4M CHANGE TAG

MAN MACHINE MATERIAL METHOD

Customer:-………………………………………………

REJECTED
Part Name/No-………………………………………….
HOLD
GEPL:4M:02

GEPL:4M:03
Machine No:………………. Lot No.:………………..
Quantity:……………………. …...……………………
Change Condition:- PLANNED UN-PLANNED ABNORMAL

Current Operation :…………………………………….


Next Operation :………………………………………..
Reason(Hold/Reject)……………………………………
Date:………………………Inspected By:……………...

ACCEPTED
7

GEPL:4M:01

4M CHANGE TAG
MAN MACHINE MATERIAL METHOD

Customer:-……………………………………………… REJECTED
Part Name/No-………………………………………….
HOLD

GEPL:4M:03
GEPL:4M:02

Machine No:………………. Lot No.:………………..


Quantity:……………………. …...……………………
Change Condition:- PLANNED UN-PLANNED ABNORMAL

Current Operation :…………………………………….


Next Operation :………………………………………..
Reason(Hold/Reject)……………………………………
Date:………………………Inspected By:……………...

ACCEPTED
7

GEPL:4M:01