Engineering Procedure

SAEP-385 25 October 2017


Preservation of Project Materials and Equipment
Document Responsibility: Project Quality Standards Committee

Contents
1 Scope ........................................................................ 2
2 Applicable Documents .............................................. 2
3 Definitions and Acronyms ......................................... 4
4 Instructions................................................................ 7
5 Responsibilities ....................................................... 10
Revision Summary......................................................... 14

Appendix A - Summary of Preservation Requirements .. 15

Previous Issue: New Next Planned Update: 25 October 2020


Page 1 of 66
Contact: Megren, Abdulaziz A. (megraa0a) on phone +966-13-8804510

©Saudi Aramco 2017. All rights reserved.


Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

1 Scope

1.1 This procedure, in alignment with project specifications, Mandatory Saudi


Aramco Engineering Requirements and manufacturers’ instructions, establishes
minimum requirements for planning, monitoring, and tracking the preservation
of project materials and equipment; through procurement, construction,
pre-commissioning, commissioning, and startup.

1.2 Minimum requirements specified in Appendix A are limited to short-term


(pre-MCC) preservation of project equipment and materials. For post-MCC
jobsite time period exceeding six months, proponent organization shall prepare
detail preservation procedure for approval to the Group Leader, Corrosion
Engineering Group (CEG), Materials Engineering Division (MED), Consulting
Services Department (CSD).

2 Applicable Documents

The requirements contained in the following documents shall apply to the extent
specified in this procedure:

2.1 Saudi Aramco References

Saudi Aramco Engineering Procedures


SAEP-12 Project Execution Plan
SAEP-14 Project Proposal
SAEP-20 Equipment Inspection Schedule
SAEP-35 Valves Handling, Hauling, Receipt Tests, and
Storage
SAEP-301 Instructions for Establishing and Maintaining
Mandatory Saudi Aramco Engineering
Requirements
SAEP-302 Instructions for Obtaining a Waiver of a Mandatory
Saudi Aramco Engineering Requirement

Saudi Aramco Engineering Standards


SAES-A-007 Hydrostatic Testing Fluids and Lay-Up Requirements
SAES-H-001 Coating Selection and Application Requirements for
Industrial Plants and Equipment
SAES-H-003 Protective Coatings for Industrial Concrete Structures

Page 2 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

SAES-H-101V Approved Saudi Aramco Data Sheets - Paints and


Coatings
SAES-H-200 Storage, Handling, and Installation of Externally
Coated Pipe
SAES-L-133 Corrosion Protection Requirements for Pipelines,
Piping, and Process Equipment
SAES-L-350 Construction of Plant Piping
SAES-L-420 Scraper Trap Station and Appurtenances
SAES-Q-001 Criteria for Design and Construction of Concrete
Structures
SAES-Q-010 Cement Based, Non-shrink Grout for Structural and
Equipment Grouting
SAES-Q-011 Epoxy Grout for Machinery Support
SAES-Q-012 Criteria for Design and Construction of Precast and
Prestressed Concrete Structures
SAES-S-070 Installation of Utility Piping Systems

Saudi Aramco Materials System Specifications


01-SAMSS-010 Fabricated Steel Piping
01-SAMSS-034 RTR (Fiberglass) Pressure Pipe and Fittings
01-SAMSS-043 Carbon Steel Pipes for On-Plot Piping
01-SAMSS-046 Stainless Steel Pipe
01-SAMSS-051 High Density Polyethylene (HDPE) Pipe and
Fittings
02-SAMSS-005 Butt Welding Pipe Fittings
02-SAMSS-011 Forged Steel and Alloy Flanges
04-SAMSS-035 General Requirements for Valves
09-SAMSS-060 Packaging Requirements for Coatings
09-SAMSS-089 Shop-Applied External Fusion Bonded Epoxy
Coating for Steel Line Pipes
09-SAMSS-106 Epoxy Coating of Steel Reinforcing Bars
09-SAMSS-113 The Requirements of External Liquid Coatings for
Buried Pipelines and Piping (APCS-113A)
12-SAMSS-007 Fabrication of Structural and Miscellaneous Steel

Page 3 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Saudi Aramco General Instruction


GI-0002.710 Mechanical Completion and Performance
Acceptance of Facilities

2.2 Other Documents

Saudi Aramco Standard Contracts


Schedule G Materials, Tools, and Equipment
Schedule Q Project Quality Requirements

Saudi Aramco Typical Test Report Forms


SATR-A-0001 Preservation Tracking System

3 Definitions and Acronyms

3.1 Definitions

Commissioning: Placement of a facility in service, after the scope of work has


been pre-commissioned and Mechanical Completion has been achieved. For a
process facility, commissioning includes the testing of a plant's system with test
medium in the line. After commissioning, the plant is ready for startup, during
which feedstock and other normal operating liquids and gases are introduced in
the lines.

Commissioning and Startup Plan (CSP): Under SAEP-12 and SAEP-14;


defines the objectives, plans, requirements, activities and procedures for startup.
Part of the Operational Readiness Plan (ORP).

Inspection and Test Plan (ITP): A detailed listing of design, procurement,


manufacturing, fabrication, construction and pre-commissioning process steps and
work activities that establishes the items to be reviewed, inspected, examined,
monitored and tested for quality. ITP’s include the following features:
a. Cites the applicable engineering and quality requirements for documents,
processes, and work activities (acceptance criteria).
b. Lists the applicable quality control procedures and data records for a
particular material, equipment, or type of work.
c. Defines and assigns the roles and responsibilities of all involved parties.
d. Assigns mandatory hold points – an inspection or testing point beyond
which a process or work activity shall not proceed without approval of the
designated organization.

Page 4 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

e. Assigns mandatory review points – the point where a process or work


activity shall not proceed without review and approval of applicable records,
documents and/or personnel qualifications by the designated organization.
f. Assigns witness points – an inspection or testing point for a process or work
activity that may proceed after timely advance notice to the designated
organization.

Layup: The temporary preservation of equipment, piping or pipelines after a


hydrostatic pressure test, to prevent corrosion. Includes wet, dry, inert gas and
ambient lay-up processes in accordance with SAES-A-007.

Materials Procurement Plan (MPP): Under SAEP-12 and SAEP-14;


describes the strategies, planning and responsibilities for material and equipment
requirements, sourcing options and logistics (movement and traffic).
Addresses the use of corporate agreements, vendor selection criteria,
preservation and quality concerns, inspection, packing and marking, shipping,
clearance, receiving, storing, issuing, staging and returns.

Mechanical Completion (MC; Certified, MCC): A facility or system that has


been installed, tested (pre-commissioned), verified and certified available for
commissioning and startup under GI-0002.710.

Performance Acceptance (PA; Certified, PAC): A facility or system that has


successfully demonstrated operation and performance at the design conditions
established by the approved Project Scope. PAC signifies Proponent acceptance
of facility commissioning and startup.

Pre-Commissioning (PC): Testing of system components for continuity,


operability and in the case of process plants, their ability to withstand operating
pressures prior to the introduction of feedstock or other final products into the
facility.

Preservation (short-term, pre-MCC): The systematic use of materials,


methods, tools and QA/QC activities to prevent damage to project materials and
equipment during the project life-cycle (manufacturing, handling, shipping,
delivery, storage, fabrication, assembly, installation, inspection, testing, lay-up
and reinstatement).

Preservation (long-term, post-MCC, > 6 months, mothballing): The systematic


use of materials, methods, tools and QA/QC activities to prevent damage to facility
systems and assets during long delays in project MC, commissioning or startup; or
long periods of shutdown and turnaround after startup.

Page 5 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Project Manager (PM): A division head representative from the Construction


Agency, who participates in the IPT during FEL2, leads the IPT during FEL3
and the project’s execution phases.

Project Quality Manager (PQM): For Type A and B projects, a division or


section head representative from the Inspection Agency, who plans and
coordinates all inspection requirements with the Project Manager throughout all
project phases. For Type C and C1 projects, the Project Quality Leader (PQL) is
a unit head representative from the Inspection Agency.

Proponent: The Saudi Aramco organization that commissions, owns, operates,


and maintains the completed facility after MCC. Responsible for chairing the MC
Acceptance Committee, approval of the MCC, facility commissioning and startup.

Quality Assurance (QA): The planned and systematic resources and activities
implemented within the quality management system to provide adequate
confidence that QC plans, resources and procedures will fulfill the requirements
for quality.

Quality Control (QC): The operational techniques, resources and activities


that are used to fulfill requirements for quality for a scope of work.

Quality Control Procedure (QCP): A documented process detailing the


resources and steps necessary to complete, inspect and test a specific work
activity.

Quality System: Organizational structure, procedures, processes, and resources


needed to implement quality management.

Reinstatement: The permanent restoration and preservation of equipment, piping


or pipelines after a hydrostatic pressure test and layup, and before mechanical
completion and commissioning.

Saudi Aramco Construction Agency (CA): Normally, a PM department for


Types A, B, & C projects; a Proponent department for Type C1 projects.
Responsible for planning, completing and delivering a quality facility as defined
in the project scope of work.

Saudi Aramco Inspection Agency (IA): Normally, Inspection Department for


Types A, B, & C projects; a Proponent department for Type C1 projects.
Plans and coordinates project quality with CA; inspects and certifies the
mechanical completion of safe facilities.

Saudi Aramco Inspection Representative (SAIR): An ID Vendor Inspection


Division Representative who reports to the PQM/PQL or CA PM, as determined

Page 6 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

by the SA PQP. Monitors vendor inspection activities to ensure quality of


procured inspectable materials and equipment.

Senior Operations Representative (SOR): A Proponent business line


representative involved in all phases of the project, to ensure Proponent short-term
and long-term objectives are incorporated and satisfied. For MCC, a Proponent
division head representative who chairs and appoints the facility’s Acceptance
Committee.

Startup: Following commissioning, the introduction of feedstock, liquids, or


gases into the facility to achieve normal operating conditions.

3.2 Acronyms
EC Energization Certificate
EIS Equipment Inspection Schedule
FEL Front-End Loading
ID Inspection Department
IPT Integrated Project Team
MSAER Mandatory Saudi Aramco Engineering Requirement
PC&MCP Pre-commissioning and Mechanical Completion Plan
PFR Preservation Failure Rate
PQP Contractor Project Quality Plan
RFI Request for Inspection
RIO Saudi Aramco Regional Inspection Office
SAIC Saudi Aramco Typical Inspection Checklist
SAIR Saudi Aramco Inspection Representative
SA PQP Saudi Aramco (Master) Project Quality Plan
SATIP Saudi Aramco Typical Inspection and Test Plan
SATR Saudi Aramco Typical Test Report

4 Instructions

4.1 Deviations from Requirements

4.1.1 SAEP-385 is a Mandatory Saudi Aramco Engineering Requirement


under SAEP-301. Any conflicts between this document and other

Page 7 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

applicable Mandatory Saudi Aramco Engineering Requirements


(MSAERs) shall be addressed to the EK&RD Coordinator.

4.1.2 Any deviation from the requirements herein shall follow internal
company procedure SAEP-302.

4.2 Preservation Planning on Projects

4.2.1 All project quality planning documents shall identify and adopt project-
specific manufacturer’s preservation plans, procedures and instructions
as minimum requirements. If Saudi Aramco requirements exceed
manufacturer’s preservation requirements, then Saudi Aramco
requirements shall also be specified and adopted.

4.2.2 The project Materials Procurement Plan (MPP) shall address


preservation strategy and planning for all classes and sources of project
materials and equipment.

