Professional Documents
Culture Documents
Funding Guidebook
DISCLAIMER
Subject to the below, the copyright in this Guidebook belongs to Frontier Impact
Group and this document must not be copied or reproduced in any other
electronic or physical form.
Frontier Impact Group is pleased to allow the material provided in this Guidebook
to be reproduced in whole or in part solely for educational and non-commercial
use, provided the meaning is unchanged and its source, publisher and authorship
are acknowledged.
This Guidebook and the information contained in it does not constitute an offer in
relation to any project and does not entitle a recipient to participate in any process
relating to any project.
Persons who receive this Guidebook and the information contained in it must
make their own enquiries to verify and satisfy themselves of all aspects of this
Guidebook and the information contained in it.
While this Guidebook and the information contained in it has been prepared
in good faith, no representations or warranties (express or implied) are made
by Frontier Impact Group or its representatives as to the accuracy, currency,
completeness, suitability, correctness, fitness for purpose or otherwise of such
document and information. The provision of this Guidebook does not place
Frontier Impact Group or its representatives under any obligation to provide any
further information in relation to the subject matter or any projects, or to update
this Guidebook or any additional information or to correct any inaccuracies in any
such information which may become apparent.
To the maximum extent allowed by Law, neither Frontier Impact Group nor its
representatives, officers, employees, contractors or agents, shall be liable to
any person for any loss, liability, damage or expense arising directly or indirectly
from or connected in any way with any use of or reliance on such document
and information.
Foreword
A
A.2 Behind the Meter and Other Models
A.3 Why Behind the Meter?
A.4 Funding Behind the Meter Solar PV Projects
B
SECTION Project Elements Overview
C
C.1 Technology Choice
C.2 Project Scale
C.3 Community Engagement
C.4 Business Structure
C.5 Project Development Resourcing
C.6 Site Selection and Acquisition
C.7 Resource Assessment
C.8 Construction
C.9 Network Connections
C.10 Permitting
C.11 Operational Resourcing
C.12 Project Funding
C.13 Power Sales
C.14 Financial Modelling
C.15 Risk Management
D
Appendix II – Financial Contacts
Appendix III – Definitions
Appendix IV – Community Energy Behind the Meter Case Studies
Thank you to the following entities that were interviewed FOREWORD
and/or provided insight into the guidebook.
One of the key barriers that has been expressed by CE project developers is the
challenge to secure funding and improve their financial literacy. Thus the aim of the
toolkit is to up-skill the financial literacy of community energy developers and increase
the likelihood that their projects can be funded. The CE Funding Toolkit currently
consists of two guidebooks the Funding Basics Guidebook and this Behind the
Financial Stakeholders
Meter Solar PV guidebook. Subject to funding, the next guidebooks will cover Grid-
Connected Solar PV and wind projects followed by energy storage projects.
At the time of publication, our project team identified that Behind the Meter solar
projects were the most likely to be commercially viable and have strong potential
to be replicated. This guidebook focuses on demonstrating the steps needed to
develop and successfully fund community Behind the Meter solar PV projects.
A large proportion of the successful projects developed to date are Behind the Meter
solar PV projects.
Attached to this module are case studies. Complementing both the modules,
the supporting case studies provide excellent examples of how communities are
developing innovative ways to secure funding for their CE projects.
I would like to specifically acknowledge the support of the following key entities:
ARENA - for their continued efforts of inspiring renewable energy adoption across
the country and their advice, support and guidance has been invaluable. Taryn Lane
from Embark and Nicki Ison and Tom Nockolds from Community Power Agency
together representing the Coalition for Community Energy (C4CE). Their insight and
experience in community stakeholder engagement, and the development of new
community investment models, has been critical in understanding the key issues
around financial literacy and what was required to enable more communities to
successfully fund CE projects.
INTRODUCTION
This guidebook is part of a Funding Toolkit that has been developed to assist
community energy (CE) project proponents in the development and delivery
of community renewable energy projects. The Funding Toolkit is designed to
be a centralised, simplified and accessible repository of information to support
the funding of community energy projects throughout the various stages of the
project development process.
The aim of this particular guidebook This guidebook is designed to be used CE projects are considered to be ones
is to provide assistance specifically to in conjunction with the ‘Funding Basics that involve the community undertaking
solar photovoltaic (PV) projects that Guidebook for Community Energy a number of the following activities:
are installed “behind the meter”, i.e. Projects’ to assist project developers
• Initiating
on a host site where the electricity is to understand the minimum criteria that
purchased by the host site rather than should generally be met at each stage • Developing
selling the electricity into the electricity of project development to assist in
• Operating
market via the main electricity network achieving successful project funding.
(grid). A good example is a local club • Owning and/or
Community energy is where a community
that installs a PV project on its roof and
comes together to develop, deliver and • Benefiting from a renewable
uses the energy for its own purposes.
benefit from a clean energy project. energy project.
There are other types of CE projects
Any of the first four of these items is
including bioenergy that can be applied
sufficient for the project to be considered
to Behind the Meter projects but,
within the scope of the toolkit.
for simplicity, this guidebook focuses
on solar PV as it is currently the most
common technology type for Behind
the Meter projects including in the CE
sector (as evidenced by the project list
in Appendix D).
• The host site may be a • It has a Behind the Meter • Since there is no host site
commercial building, factory or connection on a host site but to sell electricity to these
other premises that can utilise the majority of the electricity types of CE projects rely
the electricity produced by the produced is not ‘behind the entirely on sales of electricity
CE project. meter’ and is instead exported to third parties.
into the main electricity grid.
The concept phase The prefeasibility phase The feasibility phase Final funding refers to the
describes where a CE project evaluates key project incorporates confirming in phase where all project
idea has been conceived elements in more detail more detail all of the project elements have been
and various options for the and includes a financial element options including developed in full detail
2.2 Behind the Meter Solar PV development of the project model and scoping. This establishing more certainty including firm construction
Guidebook Structure have been discussed at a guidebook incorporates a around project costs and costs, confirmed revenue
high (conceptual) level. financial template which is revenues. Once these are streams established, all
This guidebook provides guidance on
Generally the Behind the Meter PV 2. Detailed guidance on how to: recommended to be used firmed up, project proponents contracts have been agreed
actions and factors that need to be
solar guidebook consists of three as a key input into making a will be in a position to then and the project is ready to
considered by project developers as • Develop the financial template
core elements. number of key decisions on validate outcomes of the initial be funded. Once final funding
part of the process of achieving funding
• Ensure that key project elements Behind the Meter solar PV modelling undertaken during is achieved, a
to develop Behind the Meter solar PV 1. The financial template sets out
have been appropriately addressed projects. (See the Disclaimer prefeasibility and develop project should be able to
projects. It sets out the information the information and calculates the
at each stage of project development in relation to use of the a more detailed level of move into construction.
needed to give confidence to the funders financial metrics required to:
to assist in increasing the likelihood financial template.) modelling required in order to
that the project is financially viable and
• Initially assess the likely of accessing project funding, be that achieve final funding.
worthy of investing in and/or financing.
financial viability of a CE Behind from investors or finance lenders.
The guidebook provides a financial
the Meter project
template and more detailed guidance on 3. Case studies demonstrating the
the requirements for a project to become • Satisfy the requirements of investors application of the guidebook.
‘investment ready’. and financiers in assessing the financial
viability of a CE project. Not all CE projects will be
successful but if you follow this
guidebook the chances of success
are likely to be increased.
Throughout the guidebook is a series of tips that flag key issues
to address. Generally small Behind the Meter Solar PV projects do not have distinct concept
In addition to the information in the guidebook itself, links are and prefeasibility stages and, as such, the structure of this Guidebook is structured
provided to external reference sources that are able to provide to consider the concept and prefeasibility stages as being one combined phase.
more detailed information on specific topic areas. Access these
links on our website: frontierimpact.com.au/external-resources
For Grid-Connected installations 3.2 Retail electricity prices Behind the Meter projects allow for sales
the revenue from electricity sales is at avoidable retail prices because the
The retail price is the price a business
competing with the wholesale price of host site is able to avoid a significant
pays for electricity. This includes the sum
energy. However for Behind the Meter component of its retail energy bill if
total of the following:
1. Technology 2. Project Scale 3. Community 4. Business Structure 5. Project Development / installations the electricity produced energy is generated Behind the Meter
Engagement Resourcing that is not exported beyond the meter is • The wholesale (value of electricity rather than sourced from the network.
competing with much higher retail prices generation) electricity price plus The general difference between
and as such can attract higher revenues. wholesale charges, retail charges and
• Network charges (transmission and
This is explained further below. avoidable retail charges is illustrated in
distribution costs) plus
the following chart.
3.1 Wholesale Electricity Prices
6. Site Selection 7. Resource Assessment 8. Construction 9. Network Connection 10. Permitting • Retail overhead charges plus
The avoidable retail charges are
& Acquisition The wholesale price is the price a project
• Retail profit margins plus variable charges that are volume-based
receives when exporting electricity to
and include:
the grid. The wholesale price is relatively • Retailer environmental charges (e.g.,
low in comparison to retail electricity LGCs and STCs) fees plus • Retailer energy charges
prices so selling power via a direct grid
connection will attract a lower rate than • Electricity market based fees plus • Retailer environmental charges
11. Operational 12. Project Funding 13. Power Sales 14. Financial Modelling 15. Risk Management would be achievable in a Behind the • Losses (transporting the electricity). • Retailer market fee (AEMO) charges
Resources Agreements Meter situation.
• Network energy charges.
Wholesale, Retail and Avoidable Retail Price Comparison FUNDING BEHIND THE METER SOLAR PV PROJECTS
Retail Environmental Charges
The Funding Basics Guidebook for CE projects covers a
broad range of funding mechanisms available to develop
Retail Market Fees
Retailer Margins Retail Market Fees and install CE projects. As many of these mechanisms will
be more suited toAvoided Network Charges
Retailer Margins
larger scale projects, this Guidebook
Wholesale Energy Wholesale
Energy
Wholesale concentrates on those funding types and sources which are
Energy
Network
Charges
Avoidable
Network
most applicable to Behind the Meter solar PV projects.
Charges
Network Charges
Our stakeholder engagement identified The following sources of funding are The use of debt funding is generally
Retail Retail
Environmental
Charges
Environmental
Charges Retail Energy Charge Premium
that CE projects have struggled to
deliver projects and a key barrier has
currently considered to be the most
applicable for Behind the Meter projects:
a secondary option for funding of CE
Behind the Meter projects and would
been funding. As such, this toolkit usually only be considered where a
• In-kind contributions (volunteer
aims to improve this success rate by project is unable to achieve sufficient
labour primarily)
Wholesale Retail Avoidable Retail
improving financial literacy generally and funding from community investors.
Wholesale + All Network Wholesale + Avoidable Network Charges increasing the understanding of those • Donations (from the community
+ All Retailer Charges + Avoidable Retailer Chargers
Wholesale
factors that will improve the chance of
a Behind the Meter project achieving
Energy
including individuals and businesses)
The Funding Basics Guidebook should
be referenced for more specific details
• Retail and wholesale community on each of these funding mechanisms,
successful funding.
investors (sometimes in the form of what each means and how to go about
The funding requirements will vary at angel investors from the community) procuring each.
each stage of the project development
The case studies in Appendix D to this
3.3 Behind the Meter vs Network- phase and different funding sources may
TIP guidebook demonstrate in a practical
Connected be better suited during particular stages
sense how Behind the Meter projects
There has been an extensive penetration Behind the meter installations of project development.
The current trend is the preference for
Wholesale
of rooftop solar PV in Australia in Retail
developing CE Behind the Meter projectsAvoided Retail assist host sites to avoid network
and retail costs which is why they
The table below shows the most
can be funded.
the residential sector and to a lesser because, as explained above, the common funding sources available
extent the commercial sector. A lot revenue that can be generated through attract higher revenues.
for CE projects in general at this time.
of this growth has been driven by selling electricity to the host site is higher. Critical for success of the project
government-supported feed-in-tariff (FIT) Important for success of the project
To optimise the financial return in a
subsidies. The price of FITs has reduced Common Funding Sources for CE Models Not Important for success of the project
Behind the Meter solar PV project, the
significantly in recent years, and in fact Owner Investments
scale of the solar PV installation should
some of these are no longer available.
ideally be less than the electricity usage
Consequently the economic incentives
of the host site so as to maximise the Funding Source ConceptInvestors
Community Prefeasibility Feasibility Final Funding
for investing in solar PV that is exported
amount of electricity used by the host
into the grid may not be commercially In-kind Contribution
site as opposed to selling electricity back
viable. CE developers are advised to
to the grid. Grant Funding Grants
always review factors such as the prices
of electricity (including network tariffs) Information on determining the optimal Donations
and Renewable Energy Certificates as capacity (size) of the project and other IN kind
these constantly change and so the Retail Investors
factors are contained in later sections of
economics can also change. this guidebook. Angel Investors
Wholesale Investors
Debt Financing
FINANCIAL MODELLING
A comprehensive financial model plays an important role in
being able to take a Behind the Meter CE project concept
and developing it through to a successful final funding
implementation. The financial model and supporting toolkit
resources are designed to allow project developers to quickly
grasp the key financial elements of their project and target the
financially challenging areas as high priority items to address.
