 2 30

5 Hose Bibb 5 3 3 11 1 11

Total Demand in Fixture Units 210

Selected Demand As Per UPC Chart 18-2 for 210 Fixture Unit will be 70 Gallons/Minute
Domestic Water Booster Pump Calculation
Project: Green Oasis Mall
Building: Shahaba (Part A, B & C)

Calculation obtained as follows;

For Part A, 70 GPM @ 60m Head with one Duty and one Standby

For Part B, 75 GPM @ 60m Head with one Duty and one Standby

For Part C, 70 GPM @ 50m Head with one Duty and one Standby

You might also like