The MPP should address preservation quality concerns such as


inspection, packing, marking, handling, lifting, shipping, clearance,
receiving, storing, testing, issuing, staging, and the return of excess
project material and equipment.

4.2.3 The Saudi Aramco Project Quality Plan (SA PQP) shall establish general
quality policy, objectives, and levels of QA and QC needed for
preservation and condition assessment of all project materials and
equipment.
a) The SA PQP shall designate roles and responsibilities between CA,
IA, and Contractor for effective control and assurance of materials
and equipment preservation on projects.
b) The SA PQP shall address general preservation requirements and
quality planning in procurement phase for classes of equipment and
materials, and in construction and pre-commissioning phases as well.

4.2.4 The Contractor’s Project Quality Plan (PQP) shall establish specific
quality objectives, measurements, reports and detailed QA and QC
requirements needed for preservation and condition assessment of all
project materials and equipment.
a) The PQP shall specify and schedule preservation processes,
procedures, inspection and testing in procurement, construction and
pre-commissioning phases for all project equipment and materials in
accordance with Appendix A and project-specific manufacturer
instructions.

Page 8 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

b) PQP requirements and activities during procurement phase for


Contractor-supplied materials and equipment shall address
preservation in manufacturing (factory inspection, testing,
packaging and marking) ex-works storage (monitoring, handling,
lifting, shipping, clearance and delivery) and ex-works pre-delivery
(fabrication, assembly, inspection and testing).
c) PQP requirements and activities during construction and
pre-commissioning phase shall address preservation in jobsite
receiving, storage, fabrication, assembly, handling, lifting, staging,
installation, inspection, testing, layup, reinstatement, and return of
excess equipment and materials.
d) The PQP shall outline requirements and procedures for data
collection, measurement, and reporting on preservation of
equipment and materials in the Contractor’s monthly Quality
Management Report per contract Schedule Q, and the Monthly
Materials Procurement Status Report per Schedule G.

4.2.5 The Commissioning and Startup Plan (CSP) and Equipment Inspection
Schedule (EIS) shall include system and equipment preservation and
mothballing requirements in planning and procedures as contingency for
startup delays.

A system of partial MCCs and PACs shall be planned and established


under PC&MCP and CSP; where project equipment, process systems
and facilities can be timely pre-commissioned, handed-over to
Proponent, commissioned and started-up without delay; to ensure
preservation of materials and equipment.

4.3 Preservation Implementation on Projects

4.3.1 Short-term preservation activities, as a minimum, for all project phases,


shall be in accordance with Appendix A, MSAER, and manufacturer’s
instructions.

4.3.2 In the event of delayed startup where short-term preservation


requirements are insufficient, long-term procedures approved by Group
Leader, Corrosion Engineering Group (CEG), Materials Engineering
Division (MED), Consulting Services Department (CSD) shall be used to
preserve or mothball equipment, systems and facilities, in accordance
with manufacturer’s instructions, SAEP-20.

4.4 Preservation Tracking, Measurement and Reporting on Projects

4.4.1 All preservation activities in procurement phase, from manufacturing

Page 9 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

through jobsite delivery must be measured and reported on a monthly


basis in Materials Procurement Status Reports.

4.4.2 All preservation activities in construction and pre-commissioning phases


after delivery to jobsite, through receiving, storage, installation, and
pre-commissioning must be measured and reported utilizing SATR-A-
0001, Preservation Tracking System.

4.4.3 SATR-A-0001 weekly reports shall be discussed, actioned and minuted


in routine project meetings.

4.4.4 Weekly SATR-A-0001 results shall be summarized, described and


reported in monthly Quality Management Reports.

4.4.5 Non-conformities related to project preservation shall be registered and


tracked in SATR-A-0001 on a weekly basis including; Saudi Aramco
Worksheets, Saudi Aramco NCRs, EPM/QMIS logbook entries and
Contractor internal NCRs.

4.4.6 The project maximum Preservation Failure Rate (PFR, as calculated by


SATR-A-0001 on a cumulative basis) shall not exceed the target
specified in SA PQP quality objectives.

4.4.7 If the cumulative PFR exceeds the specified target, a Company NCR is
issued and a Focus Assessment on preservation shall be conducted.

5 Responsibilities

5.1 Saudi Aramco Construction Agency, Project Manager

5.1.1 Review and issue or approve MPP, SA PQP, PQP, CSP, and EIS with
preservation requirements as specified in Section 4 of this procedure.

5.1.2 Include MPP, SA PQP, and CSP preservation requirements in project


contracts issued for bids.

5.1.3 Verify Contractor purchase requisitions and purchase orders are


reviewed, approved, and issued with standard preservation requirements.

5.1.4 Ensure Contractor implements, monitors and reports quality of


preservation.

5.1.5 Review and address planning and implementation of preservation


requirements in routine project meetings.

5.1.6 With SOR, plan and provide project support to the Proponent on

Page 10 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

preservation of equipment and systems during facility commissioning


and startup.

5.2 Saudi Aramco Inspection Agency, PQM or PQL

5.2.1 Review MPP, SA PQP and PQP for preservation requirements and
approve/reject/comment as applicable.

5.2.2 Assess/Conduct quality assessment to ensure Contractor implements


preservation requirements with inspection, testing, measurement, and
reporting.

5.2.3 Review, verify and approve all quality metric and reports on preservation.

5.2.4 Ensure MPP and SA PQP preservation requirements are used to draft
and issue a project-specific contract Schedule Q, Attachment VI.

5.2.5 Conduct general Preservation Awareness meetings as part of project


mobilization, construction phase kickoff, and pre-commissioning.

5.2.6 Review and address planning and implementation of preservation


requirements in routine project meetings.

5.3 Saudi Aramco Inspection Representative, SAIR

5.3.1 Review MPP, SA PQP and PQP for preservation requirements and
approve/reject/comment as applicable.

5.3.2 Review and approve/reject Contractor purchase requisitions and


purchase orders for preservation requirements.

5.3.3 Coordinate with RIOs as needed to provide Saudi Aramco inspection and
assessment of preservation in procurement phase.

5.3.4 Assess and ensure Contractor implements preservation requirements


with inspection, testing, measurement, and reporting jointly with PQM.

5.3.5 Conduct a general Preservation Awareness meeting as part of


procurement phase kickoff.

5.3.6 Review and address planning and implementation of project preservation


requirements in pre-inspection meetings, “in-progress” meetings, and
final inspections.

5.4 Contractor, Quality Managers

5.4.1 Plan, specify, implement, measure, and report effective preservation of

Page 11 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

all project materials and equipment through company approved PQP,


ITPs, QCPs, and work procedures in all phases.

5.4.2 Plan for and avail all preservation required tools, equipment, materials,
personnel, adequate warehouse size, and storing conditions prior to
material receiving at site.

5.4.3 Avail program to preserve materials and minimize corrosion during the
delivery, storage, construction, and commissioning activities shall be
developed in accordance with paragraph 8.7 of SAES-L-133.

5.4.4 Identify, flag, and list all inspection schedules, activities, QCP’s,
checklist forms, and test report forms planned for preservation of all
project materials and equipment.

5.4.5 Review and address preservation requirements in pre-inspection


meetings, “in-progress” meetings and final inspections with vendors and
manufacturers as part of procurement phase.

5.4.6 Measure and report the quality of preservation activities in procurement


phase, from manufacturing through jobsite delivery on a monthly basis
in Quality Management Reports.

5.4.7 Ensure the integrity and availability of procurement phase preservation


data and requirements for materials and equipment on jobsite receiving.

5.4.8 Timely assess, survey, inspect and test project-procured materials and
equipment for compliance with preservation requirements in accordance
with the jobsite PQP.

5.4.9 Maintain, provide, and make available quality records and other
evidence as needed to demonstrate preservation requirements have been
successfully performed by vendors, manufacturers, and Contractor for
the full scope of work.

5.4.10 Ensure all personnel responsible for special preservation are fully
qualified to do so and are supplied with predetermined work and
inspection instructions.

5.4.11 Collect, summarize, analyze, measure and report data, results, findings,
non-conformances and action items from preservation activities in all
project phases, in accordance with the project contract and approved
PQP.

5.4.12 Track, measure and report on a weekly basis, quality of equipment and
piping preservation; after delivery to jobsite, through receiving, storage,

Page 12 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

installation, pre-commissioning, layup, and reinstatement utilizing


SATR-A-0001, Preservation Tracking System.

5.4.13 Submit SATR-A-0001 data and reporting to Saudi Aramco on a weekly


basis for review and approval. All data shall be collected and maintained
by Contractor, as current and available for Saudi Aramco review.

5.4.14 On a weekly basis, monitor, report and prevent a backlog of incomplete,


pastdue jobsite equipment/piping preservation, hydrostatic pressure test,
layup, and reinstatement activities.

5.4.15 Conduct quality audits and management review on project’s compliance


with preservation requirements.

5.4.16 When directed by the Construction Agency, provide support to the


Proponent on preservation of equipment and systems during facility
commissioning and startup.

5.4.17 Address equipment- and material-specific preservation requirements in


jobsite meetings for deliveries, handling, storage, receiving inspections
and work front kickoffs.

5.4.18 Report and address planning and implementation of preservation


requirements in routine project meetings with Saudi Aramco.

5.5 Saudi Aramco Proponent, Senior Operations Representative

5.5.1 With PM, plan and specify procedures for preservation and mothballing
of facility systems and equipment in the CSP and EIS.

5.5.2 With PM and the Acceptance Committee, plan and implement a system
of partial ECs and MCCs where project equipment and facilities can be
timely pre-commissioned, handed-over, commissioned, and started-up
without delay.

5.5.3 Plan and mobilize sufficient Proponent resources to participate in


construction and pre-commissioning preservation activities as specified
in GI-0002.710, Supplement 5.

5.5.4 Review quality records and verify project’s compliance with


preservation requirements prior to final walk-throughs and certification
of energization and mechanical completion.

5.5.5 Direct the implementation of preservation and mothballing of facility


systems and equipment during commissioning and startup.

Page 13 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

5.5.6 Monitor and report the quality of preservation and mothballing of facility
systems and equipment during commissioning and startup.

5.6 Saudi Aramco Inspection Department, Inspection Engineering Unit

Review and comment on initial EIS preservation and mothballing requirements


in accordance with the CSP and SAEP-20.

5.7 Corrosion Engineering Group (CEG), Materials Engineering Division (MED),


Consulting Services Department (CSD)

5.7.1 CEG shall approve proponent furnished procedure for preservation of


project material and equipment in the event that time between facility
start-up and facility handover exceeds six months.

5.7.2 CEG shall provide technical support on the development and


implementation of preservation procedures.

5.7.3 CEG shall only review and approve lay-up methods not specifically
discussed in SAES-A-007 prior to the hydrostatic testing.

Revision Summary
25 October 2017 New Saudi Aramco Engineering Procedure that establishes minimum requirements for the
preservation of project materials and equipment, in alignment with project specifications and
manufacturer’s instructions. Also provides coverage through the project lifecycle procurement,
construction, pre-commissioning, commissioning, and startup.

