Professional Documents
Culture Documents
INTERNSHIP REPORT
Submitted in Partial fulfillment of the Requirements for the VIII Semester of the Degree
Of
BACHELOR OF ENGINEERING IN
CIVIL ENGINEERING
By
JANARDHANA CHARI N (1CR18CV416)
Certificate
This is to certify that JANARDHANA CHARI N (1CR18CV416), student of
CMR Institute of Technology has undergone internship in the partial fulfillment
for the award of Bachelor of Engineering in Civil Engineering of the
CMR Institute of Technology during the year 2020 -2021. It is certified that all
corrections/suggestions indicated for Internal Assessment have been incorporated
in the Report. This Internship Report has been approved as it satisfies the
academic requirements in respect of project work prescribed for the said degree.
External Viva
Name of the examiners Signature with date
1.
2.
ACKNOWLEDGEMENT
The internship opportunity I had with “SOWMYA Builders and Developers” at their project,
“Sowmya shailam”, was a great chance for learning and professional development. I am
grateful I was provided with such opportunities to be a part of it and for having a chance to
meet so many wonderful people and professionals who led me through this internship period.
Bearing in mind previous, I am taking this opportunity to express my deepest gratitude and
special thanks to the Managing Director, Mr. E. Venkat Reddy and to the Senior Project
Manager, Mr.R.N. Madhu Vamsi, who despite being extraordinarily busy with their duties,
took time out to hear, guide and keep me on the correct path and allowing me to carry out my
project at their esteemed organizations and extending during the training.
It is my radiant sentiment to place on record my best regards and deepest sense of gratitude to
all the site engineers and different workers for their careful and precious guidance which were
extremely valuable for my study both theoretically and practically.
I would like to thank our Principal, Dr. Sanjay Jain for his constant support and
encouragement throughout the entire course of Internship. I express my deepest sense of
gratitude to our HOD, Dr. Asha M Nair for her valuable guidance and constant help in every
possible way.
I perceive these opportunities as a big milestone in my career development. I will strive to use
gained skills and knowledge in the best possible way, and I will continue to work on their
improvement, to attain desired career objectives.
CONTENTS
SL.N PAGE
TOPICS
O NO.
5. Conclusion 42
LIST OF FIGURES
PAGE
SL.NO TOPICS
NO.
1.2 Vision 2
3.7 Concreting 25
PAGE
SL.NO TOPICS
NO.
The Salarpuria Sattva group established in 1986 in Kolkata, India, is a commercial and
residential property development consultancy, later expanded to Bangalore in 1992. Now
headquartered in Bangalore, it operates in Kolkata, Hyderabad, Pune, Jaipur, Goa, and
Coimbatore.
Beginning in Bangalore India in 1993, acquiring a small plot that offered just 20000 sq.ft. of
construction, today the Salarpuria Sattva group has taken giant steps to became a builder of
immense magnitude. With 3 decades of unwavering commitment to quality constructions across
7 cities in India, the group has completed 48 million sq. ft of construction with 36 million sq. ft
in the pipeline. An arduous journey marked by a steely resolve to deliver to the highest
standards of international quality be it commercial or residential spaces.
1.2 VISION:
Built on trust, innovation and knowledge-leadership, the Salarpuria Sattva group is
one of India’s leading property development, management and consulting organizations. The
excellence in our quality of delivery is achieved by our people – through insight, strategic
planning, a passion for excellence and a commitment to execute without compromise.
1.3 INTRODUCTION:
In 2006 the Sattva Group was established to diversify into non-core businesses such
as education (Greenwood High International School), Aero Accessories for Defense, Facilities
Management and warehousing.
The organization’s real estate efforts are focused on residential and commercial projects.
Currently, Salapuriya Sattva has completed developing about 15 million sq.ft. and 30 million
more remain in the development or planning stages. The company currently has 40 million sq.ft.
of development under construction, of which more than 60% is commercial development to be
completed over the next 4 years.