Financial modelling is key to obtaining 1.1 How to Apply the Behind- If these project elements cannot be
funding through all stages of the the-Meter Model Template adequately addressed to provide the
development process and will assist in: financial returns required to attract investor
This Guidebook’s financial model
or financier funding then consideration
1. Understanding the project and template is designed to assist projects
needs to be given to abandoning the
alternative project funding types seeking funding for all stages of project
project or reconceiving/redesigning
development. Modelling is important as it
2. Assessing equity returns to certain project elements.
allows the project economics to be tested
attract investors
and validated and the key elements This level of modelling included in the
3. Proving financial prefeasibility that underpin the financial viability to provided financial template concentrates
for financial decision making be quickly identified so that the project primarily on project cash flow elements
can be further developed to attract the and does not consider complex elements
4. Demonstration of cashflows
required funding. such as loan structuring or all details
to securing final funding
of tax and accounting treatments. For
commitments Initial financial modelling should
Behind the Meter projects these additional
include sensitivity analysis to identify
The funding toolkit incorporates a elements can be fine-tuned by your
project elements that need to be
spreadsheet-based financial template financial advisers as the project develops.
addressed in order to achieve required
template to assist developers in
financial outcomes. For example,
modelling the financial impact of the
sensitivity analysis will show the impact
various project elements considered
on the investor return of changes in
in this Guidebook. An explanation on
construction costs, project revenue rates
how to utilise and interpret the financial
and project life.
template is provided below.
Financial Term Description Interpretation Use 1.1.4 Applying Sensitivity Analysis 1.1.5 Sensitivity Inputs
On the Investment Return Summary The sensitivities used in each input
ROI (%) This is Return In its strictest sense Return on ROI is used to give a relatively Worksheet there are three columns used should reflect the uncertainty associated
on Investment Investment is a relatively simple simple calculation of the ratio of for sensitivity analysis: with each input. When the value of each
measure that is calculated as the total dividend payments received by input is being assessed users should
1. The first column shows the Base
sum of the dividends returned investors to the equity invested in be able to get a feel for the levels of
Case Assumptions for key input
to investors over the project life the project. sensitivity being modelled. Where
variables (from the input assumptions
divided by the equity investment professional advice is being used for
Average annual ROI can provide a worksheet). Under this column the
specific inputs the advisors should be
better measure by dividing the basic investment measures for the Base
able to provide relevant sensitivities for
ROI by the number of years over Case Assumptions are shown. There is
consideration.
which the ROI is achieved no user entry required in this column.
IRR Post-tax on Equity This is Internal Rate of This indicates the annualised IRR tells investors what the As a minimum it is recommended that
2. The second column called Sensitivity
(%) Return. It represents the returns on the equity investment actual annualised return on their +/-10% sensitivities should be examined
Variation allows users to enter an
calculated rate of return in the project (i.e., investor rate of investment would be based on but some inputs may require greater
amount that varies the Base Case
to the investor after any return) after the project company dividend payments received sensitivity values especially during
Assumption variable by a percentage
project company tax has tax has been paid compared to their equity investment the concept and early prefeasibility
amount (plus or minus). The users
been paid phase modelling. For power sales
If the value is higher than the Generally IRR is a much better enter these percentages.
revenue from electricity and LGC sales
discount rate then the project will measure than ROI or even 3. The third column includes the it is recommended to use a minimum
have a positive NPV value and the average annual ROI for long- Sensitivity Adjusted Values, i.e., the sensitivity of +/- 20% unless you have
converse applies – if the IRR is less term investments such as energy Base Case variables adjusted by the firm power sales agreements under
than the required discount rate then projects because IRR takes into Sensitivity Variation as: negotiation at rates you are reasonably
the NPV will be negative account the actual timing of the confident of obtaining.
dividend payment Sensitivity Adjusted Value =
(1+Sensitivity Variation) x
IRR Pre-tax on Equity This is the calculated This indicates the annualised This IRR value allows investors to Base Case Value
(%) rate of return to the returns on the equity investment compare the returns that they might
investor factoring in any in the project (i.e., investor rate of receive from alternative investments Under this column the investment
franking credits arising return) factoring in any franking such as bank interest rates which measures for the Sensitivity Adjusted
from any company tax credits that an investor might are always quoted pre-tax Values are shown. From this analysis
having been paid receive as a result of the company users can see the impact of changing
already having paid tax on the net key input assumptions on the investment
revenues it has received measures and consequently the
variables that have most impact on the
Debt Service Cover This is the minimum DSCR is calculated on a periodic DSCR is used by lenders to assess
project economics. There is no user entry
Ratio - DSCR value of the debt service basis (annually in the case of this how much cash is available each
required in this column.
(minimum value) cover ratio over the life template) as the ratio of the net year to meet principal and interest
of the project and is only cash flow generated by the project repayments. Different lenders will
relevant to projects that during the period to the debt have different requirements but
incorporate debt funding repayments during that period ideally the number should be 1.5 or
higher depending on the perceived
certainty of project cash flows
PROJECT ELEMENTS
to achieve funding of a CE project. The interaction with community Core organising group in place Project communicated to Clearly demonstrable support
stakeholders to increase with high-level project objectives in relevant community stakeholders for the project with all key issues
participation in or support for mind (benefits for the community). espousing project benefits. All and risks addressed to provide
the project. This may extend to Initial gauge of community key stakeholder issues addressed confidence to lenders/investors
marketing to and seeking capital interest and support. Potential key and factored into overall project that no cost overruns, etc., could
raising from community investors. stakeholders identified. considerations. occur as a result of community
related issues.
Active community engagement Advanced development of capital
undertaken with project benefits raising from community investors. All documentation in place to
clearly communicated. Support enable community investor capital
base identified and able to be raising and demonstrable investor
relied upon. Key stakeholders support fully quantified.
The type of renewable energy For Behind the Meter solar Detailed price estimates obtained Firm prices available from one
project under consideration. PV the choice will be primarily from one or two potential suppliers or two experienced suppliers.
between solar cell and inverter having investigated manufacturers Technology verification undertaken
manufacturers and technologies and their technology adequately and available for validation by
used in each. Budget quotes for and having the site inspected. others if necessary.
the technology options should be
readily obtainable for input into
4 Business Structure
financial modelling.
Project Element Concept/Prefeasibility Feasibility Final Funding
develop and operate the project. project development and for the Project governance structure
final governance arrangements Project governance working and aligned with business structure
Project Element Concept/Prefeasibility Feasibility Final Funding once the project is operational. addressing all governance issues. and in place.
Project Element Concept/Prefeasibility Feasibility Final Funding Project Element Concept/Prefeasibility Feasibility Final Funding
The resources required to Skills identified and budget Skills identified and detailed cost Skills identified and budget cost Determining the costs to Cost allowances for project Detailed cost estimates Solar Installer Contractor
develop the required elements cost estimate to progress from estimate to progress from feasibility estimate to progress from Final obtain equipment, install it construction estimated broadly. obtained from reputable solar identified and cost estimated
of a project from concept concept through to construction through to construction and Funding through to construction and commission the project to installer contractors. based on comprehensive and
operational stage. A potential solar PV supplier detailed firm quote.
through to Final Funding and and commissioning determined. commissioning determined. Funding and commissioning determined.
can usually provide budget costs
prior to implementation. Funding and/or resources and/or resources available identified
very readily.
available identified to ensure to ensure project could proceed to
project can proceed at least to the final funding phase.
feasibility stage..
9 Network Connections
6 Site Selection and Acquisition
Project Element Concept/Prefeasibility Feasibility Final Funding
Project Element Concept/Prefeasibility Feasibility Final Funding Determining the technical Budget cost allowance for network Specific cost estimates Firm cost quotations available
requirements and financial costs capital costs and ongoing annual (CAPEX and OPEX) based on for CAPEX and OPEX
Assessing, selecting and Broad host site selection criteria Narrowed down to one or two Host site selected and access of connecting the project Behind costs based on general area one or two sites. assumptions clearly outlined and
gaining access to a good host site established based on location or host sites with relatively to site secured through lease the Meter in relation to network estimates available from network able to be validated for. An agreed
for a Behind the Meter solar PV and project scale initially and then firm cost estimates and detailed or other secure site access connections. company websites. Preliminary network connection agreement
CE project. narrowed down to a few host site site assessment and access mechanism. Site suitability connection inquiry made with may be required.
choices based on estimated costs details either negotiated or assessed and confirmed. network company.
and initial site assessment criteria. under negotiation.
10 Permitting
7 Resource Assessment
Project Element Concept/Prefeasibility Feasibility Final Funding
Project Element Concept/Prefeasibility Feasibility Final Funding Obtaining all necessary regulatory, Required permits identified Permitting commenced and Permits in place or available
licensing and planning approvals (planning approvals, heritage, detailed cost estimates available. subject to final funding.
Determining the amount of energy Initial calculation based on Verified resource availability based Verified resource availability to allow a project to be built and environmental) and cost Compliance activities post-
(kWh/MWh) that a project can solar calculators. on professional solar design(s) based on final professional solar operated. allowance made. operation scheduled and budget
produce annually over its life. with sensitivity analysis included. design. Detailed sensitivity allowed for them.
More detailed calculations can be Solar suppliers can often assist
analysis included.
provided by solar providers based with this element and also provide
on manufacturer information and indicative costs as they often
local conditions. arrange the approvals.
Project Element Concept/Prefeasibility Feasibility Final Funding Project Element Concept/Prefeasibility Feasibility Final Funding
The ongoing costs of Initial assessment of operational Detailed analysis of Detailed and verifiable operational The role of financial Use templates to undertake Use templates to undertake Detailed financial model
operating the project and business resources required (operational operational costs undertaken costs supplied encompassing all modelling and various financial prefeasibility financial modelling feasibility financial modelling (to the satisfaction of financiers
structure once commissioned and and admin personnel, and quotes obtained for third operation costs of the project. factors in assessing and fine and assess whether to proceed and assess whether to proceed and/or investors) incorporating
fully operational. maintenance, etc.) and cost party services, e.g., equipment tuning project elements. to feasibility, terminate or revise to Final Funding, terminate or sensitivity modelling.
allowance made. maintenance services. the project. adjust project.
Project Element Concept/Prefeasibility Feasibility Final Funding Project Element Concept/Prefeasibility Feasibility Final Funding
The funding required to develop Potential funding sources Investor sources identified and Equity commitment demonstrated Identification and management Key risks identified and Key risks identified, risk Detailed risk management
a project from concept through identified to progress to feasibility detailed estimates of any debt (from community investors of key risks associated with documented with some risk mitigation approaches finalised, plan prepared.
to the commencement of the stage and estimates of source financing required determined. and/or other equity providers) the project. mitigation approaches considered. risk management strategies
Operations phase. values made including donations Debt quotes and conditions and funding requirements developed and risk management
and grants. obtained if required through clearly communicated in formal plan drafted.
discussions with shortlist of application process. Lender
Potential investors identified potential lenders. targeted if debt finance required.
and consider if debt financing Outcome of Final Funding
will be required for modelling will be committed finance in the
purposes. Marketing collateral form of a comprehensive finance
developed for socialising with facility agreement if debt finance
community investors. Solar panels at LIsmore Workers Club, Lismore NSW
is required. Photo courtesy of Farming the Sun
13 Power Sales
Commercial agreements Identify and roughly quantify Host site(s) PPA structure(s) or Power sales agreement
to achieve contracted potential revenue sources. These other revenue sources identified secured with host site owner
sales revenues. may come from host site PPAs, and discussions with one or two and any other revenue source
LGCs if >100kW in size, sales of host site owners well advanced. agreements (export electricity and
export energy (if any). LGCs) negotiated and ready for
Export and LGC revenue sources execution.
Analysis of host site(s) electricity identified if these are applicable.
costs undertaken to determine
potential avoidable host site costs
as part of assessment of realistic
revenue stream modelling.
1
Technology Choice
Project Element Concept/Prefeasibility Feasibility Final Funding
The type of renewable energy For Behind the Meter solar Detailed price estimates obtained Firm prices available from one
project under consideration. PV the choice will be primarily from one or two potential suppliers or two experienced suppliers.
between solar cell and inverter having investigated manufacturers Technology verification undertaken
manufacturers and technologies and their technology adequately and available for validation by
used in each. Budget quotes for and having the site inspected. others if necessary.
the technology options should be
readily obtainable for input into
financial modelling.
When considering your solar technology For reasons set out earlier in this guidebook the prevailing
choice it is important not to just go with market dynamics strongly favour Behind the Meter solar
lowest cost option PV installations. As such, this guidebook is targeted
specifically at Behind the Meter solar PV CE projects.
However project technologies such as Behind the Meter
solar PV with battery storage can also utilise this guidebook
with some minor adaptations to produce financial models
relevant to those technologies.
At the concept stage CE developers who 1.1 Solar PV Technology 4. Electrical wiring to transport the
are not familiar with the dynamics of solar electricity between the solar panels
Solar photovoltaic (PV) is the conversion
PV technologies in the current Australian and inverter to a switchboard and
of sunlight directly into electricity using
market context should carry out research a meter where the energy output of
photovoltaic (solar) cells. Behind
on the technologies and the prevailing the project is measured for revenue
the Meter solar PV systems can be
energy market conditions surrounding calculation purposes
installed on rooftops as part of building
each technology.
infrastructure or can be installed on land 5. Monitoring equipment to measure and
on host sites. The key components of a report system performance.
solar PV installation are:
When considering your solar technology
1. Solar PV panels to convert energy from choice it is important not to just go
the sun into electricity with lowest cost option. Warranties,
insurance, efficiency of the solar
2. An inverter that converts direct current
installation, maintenance availability and
(DC) electricity from the panels to
costs and other factors also need to be
alternating current (AC) electricity
considered as part of your selection.
that is compatible with the network-
supplied electricity
Northern Territory Solar Energy Transformation Program, NT For further information see:
Photo courtesy of ARENA frontierimpact.com.au/external-resources
2
Project Scale
Project Element Concept/Prefeasibility Feasibility Final Funding
The peak design output size of the Capacity range of project Project scale determined to Project scale determined and set.
project in kW/MW. determined, e.g., 30 –100kW, narrow bandwidth.