Page 14 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Appendix A
Summary of Preservation Requirements

CIVIL
Table A-1001 Documentation Requirements
a) Preservation Procedure shall be established prior to material receiving during the construction phase
b) Contractor shall establish a tracking system to register the preservation results
General
1) All manufactured materials shall be delivered in the original unopened packages and stored as per manufacturer's
recommendations
2) At least once every 2 months, the material shall be visually inspected to check its conditions are still in compliance
with the engineering requirements
CIVIL
3) The date FBE coated reinforcing steel goes outdoors without protective covering shall be recorded on the
CONCRETE identification tags on the bundled steel. In addition, FBE bars shall be protected off against corrosion and damage of
STRUCTURES coat
4) Coating materials used at a construction site must be covered with appropriate canvas, tarpaulins or equivalent for a
temporary storage period not to exceed 14 days
5) The coatings materials shall be stored in well ventilated buildings at storage temperatures as recommended in the
Manufacturer's data sheet
6) Water curing shall be continuous until the compressive strength has reached 70% of the specified strength, but not
less than what is specified in Table 1 of SAES-Q-001

Standards Quality SATIP


Material/Equipment Type Size Specification Notes
Requirements Checklist
SAES-Q-001 SATIP-Q-001-02
Cast-in Place ALL
Schedule Q SAIC-Q-1015
Concrete SAES-Q-012 During lifting, only
SATIP-Q-001-04
Pre-Cast ALL SAES-Q-001 use the identified
SAIC-Q-1028
Schedule Q lifting points
Touch up scratched
bars immediately
09-SAMSS-106
with using proper
Epoxy Coated Steel SAES-Q-001
ALL ALL SATIP-Q-001-02 procedure, avoid
Bars SAIC-Q-1008
walking on the bars,
Schedule Q
bend only with the
proper tools
09-SAMSS-060
SAES-H-003
Manufacturer's SAES-H-001
Concrete Coating ALL ALL SATIP-H-003
Specification SAES-H-101V
SAIC-H-1002
Schedule Q
SAIC-Q-1047
Cement Based Non- Manufacturer's
ALL ALL SAES-Q-010 SATIP-Q-010-01
Shrink Grouting Specification
Schedule Q
Epoxy Grout for Manufacturer's SAES-Q-011 SATIP-Q-011-01
ALL ALL
Machinery Support Specification Schedule Q SAIC-Q-1052

Page 15 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Table A-1002 Documentation Requirements


a) Preservation Procedure shall be established prior to material receiving during the construction phase.
b) Contractor shall establish a tracking system to register the preservation results.
General
STEEL 1) At least once every 2 months, the material shall be visually inspected to check its conditions are still in compliance
STRUCTURES with the engineering requirements.
2) All materials shall be stored, and handled in a manner that will prevent distortion, deterioration, or damage.
3) The structural elements shall be elevated above the ground surface.
4) The elements shall not be stored in a way that introduces unacceptable stresses and/or deflections.
Standards Quality
Material/Equipment Type Size Specification
Requirements SATIP/Checklist
Notes
12-SAMSS-007
12-SAMSS-008 Protect from soil
Structural Steel PIP STS05130 SATIP-M-001-01 contamination, moisture
ALL ALL
Shapes and Plates AISC SAIC-M-2005 and uncalculated/not
Schedule Q engineered stressing
Manufacturer's Specification
12-SAMSS-007,
Bolts, Nuts and SATIP-M-001-01
ALL ALL 12-SAMSS-005
Washers SAIC-M-2021
Schedule Q
12-SAMSS-007
Fabricated Steel SATIP-M-001-01
ALL ALL 12-SAMSS-008
Structures SAIC-M-2005
Schedule Q

Table A-1003 Documentation Requirements


a) Preservation Procedure shall be established prior to material receiving during the construction phase
b) Contractor shall establish a tracking system to register the preservation results
General
1) At least once every 2 months, the material shall be visually inspected to check its conditions are still in compliance
with the engineering requirements
BUILDINGS
2) All Where gypsum board is stored outside shall be off the ground, properly supported on a level platform and fully
protected from the weather or direct sunlight exposure, and adequate ventilation is provided to prevent
condensation
3) Masonry materials shall be stored so that at the time of use the materials are free from contaminations or damage
4) Manufacturer's recommendations for storage and preservation shall be always followed
Standards Quality
Material/Equipment Type Size Specification
Requirements SATIP/Checklist
Notes
Protect the material
SAES-M-100 from moisture and
Gypsum Wall Board ALL ALL SAIC-M-1035 SATIP-M-100-05 damage; this includes
Schedule Q metal runners, studs,
and accessories
SAES-M-100
Concrete Masonry SAIC-M-1007 Protect from soil
ALL ALL SATIP-M-100-01
Unit 2009 IBC contamination
Schedule Q
SAES-M-100
Roof Slab Manufacturer's No exposure to
ALL ALL SAIC-M-1012 SATIP-M-100-02
Waterproofing Specification sunlight
Schedule Q

Page 16 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

12-SAMSS-007
Protect from soil
Structural Steel 12-SAMSS-008
SATIP-M-100-03 contamination, moisture,
Materials and ALL ALL SAIC-M-1068
SATIP-M-100-04 and uncalculated/not
Components SAIC-M-1031
engineered stressing
Schedule Q
Protect the material
SAES-M-100,
Metal Doors and Manufacturer's from moisture,
ALL ALL SAES-M-009, SATIP-M-100-07
Windows Specification contamination with soil,
12-SAMSS-010
and damage
SAIC-M-1041
Ceramic Wall, Floor Manufacturer's
ALL ALL SAES-M-100 SATIP-M-100-06
Tiles and Accessories Specification
Schedule Q
SAIC-M-1052
Acoustical False Manufacturer's
ALL ALL SAES-M-100 SATIP-M-100-08
Ceiling System Specification
Schedule Q
SAIC-M-1062
Resilient Vinyl Floor Manufacturer's
ALL ALL SAES-M-100 SATIP-M-100-10
Tile and Base Specification
Schedule Q
SAIC-M-1075
Raised Equipment Manufacturer's
ALL ALL SAES-M-100 SATIP-M-100-11
Floor Materials Specification
Schedule Q,

MECHANICAL
Table A-2001 Documentation Requirements
a) Ensure manufacturer recommended preservation Procedure to be established prior to shipment, PID to verify
preservation compliance during shipment at time of materials/equipment arrived at site
b) Company preservation procedure and/or manufacturer recommended preservation Procedure shall be provided and
approved prior to material/equipment at all phases of preservation requirements (Procurement, packing, handling,
transportation and construction phases until startup) (Schedule Q)
c) Contractor shall establish and maintain proper tracking system to ensure registration of material/equipment
preservation compliance during all phase of preservation requirements to record results periodically, these activities
shall be periodically part of quality meeting discussion and evaluation (For construction phase it shall be weekly
discussion)
d) Lay-up procedure shall be approved by proponent before start of pressure testing (SAES-A-007)
e) For yard or shop fabricated piping systems that are constructed, hydrostatic tested, then shipped, PMT shall submit
the lay-up procedure, including water quality, to the Group Leader, CEG/MED/CSD, for approval (SAES-A-007).
f) For all materials not specifically covered in SAES-A-007 and for acceptance of other lay-up methods, obtain prior
PIPING
written approval from the Group Leader, CEG/MED/CSD.
General Requirements
Packing and Transportation
1) PID shall inspect and evaluate materials and equipment upon arrivals at site to ensure proper packing,
transportation and preservation measures were implemented as per requirements
2) Stainless Steel pipes bundles shall be wrapped in plastic, and packed in fully covered wooden boxes if the pipe size is
equal or less than 6-inch OD as per (01-SAMSS-046 paragraph 18.4)
3) Butt-welding pipe fittings shall be supplied with a protective coating for corrosion protection. The coating shall be
hard and dry, either a clear coating or a thin opaque coating. The maximum dry film thickness shall be 76 micron
(Except for clear coatings) (02-SAMSS-005, paragraph 10.4)
4) Butt-welding pipe fittings must be packaged in steel-banded wooden crates or secured to skids to prevent
mechanical damage (02-SAMSS-005, paragraph 10.5)

Page 17 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

5) Forged steel and alloy flanges shall be coated with a protective coating capable of protecting against corrosion
during transportation and at site, coating on the forged steel and alloy flanges butt ends shall be suitable for
welding, or acceptable alternate shall be employed (02-SAMSS-011, Section 13)
6) Fabricated steel piping (spools) welding ends shall be protected against damage during handling and shipment by
means of a securely fastened bevel protector as per (01-SAMSS-010 paragraph 10.4.3)
7) RTR (Fiberglass) Pressure Pipes, fittings, O-rings, gaskets, locking rings, and adhesives shall be packed in a manner to
withstand rough handling. The size and type of packing shall permit long-term storage
8) RTR (Fiberglass) Pressure Pipe and Fittings end protectors shall be provided and securely attached to open ends of
all pipes
9) Pickling and passivation for stainless steel piping shall be carried out in accordance with ASTM A380 or other
alternatives as agreed with project
10) Piping components shall be perfectly degreased and cleaned, free of contaminants such as greases, oil, water, dirt,
lubricants, filings weld splatter, rust, tape, paints, cleaning agent in accordance with eiga doc 13/12/e (oxygen pipe
line and piping system
11) Stainless pipes shall be segregated from carbon steel pipes during shipment, handling and storage, fabrication,
construction and testing activities
12) Piping components shall be preserved until they are assembled in site, by using means as:
a) Hermetically sealed wrapping, containing desiccant bag, for small items;
b) Firmly secured end-caps or plugs to seal all openings on
c) Non-hermetically packaged items.
Commentary Note:
At the bid phase, manufacturer shall submit the degreasing/cleaning, handling and packing procedures for
Contractor review and approval.

Construction Site Handling, Storage, and Preservation Inspection


PID shall conduct inspection and ensure all materials and equipment preservation are as per requirements.
13) Pipe shall not be stored directly on the ground, Pipe shall be placed on mounds or sleepers (SAES-L-350, Section 7)
14) End protectors on pipes, flanges, weld bevels, threads, and socket ends shall be firmly attached (SAES-L-350,
paragraph 7.4)
15) Bare and coated stainless steel pipe material shall be protected against exposure to seawater splash during
shipment and storage (SAES-L-350, paragraph 7.5)
16) The FBE and liquid epoxy coated pipes shall be protected from direct sunlight if to be stored in vendor’s yard, in the
field or project site for more than six (6) months in order to prevent UV degradation. This shall be done by covering
the stacked coated pipes with tarpaulins or similar protection. The tarpaulins shall be maintained in good condition
for as long as the pipes are exposed to direct sunlight (SAES-H-200, paragraph 5.2.2)
17) If externally coated pipes are stored outdoors without appropriate protection for a year or more, the coated pipes
shall be requalified. For FBE coated pipes, requalification shall be according to Table 3 of 09-SAMSS-089.
Liquid epoxy-coated pipes shall be retested as per requirements of APCS-113A and 09-SAMSS-113 (SAES-H-200,
paragraph 5.2.2)
18) RTR (Fiberglass) pressure pipe and fittings shall be properly protected from impact, especially on their ends, they
shall not be thrown, dropped, bumped, hit, or dragged and pushed over abrasive surfaces as per 01-SAMSS-034
19) High-density polyethylene (HDPE) pipes and fittings shall be delivered in wooden frames or similar arrangement to
prevent movement between the pipes or pipe sagging as per 01-SAMSS-034

Lay-up Execution
For piping system pressure tested at site/manufacturer/shop drainage, lay up and preservation shall be
implemented as per SAES-A-007