1.3.2 AEROSPACE
Sattva aerospace accessories and systems pt. ltd. (Sattva AASPL), is a landmark
achievement in the groups journey of excellence. A venture that came to fruition during early
2011, Sattva AASPL has steadily but strongly, flourished into one of the country’s leading name
in the aerospace sector. It caters to the prime requirements of the defense and aerospace industry
and includes Design & Development, Production, Testing, Life Cycle support and MRO
(maintenance, Repair & Overhaul) services for accessories & systems.
1.3.3 EDUCATION
Salarpuria Sattva has made impressive inroads into Education, with the vision of making
international standards of education a reality for Indian students. With an emphasis on world
class education right from pre-school to high school, the group’s education model paves the way
for higher education in international avenues. A hands-on, practical approach to learning,
practical applications of theories taught in class and revolutionary teaching methods that marry
traditional knowledge with modern techniques, ensure a child’s all round development in his
formative years.
CHAPTER 2
Dept. of Civil, CMRIT Page 12
Residential Building Construction Practices at Salarpuria Sattva Misty Charm
2.10 AMENITIES:
2.10.1 INDOOR AMENITIES:
Multipurpose Hall
Squash Court with viewing gallery
Table Tennis
Pool Table
Gym
Indoor Games / cards Room
Library/Reading room
Yoga/Meditation/Aerobics
Sauna/Steam
Department store
Swimming pool
2.10.2 OUTDOOR AMENITIES:
Open Green Leisure Park With Benches
Tot Lot Area
Reading Corner
Seating Courtyard
Intractive Dry Fountain
Skating Rink
Outdoor Fitness Station
Seniors' Corner With Reflexology Path
Half Basketball Court
Kids' Playground
Amphitheater
Activity Lawn
Tennis Court
Cricket Pitch
Meditation Garden
2.11 SPECIFICATIONS:
2.11.1 STRUCTURE:
R.C.C. framed structure with Porotherm / cement blocks walls.
2.11.2 FLOORING:
Common area
Ground floor with Vitrified tiles/Marble/Granite flooring.
Typical Lift Lobby: Granite Flooring/Vitrified tiles flooring.
Staircase: Tandoor /Kota stone/Step tiles.
Corridors: Vitrified tile flooring.
Apartment
Foyer: Vitrified Tiles.
Living & Dining: Vitrified Tiles.
Master bedroom: Vitrified Tiles.
Bedrooms and Kitchen: Vitrified Tiles.
Balcony: Antiskid Ceramic Tiles.
Toilets
Antiskid Ceramic tiles flooring.
Glazed/Ceramic tile dado up to 7’ height.
2.11.3 TOILETS:
CP fittings
Single lever mixer for all toilets and wash basin.
2.11.4 KITCHEN:
Provision for water purifier.
Hot and cold wall mixer.
Centralized Gas Distribution (at Extra cost).
Cladding with Glazed Tiles 2’0” above the Kitchen Platform (kitchen platform and sink
will not be provided).
2.11.5 UTILITY:
Inlet & Outlet for washing machine.
2.11.6 DOORS:
Main door of woodenised wooden frame.
Main door shutter with one side veneer with melamine polish and other side paint finish.
Internal doors of wooden frame/stone frame.
Internal shutters flush doors with paint finish.
Toilet – same as internal doors.
2.11.7 WINDOWS:
Two/Three track anodized UPVC/aluminium windows with mosquito mesh.
Balconies for living, dining and bedroom are glazed full windows with aluminium/UPVC
frames with sliding/hinged shutters and mosquito mesh.
2.11.9 ELECTRICAL:
One TV point in the living room & master bedroom.
Fire resistant electrical wires of reputed make.
One earth leakage circuit breaker for each apartment.
Electrical modular switches of Reputed make.
Split AC point in Master Bedroom and Living room.
Individual apartment to have BESCOM power of 3KVA, 4KVA and 5KVA for 1BHK,
2BHK and 2.5BHK & 3BHK respectively.
Video door phone conduit provision.
2.11.10 CABLE TV:
An exclusive network of cable TV will be provided with a centralized control room at a
convenient location (users to pay the operator on a monthly basis).