100kW–500kW, > 500kW. Total
CAPEX range estimated based
on technology and project scale
noting the advantages of
<100kW projects under the
current market arrangements.
The scale (or size) of a Behind the Meter Community Energy For solar PV, current market dynamics 2.1 Capital Cost (CAPEX) The capital costs may vary depending on
are such that Behind the Meter solar many factors including:
The overall capital expenditure (CAPEX)
(CE) project needs to be carefully considered given the cost is the only model that really works
required for a project will naturally be • Efficiency of the solar panels and
commercially without having some
and revenue implications in particular. For Behind the Meter form of financial assistance. In particular,
higher the larger the project. Although overall installation (how much energy
increased scale factors may improve is able to be produced for a given
CE projects bigger is not always better. In fact in certain cases Behind the Meter solar projects of a
returns, the additional capital required level of solar radiation). Higher
size less than 100kW have distinct
it may be more financially effective to have a large number of advantages in that they have the
can present a significant challenge efficiency panels are often used
from both a project development and on large solar farms and while they
distributed smaller-scale projects than have the same total ability to:
final funding perspective. The capital produce more electricity they are
capacity installed at a single site under a single project. • Have STCs reduce part of the costs referred to below for Behind the more expensive to purchase. Note:
capital cost Meter Solar refer to the costs of solar solar panel performance is measured
elements only. There are civil works and in terms of both initial efficiency and
• Connect with lesser (although in
other broader capital considerations the performance of the solar panels
some cases not insignificant) network
to incorporate in the overall CAPEX over their life. Solar panel efficiency
connection issues or costs
cost of a project (refer to section on will reduce over the panel’s life due
As an example, larger installations may In general terms the scale of a CE project • Avoid network and other electricity Construction) and the information below to natural material degradation but
attract network connection costs which needs to be large enough to cover the market retail costs meaning that they is only provided for the purpose of the extent of this degradation will
smaller Behind the Meter projects might development and ongoing operating can offer a higher revenue stream providing a high level range of costs for a vary with quality of the panels and
not. Conversely, generation distributed costs of the project and provide a particular project scale. environmental conditions. Typical
Solar projects that are 100 kW or greater
across multiple sites will potentially reasonable return to project investors. industry degradation values range and
have the issue that they cannot create 2.1.1 Solar PV CAPEX
require additional time and effort in terms However, the size must be of a scale might be in the range of 0.4% to 0.8%
STCs upfront and instead must rely on Solar PV installations can range from
of site identification and acquisition as small enough to be able to be largely per annum
LGCs as an additional revenue stream small single panel (<1kW) installations
well as access arrangements (refer to funded by investors and debt providers. to large solar farms. The 102MW Nyngan
until the end of the Renewable Energy • Warranties provided. The longer the
section on Site Selection). The scale should also ideally be linked Solar Plant in New South Wales is
Target period which is currently the end warranties the better and solar panel
to the host site energy usage so that the Australia’s largest solar power project.
of 2030. performance warranties typically
amount of power exported and subject to However, large-scale solar PV projects extend for 20 years. Depending on
either feed-in tariffs or wholesale-linked Additionally, >100kW to 500kW projects,
are not yet commercially viable without the business model sometimes the
prices is minimised (refer to section on even if they are Behind the Meter, are
government subsidies. risk is transferred elsewhere. For
Power Sales for more information). often faced with increased costs on a
example, there is a specific case of
revenue stream that cannot support Typical Behind the Meter solar PV
a Lismore CE project model involving
Project Scale those additional costs because: installations have a CAPEX range
the community and Lismore Council
of $1.50 to $2.50 per watt, which is
• The network connection process may where the Council provides the
equivalent to:
be more complicated and potentially warranty (refer to
Profitability
• The amount of capital required is • $1.5M to $2.5M per MW • The approach to installation.
higher and may require a different and Installations that use tracking systems
For a 100kW project the capital cost of
more expensive business structure to allow the panels to track the sun
the solar PV elements might be in the
and capital raising process to raise to maximise solar radiation input to
range of $150,000 to $250,000.
sufficient capital the solar panels will naturally be more
Note: for projects of less than 100kW expensive than fixed mounted systems
< 100kW 100kW 500kW 500kW > Consequently, projects in the range of
the capital cost could be reduced by (refer to the section on Construction).
100 kW to say 500 kW may suffer from
the supplier or a third party buying back
higher upfront capital costs, potentially
< 100kW 100kW - 500kW 500kW or greater the STCs accredited to the installation
higher operating costs and less
and as such a 99kW installation might
• Lower upfront capital due to STCs • Higher captial costs • Higher revenue base to support favourable economics.
be preferable to a 100kW one (refer to
• Lesser network issues • Higher funding costs ˚˚ Higher captial costs section on STCs under Power Sales).
The impact of the STCs on the capital
• Higher opportunity to avoid export and • More complex and expensive network ˚˚ Higher funding costs cost can be significant and depending
capture avoided cost benefits connection costs on the technology deployed and the
˚˚ More complex and expensive
network connection costs location might reduce the capital cost by
$0.40 to $0.90 per watt.
The solar PV market is a very competitive 2.2 Financial Template Inputs From the perspective of Behind the Meter
one and there may be considerable solar PV the scale may also be limited
2.2.1 Solar Scale
competition from suppliers of solar PV by the host site’s electricity profile – the
The financial template requires users
equipment so it should be relatively easy scale should be such that the project
to input the peak power capacity of the
to obtain budget quotes from suppliers does not export too much power to the
solar installation. Once the scale of the
within a short timeframe. The lowest cost grid (refer to Section 3 on Why Behind
project has been determined the model
solution may not be the optimum choice the Meter). Analysis of the host site’s
requires the input of project peak design
and consideration should be given to the electricity profile will be required to
output in kW. For solar this is generally
factors referenced above and the factors determine the optimum scale from this
referred to as kWp – the peak design
discussed in the Resource Assessment single perspective. As described in the
output. In addition, the treatment of
section of this guidebook. section on Power Sales the project will
STCs as a capital reduction upfront,
export electricity beyond the host site
At the concept and prefeasibility stages as opposed to a revenue source upon
meter if the power output is greater
of a Behind the Meter solar PV project, operation, can have significant impacts
than the host site’s electricity usage
budget costs can be readily obtained on the cash flow returns for the project
and any such export power will likely
by asking for indicative quotes on a and as such you may want to limit the
be subject to a lower priced revenue
per kW basis. Once the scale has been project scale to be less than 100kW.
regime. Ideally the scale of the project
determined a tender or competitive
In determining the scale of the project should be such that the revenue stream
quotation process for the supply and
the factors referenced earlier in this is optimised against the capital cost of
installation of solar equipment can be
section of the guidebook need to be the project, i.e., the financial returns for
readily undertaken for use in feasibility
taken into consideration but from a the project are maximised. The financial
analysis with subsequent refinement
physical limitation perspective the scale template allows for separate revenue
typically carried out prior to the final
is also limited by the space available streams for the host site energy usage
funding phase of the project.
to install solar panels in the selected and any exported electricity so that this
location. For rooftop solar there will be a optimisation can be undertaken through
physical limitation related to the roof area sensitivity analysis.
available to install solar PV panels. Solar
installers or experienced engineering
consultants can advise on this point.
3
Community Engagement
Project Element Concept/Prefeasibility Feasibility Final Funding
The interaction with community Core organising group in place Project communicated to Clearly demonstrable support
stakeholders to increase with high-level project objectives in relevant community stakeholders for the project with all key issues
participation in or support for mind (benefits for the community). espousing project benefits. and risks addressed to provide
the project. This may extend to Initial gauge of community All key stakeholder issues confidence to lenders/investors
marketing to and seeking capital interest and support. Potential key addressed and factored into that no cost overruns, etc., could
raising from community investors. stakeholders identified. overall project considerations. occur as a result of community
related issues.
Active community engagement Advanced development of capital
undertaken with project benefits raising from community investors. All documentation in place to
clearly communicated. Support enable community investor capital
base identified and able to be raising and demonstrable investor
relied upon. Key stakeholders support fully quantified.
identified and engaged.
4
Business Structure
Project Element Concept/Prefeasibility Feasibility Final Funding
The type of business (legal/ Options discussed for both the Final business structure decided Final business structure in place.
tax/financial) structure used to governance of the project during and ready to be established.
develop and operate the project. project development and for the Project governance structure
final governance arrangements Project governance working and aligned with business structure
once the project is operational. addressing all governance issues. and in place.
The final business structure associated Solar panels at Geelong Primary School, Geelong VIC Business Structure Fundraising Disclosure Challenges Benefits
with the operation of a successful CE Photo courtesy of Geelong Sustainability Group
project may have no resemblance at all Co-operative Requires a disclosure • Can be more difficult to • Allows for unlimited
with initial or transitional organisational document to be approved access legal advice as is members and therefore
and/or business structures used to e.g. Hepburn Wind and
by a registrar based on Co-operatives no limitations on the
conceive and develop a CE project. Pingala Co-operative
Law rather than the more number of investors
Equally, the structure may stay common Corporations Act
unchanged throughout. There are two • Disclosure document
key and complementary elements to this • Membership shares cannot checking process is
project element: appreciate in value less onerous than under
Corporations Act
1. The structure of the community
enterprise itself • Can distribute profits
before tax
2. The project governance processes
associated with the community • Crowdfunding for
enterprise. membership is permitted
Incorporated association N/A • No equity investment • Low cost to establish and
4.1 Business Structure Examples
permitted operate
e.g. Pingala Association
Some examples of business structures
that have been applied to various CE Company limited N/A • No equity investment • Low cost to establish
projects are set out in the table following, by guarantee permitted, members specify and operate
together with the various pros and cons the amount they
each have in relation to project funding. e.g. Moreland Energy
are willing to contribute
More details can be found in the Funding Foundation, Yarra Energy
to the property of the
Basics Guidebook. Foundation
company on its winding
up and this will determine
or limit the liability of the
company’s members
5
Project Development Resourcing
Project Element Concept/Prefeasibility Feasibility Final Funding
The resources required to Skills identified and budget Skills identified and detailed Skills identified and budget cost
develop the required elements cost estimate to progress from cost estimate to progress from estimate to progress from Final
of a project from concept concept through to construction feasibility through to construction Funding through to construction
through to Final Funding and prior and commissioning determined. and commissioning determined. and commissioning determined.
to implementation. Funding and/or resources Funding and/or resources
available identified to ensure available identified to ensure
project can proceed at least to project could proceed to the
feasibility stage. final funding phase.
5.1 Project Development Photo courtesy of Embark 5.2 Financial Modelling of Project • Technical Costs – this item covers • Other Project Development Costs
Plan / Budget Development Costs technical/engineering advice – other project development costs
associated with items such as solar include project development elements
It is essential to recognise that funds In general, the financial model template
design, network load flow modelling not specifically included above and
will be required to progress a project considers project development costs
and technical analysis of network may incorporate items such as:
from concept through prefeasibility and to be capitalisable costs but project
constraints as part of network
feasibility to final funding. The nearer a proponents should seek financial advice ˚˚ Regulatory costs – Business
connection analysis. This will normally
project progresses towards final funding on this matter. structure costs associated with
not apply for small (often <30kW)
the greater the rate at which development establishing and operating business
Apart from specific project development Behind the Meter projects and may
funds will be expended so it is important structures during the project
costs, which are covered under not even apply for larger Behind the
through each stage of the process that development phase
other project element sections of Meter installations. The extent of any
budgets are reviewed to ensure there are
this guidebook, the following project potential export beyond the host site is ˚˚ Insurance Costs – Insurance costs
sufficient funds forecasts for the project to
development specific cost items are one of the major considerations on the associated with the business
proceed to the next stage of development.
included in the financial model template: requirement for network analysis. Refer structure during the project
Project developers need to have a plan to the section on Network Connections development phase. An estimate
• Financial Advice – this item covers
developed to ensure that the project is for more resources detailing these of these costs can be obtained
financial advice associated with
developed in a structured and efficient requirements. Note: if you decide to from insurance websites and as
accounting and tax elements in
manner and the project development work exclusively with a single solar a minimum would include Public
particular and could range from
budget is a key part of that planning supplier then much of the technical Liability Insurance.
zero where voluntary professional
process. While, from a financial modelling work such as the solar design and any
services are accessible to much
perspective, project development costs network connection analysis is often
higher figures (>$50,000) for large-
are generally capitalised when undertaking undertaken by that supplier on a low
scale solar projects
project evaluations, the project needs to cost or even nil cost basis as a trade-
ensure that sufficient capital is incorporated • Legal Costs – this item covers legal off for agreeing to purchase the solar
in the business to meet ongoing cash flow costs associated with items such as installation from that supplier.
needs for project development. In other establishing business structures and
words, developers need to ensure that they can range as per financial advice
have sufficient working capital to progress costs. Where possible use template
the project to the next stage of the project legal agreements, but please note
development process and need to plan the that given that each CE project is
cash requirements for the projects as part slightly different the template will
of a budgeting process. This requires a have to be adapted or reviewed
cashflow budget to be prepared so that the by a lawyer (though this may be
project cashflows can be managed along
5.3 Resource Links
less expensive than developing an
with ongoing funding requirements to meet agreement from scratch) For further information see:
the cashflows. frontierimpact.com.au/external-resources
6
Site Selection and Acquisition
Project Element Concept/Prefeasibility Feasibility Final Funding
Assessing, selecting and Broad host site selection criteria Narrowed down to one or Host site selected and access
gaining access to a good host established based on location two or host sites with relatively to site secured through lease
site for a Behind the Meter solar and project scale initially and then firm cost estimates and detailed or other secure site access
PV CE project. narrowed down to a few host site site assessment and access mechanism. Site suitability
choices based on estimated costs details either negotiated or assessed and confirmed.
and initial site assessment criteria. under negotiation.