Page 18 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
Carbon Steel Pipes a, b, c, d, e, f,
CS All 01-SAMSS-043, Section 5 SATIP-L-350-01
(On-Plot Piping) g, 1, 1 - 15
SAIC-L-2005
a, b, c, d, e, f,
Stainless Steel Pipe SS All 01-SAMSS-046, Section 18 SAIC-L-2006
g, 2, 3, 1 - 15
Saudi Aramco supply
To be evaluated SATIP to be created
and stored material
SATIP-A-004-02
SATIP-A-004-03
a, b, c, d, e, f,
Piping Lay-Up CS, SS All SAES-A-007 SAES-A-007 SAIC-A-2007
g, 16 - 41
SAIC-A-2018
SATR-A-2009
Butt Welding Pipe a, b, c, 4, 5, 1 -
CS All 02-SAMSS-005, Section 10
Fittings 16
Forged Steel and Alloy
CS All 02-SAMSS-011, Section 13 a, b, c, 6, 1 - 15
Flanges
SATIP-L-350-01
SAES-L-350
Bare and Coated Pipe SAIC-L-2005
Sections 7 & 8 a, b, c, d, e, f,
Storage and All All SAIC-L-2006
SAES-H-200 g, 1 - 15
Preservation
Section 5
a, b, c, d, e, f, 1
Fabricated Steel Piping All All 01-SAMSS-010, Section 10
- 15
RTR (Fiberglass)
SAES-S-070 SATIP-S-010-01
Pressure Pipe and Non-metallic All 01-SAMSS-034, Section 13 a, b, c, 1 - 15
Section 5 SAIC-S-056
Fittings
High Density
Polyethylene (HDPE) Non-metallic All 01-SAMSS-051, Section 6 a, b, c, 1 - 15
Pipe and Fittings
Scraper Trap Station All All SAES-L-420 SATIP-L-420-01 a, b, c, 1 - 15

Table A-2002 Documentation Requirements


a) Contractor shall include procedures for handling, storage, and preservation of material as specified in all applicable
specifications, manufacturer recommendations, and Company’s standards.
b) Contractor shall issue a Materials Status report monthly, or as otherwise requested, reporting on the status of
preservation
General Requirements
1) All valves shall be completely drained of test fluid and thoroughly dried after hydro-testing, the machined surfaces
shall be coated with a light film of high viscosity rust inhibiting oil which will not become fluid and run off at
temperatures below 80°C (04-SAMSS-035 Section 12.1)
2) Discontinuities in corrosion protection are not permitted, interface areas between coating and corrosion resistant
VALVES material shall include overlaps (04-SAMSS-035 Section 10.2 b)
3) Flanged valves NPS 6” and smaller in Class 150 and Class 300 shall be fitted with UV resistant plastic covers. For other
sizes, valve end flanges shall be fitted with plywood covers (04-SAMSS-035 Section 12.2)
4) The ends of threaded and socket weld end valves shall be protected with tight fitting plastic caps as mandated in
04-SAMSS-035 paragraph 13.2
5) Verify the end covers are intact and no dirt or sand has entered the valve body.
6) Valve subject for field hydro-testing, it shall be done within 3 months prior to installation (SAEP-35).

Construction site handling, storage and preservation of valves shall be as per SAEP-35.

Page 19 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
Angle Valves
Check Valves,
Gate Valves,
Globe Valves, Carbon Steel, ALL (Class 150 SAES-K-100
MSS SP 80 2013
Bypass Valves, Malleable Iron, Bronze min) SAES-S-060
All
Flush Valves, SAES-L-108
2way/3way ASME B16.34
Balancing Valves
Carbon Steel, ALL (Class 150
Butterfly Valves MSS SP 67 2002
Malleable Iron, Bronze min) SATIP-L-108-1
Pressure Relief SAIC-L-2041
Per heater vendor ASME A112.4.1-1993 SAIC-L-2040
Valve Bronze
(Class 150 min) (R2002) SAIC-L-2074
(Water Heater) SAES-S-060
Pressure Relief Calc. CSA Z21.22b-2001
Bronze
Valve (Class 150) (R2003)
SA-2787, ISS (Pressure a, 4, 5, 6, 7
Regulators)
SA-8020-711, ISS
Control Valve Bronze 1” min. (Class 150 SAES-K-100
(Globe/Angle)
(2way/3way) SS min) SAES-J-700
SA-8020-712, ISS (Ball)
SA-8020-713, ISS
(Butterfly/ Rotary Plug)

Table A-2003 Documentation Requirements


a) Manufacturer recommended preservation Procedure shall be established prior to shipment, PID to verify preservation
during shipment compliance at time of materials/equipment arrived at site
b) Company preservation procedure and/or manufacturer recommended preservation Procedure shall be provided and
approved prior to material/equipment arrive at site.
c) Contractor shall establish and maintain proper tracking system to ensure registration of material/equipment site
preservation compliance as soon as arrived to and record results periodically, these activities shall be part of weekly
quality meeting discussion and evaluation
General Requirements
1) Designated materials yards/holding areas shall be properly selected, prepared and approved by PID prior to
receiving static equipment
STATIC 2) Static equipment without externally coated at fabrication shop shall have temporary preservative appropriate for
the metallurgy of the static equipment and can be easily removed
EQUIPMENT
3) Stainless Steel Static equipment which were shipped via ocean freight shall be protected using a temporary
protective system compatible with stainless steel and suitable for outdoor exposure
4) Static equipment that are partially shop fabricated and/or likely to suffer from distortion shall have the following
protection during shipment:
a) Adequate bracing
b) All open ends shall be covered to prevent ingress of dirt and other foreign matters
5) Upon Static equipment arrival, ensure that Static equipment internal is completely and thoroughly clean and dry.
6) Static equipment interior surfaces shall be protected from corrosion (during shipment and at site) by use of a
nontoxic liquid or vapor phase corrosion inhibitor (VpCI) that is compatible with the metallurgy of all components in
the equipment being protected and is environmentally friendly for disposal at sea.

Page 20 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

7) For vessels made completely of stainless steels and vessels internally cladded or weld-overlaid with these materials,
in addition to vapor phase corrosion inhibitors applied per 19.2.2, nitrogen blanketing shall be used during shipment
or periods of storage at the construction site. To apply nitrogen blanketing, dew point to be measured before
applying nitrogen pressure to confirm dryness of the internal surfaces, pressurize the vessel to 60 psig or MAWP,
whichever is lower, with nitrogen and then bleed down slowly to 5 psig. Pressurization in this manner shall be
repeated 3 times. Bleed down must be slow and controlled to minimize the loss of vapor phase inhibitor. The vessel
shall be clearly marked with a warning: asphyxiation hazard--preserved with nitrogen.” As per 32-SAMSS-004
paragraph 19.2.2.
8) For pressure vessels accumulator/cylinder to be provided to compensate the pressure during transportation or
storage period. Moreover, pressure gauge to be attached to vessels in order to maintain the nitrogen pressure
inside the equipment for continuous monitoring.
Commentary Note:
The vessel shall be clearly marked with a warning: "Warning: asphyxiation hazard--preserved with nitrogen"
9) Telltale holes in reinforcing pads shall be protected with wooden plugs or packed with rust preventative grease
10) Flanged connections and all other machined surfaces shall be protected by a coating suitable for the metallurgy of the
vessel and can be easily removed in the field.
11) Spare bolts shall be protected with a rust preventative compound to prevent corrosion during shipment, storage, and
construction.
12) Davits shall be preserved, drain holes/notches shall be checked for blocks, and greasing shall be done periodically
through grease fitting.
13) After erection, in situations where nitrogen pressure cannot be maintained at 35 psi fully assembled heat exchangers,
spray interior surfaces with suitable vapor phase inhibitor. If possible, vapor phase inhibitor powder shall be sprayed
directly into the tubes so that it can be easily detected exiting from the opposite end of the tube. Exchangers must be
sealed vapor tight using metallic covers for the inhibitor to be effective.
14) Unless otherwise specified, after site installation machinery shall be stored with dry nitrogen purge or vapor phase
inhibitors and desiccant bags till final piping connection. If preservation gas purging required then equipment shall be
equipped with pressure gauges and the purge pressure shall be routinely monitored and documented. In other cases
where VCI/desiccant bags are present inside, care shall be taken to track the validity and expiry of these bags.
Also, clear external notice about presence of VCI/desiccant bags shall be available on the equipment to remind
removal before final connection.
Equipment Pressure Testing and Lay-up
15) For equipment pressure tested at site/manufacturer/shop drainage, lay up and preservation shall be implemented as
per SAES-A-007
16) For equipment with no drain points, Contractor/ manufacturer shall provide a procedure that will insure water is fully
removed and dried
Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
Pressure Vessel Stand-alone/skid mounted All 32-SAMSS-004 SATIP-D-001-01 All
Fire Heaters Check SATIPS/SAIC
Shell and Tube Heat TEMA Shell and Tube
All 32- SAMSS-007 SATIP-E-004-01 All
Exchanger heat exchanger
Air-Cooled Heat
Stand-alone/API STD 661 32- SAMSS-011 SATIP-E-007-01 All
Exchangers
Plate and Frame
All All 32- SAMSS-019 All
Heat Exchangers
Water Tube Boiler All 32- SAMSS-021 SATIP-F-001-04 All
Electric Heat Exchangers All All 32- SAMSS-027 All
Double Pipe Heat
All All 32-SAMSS-028 All
Exchangers

Page 21 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Table A-2004 Documentation Requirements


a) Contractor shall prepare the site for storage of pre-fabricated tank material prior to receive at site.
b) Contractor preservation procedures for low pressure tanks including the manufacturer recommendation shall be
established and obtained approval
c) Contractor shall establish a tracking system to register the periodically preservation results.
General Requirements
1) For CS ensure tanks are preserved with medium that is compatible to metallurgy of equipment or Nitrogen as per
32-SAMSS-030 Section 12
2) SS cladded or overlaid tanks shall be preserved with Nitrogen on top of VpCI as per 32-SAMSS-030 Section 8
TANKS 3) Plates shall be adequately protected during shipping and storage to avoid damage to plate surfaces and edges from
handling (scratches, gouge marks, etc.) and from environmental conditions (corrosion, pitting, etc.). (API 620)
4) Field erected tanks preservation procedure shall be submitted for approval by Group Leader, Corrosion Engineering
Group (CEG), Materials Engineering Division (MED), Consulting Services Department (CSD)

Equipment Pressure Testing and Lay-up


5) For equipment pressure tested at site/manufacturer/shop drainage, lay up and preservation shall be implemented
as per SAES-A-007
6) For equipment with no drain points, Contractor/ manufacturer shall provide a procedure that will insure water is fully
removed and dried as per SAES-A-007
Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
Low pressure SAES-D-100,
32-SAMSS-030, 32-SAMSS-006, SATIP-D-100
Tanks atmospheric SAES-D-108, ALL
API 620, 32-SAMSS-005, API 650 SATIP-D-109
tanks SAES-D-109