2.11.11 TELEPHONE/ INTERCOM FACILITY:
Telephone points in living room.
Intercom facility from each apartment to the security room and other apartments.
2.11.12 LIFT:
Automatic passenger lifts of reputed make.
Fig No 2.5: JCB Skid Steers Fig No 2.6: Steel Bar Cutting
Fig No 2.10: Curing of concrete cubes Fig No 2.11: Compression test Machine
2.15 PLANNING:
Money, manpower, methods, materials and machineries are under them. Taking care of
all project related documents and drawings. Preparing project completion schedule using MS
project. Preparation of monthly and daily work plans. Communicating with all the contractors
and subcontractors. Creation of purchase requisition (PR) for sub-contractors.
2.16 EXECUTION:
Execution surveyor is to be in site for checking and updating daily working progress.
Checking of the reinforcements for beams, slabs, columns and also for foundation. Level
checking for slab and staircase. Layout checking has to be done for block works. Checking for
plastering and determination of undulations.
2.17 EHS:
Responsible for monitoring all maintenance and safety policies. Inspect the construction
site to ensure that everything is safe. Conducting safety meeting with the contractor. Regular
awareness program for the labours in safe working practices. Wearing of safety belts at height.
Helmet and Shoes are to be worn at workplace. Before starting of any works in site, work
permits to be followed. Hospital tie up should be done by company with the nearest hospital.
Training for labours as per work schedule. Barricades should be provided at the edges. Fire point
at designated places and where ever required. For higher levels bracket fixing and net should be
cover to the outer sides.
Labour welfare facilities:
RO plant should be installed for drinking water
Periodically health check up for labours
Labour camp
Canteen
CHAPTER 3
TASK PERFORMED
Starter has casted for support the column shuttering. Then the reinforcement is done by
the bar bending team. The vertical bars are present up to a certain height and are extended by
lapping. The vertical ties are provided as per the drawing. The sheer key provided for better
bonding and column terminates in size as level increases. The next step is shuttering which
carried out based on the framing. Type of shuttering used for columns is MIVAN
SHUTTERING. With the help of jacks, runners, channels and plywood the shuttering
adjustments are done. The shuttering is done and plumb is checked and proper cover blocks are
provided. Concrete is poured using proper vibrations and de-shuttering is done on next day. Any
repair work is done to close any honeycombs present. Columns are marked with date of casting
and column number. The levels are checked of the using auto level and the layout dimensions are
noted.
The shuttering is carried out based on drawings. Levels are the most important thing to be
carried out perfectly. The upper surface of shuttering is inspected for any undulations before tie
up the steel. After beam reinforcement checking bottom mat for the slab is made. Electrical team
and plumbing team will place pipes on bottom mat and then again bar bending will make top
mat.
3.4 CONCRETING:
After the reinforcement is done quantity surveyor will check and give the volume of concrete
needed to cast the slab, concrete, beams. The quality controller will check the slab reinforcement
and also the electrical conduit. After checklist is approved then the contractor can cast the slab.
Concreting starts with the columns since it requires higher grade of concrete. Then slabs and
beams are casted. The thickness of the slab needs to be checked regularly. At last the level is
checked using auto-level. Curing is done for 7 days. Nitobond is the chemical applied at
construction joints. Shalitex board is applied at expansion joints.
3.5 BLOCKWORK:
After completion of RCC frame structure the block work is done as per the architecture
drawing. The block work is done by 3-4-5 method. 1st course having solid cement blocks. The
plumb is checked from the beam and first line of block work is laid. The internal dimension of
the room is checked and then proceeds to the next course. From second course is porotherm
block in towers area and in sides of openings have solid blocks. The care should be taken in the
last course and door jamb. The pointing is done and the lintel is laid wherever there is an opening
like doors and windows. The porotherm and the concrete block of 200, 150 and 100mm is used
and wherever 100mm is used for every 1m there should be a 100mm thickness concrete is
provided where the block work and the RCC framework meets for better to avoid cracks and also
done at every electrical conduit. Fig No 3.9: Block work
3.7 PLASTERING:
Dept. of Civil, CMRIT Page 35
Residential Building Construction Practices at Salarpuria Sattva Misty Charm
Porotherm smart bricks are new age advanced clay bricks used for both load bearing and
non load bearing construction. These bricks are environmental-friendly, cost-effective and easy
to use resulting in faster construction. Porotherm is manufactured by Wiener Berger in its state of
the art factory at Bangalore. Wiener Berger is a 193 years old Australia based company with 226
plants worldwide. Porotherm blocks are certified by IGBC rating. The clay is made from de-
silting of dead water tanks and only natural additives like coal ash, rice husk and saw dust.