The selection of suitable sites for a CE project can be quite complex given
the range of other factors impacted by site choice and is a critical decision
that needs to be made relatively early in the development process. Resource
availability and network connection access costs are just some of the elements
that are impacted by the choice of site. Resource availability and network
connection elements are considered in other sections of this toolkit but there are
a number of other specific site considerations that should be factored in when
deciding upon a choice of location and specific sites with that location. Funding
availability at various stages of the development will be dependent on the site
choice and the ability to secure access to suitable sites.
For Behind the Meter solar PV The information to the left represents 6.1 Site Costs – Financial 6.2 Host Site Benefit – Financial TIP
installations it is important to find a host the key technical parameters for a host Modelling Modelling
The direction that the solar panels are
site that supports the scale of project site. However, one of the key challenges
The site costs included in the financial The host site benefits are modelled facing is important so as to optimise
being contemplated in terms of roof area faced in accessing a suitable site is
templates fall into two categories: in the financial template using the the generation from the system. Facing
available for panel installation and the finding a host site operator that is
following factors: somewhere between NE and NW in
electricity consumption pattern of the amenable to installation of the solar 1. Those applicable to securing and
direction is best.
host site. equipment and who is receptive to the facilitating access to the site as part • Annual Electricity Usage: The total
benefits of the solar installation from of the project development process. amount of electricity used on the host
A (non-exhaustive) list of important
both a commercial perspective and For financial modelling purposes these site in one year in kWh
factors is set out below:
an environmental perspective. The costs are assumed to be capitalisable
• Current Retail Pricing: The current
• Roof space or available land financial template includes a host site but financial advice should be sought
average retail price paid by the host
benefits worksheet that will assist in in this regard. In the financial template
• Solar access site in c/kWh
identifying both the the commercial and the relevant inputs are:
• Host site electricity usage profile environmental benefits for the host site • Avoidable Retail Pricing: The avoidable
• Legal costs associated with
operator. element of the retail price paid by the
• Host retail costs including a negotiating and agreeing use of the
host site in c/kWh
breakdown of all costs including Many CE project developers will not host site(s). Such an agreement is
network charges commence any other project work until usually negotiated and incorporated • Assumed escalation on Host site
they have already engaged with a host as part of the overall power sales pricing: The assumed annual increase
• Community benefit of host site
site operator who is receptive to a Behind agreement for Behind the Meter in electricity retail prices at the host
• Shading considerations the Meter Solar PV installation. installations. site as a percentage of the annual
inflation rate e.g. 100% means prices
• Roof slope that minimises tilt costs 2. Those applicable to ongoing
are escalated at the full inflation rate.
payments associated with utilisation
• Orientation that supports panels facing
of the site(s) as part of ongoing • Business Discount Rate: The discount
in a northerly direction
operations and which fall into the rate the business owner would use for
category of operating expenditure any discounted cashflow analysis
in the financial modelling. These are
• Business Tax Rate: The tax rate
referred to as land/site rental costs
payable by the business
and would include:
• Project Evaluation Period: The
• Host site lease payments for Behind
timeframe in years over which the
the Meter installations
Host Site economic evaluation will be
undertaken (usually the same as for
6.3 Resource Links
the project)
For further information see:
frontierimpact.com.au/external-resources
7
Resource Assessment
Project Element Concept/Prefeasibility Feasibility Final Funding
Determining the amount of energy Initial calculation based on Verified resource availability Verified resource availability based
(kWh/MWh) that a project can solar calculators. based on final professional solar on final professional solar design.
produce annually over its life. design(s) with sensitivity analysis. Detailed sensitivity analysis.
More detailed calculations can be
provided by solar providers based
on manufacturer information and
local conditions.
There are many online resources 7.1 Annual Capacity Factor 7.2 Network Loss Factors 7.3 Financial Modelling of Solar
available to assist in assessing the
Annual capacity factor is a relative When electricity is transported significant
Resources
amount of power that can be produced
measure of the availability of solar distances power is lost through physical The toolkit includes the following
from solar panel installations. There
resource in relation to the peak output processes associated with heating modelling factors that need to be input
are a significant number of factors that
capacity of a generation project. This resistance and other electrical related to allow an assessment of the power that
will influence the power output from a
factor is calculated as the ratio of factors. These losses can impact retail will be produced from a solar installation
solar installation and so while online
forecast or actual generation that can be electricity costs and may be applied (see table).
solar calculation resources may be
obtained from a project to the maximum in power sales agreement calculations
useful starting points, professional At the feasibility and final funding
generation output capacity. although this is a matter of commercial
solar system designers should be used stages of the project professional solar
negotiation in Behind the Meter power
to assess energy output from a solar Annual Capacity Factor = designers can provide detailed data
sales agreements.
installation, noting that often CE groups Total Energy Produced Annually / on the above aspects as part of a
have solar professionals involved. The (Peak Capacity x 8760) Each location on the network is tender or quotation process to firm up
resource links at the bottom of this assigned loss factors in the main Construction costs.
Note: 8760 is the number of hours
section include links to a number of electricity grids in Australia. Typically
in a year
solar resource calculation sites. the loss factors might range from 0.7
The higher the capacity factor the more to 1.5. The higher the loss factors the
output that could be produced from a greater the opportunity for the Behind
specific project size and conversely the the Meter generation project to increase
lower the capacity factor the lower the revenue. The source of these loss
output. The capacity factor of rooftop factors for Behind the Meter installations
solar installations will vary considerably is an electricity account for the host site.
depending on a number of factors but This might be split into a Transmission
might typically be in the range of 12% Loss Factor (TLF) and Distribution
to 25+%. Loss Factor (DLF) or a combined loss
factor which is equivalent to TLF x DLF
or can be calculated as such. The
combined loss factor may be included
Global Horizontal Irradiation, Australia in the financial template but depends
on how the power sales agreement is
structured. If the power sales agreement
does not include specific provision for
losses then set these loss factor values
to 0% in the template. 7.4 Resource Links
For further information see:
frontierimpact.com.au/external-resources
TIP
• Shading Losses – these occur when some of the solar radiation is blocked from
accessing some or all of the panels due to the shading impacts of nearby buildings,
trees, etc. A professional solar designer would be able to assess this impact. Sites
should be chosen to minimise this potential loss impact
• Temperature Losses – solar panels do not perform as well on hot days and power is
lost due temperature impacts. For a particular location this impact should be able to
be modelled by solar calculators
• Voltage drop (wiring) losses – these occur as a result of the length of wire from solar
panels all the way to the metering point. As such there will be a reduction in power
produced from the project. A properly-designed system will minimise this but it could
be in the range of 1 to 3%
• Dust (soiling) losses – over time solar panels will become covered with dust and
other particles, which filter the solar radiation reaching the panels. Routine cleaning
will reduce this impact but it might impact performance by 1% up to 5%.
Doomadgee Solar Project, Doomadge QLD
Photo courtesy of ARENA
8
Construction
Project Element Concept/Prefeasibility Feasibility Final Funding
Determining the costs to Cost allowances for project Detailed cost estimates Solar Installer Contractor
obtain equipment, install it construction estimated broadly. obtained from reputable solar identified and cost estimated
and commission the project to installer contractors. based on comprehensive and
operational stage. A potential solar PV supplier detailed firm quote.
can usually provide budget costs
very readily.
9
Network Connections
Project Element Concept/Prefeasibility Feasibility Final Funding
Determining the technical Budget cost allowance for Specific cost estimates Firm cost quotations available
requirements and financial network capital costs and ongoing (CAPEX and OPEX) based on for CAPEX and OPEX
costs of connecting the project annual costs based on general one or two sites. assumptions clearly outlined and
Behind the Meter in relation to area estimates available from able to be validated. An agreed
network connections. network company websites. network connection agreement
Preliminary connection inquiry may be required.
made with network company.
If you can structure your project so 9.1 Small Scale Including Behind 9.3 Financial Modelling of • Network charges – These refer to
that the scale is not too large and there the Meter Network Connections ongoing network charges associated
is not a large amount of export you with connection to the network (to
See the online resource link for a guide The toolkit includes the following
should be able to use a standard network contribute to network business
providing information on the connection modelling factors that need to be input in
connection agreement which is simpler maintenance costs, other overheads
of small generation facilities including relation to network connections:
and much cheaper. and returns on network investment).
Behind the Meter solar PV, which are
• Initial network connection costs – This For appropriately sized Behind the
For Behind the Meter projects the process below 100kW in size.
is the initial capital cost associated Meter installations this would likely be
is generally much simpler due to the
9.2 Medium Scale with connecting to the network. For zero. However, for larger installations
typically smaller size of the projects and the
<30kW Behind the Meter this will and those with significant export in
lower levels of export resulting in a much The Clean Energy Council has
generally be small provided significant particular, in order to estimate costs
lower impact on the network and a much produced an ‘Embedded Generation
export is not proposed in rural enquiries need to be made of the
simpler network connection process. The Connection Guide’ aimed at providing
locations with a very low capacity relevant distribution network business
easiest way to minimise network charges is any embedded generation proponent
network available for connection. and you may require technical advice.
to keep the projects small with a relatively with information applicable to the
For >30kW installations and those Unfortunately network factors can be
low level of network export. The size at connection of medium scale embedded
with significant export in particular, quite site specific so it is not possible
which a project begins to attract more generation including Behind the Meter
in order to estimate costs, enquiries to estimate costs without specific
complex network approval arrangements solar PV to distribution networks. It
need to be made into the relevant enquiries being made
and higher network costs varies between is designed to apply to generators in
distribution network business and
distribution network operator areas and the size range of 100 kW to 5 MW and • Grid availability – Grid (network)
you may require technical advice.
can vary down to a specific site location in as such is applicable for Behind the availability refers to the amount of
Unfortunately network factors can be
a specific distribution network area. Many Meter installations which are 100kW time that the network connection
quite site specific so it is not possible
distribution network operators currently or greater in size. The guide has been is available for the conveyance of
to estimate costs without specific
have a threshold of 30kW above which produced through consultation with power from the generation connection
enquiries being made
more complex network approval processes Australia’s distribution businesses point to electricity consumers.
apply. However, you should make and takes into account the relevant The availability will depend on the
yourself familiar with the requirements of network rules and guidelines. Individual connection point in the network and
a particular distribution network operator distribution businesses will have different could range from around 95% up to
and factor the rules in when deciding on requirements so it is important to know nearly 100%.
the scale of your project. Be prepared to which distribution business’ network you
compromise or negotiate on the scale and may be connecting to. A link to the guide
network connection arrangements. In some is provided below:
instances distribution network operators
will prohibit the exporting of energy so you 9.4 Resource Links
may need to have your solar installer allow
For further information see:
for export limiting devices to be installed.
frontierimpact.com.au/external-resources
10
Permitting
Project Element Concept/Prefeasibility Feasibility Final Funding
Determining the technical Required permits identified Permitting commenced and Permits in place or available
requirements and financial (planning approvals, heritage, detailed cost estimates available. subject to final funding.
costs of connecting the project environmental) and cost Compliance activities post
Behind the Meter in relation to allowance made. operation scheduled and budget
network connections. allowed for them.
Solar suppliers can often assist
with this element and also provide
indicative costs as they often
arrange the approvals.
TIP
Depending on the Council location and If you are not selling the electricity to 10.1 Financial Modelling of
the size of the project, Behind the Meter a licensed electricity retailer and not Permitting Costs
solar installations may not even require selling it via a feed-in tariff then in theory
The toolkit includes the following
a building application to be submitted you would need to obtain an electricity
modelling factor that needs to be input in
although this would be an exception and retail licence to see the electricity output
relation to permitting costs:
not the normal situation. Certainly for from the solar PV unit. This can be a
larger installations a building application very onerous process requiring ongoing • Permitting costs – This covers the
would be required and potentially a reporting requirements and incurring project development costs associated
development application as well. The potentially significant costs, which are not with permitting which are capitalised
local Council would be the first place to warranted for a CE project. Fortunately a in the financial template although you
start when trying to assess the required retail licence exemption can be obtained should obtain financial advice as to
planning approvals and any associated for the sale of electricity and in particular the appropriateness of this treatment.
permitting as part of those planning for Behind the Meter installations through For Behind the Meter solar PV
approvals. In certain instances heritage the Australian Energy Regulator (AER). installations the permitting costs would
aspects may be relevant for buildings of Complete details of the process for generally be minimal and may only
historical or architectural significance and obtaining an exemption can be obtained require a building application/small
may require specific additional approval from the AER website. development application. However,
elements to be undertaken while in other issues such as heritage assessments
In some states exemptions are
very small solar installations no specific need to be considered if relevant and
automatically granted for small scale
approvals may be required, as they may can add costs to the project if these
installations but you should check this
automatically be considered as being a need to be accommodated. Solar
on a state by state basis and the rules
complying development. installers will generally be equipped
surrounding such exemptions.
to carry out the most of the permitting
process on your behalf.