Table A-2005 Documentation Requirements


a) Manufacturer recommended preservation Procedure shall be established prior to shipment, PID to verify
preservation during shipment compliance at time of materials/equipment arrived at site
b) Company preservation procedure and/or manufacturer recommended preservation Procedure shall be provided and
approved prior to material/equipment arrive at site
c) Contractor shall establish and maintain proper tracking system to ensure registration of material/equipment site
preservation compliance as soon as arrived to and record results periodically, these activities shall be part of weekly
quality meeting discussion and evaluation
General Requirements
1) Prior to shipping skids complete with all piping and equipment mounted shall be completely and thoroughly dried
MOUNTED and cleaned from all loose scales, weld slags, dirt and debris to the satisfaction of the Saudi Aramco Inspector as per
32-SAMSS-038 paragraph 12.6
SKIDS
2) All skid-mounted unit’s component shall be (internally and externally) protected in accordance with requirements of
the relevant SAMSS and industry standards as per 32-SAMSS-038 paragraph 12.7 and paragraph 12.8
3) Lifting and transport of the skid-mounted unit, complete with all equipment mounted, shall not permanently distort,
or otherwise damage the skid or the machinery mounting surfaces as per 32-SAMSS-038 paragraph 12.9
4) The skid-mounted unit’s manufacturer shall provide all materials required for preservation and protection during
shipment and storage on site prior to installation considering long-term storage after delivery as per 32-SAMSS-038
paragraph 12.10
5) The skid-mounted unit’s manufacturer is responsible for ensuring that the skid-mounted unit and the associated
equipment’s and internals being shipped are adequately braced and shall provide temporary supports where
appropriate to ensure adequate supporting to prevent damage during handling and transporting as per

Page 22 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

32-SAMSS-038 paragraph 12.11


6) For Stainless Steel components / equipment, which to be shipped via ocean freight, shall be protected using a
temporary protective system compatible with stainless steel and suitable outdoor exposure.
7) Telltale holes in reinforcing pads shall be protected with Hard Grease as per 32-SAMSS-038 paragraph 12.12
8) Skids components which is shipped loose for reassembly in the field, shall be boxed and properly tagged to prevent
damage during transit as per 32-SAMSS-038 paragraph 12.16
9) Each package or material shipped separately shall be clearly marked with the Purchase Order number. All components
of the system such as relief valves and control valves shall be identified with a permanently affixed corrosion-resistant
tag showing the component identification number referenced to the piping and instrument diagram
10) Small or fragile components shall be removed, tagged, wrapped in waterproof material, and packed in a box,
fastened to the unit skid or baseplate
11) All unpainted surfaces of parts made of unalloyed and/or low-alloy carbon steels and martensitic / ferritic steels
(e.g., coupling, motor stool, bearing housing) shall be subjected to anti-corrosive treatment
12) External load such as scaffolding and temporary pipe support shall not be clamped/arrested to machinery/skid
during the course of construction.
Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
Skid-Mounted Units All All 32-SAMSS-038 All

Table A-2006 Documentation Requirements


a) Contractor shall prepare the site for storage of rotating equipment such as pumps, compressors, turbines, etc. and
their spares prior to site delivery.
b) Contractor preservation procedures including the manufacturer recommendation shall be established and obtained
approval.
c) Contractor shall establish a tracking system to register the periodically preservation results
General Requirements
1) Unless otherwise agreed with projects during bidding stage capital spare parts such as Rotor and gear sets to be
supplied with Nitrogen purging system in order to maintain the nitrogen pressure inside the equipment pressure
gauge to be attached to it for continuous monitoring and moreover additional nitrogen cylinder / accumulator to
compensate the pressure if reduced during transportation or storage period
2) If not specified by manufacturer regarding any of routine preservation requirements, API 686 shall be followed.
3) If the equipment or loose items are supplied in vacuum pack or hermetically sealed containers, the condition of
seals shall be examined when arrived at the jobsite. Any damaged vacuum pack shall be repaired or replaced, and
ROTATING the inhibitor renewed if necessary, or preservation activities shall commence as per manufacturer recommendation.
EQUIPMENT 4) Auxiliary piping and tubing installed on mechanical equipment shall be properly protected against impact damage
during transportation. Piping which cannot be installed on the mechanical equipment during transport for reasons
of space or risk of damage shall be packed in a wooden box or crate and shall be shipped together with the
mechanical equipment as per 31-SAMSS-003, Section 1.
5) Stainless steel/metal parts shall be protected against rust during transport and storage
6) For Submersible Pumps and Motors
7) For Submersible Pumps and Motors for Water Well and Offshore Service, the vendor shall provide any instructions
necessary to preserve the integrity of the storage preparation after the equipment arrives at the job site and before
startup as per 31-SAMSS-010, Section 9.3
8) Stainless steel/metal parts shall be protected against rust during transport and storage, the metal parts are to be
packaged clean, dry, corrosion-free and without remains from earlier process steps
9) Sensitive components should be wrapped in airfoil in order to absorb shocks
10) All rotors shall be properly secured to prevent axial and radial movement, (31-SAMSS-004 Section 8.4.1)

Page 23 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

11) The corrosion resistant metal tag shall be stamped in accordance with the Purchase Order, (31-SAMSS-004
Section 8.4.5)
12) Equipment shall be suitably prepared for the type of shipment specified, including restraint of rotors when
necessary. Restrained rotors shall be identified by means of corrosion resistant tags attached with stainless steel
wire, the preparation shall make the equipment suitable for six months of outdoor storage from the time of
shipment, with no disassembly required before operation, except for inspection of motor seals, (31-SAMSS-010
Section 9.3.1)
13) The Vendor shall provide any instructions necessary to preserve the integrity of the storage preparation after the
equipment arrives at the job site and before startup. (31-SAMSS-010 Section 9.3.2)
14) Flanged openings shall be provided with metal closures at least 5 mm thick with elastomeric gaskets and at least
four full diameter bolts, For studded openings, all nuts required for the intended service shall be used to secure the
enclosures, (31-SAMSS-010 section 9.3.5)
15) Threaded openings shall be provided with protection plugs
16) Exposed shafts and shaft couplings shall be wrapped with waterproof, moldable waxed cloth or volatile corrosion
inhibitor paper, The seams shall be sealed with oil proof adhesive tape, (31-SAMSS-010 Section 9.3.8)
17) All valves spindles exposed shall be covered with grease tape
18) General clean up routine and good housekeeping is a prerequisite for successful execution of preservation.
19) Unsupported piping shall not be installed on the machinery. Temporary supports shall be installed as specified by
design to minimize piping applied strain on the machinery. The casual addition or deletion of piping supports during
field construction can result in piping stresses not anticipated by the piping designer and is prohibited.
20) Bearing shall be filled with vendor recommended Oil , Shaft shall be rotated with a strap wrench or other non-
marring devices on frequency as specified in vendor IOM or API 686, which ever more stringent. If the rotor was
initially blocked for shipment, unblock before turning and re-block (per the manufacturers recommendation) after
turning, will be required.
21) During short and long term storage till erection machinery shall be preserved as per manufacturer instruction, all
openings shall then be closed and sealed tightly, nozzles shall be closed using temporary metal blinds, temporary
protective coverings shall allow free air circulation to prevent humidity condensation and collection of water.

Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
31-SAMSS-001
Centrifugal API RP 686 SAES-K-402 SATIP-K-402-01 A, b, c
API 617
Compressor
31-SAMSS-003
Reciprocating API RP 686 SAES-K-403 SATIP-K-403-02 A, b, c, 1
API 617
32-SAMSS-009
Steam Turbine SAES-K-502 A, b, c, 2
32-SAMSS-010
Pumps API 610 Centrifugal 31-SAMSS-004 SAES-G-005 SATIP-G-005 A, b, c
Pump with Canned
Centrifugal 31-SAMSS-004 SAES-G-005 SATIP-G-005 A, b, c
Motor
Gas Turbines Combustion All 32-SAMSS-008 All
SATIP-G-005-01
SAES-G-005 Note: for
SATIP-P-113-01
50 HP and less refer to
Centrifugal Pumps Centrifugal All API STD 610 SAIC-K-402 a, 1, 2, 3, 4, 5
manufacturer
SAIC-G-2001
recommendation
SAIC-P-3407
ASTM A743 CF3M
ASTM A276 XM19
Submersible Pumps All SAES-G-007 a, 6, 7, 8, 9, 10, 11
ASTM D4745 Type 8
Type 316 S.S.

Page 24 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

ELECTRICAL
Table A-3001 Documentation Requirements
a) The Contractor shall include procedures for handling, storage, and preservation of material as specified in all
applicable specifications, manufacturer recommendations and Saudi Aramco's standards
b) Contractor shall establish a tracking system to register the periodically preservation results
c) The procedure shall list all inspection schedules for maintaining the quality of the material or equipment as well as
provide for documentation that the required activities have been performed
General Requirements
1) Electrical equipment should be moved and stored in an upright position
2) Outdoors Equipment- electrical equipment wooden boxes, crates and panels shall be supported off the ground and
provided with a weatherproof (i.e., rain and dust-tight) cover
GENERAL - 3) Electrical equipment wooden boxes, crates and panels shall be stored away from construction equipment, road
traffic, falling or flying objects, and areas where there is a risk of physical damage
ELECTRICAL
4) Indoor Equipment- Electrical equipment shall be stored indoor in a clean dry area
EQUIPMENT
5) Periodical inspection by Contractor QC and routine surveillances by Saudi Aramco Inspector as stated on approved
preservation procedure
6) Verify that the storage area provided is not located near water sources nor flammable materials.
7) Verify that the storage area is well secure and provided with environments control for the protection of the equipment
8) For indoor storage, verify that the storage area provided is well ventilated and the room temperature maintained in
accordance to manufacturer recommendation.
9) Internal parts of electrical equipment shall not be damaged or contaminated by foreign materials such as paint,
plaster, cleaners, abrasives, or corrosive residues. There shall be no damaged parts that may adversely affect safe
operation or mechanical strength of the equipment such as parts that are broken, bent, cut, or deteriorated by
corrosion, chemical action, or overheating

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


"Schedule Q Att. IV Section 6",
"SAES-P-100 Section 5.2", a, b, 1, 2, 3,
Outdoors Equipment SAIC-P-3002
NFPA 70, NEC 110.3(B), 5, 7, 9
NEC 110.12(B)
Schedule Q Att. IV Section 6
a, b, 1, 3, 4,
Indoor Equipment and Section 4.2, SAIC-T-5001
5, 7,8,9
NEC 110.12(B)
Light Fixtures and SAIC-P- 3002, SAIC-T-5001
ALL ALL ALL
Lighting Systems SATR-P-3806
Factory Assembled
(Packaged) and SAIC-P- 3002,
ALL ALL ALL
Auxiliary Electrical SATIP-P-515-01
Systems "Schedule Q Att. IV Section 6"
“SAES-P-100”, SAIC-P- 3404, SAIC-P- 3406
Cranes, Hoists, and NEC 110.3 (B) and 110.12
ALL ALL SAIC-P- 3002, SAIC-T-5001 ALL
Elevators SATIP-P- 113 -04
SAIC-P- 3404, SATR-P- 3806
SAIC-P- 3002, SAIC-T-5001
Switch-gear ALL ALL ALL
SATIP-P- 116 -01, SATIP-P-
116 -03

Page 25 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Switch-racks and SATIP-P- 116 -05,


ALL ALL
Distribution Racks SAIC-T- 5001
SATIP-P- 119 -01,
SAIC-P- 3901
HV Switchyard ALL ALL
SAIC-P- 3002, SAIC-T- 5001
SAIC-P- 3902
Galvanic Cathodic
ALL ALL SATIP-X-400-01, SAIC-P-3002 ALL
Protection
Impressed Current
ALL ALL SATIP-X-600-02, SAIC-P-3002
Cathodic Protection
SAIC-P- 3002, SAIC-P- 3001
MV Cable-bus ALL ALL
SATIP-P- 116 -10
SATIP-P- 116 -12,
LV Cable-bus ALL ALL
SAIC-P- 3002
Control-gear and ALL ALL "Schedule Q Att. IV Section 6" SATIP-P- 116 -02, All
Motor control “SAES-P-100” SATIP-P- 116 -04
Center (MCC) NEC 110.3 (B), NEC 110.12(B), SAIC-P- 3002
“NECA/NEIS 402, Section 4”

