Prepared by IPC Cirebon 21/09/17

A glimpses of Port of Cirebon


Operation Area of Pelindo I,II,III and IV

We are ‘HERE’

3 | Energizing Trade. Energizing Indonesia


Port of Cirebon – Facility and Equipment

Dermaga Samadikun : 67 M / -4 MLWs LAPANGAN


2
Lp. Muarajati : 4.480 M
Dermaga Perniagaan I - IV : 44 M / -3 MLWs 2
Lp. Pelita : 9.780 M
Dermaga S. Sumantri I - V : 68 M / -3,5 MLWs Lp. Suryat Sumantri : 8.048 M
2

2
Dermaga Muara Jati I - III : 603 M / -5,5 sd -6 MLWs Lp. Linggarjati : 5.600 M
GUDANG
Dermaga Linggar Jati I -II : 171 M / -4,5 MLWs 2
Gudang Muarajati : 4.000 M
Dermaga Pelita I - III : 98 M / -5,5 MLWs 2
Gudang 101 : 1.806 M
Kade Khusus Pelra : 150 M / -2 MLWs : 1.500 M
2
Gudang 102
2
Total Panjang Dermaga : 1,201 M Gudang 103 : 306 M
2
Gudang 104 : 1.050 M
2
Gudang Terbuka Pelra : 1.200 M

Mobil Crane IHI 25 Ton 1 Wheel Loader Kap.5,1 M3 HL 780-


1
7A Merk Hyundai
Jembatan Timbang 1 Wheel Loader Kap.5 Ton 1

Excavator Komatsu 2 Wheel Loader kap 3 Ton 1

Excavator Hyundai 2 Rampdoor 3

Excavator Caterpilar 2 Forklift Kap.5 Ton 1

Dump Truck 4 4 Mobil PMK Kapasitas 5.000 m3 1


4 | Energizing Trade. Energizing Indonesia
Port of Cirebon - Ships Traffic
Dominate by Tug and Barge

Gross Tonnage Unit


2.500.000 1.800

1.600
2.000.000 1.400

1.200
1.500.000
1.000

800
1.000.000
600

500.000 400

200

- -
s/d Juli s/d Juli
2013 2014 2015 2016 2013 2014 2015 2016
2017 2017
GT 1.974.9 2.139.0 1.987.1 1.048.8 1.296.7 UNIT 1.407 1.536 1.329 788 934

5 | Energizing Trade. Energizing Indonesia


Port of Cirebon – Cargo Throughput

Dominate by Dry Bulk Commodity


(Tonnage)
5.000.000
4,513,941
4.500.000 4,028,447 4,200,471
4.000.000
3.500.000
3.000.000 2,359,869 2,271,442
2.500.000
2.000.000
1.500.000
1.000.000
500.000
-
2013 2014 2015 2016 s/d Juli 2017
General Cargo - - 46.606 28.884 893
Curah Cair 331.169 322.516 313.100 288.568 200.059
Bag Cargo 264.029 144.709 115.021 108.955 61.775
Curah Kering 3.433.249 4.046.716 3.725.744 1.933.462 2.008.715

6 | Energizing Trade. Energizing Indonesia


Potential Market Opportunities
Due to limited draft, the cargo is currently transit in some neighbouring ports.
Strategic Market Opportunities

3 Biggest Animal Feed Factory in Cirebon have average production 1.000.000 tonnes
1 annually, currently it is unloaded at Ciwandan dan Cigadeng Port in Banten

2 Fertilizer company around Cirebon have average production up to 50.000 tonnes annually

More than 20 textile company and other industries moved from Bandung, Jakata, and
3 Tangerang to Cirebon-Indramayu-Majalengka-Kuningan (CIAYUMAJAKUNING)

4 Potential volume form salt, sugar, and cattle industry

5 Cargo handling of PLTU 2 & 3 project

6 Liquid bulk facility improvement potential

7 Passenger Vessel & Roro services

8 Domestik and international container services

8 | Energizing Trade. Energizing Indonesia


WEST JAVA SPATIAL PLAN
West Jawa Saptial Structure Plan

PKN
METROPOLITAN
BODEBEK
Kawasan
Industri

PKN
METRO
PKN CIREBON
PKW METRO
PELABUHAN BANDUNG
RATU

PKWp
RANCA
BUAYA PKNp
PANGANDA
RAN

Sumber : BAPPEDA JABAR


PKN, PKW : National/Regional Center of Activity
Cirebon Spatial Plan Pengembangan Kawasan Strategis
Kabupaten Cirebon
Economic Growth
Strategic Region (KSK) -
(Agro Region
Arjawinangun)
Java
Social and Sea
Culture
Strategic
Region
Economic (Gunung
Jati Region)
Growth
Strategic Region
(KSK) -
(Plumbon
Region)

Economic Growth
Strategic Region
(agro Ciledug
KABUPATEN KUNINGAN
Cirebon District Strategic Region) 10

Region Plan
(KSK Cirebon) Sumber : BAPPEDA Kabupaten Cirebon
Port of Cirebon
DLKR/DLKP Pelabuhan Cirebon

According to “Keputusan Bersama Menteri Dalam


Negeri dan Menteri Perhubungan No. 58 tahun 1988
dan Nomor : KP 25/AL 108/PHB-88 tentang Batas-
batas DLKR/DLKP Pelabuhan Cirebon”, it has been
stated that Cirebon Port have 51 ha DLKR dan 25 ha
DLKP, also 8.410,91 ha of Port Basin Area.

Port of Cirebon is currently can handle only for the


vessel up to -6.5m. For the vessel that have more
than -6.5mlws has to be discharge at the outer area
that safe and recommended by Harbour Master.
The future plan, Port of Cirebon expected big
vessels that have draft up to -10mlws to come and
discharge in the port.

11
Port of Cirebon Development Plan
Fairway Developmen Plan
before -5.5mlws to be -12mlws
DATA SURVEI ARUS DAN
GELOMBANG

Arah Arus Laut

Pelabuhan
Cirebon

Gugusan
karang

CIREBON Palung

Alur Rencana – 12 MLws , jarak ±


36 KM / 18 Mil

Alur Eksisting
BREBES

13 | Energizing Trade. Energizing Indonesia


Project Detail

Port of Cirebon Pelabuhan


Pengembangan Development
Cirebon :

The development of Deep Sea Port that is integrated with Industrial estate to
accommodate the cargo throughput growth, industrial estate development, and potential
hinterland of Cirebon Port.

Informasi Proyek :
Project Information
IRR : 11,2 %
Capital Expenditure: Rp 8,9 Triliun; Phase One: Rp 3,8 Triliun

14 | Energizing Trade. Energizing Indonesia


Master Plan of Port of Cirebon

15 | Energizing Trade. Energizing Indonesia


Port Development Plan
Phase I: 50 Ha

16 | Energizing Trade. Energizing Indonesia


Port Development Plan
Phase I (2018 – 2021)
Reclamation Area : 50 Ha
Berth Area : 19.200 M2

Phase II (2022 – 2032)


Reclamation Area : 153 Ha
Berth Area : 31.200 M2

17 | Energizing Trade. Energizing Indonesia


Thank you