11
Operational Resourcing
Project Element Concept/Prefeasibility Feasibility Final Funding
The ongoing costs of operating Initial assessment of operational Detailed analysis of Detailed and verifiable operational
the project and business structure resources required (operational operational costs undertaken costs supplied encompassing all
once commissioned and fully and admin personnel, and quotes obtained for third operation costs of the project.
operational. maintenance, etc.) and cost party services, e.g., equipment
allowance made. maintenance services.
11.1 Financial Modelling of • Inverter life – This represents the life • Administration – this item covers
Operational Resourcing Costs of the inverter after which time the the costs associated with operating
inverter needs to be replaced. Inverter the business structure including
The following factors related to
manufacturers should be able to invoicing and managing payments
ongoing operating costs are included
provide this information. It is typically associated with revenue sales and
in the financial modelling and require
5 or 10 years with 10 years obviously project expenditures.
user input:
being preferable.
• Share registry – if the project is issuing
• Insurance – This item covers the
• Maintenance cost escalation – This shares to obtain funds from investors
cost elements associated with two
item represents the percentage of then a share registry needs to be
insurance elements:
inflation by which the maintenance established and maintained. This is a
˚˚ Insurance for the operation of the costs increase over time. A default specific administrative cost that needs
business structure – estimated value of 100% should be assumed to be considered.
costs associated with this item unless better information is available.
• Ongoing community engagement and
could be obtained from insurance
• Accounting and legal – this item benefit programs – this covers the
companies. Insurances should
covers the costs associated with situation where the CE project may
include Public Liability, Directors’
routine financial accounting and distribute some of the project profits/
Insurance and others depending on
auditing. An accountant should be revenues back into the community in
the requirements of the project.
able to provide indicative costs. some way.
˚˚ Insurance for the operation of
• Maintenance costs – this item covers
the solar installation – estimated
the costs of routine maintenance
costs can be obtained from
including cleaning of the solar PV
insurance companies. In some
installation. For solar installations
cases the host site operator may
the costs might equate to around
be able to cover the cost as part of
0.5% to 1% of the capital cost of the
their own building insurance.
project but can be obtained from
the supplier of the equipment and a
long-term maintenance contract could
be provided by the supplier if price
TIP certainty was required.
12
Project Funding
Project Element Concept/Prefeasibility Feasibility Final Funding
The funding required to develop Potential funding sources Investor sources identified and Equity commitment demonstrated
a project from concept through identified to progress to feasibility detailed estimates of any debt (from community investors
to the commencement of the stage and estimates of source financing required determined. and/or other equity providers)
Operations phase. values made including donations Debt quotes and conditions and funding requirements
and grants. obtained if required through clearly communicated in formal
discussions with shortlist of application process. Lender
Potential investors identified potential lenders. targeted if debt finance required.
and consider if debt financing Outcome of Final Funding will
will be required for modelling be committed finance in the
purposes. Marketing collateral form of a comprehensive finance
developed for socialising with facility agreement if debt finance
community investors. required.
TIP
Many CE projects may not be financially 12.1 Modelling of • Funding costs – this item covers the
viable compared to large-scale non- Project Funding costs associated with:
renewable and renewable projects.
The financial template incorporates the ˚˚ Capital raising – the costs payable
However, given the other benefits
following items related to project funding: to third parties for assistance
offered by CE projects there may be
in raising funds. For Behind the
the ability to assist the financial viability • Grants – this item covers the level of
Meter solar PV projects this would
of CE projects through other sources. grant funding able to be procured in
normally be zero or a very low
These sources may include grants and relation to the project being evaluated.
percentage amount. However, if
donations to cover the development There are no guarantees that grant
the expertise is not available in the
costs, particularly in the early stages of funding will be available so at the
team, a commercial external adviser
project development. concept and prefeasibility stages it
is may be required to assist in the
should be assumed that grant funding is
However, regardless of the type of fundraising process. Payment for
not available
project, financial modelling needs to these services may be on the basis
be carried out in order to establish the • Donations – this item covers the receipt of a scheduled rate or a success fee
likely level of funding support required of donations to assist in funding the and may be limited to developing
to make a project viable. There are often project, particularly during early stage an information memorandum or
many projects seeking grant funding and development phases prospectus, or extend to finding
it is likely that those with clear financial investors and arranging finance
modelling which are near-commercial
˚˚ Debt establishment fees – the
would receive higher consideration for
costs of establishing debt facilities,
funding in advance of similar projects
typically around 1.5% of the debt
without a similar level of modelling having
amount, which is an amount that
been undertaken.
is charged by the financier. The
The final funding stages will incur financier that you are dealing with
expenditure to establish the funding will disclose this figure.
(typically sourced from equity) for CE
Behind the Meter projects. For larger
Behind the Meter projects some debt
may be required. The fees associated
with establishing the funding need to be
factored into the financial modelling as
described below.
12.2 Resource Links
Newlands Community House solar panels, Coburg VIC For further information see:
Photo courtesy of Moreland Energy Foundation frontierimpact.com.au/external-resources
13
Power Sales
Project Element Concept/Prefeasibility Feasibility Final Funding
Commercial agreements Identify and roughly quantify Host site(s) PPA structure(s) or Power sales agreement
to achieve contracted potential revenue sources. These other revenue sources identified secured with host site owner
sales revenues. may come from host site PPAs, and discussions with one or two and any other revenue source
LGCs if >100kW in size, sales of host site owners well advanced. agreements (export electricity
export energy (if any). and LGCs) negotiated and ready
Export and LGC revenue sources for execution.
Analysis of host site(s) electricity identified if these are applicable.
costs undertaken to determine
potential avoidable host site costs
as part of assessment of realistic
revenue stream modelling.
Revenue from Behind the Meter Solar PV installations can come in a number of
TIP
forms. Traditionally many of the projects are structured to have their main revenues
Energy costs also include the cost
come for Power Purchase Agreements although this is changing. Power purchase of electrical losses. Behind the Meter
agreements (PPAs) or offtake agreements are arrangements for the purchase of installations will assist the host site
to avoid the cost of losses so don’t
power from the solar PV system. forget to factor this saving into your
negotiations!
CE projects are no different to any other 13.1 Wholesale Electricity Prices 13.2 Retail Electricity Prices Avoidable charges might include: 13.4 LGC Revenue 13.5 Power Sales Structures
energy generation projects in that it costs
The wholesale price is the price a project The retail price is the price a business • Retailer energy charges (at a flat rate For Behind the Meter solar PV projects Obtaining a long-term agreed power
money to purchase, install, operate and
receives when exporting electricity to the pays for electricity. This includes the and/or peak/off peak/shoulder rates) above the STC threshold levels (>= sales agreement that provides certainty
maintain generation equipment and the
grid. The wholesale price is relatively low wholesale price plus network charges, 100kW) there is an ability to create of revenue for a CE project is perhaps
projects need revenues to offset those • Retailer environmental charges
in comparison to retail energy rates so retail charges, retail margins, LGC and Large Generation Certificates (LGCs), the single most important element in
costs. The prime source of revenue
selling power via a direct grid connection STC fees and other market-based fees • Retailer market fee (AEMO) charges which are also saleable instruments. One successful project funding arrangements
is the purchase of generation output.
will attract a lower rate than would (all adjusted up for network losses). The LGC is created for every megawatt hour (provided of course that the pricing
In addition to revenue from electricity • Network energy charges (at a flat rate
be achievable in a Behind the Meter retail price could be between two and (MWh) (note 1MWh = 1000kWh) levels support the required level of return
generation output, eligible renewable and/or peak/off peak/shoulder rates).
situation, as set out in this guidebook. seven times the wholesale energy price. of electricity produced as metered at to investors).
energy projects will be able to produce
Behind the Meter projects allow for sales The general difference between the generator output source. Once
certificates in the form of either Small- The following contractual power sales
at avoidable retail prices because the wholesale charges, retail charges and LGCs are generated they can be
scale Technology Certificates (STCs) or structures might be considered:
host site is able to avoid a significant avoidable retail charges is illustrated in created and then sold either as part of a
Large Generation Certificates (LGCs).
component of its retail energy bill if the chart on page 91: power sales arrangement or a separate 13.5.1 Behind the Meter Power
Both of these certificate types are
energy is generated Behind the Meter sales arrangement. Purchase Agreements (PPAs)
tradable in the energy market and are 13.3 STC Revenue
rather than sourced from the network. A Power Purchase Agreement (PPA)
a potential revenue source for projects
Under the Federal Government’s RET is an agreement with a party to purchase
although STCs are usually not a direct Avoidable retail charges are usually
legislation solar PV units with less than the electricity output from a generation
revenue source but rather reflected as a volumetric charges, denoted on an
100kW of capacity and total annual project such as a Solar PV installation.
capital cost reduction. electricity bill as being charged on a
electricity output of less than 250MWh Ideally, such an agreement might
cents/kWh basis, as opposed to fixed
For grid-exporting installations the are eligible to create Small Technology include the purchase of both the
charges ($/day) or demand charges
revenue from electricity sales is Certificates (STCs). The number of STCs electricity generation and the Renewable
($/kVA/month or $/kW/month).Fixed
competing with the wholesale price of able to be created are deemed to be Energy Certificates.
charge are not avoidable and demand
energy. However, for Behind the Meter equivalent the total renewable energy
charges are generally not avoidable for For Behind the Meter installations a PPA
installations, the electricity produced output over the life of the project until the
solar unless coupled with some form of and site leasing agreement are often
that is not exported beyond the meter is end of 2030. An online STC calculator is
storage such as batteries. combined in the one document entered
competing with much higher retail prices used to calculate the number of STCs
into by the customer (host site) behind
and as such can attract higher revenues. that can be created from the project.
whose meter the CE project is installed.
Because the STCs are available from
the start of the project they can be used For Behind the Meter installations the
to offset the capital costs of the eligible PPA price is based upon the avoidable
CE installation through their transfer to retail prices where the project achieves
the solar contractor on completion of sufficient revenue and the host site also
the installation. achieves cost savings (as described in
Section 13.2).
Generally the pricing of such PPA • The term of the contract (the number • In some cases Behind the Meter Wholesale, Retail and Avoidable Retail Price Comparison
agreements will be in one of two forms: of years over which the PPA will extend PPAs provide for the equipment to be
– preferably the life of the project) handed back to the host site after a
1. Based on a fixed price (with escalation
period of time (usually 10 to 20 years)
provisions of the fixed price being • The basis for calculating the volume Retail Market Fees
negotiated around the prevailing under the contract. This will be with An example relating to Behind the Meter Retailer Margins Retail Market Fees
Retailer Margins
avoided retail price), or reference to the meter(s) associated PPAs and combined PPA and associated
with the project and is generally development and leasing agreement can Wholesale Energy Wholesale
2. Based purely on calculated avoidable Energy
calculated directly from the meter be found online. Wholesale
retail prices of the host site which will Energy
volumes or from the meter volumes Network Avoidable
vary each year. 13.5.2 Export and LGC Sales Charges
adjusted for transmission and Network
Where the project is exporting power Charges
The first structure is typically preferable distribution loss factors
“beyond the meter” into the network the
for a CE project developer as there is
• The volume of electricity being export power will be subject to a feed-in
no risk associated with movements in
contracted which will be the entire tariff or a separate sales arrangement
retail prices. Under the second structure
project energy in just about every case with the host site’s electricity retailer.
the host site is usually guaranteed to
Where the project is 100kW or greater
be paying a price for electricity that is • The price of electricity including any Retail Retail
in size then LGCs will be produced and Environmental Environmental
less than the prevailing retail prices price escalation factor over time
ideally a long-term sales agreement for Charges Charges
but the CE developer takes on the risk (e.g., at CPI, at 75% of CPI, at a fixed
the sale of LGCs can be agreed with a
that avoidable costs could become escalation percentage or at a fixed
third party (the host site will generally
lower, thus reducing the revenue for price over the term of the contract)
not require all of the LGCs produced).
the project. This risk exposes investors Wholesale Retail Avoidable Retail
• In the case of LGCs being produced Where there is export and the production Wholesale + All Network Wholesale + Avoidable Network Charges
to any restructuring of network tariffs
(>100kW projects) the developer may of LGCs then the first candidate for the + All Retailer Charges + Avoidable Retailer Chargers
that move more of these charges to be
choose to separately manage the sale sale of both would be the host site’s
”fixed” which would reduce the variable
of the LGCs or assign some or all to retailer although other electricity retailers
(avoidable) energy related charges
the host site owner at a price are also potential sales agreement
and therefore the value of the Solar PV
counterparties.
installation output. • The billing frequency associated with
TIP
13.6 Operating Lease and Loan 13.7 Power Sales Financial • LGC price – this item represents the against the capital cost but they are
Revenue Models Modelling price of LGCs that could be sold to only allowed in sites generating less
create an ongoing revenue source than 100kW.