Table A-3002 Documentation Requirements


a) The CONTRACTOR shall include procedures for handling, storage, and preservation of material as specified in all
applicable specifications, manufacturer recommendations, and Saudi Aramco's standards.
b) Contractor shall establish a tracking system to register the periodically preservation results
c) The procedure shall list all inspection schedules for maintaining the quality of the material or equipment as well as
provide for documentation that the required activities have been performed.
General Requirements
1) Transformers shipped with its main tank filled with insulating liquid and blanketed with gas under pressure, measure
and record the gas pressure and the ambient temperature when the unit arrives at the work site and every month
thereafter.
POWER
2) The Vibration Event / Recorder shall be in operation during any kind of transformer handling from one location to
TRANSFORMER another.
3) The heating element in control cabinet shall be connected and in operation to prevent condensation of humidity. It
(PAD MOUNTED shall be checked and recorded weekly.
AND OIL-FILLED) 4) In case the transformer has been stored for more than two months after the assembly, possible leakages shall be
checked. All sealing joints must be re-tightened.
5) The transformer must be kept under positive pressure between 0.1-0.3 bar (1.5 - 4.4 psi) at all times while in storage
in accordance to IEEE C57.93 Clause 3.6. The filling pressure shall be checked and recorded weekly.
6) The transformer should be stored upright and completely assembled.
7) If the gas pressure is zero, there is a possibility that outside air and moisture may have entered the tank and the
manufacturer should be notified.
8) Conservator type units should be stored with proper liquid level in the conservators.
9) Weekly inspection by Contractor QC and Saudi Aramco Inspector.

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


"Schedule Q Att. IV Section 5"
Pad Mounted and SAIC-P-3922, SATR-P-3909
"SAES-P-121 Section 3.2
Oil-filled ALL ALL SATR-P-3910, SATIP-P-121-02 All
“NECA/NEIS 410 SECTION 3”
Transformer SATIP-P-121-04
“IEEE C57.93”

Page 26 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Table A-3003 Documentation Requirements


a) The Contractor shall include procedures for handling, storage, and preservation of material as specified in all
applicable specifications, manufacturer recommendations, and Saudi Aramco's standards.
b) Contractor shall establish a tracking system to register the periodically preservation results
c) The procedure shall list all inspection schedules for maintaining the quality of the material or equipment as well as
provide for documentation that the required activities have been performed.
General Requirements
1) The transformer shall be handled in accordance with manufacturer recommendations.
2) Transformers are to be transported in the upright position.
3) Avoid subjecting the transformers to impact, jolting, or denting of the enclosure. Use the manufactures
recommended lifting points. When handling outdoors during inclement weather.
4) Ventilated indoor transformers shall be protected against the entrance of dust and rain.
DRY-TYPE
5) The transformer shall be protected from weather, dirt, water, moisture, contamination, and physical damage during
TRANSFORMER storage.
6) A space heater shall be installed to prevent condensation for:
i. Outdoor transformers stored outdoors without protective covering.
ii. Indoor transformers stored in a non-heated building or where stored outdoors.
7) Weekly inspection by Contractor QC and surveillances by Saudi Aramco Inspector.
8) Outdoor Control cabinet(s) shall be provided with a space heater, suitable for 230 VAC operation but rated for
460 V. A disconnecting means shall be provided for each power supply. A wiring diagram, printed on weather
resistant material indicating the control cabinet circuits and fuse or circuit breaker ratings shall be affixed inside the
cabinet door.
9) The Contractor shall provide documentation that the required Storage, Handling, and Preservation (SHP) activities
have been performed for Dry Transformer at the factory shop and during shipment.
Quality
Material/Equipment Type Size Specification Standards Requirements Notes
SATIP/Checklist
Low Voltage ALL ALL "Schedule Q Att. IV Section 6" ALL
SAIC-P-3918
“NEC 110.3 (B) and 110.12”
SAIC-P-3919
Medium Voltage ALL ALL “NECA/NEIS 409-3.1” All
SATIP-P-121-01
"14-SAMSS-533 Section 6.8.5.2"

Table A-3004 Documentation Requirements


a) The Contractor shall include procedures for handling, storage, and preservation of material as specified in all
applicable specifications, manufacturer recommendations, and Saudi Aramco's standards.
b) Contractor shall establish a tracking system to register the periodically preservation results.
LOW & MEDIUM
c) The procedure shall list all inspection schedules for maintaining the quality of the material or equipment as well as
VOLTAGE – provide for documentation that the required activities have been performed.
General Requirements
INDUCTION 1) When indoor storage is not possible, the motors must be covered with a tarpaulin. This cover should extend to the
MOTORS ground; however, it should not tightly wrap the motor. This will allow the captive air space to breathe, minimizing
AND formation of condensation.
SYNCHRONOUS 2) Whether indoors or out, the area of storage should be free from ambient vibration. Excessive vibration can cause
bearing damage. A unit which must be stored in areas with high ambient vibration, such as from heavy construction
MOTORS equipment or other sources, must have the shaft locked to prevent any movement.
3) Precaution should be taken to prevent rodents, snakes, birds, or other small animals from nesting inside the motors.
In areas where they are prevalent, precautions must be taken to prevent insects, such as mud dauber wasps, from

Page 27 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

gaining access to the interior of the motor.


4) Inspect the rust preventive coating on all external machined surfaces, including shaft extensions. If necessary,
recoat the surfaces with a rust preventive material, such as Rust Veto No. 342 (manufactured by E.F. Houghton Co.)
or equivalent. The condition of the coating should be checked periodically and surfaces recoated as needed.
5) Grease lubricated cavities must be completely filled with lubricant during storage. Remove the drain plug and fill
cavity with grease until grease begins to purge from drain opening.
6) To prevent moisture accumulation, some form of heating must be utilized to prevent condensation. This heating
should maintain the winding temperature at a minimum of 5ºC above ambient. If space heaters are supplied, they
should be energized. If none are available, single phase or "trickle" heating may be utilized by energizing one phase
of motor's winding with a low voltage. A third option is to use an auxiliary heat source and keep the winding warm
by either convection or blowing warm air into the motor.
7) Motors above 75 hp are provided with space heaters and shall be energized to avoid the condensation of moisture.
Inspection shall be conducted for space heaters weekly or as determined by manufacture recommendations.
8) Exposed internal stator, rotor, and shaft surfaces shall be protected against moisture and corrosion by a suitable
protective coating during preservation.
9) Fan motors shall be run-tested for 30 minutes to verify normal operation every six month.
10) Electrical megger testing shall be conducted monthly.
11) For mechanical preservation instructions, refer to Table A-2006 (Rotating Equipment).
Quality
Material/Equipment Type Size Specification Standards Requirements Notes
SATIP/Checklist
"Schedule Q Att. IV Section 6"
Low Voltage Squirrel SAIC-P- 3407,
“SAES-P-100 ,17-SAMSS-511, SAES-P-113”,
Cage Induction ALL ALL SAIC-P- 3406 ALL
“NECA/NEIS 230 SECTION2”,
Motors (SCIM) SATIP-P- 113 -01
“NEC 110.3 (B) and 110.12”
"Schedule Q Att. IV Section 6"
Medium Voltage "SAES-P-100 Section 3.2" "SAES-P-113 SAIC-P-3414
ALL ALL ALL
Induction Section 3.2" SATIP-P-113-02
“IEEE Std. 841-2009 NEC 110.3 (B)”
"Schedule Q Att. IV Section 6"
"SAES-P-100 Section 3.2" "SAES-P-113 SAIC-P-3414
Synchronous Motors ALL ALL ALL
Section 3.2" SATIP-P-113-02
“IEEE Std. 841-2009 NEC 110.3 (B)”

Table A-3005 Documentation Requirements


a) The Contractor shall include procedures for handling, storage, and preservation of material as specified in all
applicable specifications, manufacturer recommendations, and Saudi Aramco's standards.
b) Contractor shall establish a tracking system to register the periodically preservation results.
c) The procedure shall list all inspection schedules for maintaining the quality of the material or equipment as well as
provide for documentation that the required activities have been performed.
UPS, General Requirements
DC EQUIPMENT 1) Cells shall be shipped empty from electrolyte and electrically uncharged. The electrolyte shall be shipped in solid or
liquid form in a separate container.
AND
2) Individual cells shall be packed to provide protection against physical damage and moisture. All cells with defects,
DC BATTERY such as cracked jars, loose and/or lifted terminal posts, or cracked, broken, or improperly aligned plates, should be
reported to the manufacturer for resolution or replaced as needed. Shipping crates shall be marked with handling
and storage instructions. Labels on the shipping crate shall state the storage conditions, date of shipment, and the
date beyond which the product must not be stored.
3) Shipping crates shall be marked with handling and storage instructions. Labels on the shipping crate shall state the
storage conditions, date of shipment, and the date beyond which the product must not be stored.

Page 28 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

4) Batteries / cells must be stored indoors in a clean, level, dry, and cool location; extremely low or high ambient
temperatures or localized sources of heat should be avoided; and the top protected from falling moisture, dirt, and
dust.
5) Batteries / cells must be stacked and secured to palette to prevent slipping, falling over or damage during transport.
Batteries must not be in contact with the ground.
6) Batteries to be stored upright.
7) Batteries / cells must be stored in a dry room, and the top protected from falling moisture dirt and dust.
8) Ensure adequate air flow around the battery storage area.
9) The temperature of the room used to store the batteries must be maintained between 10 and 30°C. (Batteries are
not to be stored in direct sunlight or exposed to excessive heat).
10) Battery to be stored for a long period of time (more than one month) must be checked frequently for damage and
cleanliness.
11) Protect battery terminal posts from damage during transporting and lifting. Temporarily place a piece of non-
conducting material over the top of the battery until lifting activity is complete.
12) Batteries / cells are stored uncharged and empty, transport plugs are to be left in place till filling and charging
activities are ready to start.
13) Storage and Handling areas should be equipped with Eyewashes and Safety Showers. (SAES-B-069)
14) Conditions to avoid; contact with organic materials, combustibles, strong reducing agents, metals, strong oxidizers,
and water.
15) The shelf life of vented lead-acid batteries shall be minimum 2 years when stored at 35°C room temperature.
16) If batteries are to be delivered to the Buyer in a fully charged condition, the Vendor shall recommend a method of
maintaining the battery in charged condition until the battery is commissioned. Detailed instructions and required
equipment shall be provided for dry charged batteries requiring on-site activation.
17) Vent caps should be in position securely.
18) Valve-regulated cells and modules shall be shipped in a fully charged condition.
19) Store and Handle in a well ventilated area. Mechanical Ventilation should be used to control hazardous conditions.
Ventilation systems to be corrosion resistant. Exhaust directly to outside.
20) Do not use with incompatible materials such as strong acids, nitro aromatic, nitroparaffinic, or organohalogen
compounds and metals such as aluminum, zinc, and tin.
21) Inspect storage areas weekly for any deficiencies, including corrosion damage, leaking containers, or poor
housekeeping. Correct all deficiencies as soon as possible.
22) Weekly preservation inspection shall be conducted by Contractor QC and Saudi Aramco Inspector.
23) If stored at site and mounted or positioned on designated location (e.g., battery room), batteries/cells, and
associated equipment shall be protected from physical damages that may be inflicted due to ongoing work in the
area or room.
Quality
Material/Equipment Type Size Specification Standards Requirements Notes
SATIP/Checklist
"Schedule Q Att. IV Section 6"
SAIC-P-3002
"SAES-P-100 Section 3.2" Table A-3001
UPS, DC Equipment SAIC-T-5001
SAES-P-103 & Table A-3002
SATIP-P-103-01
NEC 110.3 (B)
Schedule Q Att. IV Section 6
SAES-P-100 Section 3.2
Vented Ni-Cad Wet Cell SAIC-P-3101
SAES-P-103 All
Battery SATIP-P-103-01
NEC 110.3 (B)
Battery 17-SAMSS-511 Section 18
Vented Lead-Acid Wet Cell IEEE 484, Section 6.1 SAIC-P-3102 All
Valve Regulated Lead-Acid
SAIC-P-3103 All
(VRLA) Gelatin Cell