3.8.1 ADVANTAGES:
Light weight, that is, it has 60% less weight than conventional walling material.
Strong and durable-high compressive strength.
Excellent Thermal and Sound Insulation.
Low water absorption (15%), thus minimal risk of dampness, cracks or shrinkage of
walls.
Non-susceptible to carbonation.
Unlimited life and maximum fire protection, because it is already burnt at 1000 degrees.
3.8.2 LIMITATION:
It cannot be used in the construction of huge structures due to its density which is about
694 to 783 kg/m3.
It may could be exposed to salt attacks due to its water absorption which is about 15%
and hence the strength of the structure would be decreased.
It may not able to withstand the negative pressure of water and capillary action.
3.9.1 COMPONENTS:
The aluminum components are of high-strength, light in weight and with excellent
stiffness-to-weight ratio, yielding minimal deflections.
All the elements are named based on their location in the formwork assembly, viz. as
wall, deck and beam components for walls, slabs and beams respectively.
High strength wall ties hold the wall panels together.
Beams and props hold the deck components.
A simple ‘pin and wedge arrangement’ / ‘Stub Pins’ is used to lock the components
together.
Bracing and tie rods are not required in general, only wall ties are used at desired
intervals to keep the shuttering intact.
However uniquely for our Brigade Exotica special wailers are designed to take care of
400 thick oblique walls to shape the patios.
At times, if any panel is out of line (owing to repetitive usage), it is fastened to a panel on
the opposite side by means of a turn buckle.
3.9.4 ADVANTAGES:
Good speed of construction, because:
Not much time and skilled workmanship required for assembly on site.
Simple and quick inter – connections using pins and wedges.
Provision of kicker pieces avoids starters compared to conventional practices.
Lifting & Shifting becomes easier because it is lighter in weight.
Total system forms the complete floor with all components includes staircases,
balconies, parapets etc. in one go.
Excellent degree of pre-engineering includes minor detailing, sleeves for electrical main
lines, etc.
Accurate dimensions and right angles, good finishes.
External plaster is avoided.
Precision in maintaining verticality of a tall structure like Exotica.
System is well designed keeping in view of the utmost safety precautions of the workers.
Durability of the structure is more because the entire envelop of structure is made with
RCC.
Finish activities are safer because the entire envelop is done in structure.
Standard Panels can be re-used for more than 100 times.
Nails are not required, hence, injuries are avoided.
3.9.5 DISADVANTAGES:
Huge number of components are used, more chances of miss out which impacts badly on
finish surface.
Modifications are not easily possible as all members are cast in RCC.
Minimum No. of repetition should be maintain to make it cost effective.
CHAPTER 4
GENERAL NOTES
4.1 GENERAL
All dimensions are in mm & levels are in meters
For centerline dimensions read with Relevant architect drawing.
The drawings shall be correlated with relevant architecture drawings, sanitary &
plumbing drawings. Dowels for drops if any shall be provided as per the respective
drawings.
All the reinforcement bars and spacing of bars are in mm
All levels are read from architectural drawings.
BBS for reinforcing steel and concrete pour schedule shall be submitted to the architects
representative and a stamped approval received before fabrication can proceed.
Toilet sunk slabs if provided shall be filled with foam concrete, after relevant water
proofing treatment.
Drawing should not be scaled. Only written dimensions shall be followed.
All dimensions shall be cross checked with relevant arch. drawings
Details marked as “Hold” on drawings shall not be taken for construction till the “Hold”
is removed.