While not strictly power sales models, The financial template includes the
for the project in addition to power
operating leases and loan agreements following elements related to revenue
sales. Prevailing market prices for
are alternative models where the requiring user input
LGCs can be readily sourced online
revenue (for community investors in
• Power Sales to Host Site – this item through the use of a simple search
particular) is achieved through payments
represents the sale price in c/kWh on ‘LGC price’ although short term
in the form of equipment lease and/
at which the project is able to sell its LGC prices are currently generally
or loan repayments rather than from
electricity to the host site. For Behind significantly discounted if a long term
metered electricity sales. These are
the Meter projects the prevailing LGC agreement is required
simpler and lower risk arrangements for
variable (c/kWh) components of
CE project investors. • Electricity revenue escalation – this
the host sites’ electricity accounts
item represents the percentage of
13.6.1 Operating Lease Model represent the sale price that could
inflation by which power sales and
Under this model the community energy potentially be achieved. Some host
potentially LGCs can be increased
project would fund the solar installation sites may be willing to pay a small
over time as part of a PPA or other
and lease the equipment to the host premium on top of the retail price if
sales agreement. A conservative
site owner for a period of time until the the community nature of a CE project
starting point would be to assume an
installation costs are repaid (with interest) is valuable to them for marketing and
escalation rate of 0%
at which point in time ownership transfers corporate social responsibility reasons
to the host site. During the lease period • Lease or loan payments –
• Export Power Sales Price - this item
the CE project developer would be where revenue is achieved through
represents the price from sales of
responsible for the maintenance of the an operating lease or a loan
electricity exported to the grid through
solar installation. Pingala’s Young Henrys arrangement this factor requires input
a separate PPA, Feed-In-Tariff or other
project was designed around this model. of the monthly payments under the
commercial arrangement
lease or loan arrangement
13.6.2 Loan Revenue Model
• Export Sales % - this item represents
A loan revenue model is very similar • Term of lease/loan – This factor
the percentage of the total energy
to an operating lease model with the covers the length of the loan or lease
exported at the export sales price and
exception that the ownership of the arrangement in months
for an appropriately sized Behind the
project goes immediately to the host
Meter installation would ideally be zero • Escalation applied to loan/lease –
site owner and the community energy
or a very small percentage this is the escalation factor
investment in funding the solar PV
(if any) that is applied to lease
installation is effectively providing a loan • STC price – this item represents the
payments in particular.
to the host site. Revenue for investors price of STCs that could be sold to
is thus effectively principle and interest create a revenue source to offset
repayments on the funds invested based capital costs of the project. Most
on the loan repayments. Lismore City projects assign the STCs to the solar
Council’s proposed solar projects are installation contractor who in turn
designed to utilise this type of model. provides a lower capital cost to the
project. If this is the case then place
Note: Be aware that lease agreements
the price of STCs as $0 in the template
may have significant GST implications
and for capital costs use the reduced
that may impact cashflows early in the
capital cost net of STCs. Users are
project. You should get tax advice on this
encouraged to seek taxation and
aspect.
accounting advice on the best way to
manage any potential STC revenues.
Prevailing market prices for STCs can
be readily sourced online through the
use of a simple search on ‘STC price’ 13.8 Resource Links
For further information see:
frontierimpact.com.au/external-resources
14
Financial Modelling
Project Element Concept/Prefeasibility Feasibility Final Funding
The role of financial modelling Use templates to undertake Use templates to undertake Detailed financial model
and various financial factors prefeasibility financial modelling feasibility financial modelling (to the satisfaction of financiers
in assessing and fine tuning and assess whether to proceed and assess whether to proceed and/or investors) incorporating
project elements. to feasibility, terminate or revise to Final Funding, terminate or sensitivity modelling.
the project. adjust project.
The template enables you to focus on template allows for an early assessment simply seeking their initial investment • Accounting Depreciation Method: • Diminishing Value Multiplier: • Asset disposal value if transferred
key areas that you will need to cover of potential issues prior to incurring the to be returned given the community The financial template supports This value is the numerator in the to 3rd party at end of modelling
prior to deciding whether or not the additional expenditure needed to move benefits of the project) to 20% or more linear (straight line or prime cost) diminishing value formula and is period: The value at which the solar
project is likely to be viable and whether to final funding. for seed investors who perceive that depreciation and diminishing value usually 200%. For more information installation will be handed over to the
or not to invest more resources into the they require higher returns because depreciation. For accounting linear refer to resource links. host site or the value at the end of the
14.3 Business Case
project. You can then use the information of potential risks in achieving those depreciation is commonly used life of the project.
• Taxation Concessions for Small
gathered at this stage to start to consider The financial models produced will form returns. Typically, community energy where the capital base is depreciated
Business Apply: Currently tax • Working Capital balance required: The
if you might be eligible for grants or other the basis of a business case, which investors are receiving 3-9% by the same amount each year. So
concessions related to depreciation level of working capital funds to be
financial assistance measures that may will be used to initially attract project if the asset cost $100,000 and the
• Debt % – this is the percentage of apply for small businesses. If these maintained by the project. Can be $0
make the project viable. development funds for the project accounting deprecation period is
debt funding compared to the total for apply to the project then enter YES or greater.
and eventually support funding for 10 years the asset base would be
Section B in this guidebook explains the project. The level achievable will otherwise NO. If YES is entered then
project construction and operations. depreciated by $100,000 / 10 = • Interest on working capital:
the elements of this template, how depend on the riskiness of cash flows the depreciation rates under the next
It is important that the assumptions $10,000 per year The interest rate applicable to
to populate the template and how to associated with the project. Many 2 items are applied rather than the
used in financial modelling are robust working capital maintained in a
interpret the results of this template. Behind the Meter projects will not • Tax Depreciation Period: This is the taxation depreciation values specified
as investors are basing their funding financial institution
require debt and so the value will be period over which capital can be above.
14.2 Feasibility/Final Funding decisions on this information.
0% in this case depreciated for taxation purposes. The • Are dividends to be paid to investors
Modelling 14.4 Funding and Accounting/ • Tax Depreciation Rate 1st Year: This
period would typically be the life of the to be franked? If YES the dividends to
• Debt cost % – this is the interest rate is the taxation depreciation rate in the
As a CE project progresses further along Tax Factors Modelled solar project but tax accounting advice be paid to investors are taxed under
associated with the debt finance. first year under small business taxation
the development path the costs and should be sought. the business structure tax rates prior
The financial models include the This can be estimated from prevailing concessions and at the time of writing
revenue assumptions will become more to distribution. If NO dividends are
following factors that assist in the interest rates • Tax Depreciation Type: The financial was 30%.
accurate. The financial model template paid before tax?
financial evaluation of a project in terms template supports linear (straight
can assist you to gather the information • Leasing or debt term – This is the term • Tax Depreciation Rate after 1st Year:
of assessing the commercial viability. line or prime cost) depreciation and • Are investors to be paid a fixed or
required to support a funding decision. in years over which lease payments This is the taxation depreciation
All of these factors will have a potential diminishing value (reducing value) variable dividend amount? If FIXED
impact on the project’s cash flows and are to be made or the debt funding is rate after the first year under small
Certain funding providers (such as depreciation. For tax depreciation the the model will fix the dividend to be
financial viability: to be repaid business taxation concessions and at
banks) may require detailed information diminishing value approach is often paid each year to investors. If variable
the time of writing was 15%.
to ensure that the project is going to • Tax rate – This is the tax rate used. This approach allows for more the model will utilise the percentage
• Base discount factor – this rate is seen
be viable and able to meet the debt applicable to the business structure rapid depreciation in the early years of • Is Asset to be disposed of at the end of profits to be distributed to investors
as the minimum return that investors
servicing obligations that would arise used for the project the project and less in later years. of the modelling period? If the solar (see following page)
in the project would expect to see
with successful debt funding. The costs installation is to be decommissioned
on their investment after tax – also • Accounting Depreciation Period: This
and revenue streams will need to have or handed over to the host site at
referred to as project hurdle rate. is the period over which capital can be
been firmed up significantly at this point. the end of the project then enter YES
The level will depend on the type of depreciated for accounting purposes.
In addition, significant sensitivity analysis otherwise NO.
investor and might range from 0% The period would typically be the life of
needs to be done to ensure that the
(e.g., for investors not interested in the solar project but accounting advice
project can be viable under adverse
achieving a return on their money but should be sought.
forecast scenarios. The financial model
15
Risk Management
Project Element Concept/Prefeasibility Feasibility Final Funding
Identification and management Key risks identified and Key risks identified, risk Detailed risk management
of key risks associated with documented with some risk mitigation approaches finalised, plan prepared.
the project. mitigation approaches considered. risk management strategies
developed and risk management
plan drafted.
• Risk identification – identify all of the 15.1 Specific Behind the The table below shows some of the risks that need to be addressed and mitigated.
key risks to the project Meter Risks
• Risk quantification – attempt to The following table sets out some of the Risk Element Description of Risk Potential Mitigation Approaches
quantify the risks. Sensitivity analysis is specific risks that should be considered
for Behind the Meter projects together Network tariff structure Network tariffs are changing • Structure any PPAs to have a fixed price subject to
one way to achieve this
with some potential risk mitigation changes structurally and moving more escalation without any reference to avoidable charges
• Risk mitigation strategies –show and more to fixed price and
strategies. This is by no means an • Use an alternative structure to a PPA such as a loan/lease-
how the risks will be managed demand charges which are
exhaustive list and developers should not based model where the revenues are fixed based
rely on these as being the only risks that not avoided by installing a
on repayments rather than energy production of the solar
they need to manage: Behind the Meter solar PV
PV installation
project. If revenues are based
purely on avoidable costs
then the revenue base for the
Bendigo Library solar install, Bendigo VIC project may decline over time
Photo courtesy of the City of Greater Bendigo
Energy efficiency The host site reduces its • Structure any PPAs to have “take or pay” provisions so
energy such that the project that the host site owner pays whether the energy is used
exports much more energy at internally or exported
lower prices thereby reducing
• Select a host site which is already energy efficient or one
the energy base
whose load is much greater than the size of the Behind the
Meter project so that there is a safety margin included to
cover this situation
102 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 103
SECTION C SECTION C
C 15 RISK MANAGEMENT 15 RISK MANAGEMENT
C 15
˚˚ Obtaining STCs upfront (<100kW) versus ongoing Operational Resourcing • Have you set up a structure to minimise ongoing
LGC revenues? operating costs?
Community Engagement • Do you have a good community engagement model in
place that will: Project Funding • Have you prepared a budget?
˚˚ Engender community goodwill? • Have you identified all potential funding types and sources
and selected the most appropriate one?
˚˚ Assist with permitting approvals?
• Have you determined a marketing approach for
˚˚ Provide a base for potential community investors to be
attracting investors?
identified and targeted?
Power Sales • Have you identified the most appropriate revenue generating
Business Structure • Is the business structure appropriate in terms of:
structure for your project:
˚˚ Engaging community participation?
˚˚ PPA?
˚˚ Obtaining funding particularly from community
˚˚ Loan-based?
investor sources?
˚˚ Lease-based?
˚˚ Keeping business operation costs under control?
Project Development Resourcing • Have you identified the resources required for the development • Do you have an agreement in place that guarantees
of the project? sufficient revenue?
• Have you prepared a business plan and a budget that can be • Is this agreement legally and commercially sound?
used to manage the project? • Do agreements cover situation where host site lease may expire
Site Selection and Acquisition • Have the following aspects been considered in relation to the or building is sold?
host site you have chosen: Other Revenue • Have all sources been identified?
˚˚ Minimising export, i.e. match host site load profile to Financial Modelling • Have you completed the financial template and does it indicate
project scale? the project is viable?
˚˚ Minimising construction costs (e.g. is roof structure good, not • Have you carried out sensitivity analysis on the template to
requiring additional work)? cover potential variations in project elements?
˚˚ Is host site tariff high enough to provide good revenue base? • Does the modelled Power Sales revenue structure provide
˚˚ Is host site owner creditworthy? savings to the host site?
104 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 105
D
SECTION D SECTION D
D APPENDIX I - SUCCESSFUL COMMUNITY ENERGY PROJECTS APPENDIX I - SUCCESSFUL COMMUNITY ENERGY PROJECTS
D I
Hepburn Wind Hepburn Wind Vic Wind 4100 Ravenshoe Qld Solar PV 6
Citizens Own
Repower One NSW Solar PV 99 Renewable Energy Nannup WA Solar PV 10
Repower Shoalhaven Network Australia Pegasus Riding for the Disabled ACT Solar PV 6
Repower Two NSW Solar PV 30
(CORENA)
Terrey Hills NSW Solar PV 15 Moss Vale NSW Solar PV 2.12
Walgett NSW Solar PV 25 The People’s Solar St Kilda Community Housing Vic Solar PV 15
Broken Hill NSW Solar PV 100 Narara Ecovillage Co- Narara Ecovillage Co-operative Ltd NSW Solar PV 29.75
operative Ltd
Repower Shoalhaven Kangaroo Valley NSW Solar PV 9
Blue Mountains Blue Mountains NSW Solar PV 4.5
Renewable Energy
Cooperative
Nimbin Community Nimbin Community Solar Farm NSW Solar PV 45
Solar Farm
Projects that Aggregate Households
Moreland Energy Darebin Solar Savers Vic Solar PV 600
Foundation Ltd (MEFL)
Bendigo Sustainability Bendigo Vic Solar PV 2500
Group
108 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 109
SECTION D SECTION D
D APPENDIX II – FINANCIAL CONTACTS APPENDIX II – FINANCIAL CONTACTS
D II
FINANCIAL CONTACTS
Global Head of Clean Energy, Specialised Finance Corporate Affairs Senior Consultant
Corporate & Institutional Banking | National Australia Bank Limited Kew, VIC 3101
Level 32, 500 Bourke Street Melbourne VIC 3000
Tel: +61 3 9854 4847
Tel: +61 3 8697 6565 | Mobile: +61 484 636 324 Email: Jane.Kern@bankaust.com.au
Email: andrew.w.smith@nab.com.au
Lee Brennan
David Wilson
Head of Alternative Assets & Impact Investing
Business Development Area Manager – Asset Finance Future Super | Unit 127A 24 Lonsdale Street, Braddon ACT 2612
Client Acquisition & Specialist Solutions
Tel: 1300 658 422
Corporate Financial Services
Email: info@myfuturesuper.com.au
Business & Private Banking
Level 9, Darling Park, Tower 1
201 Sussex Street, Sydney NSW 2000
Katharine Tapley
110 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 111
SECTION D SECTION D
D APPENDIX III – DEFINITIONS APPENDIX III – DEFINITIONS
D III
DEFINITIONS
Angel investors: Angel investors Depreciation Method: The financial Grid Connected: A project that is Maintenance Cost Escalation: The Project Development Costs: The costs solar installation contractor who in turn
(also referred to as seed investors) template currently supports a number of connected directly to the electricity percentage of inflation by which the of taking a project from concept to Final provides a lower capital cost to the
normally provide equity during the depreciation methods including Linear network via its own network managed maintenance costs are expected to Funding phase project
earlier development stages where there (straight line or prime cost depreciation) meter and therefore exposed to increase over time. A default value of
Project Evaluation Period: The period Transmission Loss Factors (TLFs):
is less certainty on project success. To and Diminishing Value - refer to https:// wholesale electricity pricing 100% of CPI should be assumed unless
over which the project is to be evaluated The published loss factors associated
compensate for the early investment risk, www.ato.gov.au/Business/Income-and- better information is available
Grid-Integrated: A project that is which could be as long as the economic with losses in the transmission network.