Page 29 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Aqueous Sulfuric Acid Schedule Q Att. IV Section 6, SAIC-P-3104 a, b, 3, 7, 12, 13,


Electrolyte SAES-P-103 and NEC-110.3 (B) SATIP-P-103-01 18, 20, 21, 22
Electrolyte Dry Potassium or Sodium Schedule Q Att. IV Section 6, SAIC-P-3105 A, b, 3, 12, 13,
Hydroxide Electrolyte SAES-P-103 and NEC-110.3 (B) SATIP-P-103-01 18, 19, 20, 21, 22

Table A-3006 Documentation Requirements


a) The CONTRACTOR shall include procedures for handling, storage, and preservation of material as specified in all
applicable specifications, manufacturer recommendations, and Saudi Aramco's standards.
b) Contractor shall establish a tracking system to register the periodically preservation results.
c) The procedure shall list all inspection schedules for maintaining the quality of the material or equipment as well as
provide for documentation that the required activities have been performed.
General Requirements
1) Firm dry support shall be provided for storage of cable reels.
2) Cable reels shall be stored on edges of flanges only (not on flat side of flanges). Reels shall be chocked during
storage. Cable reels shall be aligned flange to flange in storage.
3) Cable reels shall be stored to provide easy access for lifting and moving
4) Cable ends shall be sealed (water and dust-proof seals) and firmly secured during shipping and storage.
5) If cable ends are exposed for on-reel testing or sampling, they shall be re-sealed (water and dust-proof seals) and
POWER CABLE, firmly secured during storage and handling
CONDUCTORS 6) Cable reels shall be stored away from open flame, fire, arc welding, brazing, grinding, and other sources of high heat
or ignition.
AND
7) Cable reels shall be stored away from chemicals and petroleum products (including potential spilled liquids and
BUILDING WIRE spray mist).
8) Cables with an exposed metal sheath or armor (aluminum or steel) shall be stored indoors.
9) Cable reels shall be stored away from construction equipment, road traffic, falling or flying objects, and areas where
there is a significant risk of physical damage.
10) Cable jacket material not rated for exposure to sunlight shall be stored under a sunshade or indoors.
11) Cable reels shall be supported off the ground and provided with a weatherproof (i.e., rain and dust-tight) cover.
12) Cable reels shall be rolled on hard surfaces and not allowed to sink into soil during handling.
13) Cable reels shall be rolled in accordance with roll directional arrows labeled on reel flanges.
14) Cable reels shall not be dropped. Reels shall not be rolled over sharp edges.
15) Wooden cable reel flanges shall be firmly lagged (no loose or missing pieces) and undamaged from shipping and
handling. No loose screws, bolts, nails, or staples.
16) Weekly inspection by Contractor QC and surveillance or inspection by Saudi Aramco Inspector.
Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes
SAIC-P-3201
SATIP-P-104-01
Schedule Q Att. IV Section 6
Power Cable All All SATIP-P-104-02 All
SAES-P-100, NEC 110.3 (B)
SATIP-P-104-10
SATIP-P-104-11
Overhead Schedule Q Att. IV Section 6,
Overhead
Transmission and NEC-110.3 (B) SAIC-P- 3201
Transmission ALL ALL
Distribution Section Standards 10-TMSS-01 SATIP-P-107-01
(Cable)
(up to 35 kV) Section 6
Overhead Schedule Q Att. IV Section 6,
Transmission Line NEC-110.3 (B)
All All SAIC-P- 3201 All
Cable and Conductor SECTION Standards TES-104.01,
(69 kV and Above) TES-104.03, TES-P-122.12

Page 30 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

SAIC-P-3002
Grounding and "Schedule Q Att. IV Section 6"
ALL ALL SAIC-P-3001 ALL
Bonding Conductor “SAES-P-100”, NEC 110.3 (B)
SATIP-P-111-01

Table A-3007 Documentation Requirements


a) The CONTRACTOR shall include procedures for handling, storage, and preservation of material as specified in all
applicable specifications, manufacturer recommendations, and Saudi Aramco's standards.
b) Contractor shall establish a tracking system to register the periodically preservation results.
c) The procedure shall list all inspection schedules for maintaining the quality of the material or equipment as well as
provide for documentation that the required activities have been performed.
General Requirements
1) Cable tray systems shall not be subjected to physical damage. Cable tray shall be free from burrs or other sharp
projections that could cause damage to the cable jacket during installation.
2) Cable Tray shall be loosely stacked
3) Cable Tray shall be elevated off the ground
CABLE TRAY, 4) Cable Tray shall be ventilated to prevent storage stain
FITTINGS 5) Cable Tray shall be protected from scratching and marring of finish
AND 6) Cable Tray shall be small accessories should be stored to prevent loss
ACCESSORIES 7) Cable Tray shall be stored away from high traffic areas
8) Cable Tray shall be stacked by width and type
9) Shipments shall be hand unloaded unless provisions have been made with the cable tray manufacturer for forklift
unloading.
10) To prevent damage to cable tray:
i. Never pull cable tray from truck trailer by chaining to bottom rung and dragging out of trailer
ii. Special care must be exercised using slings so cable tray is not crushed from the improper location and lifting by
sling
11) Hot Dip Galvanized cable trays shall be stored indoor to avoid any corrosion or detritions to the coating (microns).
12) Weekly inspection by Contractor QC and surveillance by Saudi Aramco Inspector
Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes
"Schedule Q Att. IV Section 6"
SAIC-P-3301
Cable Tray ALL ALL “NEC 110.3 (B)” All
SATIP-P-104-03
NEMA VE 2

Table A-3008 Documentation Requirements


a) The Contractor shall include procedures for handling, storage, and preservation of material as specified in all
applicable specifications, manufacturer recommendations, and Saudi Aramco's standards.
b) Contractor shall establish a tracking system to register the periodically preservation results.
c) The procedure shall list all inspection schedules for maintaining the quality of the material or equipment as well as
provide for documentation that the required activities have been performed
CONDUIT
AND General Requirements
1) The recommended number of pieces of Metal Conduit in a master bundle of each trade sizes shall be as per
BOXES NEMA RN2 Section 1.1.
2) Number of Pieces per Master Bundle for PVC Conduit - The recommended number of pieces of EPC-40 PVC
electrical conduit in a master bundle of each trade size is shall be as per NEMA TC18 Section 3.1.
3) Construction of Bundles for Steel Conduit (RGS or EMT) - Master bundles should be secured with at least two bands
of steel strapping meeting the requirements of ASTM D3953-83.

Page 31 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

4) Construction of Bundles for PVC Conduit - Master bundles of PVC conduit should be secured with at least two bands
of steel strapping meeting the requirements of ASTM D3953-83.
5) Transport conduits by methods in accordance manufacturer's instructions to avoid product damage; deliver in
undamaged condition in manufacturer’s packaging, dry.
6) Remove conduit from a stack from the ends of the stock.
7) PVC-coated rigid steel conduit shall be handled in a manner that prevents injury to the PVC coating by stones and
any other material.
8) Store conduits in a planned and orderly manner that does not endanger employee safety. Ensure stacks and tiers
are stable and stacked to aid safe handling and loading.
9) Conduits shall be stored in a clean, dry, and secure location. Especially avoid places where water might accumulate
or where significant dust or dirt is present. If such a location is not available, materials shall be stored on pallets or
other means to rise above the floor and possible water levels, and wrapped in protective plastic sheeting at both
ends of the bundle.
10) Should any event such as water leaks occurs, that could damage stored materials, the affected material shall be re-
inspected for damage and necessary replacement shall be obtained.
11) All equipment and materials that could be damaged or deteriorate from exposure to the elements shall be stored
indoors, off the ground in suitable warehousing. Storage shall offer full protection from outside elements and shall
be properly ventilated.
12) Place steel conduit bar stock in racks or stack and block them on a firm, level surface to prevent spreading, rolling,
or falling. Use either a pyramided or battened stack. Step back battened stacks at least one unit per tier and
securely chock them on both sides of the stack.
13) Plastic (e.g., PVC) materials suitable for direct-burial shall be stored on flat surface to prevent curvature.
14) Plastic (e.g., PVC) materials not identified as "sunlight resistant" shall be stored in areas shaded from direct sunlight.
15) All conduits shall be always stored with end caps at both ends.
Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes
Boxes (Junction,
Terminal, and Pull) Schedule Q Att. IV Section 6, SATIP-P-104-04
ALL ALL Table A-3001
Wire Troughs, and NEC-110.3 and 110.12 SAIC-P-3002
Wire-ways
Schedule Q Att. IV Section 6,
Above-Grade
NEC-110.3 and 110.12 SATIP-P-104-05
Conduit, Fittings, ALL ALL ALL
ASTM D3953-83 SAIC-P-3310
and Accessories NEMA RN2 Section 1.1
Schedule Q Att. IV Section 6,
Below Grade
NEC-110.3 and 110.12 SATIP-P-104-05
Conduit and Duct ALL ALL ALL
ASTM D3953-83 SAIC-P-3310
Bank NEMA TC18 Section 3.1

Table A-3009 Documentation Requirements


a) The Contractor shall include procedures for handling, storage, and preservation of material as specified in all
applicable specifications, manufacturer recommendations, and Saudi Aramco's standards.
b) Contractor shall establish a tracking system to register the periodically preservation results.
DIESEL c) The procedure shall list all inspection schedules for maintaining the quality of the material or equipment as well as
GENERATOR provide for documentation that the required activities have been performed

SETS General Requirements


1) The diesel generator set, including the control panel and radiator, shall be mounted and shipped on a single steel
skid, and shall be provided with suitable vibration dampers.
2) Space heaters shall be energized to protect the generator, generator circuit breaker, and control components from

Page 32 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

condensing moisture.
3) Batteries shall be maintained as per manufacturer’s instructions prior to generator energization.
4) Exterior surfaces, except for machined surfaces, shall be primed and painted.
5) After having been thoroughly drained and cleaned, internal areas of bearings and all auxiliary equipment in oil
lubrication systems using carbon steel shall be coated with a suitable oil-soluble rust preventive.
6) Weekly inspection by Contractor QC and surveillance by Saudi Aramco Inspector
Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes
SAIC-P- 3420, SAIC-P- 3103
Diesel Generator Set ALL ALL "Schedule Q Att. IV Section SAIC-P- 3002, SAIC-P- 3421 ALL
6" SATIP-P- 113 -03
“SAES-P-100”, “NEC 110.3
Diesel Generator Set
ALL ALL (B)”
VRLA Battery

Table A-3010 Documentation Requirements


a) The Contractor shall include procedures for handling, storage, and preservation of material as specified in all
applicable specifications, manufacturer recommendations, and Saudi Aramco's standards.
b) Contractor shall establish a tracking system to register the periodically preservation results
c) The procedure shall list all inspection schedules for maintaining the quality of the material or equipment as well as
provide for documentation that the required activities have been performed.
General Requirements
1) Comply with the general requirements listed on Table A-3001.
2) Handle Panelboards and accessories carefully to avoid damage to the cabinet, front cover, panelboard, frame, and
components. Avoid subjecting panelboards to impact, jolting, jarring and rough handling.
Panelboard
3) Protect Panelboards from dust, dirt, moisture, contamination, and physical damage. Cover with suitable temporary
covering to prevent deposits of dirt or other foreign material on movable parts and electrical contact surfaces.
4) Store panelboards in a clean, dry, properly ventilated building having a uniform temperature and adequate air
circulation to prevent condensation.
5) If panelboards are stored for extended periods of time (more than 3 months), inspect the panelboards and spot
check insulation resistance in accordance to the NECA/NEIS 407 every three month. If any readings are low, dry out,
clean, and/or replace components as necessary (consult the manufacturer for recommendations).
6) If the panelboards installed outdoor, immediately all openings shall be properly plugged and sealed while the
breather and drain must be provided.

