DIE HISTORY SHEET
Part Name/ No: Process
Die No.: Responsbilty
Breakdown B/D Release Total B/D
Breakdown Details Root Cause Action Taken Sign
Date Time Date Time Hours
3 डाई के स्टॉपर को चेक करें लूज़ नहीं होना चाहिए स्ट्रिप को मिलाकर
10
11
Rev.No. date
Prepared By : Anuj shukla Approved By : Shailendra singh 00--30/11/2017
Growth engine pvt.ltd. Layout Inspection Plan ( Year 2018) Doc.No. GEPL:D:QA:03
Frequency
S.No. Part Name Drawing No. of Layout Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Inspection
10
11
Growth engine pvt.ltd. Estimating of Raw Material GEPL:QA:04
As per
2 WASHER BEARING UPPER S5581-752-01 AQ C-80
requirment
50 1 ± 0.05
As per
3 WASHER BEARING LOWER 67101-750-00-ID AQ C-80
requirment
50 1 ± 0.05
10
11
Growth engine pvt.ltd. List of Dies Doc.No.
GEPL:L:PRD:03
S.No. Part Name Drawing No. Process Name Die No. Remarks
Frequency of
S.No. Part Name Drawing No. Process Name Die No. Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Maintenance
BEARING
1
SPACER 69201-752-00 BLANKING 1 4 month
WASHER
2 BEARING S5581-752-01 BLANKING 2 4 month
UPPER
WASHER
3 BEARING 67101-750-00-ID BLANKING 3 4 month
LOWER