angel investors will typically be offered deductions-for-business/Depreciating-
connected Behind the Meter but exports Network Charges: Ongoing network life of a solar PV projects, which is
a higher return than those investing assets/General-depreciation-rules/Prime- Wholesale Electricity Prices: The
much of its power to the network charges associated with connection to generally considered to be 20 to 30
at a later stage in the project (i.e., a cost-and-diminishing-value-methods/ for price a project receives when exporting
the network (to contribute to network years.
greater share of the project per unit of more details on each In-Kind Contribution: primarily electricity to the grid through either the
business maintenance costs, other
investment) volunteer labour but refers to any Retail Electricity Prices: The price market based spot price for electricity or
Depreciation Period: The period over overheads and returns on network
contribution to a project that does not a business pays for electricity. This via a PPA or other sales agreement.
Behind the Meter: A connection where which the project is to be depreciated investment). For appropriately-sized
incur cash payments for goods and includes the wholesale electricity price
an electricity project is connected to the for tax and accounting purposes and Behind the Meter installations this would
services plus network charges, retail charges,
internal electricity network of a host site. should be based on tax and accounting likely be zero. However, for larger (often
retail margins, LGC and STC fees and
The connection is “behind the meter” standards and financial advice Inverter Life: The life of the inverter a 30kW threshold applies) installations,
other market-based fees (all adjusted up
that the network company and electricity after which time it needs to be replaced. and those with significant export in
Distribution Loss Factors (DLFs): The for network losses)
retailer use to measure the electricity Inverter manufacturers should be able to particular, in order to estimate costs
published loss factors associated with
consumed on the host site so that the provide this information enquiries may need to be made into the Sensitivity Analysis: Analysis of project
losses in the distribution network.
power will be used by the host site first relevant distribution network business financial performance variability through
Lease Payment Revenues: Where
and only any excess is exported beyond Electricity Revenue Escalation: The and you may also require technical changing key template inputs.
revenue from a CE project is achieved
the meter into the network percentage of inflation by which power advice. Unfortunately network charges
through an operating lease rather than Share Registry: If the project is issuing
sales and potentially LGCs can increase can be quite site specific so it is not
Below-the-Load: Behind the Meter from sales of electricity. The financial shares to obtain funds from investors
over time under the terms of a PPA or possible to estimate costs without
projects that do not export any energy to template included in this guidebook then a share registry needs to be
other sales agreement specific enquiries being made
the grid models the lease as monthly payments. established and maintained.
Feasibility Phase: The project Network Connection Costs: The initial
Capital Cost (CAPEX): The total LGC Price: The price of LGCs that could Social Impact Funds: Investment
development phase that incorporates the capital cost associated with connecting
installed cost of a project be sold to create an ongoing revenue funds with a specific investment focus
firming up all of project element options to the network. Unfortunately network
source for the project in addition to on projects that offer a large social and
Community Investors: Investors who including establishing more certainty costs can be quite site-specific so it is
power sales. Prevailing market prices environmental impact to society
are members of the community and may around project costs and revenues not possible to estimate costs without
for LGCs can be readily sourced online
be retail, wholesale, angel investors specific enquiries being made Solar Losses: The reduction in
Feed-in Tariffs: Regulated price through the use of a simple search on
theoretical power output from solar
Concept Phase: The project arrangements under which retailers pay ‘LGC price’. Network Loss Factors: Distribution and
panels as a result of various technical
development phase in which a CE for energy exported into the grid from transmission loss factors collectively
LGC Revenue: The revenue that is and environmental factors.
project idea has been conceived and solar PV projects
obtained through the sale of LGCs at the Peak Power Capacity: The peak design
interested project proponents have Solar Resource Assessment:
Final Funding: The project development LGC price output of the solar PV installation in kW
engaged to consider how to develop the Calculation of the amount of power that
phase where all project elements have
project to prefeasibility and feasibility Loan Repayment Revenues: Where Power Purchase Agreement (PPA): can be produced from a solar installation
been developed in detail and the project
phases revenue from a CE project is achieved An agreement for the purchase (and over (usually) an annual period which
is ready to be put forward to potential
through a loan arrangement rather than sale) of electricity output from an can be done using solar calculators or by
Debt Cost % (interest rate): The funders for final funding to support
from sales of electricity. The financial electricity generation project engaging solar design professionals
interest rate associated with the debt construction and operation of the project
template included in this guidebook
finance. This can be estimated from Prefeasibility Phase: The project Sophisticated Investors: A sub-
Grid (network) Availability: The amount models these as monthly repayments
prevailing interest rates development phase that arises out of category of wholesale investors under
of time that the network connection is of principle and interest as a revenue
the concept phase once key project Corporations Law that meet certain
Debt Financing: Funding via a loan available for the conveyance of power stream for this project.
elements have been decided upon and minimum asset or salary thresholds
from the generation connection point to
options around these key elements are
electricity consumers. The availability will STC Price: The price of STCs that could
considered in more detail
depend on the connection point in the be sold to create a revenue source
network and could range from around to offset capital costs of the project.
95% up to nearly 100% Most projects assign the STCs to the
112 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 113
SECTION D
D APPENDIX IV – COMMUNITY ENERGY BEHIND THE METER CASE STUDIES
D IV
Introduction
In this section of the Behind the Meter Solar PV
Guidebook, the information provided in the early part
of this guidebook and in the Funding Guidebook is
illustrated through two CE case studies that describe
two different funding models which can be applied to
further CE projects.
The Funding Basics Guidebook itself The two case studies that have been could be considered are:
describes various business models selected for this Behind the Meter Solar
• ClearSky Solar Investments’ trust
that may be applicable to CE projects. PV Guidebook are:
model, where they partner with a solar
Currently there are over 30 Behind the
Repower Shoalhaven’s PV installation company
Meter CE projects in Australia that are
Repower One project
either operational or in the advanced • Embark’s small-scale solar loan
project development phases. Many of Pingala’s Young Henrys project. model that is being considered for the
these projects have acquired all or the Farming the Sun project in Lismore
Specifically, these case studies detail:
majority of their funding from donations.
• The Sydney Renewable Power
This guidebook deliberately focuses on • The funding model used in each case
Company’s mid-scale solar public
investment-based projects as opposed including the type of funding and the
company model.
to projects funded by donations, as source of those funds as explained in
donation-funded projects models are the Funding Basics Guidebook More information on the various business
unlikely to be replicable to the extent of models is set out online
• Key lessons and tips these CE groups
creating a broader base of projects.
learnt in developing their projects and
Investment-based models are likely to particularly in securing funding
appeal to a wider cross section of the
• How the project elements set out in
community given there is a return on
this Behind the Meter Guidebook have
any investment (equity) in the project. A
been addressed in each case.
commercial, profit-based model is likely
to result in the development of a greater The two case studies have a number of
number of CE projects. It is important to similarities when considering the factors
highlight that community investors may above. The case studies are both Behind
be willing to accept a much lower rate the Meter projects that are of a small
of return than institutional investors in scale using proven solar PV technology.
recognition of the fact that the projects The key differences influencing funding
provide benefit to their local community. in these case study projects is the legal
structure which was driven from different
The two case studies that have
investment objectives of the two cases.
been selected and incorporated in
Pingala is not complete at the time of
this guidebook are both community
writing but is expected to be operation in
investment-based models that have been
April/May 2016.
developed and can be replicated by
other CE groups.
D.IV Resource Links
Other investment based models that
For further information see:
frontierimpact.com.au/external-resources
114 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 115
Broken Hill solar power plant, Broken Hill NSW
Photo courtesy of ARENA
CS1
Case Study 1 –
Repower Shoalhaven:
Repower One Project
Repower Solar One
Local Funding $119,800
Number of investors 20
Expeced minimim return 6.5%
Located in Shoalhaven Heads, NSW
99kW solar system
SECTION D SECTION D
D CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT
D IV
CASE STUDY 1 –
Repower Solar One
Local Funding $119,800
Number of investors 20
REPOWER SHOALHAVEN: Expeced minimim return 6.5%
Located in Shoalhaven Heads, NSW
REPOWER ONE PROJECT 99kW solar system
Project Overview The timeline for development of KEY LESSONS AND TIPS MAY 2013 FEBRUARY 2014 FEBRUARY 2014 JUNE 2014 AUGUST 2014 LATE AUGUST 2014
the concept through to commercial
The Repower One project involves • The importance of strong leadership.
operation of the Repower One project is
construction and operation of a Behind Having a leader who is committed
summarised to the right:
the Meter 99kW solar power system on the and able to spend significant Repower Kangaroo Repower Grant received Community Project
roof of the Shoalhaven Heads Bowling and Repower Shoalhaven is a not-for-profit volunteer time at the early stages Shoalhaven Valley small One concept from NSW fund raising commenced
Recreation Club (SHBRC) on the South organisation established to develop of the project to drive the project established solar project originated, Government conducted, operation
Coast of NSW. The project was developed community renewable energy projects was essential to the success of the completed indirect project
by Repower Shoalhaven, a local not-for- for the benefit of local people, groups organisation and its projects. donation commenced
profit community energy association which and businesses. One of Repower received for construction
• The need to convert community
established Repower One as a company Shoalhaven’s goals was to develop a legal work
support into momentum. Moving
to build and operate the project. Funds financing model for community solar
quickly when there is strong
required to construct the solar project and then to deploy it in the Shoalhaven
community support ensures positive
were raised from individual investors from community. Repower One is the first
the community, referred to as ‘community deployment of this model and since then
momentum is established from the Funding Model Overview At the final funding stage, a total of Funding Model Evolution
beginning of the project $119,800 was raised from community
shareholders’ and from volunteer and in- Repower Shoalhaven has implemented The Repower One project was the A lot was learnt in the process of
kind contributions, grants and donations. Repower Two, and Repower Three is in • The importance of building the
shareholders who are the investors in
culmination of an initiative within developing Repower One and the
development. group’s knowledge and reputation.
a project entity. The project entity (also
The project has been successfully Repower Shoalhaven to develop and funding model has now been refined.
Delivering a ‘quick win’ donation-
known as a special purpose vehicle
operating since October 2014 and has Repower Shoalhaven is run by volunteers implement a model for community For example, in Repower Two, a high-net
based project at Kangaroo Valley
or SPV) was incorporated as a private
achieved forecast energy production and, since the commencement of the financing of renewable energy projects. worth community investor agreed to
built knowledge and expertise within
company with the name of Repower
estimates and paid dividends to Repower One project, some part-time The development of this model spanned underwrite the project by agreeing to
the group and raised the profile and
One Pty Ltd. The critical funding for the
community shareholders in line with the staff have been employed. the concept, prefeasibility and feasibility fund up to a certain percentage of the
reputation of Repower Shoalhaven in
concept, prefeasibility and feasibility
estimates provided in the offer information project development stages whereas the required funding if there was a shortfall
their region.
stages came from volunteer and in-
document. implementation of the model (Repower in the funds raised through the general
kind time, donations and a grant. The
One) spanned the feasibility and final funding offer. While the number of
Brief History of development funding comprised $37,000
funding stages. investors was still capped at 20, this
Repower Shoalhaven in grants and donations and many hours
meant Repower Shoalhaven were able
The Repower One solar installation of in-kind time which, if assessed at $50
Chris Cooper lead the development to reduce the minimum share size from
is 20% owned by Shoalhaven Heads per hour, amounted to around $90,000
of Repower Shoalhaven following the $6000 in Repower One to $600, thus
Bowling and Recreation Club with the in value.
success of Kangaroo Valley which opening up participation to community
remaining 80% financed and owned by
involved a project to install solar members with less disposable income.
19 community shareholders.
panels on the roof of Kangaroo Valley
Ambulance Station and funding for this
project was sourced from donations from
the local community, allowing the project
to be completed rapidly and easily for a
quick win. REPOWER ONE REPOWER TWO REPOWER THREE
SPV* SPV SPV
Repower Shoalhaven was established in
May 2013 when Chris Cooper organised
a community event to gain support for the * SPV represents a special purpose vehicle which is a separate private company
created for each project.
development of local CE projects and it
was attended by 180 people. The success
of the event lead to the development of a
committee within a week of the event.
