ID Task Task Name Duration Start Finish Oct 3, '21 Nov 7, '21 Dec 12, '21 Jan 16,

rt Finish Oct 3, '21 Nov 7, '21 Dec 12, '21 Jan 16, '22 Feb 20, '22
Mode T W T F S S M T W T F
1 Tender Pengurusan Fasiliti Bagi Istana Melawati untuk 44 days Fri 10/29/21 Thu
Tahun 2022 Sehingga 2026 12/30/21
2 Perancangan 13 days Fri 10/29/21 Wed 11/17/21
3 terima surat dari TKSUK JPM 1 day Fri 10/29/21 Fri 10/29/21
4 Pemakluman kepada BKK 1 1 day Mon 11/1/21Mon 11/1/21
5 Perbincangan awalan bersama BKUB 1 day Tue 11/2/21 Tue 11/2/21
6 Penyediaan Jadual Perancangan oleh BBK 1 bersama 1 day Wed Wed
JPM & Istana 11/3/21 11/3/21
7 Menguruskan Bengkel Permurnian Skop Kerja 2 days Fri 11/5/21 Mon 11/8/21
8 Surat Niat Kepada Kontraktor 1 day Mon 11/8/21Mon 11/8/21
9 Mesyuarat Koordinasi Bil 1 1 day Tue 11/9/21 Tue 11/9/21
10 Penyediaan Skop Kerja dan SLA 6 days Wed 11/10/21Wed 11/17/21
11 Penyediaan Dokumen Kontrak 3 days Thu 11/18/21Mon 11/22/21
12 Bengkel Permurnian Skop dan Muktamadkan Skop 2 days Thu 11/18/21Fri 11/19/21
13 Penyediaan Anggaran Jabatan 1 day Mon 11/22/21Mon 11/22/21
14 Rekabentuk Dan Perolehan 58 days Tue 11/23/21Thu 2/10/22
15 Penyediaan Dokumen Tender 9 days Tue 11/23/21Fri 12/3/21
16 Permohonan Pengesahan Peruntukan 1 day Mon 12/6/21Mon 12/6/21
17 Perlantikan Ahli Panel Rundingan Harga 5 days Tue 12/7/21 Mon 12/13/21
18 Semakan Dokumen Tender oleh BKUB 5 days Tue 12/14/21Mon 12/20/21
19 Pindaan Dokumen Tender dan Cetak Dokumen 5 days Tue 12/21/21Mon 12/27/21
20 Jual Dokumen Tender 7 days Tue 12/28/21Wed 1/5/22
21 Tutup Tender 1 day Thu 1/6/22 Thu 1/6/22
22 Penilaian Tender 3 days Fri 1/7/22 Tue 1/11/22
23 Pra Rundingan Harga 1 day Wed 1/12/22Wed 1/12/22
24 Rundingan Harga Bersama Kontraktor 1 day Thu 1/13/22 Thu 1/13/22
25 Keputusan Lembaga Tender 5 days Fri 1/14/22 Thu 1/20/22
26 Pemakluman kepada MOF keputusan Rundingan Harga5 days Fri 1/21/22 Thu 1/27/22
27 Penyediaan SST oleh BKUB 2 days Fri 1/28/22 Mon 1/31/22
28 Milik Tapak 8 days Tue 2/1/22 Thu 2/10/22
32 Tamat 1 day Fri 2/11/22 Fri 2/11/22

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
Project: Istana Melawati CPM
Date: Fri 11/5/21 Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only