Any discrepancy in the drawings should be brought to the notice of the architects or
consultants before commencement of the work.
Load considered based on IS 875 are as follows:
Dead load
Partition wall = 1 KN/sq.m
Floor finish = 1.5 KN/sq.m
100/150/200mm thick light weight block wall loads considered on the beams.
Live load = 2 KN/sq.m
Fire tender = 15 KN/sq.m
Parking = 5 KN/sq.m
By providing proper cover blocks, spacers, chairs etc. all reinforcement shall be placed
and maintained in position as shown in structural drawings.
4.3.2 CEMENT
Cement used shall be as specified
43 grade PPC conforming to IS:8112
53 grade PPC conforming to IS:12269-1987
Cement shall be stored in dry places on a raised platform about 200mm above floor level
300mm away from wall. Bags to be stacked not more than 10 bags high in such a manner
that it is adequately protected from moisture and contamination.
Water used for both mixing and curing shall be clean and free from injurious amounts of
oils, acids, alkalis, salts, sugar and organic materials or other substances that may be
deleterious to concrete pH shall generally be b/w 6 & 8.
Minimum cement content, maximum water cement ratio and minimum grade of concrete
for different exposures with normal weight aggregates of 20mm nominal maximum size.
Table No 4.1: Min cement contents
sl/no Min cement content kg/cum Max free w/c ratio Min grade of cement
1 300 0.55 M20
2 300 0.5 M25
3 320 0.45 M30
4 340 0.45 M35
5 360 0.4 M40
Concrete in toilets, kitchens, water body areas shall be mixed with approved waterproof
compound and waterproofing over the slabs and sides of walls shall be done as per BOQ
and specifications.
The secondary beam bars shall be placed over main beam bars when the depths of beams
are same at junctions.
Short span steel shall be at bottom layer in two way slab system.
Splices if un avoidable, must be located from face of the column at not closer than twice
the beam depth.
Spacing of stirrups shall not exceed effective depth/300mm whichever is less.
4.6 COLUMN
Lap length,
M15 – 50D
M20 – 46D
M25 – 39D
M30 – 37D
M35 – 35D
M40 – 33D
Note: Grade of M15 with 150mm minimum lap.
If column casting is more than 2400mm high it shall be done in two lifts.
Beam bottom levels are to be marked on column rods and column to be stopped at this
level to avoid extra shuttering of columns below beam bottom.
All spacings shall be centre to centre of bars.
Shuttering can be replaced earlier than specified above provided. The props are retained
at reasonable spacings and concrete attains the full strength at the time of deshuttering.
As per IS456-2000 deshuttering shall be done by providing dampening materials below
in order to reduce the impact at the lower level.
Simply supported and continuous beams shall be deshuttered from mid span towards
supports.
Slabs/beams shall be reopened until the next level slab is cost and deshuttered.
4.9 CURING:
Curing by water shall be done for the other elements for a minimum period of 7 days.
CHAPTER 5
CONCLUSION
Some of the highlights of my internship are:
I got familiarized with site execution work.
It was a wonderful learning experience as a trainee engineer for the 4 weeks gained a lot
of insight regarding almost every aspect of site was given exposure in all most all
department of the site.
The friendly welcome from all employees is appreciating, sharing their experience and
giving their pieces of wisdom which, they have gained in a long journey of work.
Thoroughly study of relevant drawings helped me to how to read them and also helped in
understanding the nature of the project.
This internships provide an overall look over site execution, planning, QS, QA & QC. It
demonstrates the steps to be followed to produce at the site work and also how the system
works at the site.
I learnt the importance of work ethics.
I am very much thankful to Salarpuriya Sattva Group for providing an opportunity to do
my internship & be associated with them. I hope, I have gained some knowledge which
will not only help in my future but also in shaping my carrier.
The internship has helped me to find out my strength and weakness. It also helped me to
recognize the knowledge and professional skills that I need to improve upon.
I never expected that it would be so satisfying and that I would be so fortunate to meet
such friendly and helpful colleagues after one-month completion of my internship.