118 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 119
SECTION D SECTION D
D CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT
D IV
120 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 121
SECTION D SECTION D
D CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT
D IV
Total (cash)
$185,750
Owner Investments
122 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 123
$29,750
SECTION D SECTION D
D CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT
D IV
Retail and Wholesale Investors Community investors contributed KEY LESSONS AND TIPS
Funding raised: $119,800 from 19 community investors
from the Local Community $119,800 to the project over the course
• Build trust. People need to have
(Community Investors) of a financing campaign that was fully Under what conditions Investors had clear information provided in an offer information document. This included, among
trust to invest. Repower Shoalhaven
subscribed in just 10 days. Repower and why did they invest? other items:
Financing an energy project using were able to build this up over time
Shoalhaven used a combination of • An expected minimum rate of return of 6.5% based on a long-term fixed price power purchase
investment funds from community through good corporate governance
emails and newsletters to their members, agreement
members was the goal of the initiative and a democratic decision-making
website updates and social media
that delivered the Repower One process whereby members could
activity to achieve this result. • A minimum investment amount of $6,000.
project. The project construction vote on key aspect of the project
was successfully funded using 100% The following table summarises the development Investors were interested in the financial opportunity but were equally motivated by the ethical nature
community investment funds. These community investor contributions: of the project and its ability to be replicated
• Inspire and motivate – tell the story.
investors were all members of the What was done to secure • Building a large base of members and offering a competitive rate of return
Repower Shoalhaven have shown it
Repower Shoalhaven Association and community investors?
is as important to appeal to people’s • The 20/12 exemption rule meant that Repower One was limited to only offering investments to
were invited to participate in the project
emotions as it is to their intellect. individuals with whom they had a direct relationship. It was beneficial that a large membership
via direct invitation. The project depends
See the resource links for an article existed from which the community investors were drawn
on the “20/12” small-scale offering
by Chris Cooper that demonstrates
exemption ruling. This ruling allows • Repower Shoalhaven were aware of the anti-avoidance provisions associated with the
the importance of leadership and
private companies to offer investments application of the 20/12 exemption rule and structured their offering to comply with these
key messages.
to individuals with whom they have a provisions
direct relationship. There are limits to
this ruling, such as shares being issued • The rate of return in equity was set at a minimum of 6.5% (internal rate of return). It took just 10
to no more than 20 investors and a days for the share offer to be fully subscribed by retail and wholesale investors from the local
maximum of $2 million in funds being community.
raised, in any 12 month period. An offer What needed to be Repower Shoalhaven delivered the 15 project elements referenced in the Funding Basics Guidebook
information document was provided to in place in order for and detailed in this Behind the Meter Guidebook and the following section shows how they applied it
D.CS1 Resource Links
prospective investors but this didn’t need investment to be
to be lodged with ASIC which resulted in For further information see: possible?
reduced costs. frontierimpact.com.au/external-resources
124 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 125
SECTION D
CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT
D IV
Divedends
Operations &
Maintenance Shareholders
Contract Agreement
Community
Investors
Repower Shoalhaven had to clarify the wording on the 10 year inverter warranty start
date (it was unclear whether it was six months from the date of shipment or the date of
installation). Given the 10 year project term for the first two projects, an inverter failure
in the final months would be detrimental to investor returns if it was outside of warranty
The incident response time was tested (and passed) when the customer notified of a
flapping awning over the Repower One inverter set-up, after a storm. The installer was
notified immediately and had someone on site to fasten the awning in a matter
of hours
128 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 129
SECTION D SECTION D
D CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT
D IV
• Output monitoring
• Shareholder communications
130 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 131
SECTION D SECTION D
D CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT
D IV
Project Element 4 Business Structure...continued Project Element 6 Site Selection and Acquisition
Lessons Learnt and Challenges Challenge was to find a business structure with the following suitable components: Required Status When Seeking Site selected and access to site secured through purchase, lease, option or other
Faced Final Funding secure site access. Site suitability assessed and confirmed
• Economically viable
This data is presented to the client and also feeds into Repower Shoalhaven’s
financial model and client proposal
Lessons Learnt and The delays in getting potential host site meter data via either utility request or
Challenges Faced installation of data loggers can slow the project down, losing important sales cycle
momentum with the potential client
132 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 133
SECTION D SECTION D
D CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT
D IV
Lessons Learnt and The solar contractor managed all requirements. • $7/kW contingency (set aside)
Challenges Faced • $165 office registration
• Repower Shoalhaven administration fee (7-10% of revenue). See ‘Business Structure’ for
itemised list of responsibilities associated with this fee
Lessons Learnt and Insurance costs were included in the PPA as being payable by the Recreation Club
Challenges Faced as part of their broader building insurance. This saved the project costs. The key
solar equipment is covered by warranties from Tier 1 supplier.
134 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 135
SECTION D SECTION D
D CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT CASE STUDY 1 – REPOWER SHOALHAVEN: REPOWER ONE PROJECT
D IV
Investors receive their income back over the course of the contract term. It is Lessons Learnt and Challenges Whilst there are many benefits to a PPA from the perspective of a business
returned in three forms of cash: Faced customer, the long term nature of a PPA contract (10-15 years) can be a barrier to a
customer signing up and also create an element of counterparty risk to the investor
• Capital return
(for certain projects).
• Dividend
Repower Shoalhaven are working on diversifying their financial offering to include
• Franking credit. a community loan agreement to offer to certain clients (4-6 years) as opposed
to a PPA so that the Repower Shoalhaven project generates a return from loan
Repower Shoalhaven’s first project had a forecast cash return on the initial
repayments as opposed to PPA revenue.
investment of between 6.5% and 7.8% per annum, internal rate of return
In response to barriers identified in the field, Repower Shoalhaven has amended the
Repower Shoalhaven has a private underwriter on hand to make up for any shortfall
front page of the PPA by including a form which allows customers to easily transfer
in finance, should they not reach their funding target by the set financing date. This
the PPA contract to a new tenant. This provides additional certainty for business
underwriter has not been used to date. The underwriter will only invest if they deem
owners on the ease of transferability, something which Repower Shoalhaven has
the project safe to do so
identified as a barrier for some customers signing the PPA
Lessons Learnt and The chosen method of capital-raising can at times be confusing for prospective
Challenges Faced investors to understand due to the impact of depreciation on the accounting
treatment of shareholder capital. In light of this Repower Shoalhaven is exploring a
new project structure in 2016 whereby capital is raised via shareholder debentures Project Element 14 Financial Modelling
as opposed to equity. This also provides other advantages in relation to tax,
Required Status When Seeking Detailed financial model provided (to the satisfaction of financiers and/or investors)
streamlining the financial auditing process and reducing complexity associated with
Final Funding incorporating sensitivity modelling
franking credits.
Repower Shoalhaven’s Approach Repower Shoalhaven developed its own financial model to allow up to 10 projects
to be modelled together as a single investment, each with differing term lengths and
offer prices
Project Element 12 Project Funding
The model has been reviewed by multiple accountants and members with technical
Required Status when Seeking Grants significantly utilised prior to final funding with any remaining grant expertise to ensure it is accurate
Final Funding funding utilised in construction stage.
Lessons Learnt and Challenges This model has been developed with accountant input and review. It is worthwhile
Repower Shoalhaven’s Approach Repower Shoalhaven received $10,000 from the NSW Government Office of Faced getting professional assistance when developing such a sophisticated model,
Environment and Heritage to use for accounting, capital, marketing materials and particularly to navigate trickier aspects such as depreciation and taxation
other elements associated with developing the business model
Repower Shoalhaven has a separate set of accounts for each of their project entities
Project Element 15 Risk
Lessons Learnt and
Required Status when Seeking Detailed risk management plan prepared
Challenges Faced
Final Funding
Repower Shoalhaven’s Approach Repower Shoalhaven has developed a detailed project risk management document
which serves as a guide for mitigating risk through good project design and
responding to risk events
Lessons Learnt and This is reviewed at each new investment project prior to the release of the share
Challenges Faced offer document
136 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 137
CS2
Case Study 2 –
Pingala: Young Henrys Project
Young Henrys
Total Cost $38000
Local Investor Funding $18000
Expected Minimum Return 5%
Located in Newtown NSW
29kW Solar System
SECTION D SECTION D
D CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT
D IV
CASE STUDY 2 –
Young Henrys
Project Overview
Total Cost $38000
Local Investor Funding $18000 The Pingala project (Pingala) has
PINGALA: Expected Minimum Return 5%
Located in Newtown NSW
installed a 29kW solar system on the
roof of Young Henrys, a micro-brewery
YOUNG HENRYS PROJECT 29kW Solar System located in the inner-Sydney suburb of
Newtown. The project has been funded
by local community investors together
with grant funds (noting that the grant
funds are not essential for the project to
be financially viable).
Establishes a distributing co-operative legal • The distributing co-operative model allows a larger number of shareholders
structure instead of creating separate private through a lower-cost fundraising process than a company or trust structure
companies for each project. (see Funding Basics Guidebook).
• Allows multiple projects to be developed under one entity and creates the
potential for lower administrative costs that are able to be recovered in time
over a larger number of projects.
Uses a leasing approach rather than a PPA. • The return for shareholders under a Power Purchase Agreement is based
Pingala will purchase the solar PV system and on amount of energy generated so the shareholders are directly impacted
lease the solar PV system to the host site. by the generation output risk of the project. A lease agreement provides
Ownership is transferred to the host site at the less risk for the shareholders as revenues are not dependent on generation
end of the project term output and as such there is a fixed cash flow revenue stream available to
provide a return on shareholders’ funds.
• Under a PPA arrangement Pingala would likely have to obtain a retail licence
exemption to onsell the power to Young Henrys and using a lease avoids this
requirement.
Note: Pingala has not ruled out using PPA or other structures in the future
Explores crowdfunding as a possible • Under a co-operative structure, Pingala is considering being able to
mechanism in sourcing equity funds (subject to streamline the raising of equity using an approach similar to an equity
final legal advice) crowdfunding mechanism (see below and Funding Basics Guidebook)
140 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 141
SECTION D SECTION D
D CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT
D IV
142 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 143
SECTION D SECTION D
D CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT
D IV
Types and Sources of Funding CONCEPT PREFEASIBILITY FEASIBILITY FINAL FUNDING Young Henrys Project
The types and sources of funding In-kind In-kind In-kind In-kind
used for the project through each of Donations Donations Donations Equity - Co-operative
the project development phases are Grants Grants Members
summarised in the table adjacent: investors
Total (including in-kind) base for the organisation. As a result, Equity Cooperative Members
templates - CE developers can
access financial templates that
$154,000 Pingala now claims to be one of the most
Grants
$40,000 strongly-supported community energy $18,500
have been developed by Pingala
which will reduce duplication
organisations in Australia with its large
membership and newsletter readership, Total (cash)
of effort and costs for other CE
developers.
strong social media following and a large
group of volunteers.
$38,500
Total (cash) The second grant, was for $44,000 Total (including in-kind)
$74,000 and was used for the development of
legal and financial templates as well as
$58,500
providing funds for the first project which
will also benefit future projects.
* In-kind contributions valued at $50 per hour
144 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 145
SECTION D SECTION D
D CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT
D IV
146 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 147
SECTION D SECTION D
D CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT
D IV
Attending markets and fairs helps build the base of Pingala supporters.
148 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 149
SECTION D SECTION D
D CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT
D IV
• Not restricting the number of members (although no-one member can hold more
Project Element 2 Project Scale than 20% of the shares)
Required Status when Seeking Project scale determined and set • Supporting raising capital for new projects by public invitation
Final Funding
• Keeping administrative costs to a reasonable level.
Pingala’s Approach The project size is limited to around 29kW based on the available roof area at the
site and the desire to keep <30kW for ease of network connection approvals Pingala is maintaining the association structure to allow it to also undertake some
other not-for-profit activities
At this size the project revenues were not enormous but sufficient to support a low
Lessons Learnt and Structure is important and needs to be aligned with the objectives of the community
operating cost model.
Challenges Faced organisation
Lessons Learnt and The economics for sites under 30kW are tight as there is a high fixed cost recovered
Challenges Faced against a smaller revenue outcome Factor in the cost and operating requirements for competing business structures
when considering options.
150 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 151
SECTION D SECTION D
D CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT
D IV
Project Element 9 Network Connection Pingala’s Approach The project has developed the project on the basis of in-kind support, donations
and grants. Grant funding covered 50% of the construction cost which means that
Required Status when Seeking Firm cost quotations for any CAPEX and OPEX assumptions associated with the Pingala Co-operative will only need to fund 50% of the project. Additional grant
Final Funding network connections. A network connection agreement may also be required funding received also paid for a share of the final funding stage
Pingala’s Approach Network connection is outsourced to the solar contractor. For systems less than
Additional grant funding received also paid for a share of the final funding stage
30kW there are usually no unexpected costs or delays to network approvals in
Pingala’s installation area Lessons Learnt and Challenges If you can get grant funding it may help reduce the risks for the investors in the first
Faced project.
Lessons Learnt and Outsource the network component if the skills do not exist in the CE group
Challenges Faced
152 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 153
SECTION D SECTION D
D CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT CASE STUDY 2 – PINGALA: YOUNG HENRYS PROJECT
D IV
154 FRONTIER IMPACT GROUP BEHIND THE METER PV SOLAR FUNDING GUIDEBOOK 155
frontierimpact.com.au