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


"Schedule Q Att. IV Section 6"
LV Panelboard ALL ALL NECA/NEIS 407 Section 4 SAIC-P- 3002, SATIP-P- 116 -07 ALL
NEMA PB1 Section 6

Page 33 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

HVAC and PLUMBING


Table A-4001 Documentation Requirements
a) Contractor shall include procedures for handling, storage, and preservation of material as specified in all applicable
specifications, manufacturer recommendations, and Company’s standards.
b) Contractor shall issue a Materials Status report monthly, or as otherwise requested, reporting on the status of
preservation
General Requirements
1) Stacking of pipes shall be made in a manner to avoid damage to pipes or coatings. (SAES-L-350 Section 7.2)
2) Fittings and valves shall be stored in shipping crates or on racks. (SAES-L-350 Section 7.3)
3) Pipe shall not be stored directly on the ground. Pipe shall be placed on mounds or sleepers. (SAES-L-350 Section 7.1)
Coated pipes shall have ring protections as per manufacturer
4) Stacking of pipes shall be made in a manner to avoid damage to pipes or coatings. (SAES-L-350 Section 7.2)
METALLIC
5) End protectors on pipes, flanges, weld bevels, threads, and socket ends shall be firmly attached.
PIPING (SAES-L-350 Section 7.4)
6) All materials shall be handled with care during fabrication and installation to prevent damage.
(SAES-L-350 Section 8.1)
7) Lined and coated pipes and fittings shall be lifted with wide fabric or rubber-covered slings and padding shall be used
to prevent damage to lining or coating in accordance with SAES-H-200. (SAES-L-350 Section 8.2)
8) This standard establishes requirements to control internal corrosion during and after hydrostatic testing of new,
revalidated, and refurbished equipment when equipment is hydrostatic tested in accordance with SAES-A-004,
SAES-L-150, or as required by other standards that specifically reference SAES-A-007. (SAES-A-007 Section 1.1)
9) General clean up routine and good housekeeping is a prerequisite for successful execution of preservation.
10) Stacks of pipe are secured by a minimum of 3 straps made of a resilient material. (SAES-H-200 Paragraph 5.2.3.5)
Standards Quality SATIP /
Material/Equipment Type Size Specification Notes
Requirements Checklist
Sch. 40 SML 3” & smaller
ASTM A53, ASTM A106
Carbon Steel Pipe Sch. 40 SML or ERW 4” to 6”
or API 5L Gr. B Galvanized
0.25 in. min. SML or ERW 8” - 24”
Cast Iron SW, single or double hub 2”-12” ASTM A74
ASTM A106 or API 5L, Cement SAES-L-105
Cement Lined CS SML or ERW 4” and larger SAES-L-350 SATIP-L-350-01
Lined to 01-SAMSS-005
ASTM A106 or API 5L Fusion SAES-K-100 SATIP-L-350-07
FBE Lined CS SML or ERW 2” and larger bonded Epoxy lined to 09- 01-SAMSS-005 SATIP-L-350-08
SAMSS-091 09-SAMSS-091 SAIC-L-2001
HDPE Lined CS SML or ERW 2” and larger ASTM A106 or API 5L HDPE lined SAES-S-010 SAIC-L-2005
All
SAES-S-020 SAIC-L-2006
Polypropylene-Lined ASTM A106 or API 5L, SAES-S-030 SAIC-L-2007
SML or ERW 2” and larger
CS Polypropylene lined SAES-S-040 SAIC-L-2008
UNS-C70610 to BS 2871, Part 2 SAES-S-050 SAIC-L-2074
90/10 Cu-Ni SML ½”-4” and EEMUA Publication No. 144, SAES-S-060 SAIC-L-2034
Section 1 SAES-S-070
PTFE Lined CS SML or ERW 2” and larger API 5L Polypropylene lined
½” - 3-⅛”
O.D. (⅜” - 3” Copper, ASTM B88 Type “K”
Copper Pipe / Tube Type “K” or “L”
in std. tube or “L”, plain ends
size)

Page 34 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Table A-4002 Documentation Requirements


a) Contractor shall include procedures for handling, storage, and preservation of material as specified in all applicable
specifications, manufacturer recommendations, and Company’s standards.
b) Contractor shall issue a Materials Status report monthly, or as otherwise requested, reporting on the status of
preservation
General Requirements
1) Pipe and fittings shall be sealed and protected with plastic end caps. (01-SAMSS-042 Section 5.8)
2) End protectors shall be provided and securely attached to open ends of all pipes, (01-SAMSS-034 Section 13.2.1)
3) The ends shall be checked for missing or broken end protectors, (01-SAMSS-042 Section 12.6.2)
4) Pipes and fittings shall be inspected for evidence of damage or distortion, (01-SAMSS-042 Section 12.6.10)
5) Pipe edges shall be coated with resin and inspected to be smooth, not prone to cutting skin on contact,
(01-SAMSS-042 Section 12.6.11)
6) Do not allow pipe to roll off to ground or racks. (SAES-L-650 Section 6.1 b)
7) Pipe may be lifted with a sling provided the sling is a canvas or compatible plastic, at least 4 in wide, (SAES-L-650
Section 6.1 c)
8) Pipe shall be transported in a container or pallet that does not permit contact pipe-to-pipe nor relative movement of
the pipe during transport, (SAES-L-650 Section 6.1 d)
9) Fittings shall be loaded onto pallets with packing to prevent contact fitting-to-fitting or relative movement of the
fitting during transport. (SAES-L-650 Section 6.1 e))
NON-METALLIC 10) Pipe spools shall be lifted by at least two slings to evenly support the weight and prevent overturning or fall,
(SAES-L-650 Section 6.1 f))
PIPING
11) Yard storage shall be in accordance with the manufacturer requirements. (SAES-L-650 Section 6.3 a)
12) The pipes shall be set on a flat surface, free of sharp edges, (SAES-L-650 Section 6.3 b)
13) Pipes shall be adequately supported in accordance to manufacturer requirements, (SAES-L-650 Section 6.3 c)
14) Maintain end protectors throughout storage. (SAES-L-650 Section 6.3 d)
15) If they are to be bundled, pipes and fittings shall be secured by straps; chains are not permitted,
SAES-L-650 Section 6.3 e)
16) Thermoplastic and RTR fittings shall be stored in their original containers. Fittings shall be stored in a safe area under
a cover / shaded that allows free air circulation, (SAES-S-070 Section 5.3)
17) Precautions shall be in place to tie-down pipes and fittings to prevent overturning or fall. SAES-L-650 Section 6.3 f)
18) Gaskets and adhesive systems and lubricants shall be stored in their original packing in accordance with the
manufacturer recommendations. SAES-L-650 Section 6.3 g)
19) At the end of every work shift, personal performing the pipe installation shall ensure that the pipe ends are capped
to prevent the egress of foreign material, and the piping is anchored to prevent floatation, (SAES-S-070 Section 9.4)
20) The line shall be filled with hydro test clean water, vented, and be free or air or gas, (SAES-L-650 Section 11.2 b, c)
21) Ensure pipe are dry and clean after completion of testing
22) Comply with the requirements of SAES-S-070 Section 5 Storage and Handling and section 6 - Transportation.
Section 7- Inspection before Assembly
23) General clean up routine and good housekeeping is a prerequisite for successful execution of preservation.
Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
RTR Refer to 01-SAMSS- 01-SAMSS-029 RTR SAES-K-100 All
Glass Fiber 80 mm - SATIP-S-070-03
029 sewer(Gravity) pipe and 01-SAMSS-029 Note: For
Reinforced 3700 mm SAIC-S-4056
Class 3 fittings, 0 to 49°C 01-SAMSS-034 potable

Page 35 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Thermosetting 01-SAMSS-034 RTR 01-SAMSS-051 water it


25 mm -
Resin Pipe (RTR) 01-SAMSS-034 (pressurized) Pipe and SAES-S-010 shall be
3700 mm
Fittings, 0 to 93°C SAES-S-020 NSF
UPVC SAS 14/15 Class 3 SAES-S-030 certified
with Anger joints ASTM SAES-S-040
SAES-S-010 D3034, Type PSM, PVC SAES-S-050
160 mm -
pipe and fittings may be SAES-S-060
315 mm
Class 3 used to match existing SAES-S-070
PVC Pipe pipe.60 C max. LOCALLY
MADE ARTICLE
SAES-S-060 Sch. 40
Drain, Waste and Vent 2” - 8” ASTM D2665 PVC, 60°C
Pipe
20 - 200 PVC/uPVC, SAS 14/15
SAES-S-060 Class 5
mm Class 5 Local Made Article
PVC/UPVC Pipe
ASTM D1785 PVC 1120 or
Sch. 80 ½” - 6”
1220

CPVC Pipe Sch. 80 ½” - 6” ASTM F441 CPVC 4120

High Density 01-SAMSS-051 High


ASTM D3350 or ISO
Polyethylene (HDPE) All Density Polyethylene
4427-07
Pipe (HDPE) Pipe and Fittings

Table A-4003 Documentation Requirements


a) Contractor shall include procedures for handling, storage, and preservation of material as specified in all applicable
specifications, manufacturer recommendations, and Company’s standards.
b) Contractor shall issue a Materials Status report monthly, or as otherwise requested, reporting on the status of
preservation
General Requirements
1) Reinforced concrete pipe in direct contact with earth shall be coated with two coats of coal tar or bitumen coating
CONCRETE that conforms to SAES-H-001.
PIPE 2) Reinforced concrete pipe shall not be stored in an upright position until the designated handling and storage
compressive strength, as shown on the working drawings, has been achieved.
3) The manufacturer technician is required to determine that the repairs are sound, properly finished, cured, and the
repaired pipe or structure conforms to the requirements of the specifications. The manufacturer technician should
examine the pipe before and after the repairs are made.
4) General clean up routine and good housekeeping is a prerequisite for successful execution of preservation.
Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
Reinforced Concrete 300 mm and
ASTM C76M Class III, Wall B
Pipe larger
SATIP-Q-001-04
SAES-S-030 ASTM C14 Class III non- SAES-S-030 a
250 mm and SAIC-Q-1022
Concrete Pipe reinforced, bell and spigot, or
smaller
tongue and groove sewer pipe.

Page 36 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Table A-4004 Documentation Requirements


a) Contractor shall include procedures for handling, storage, and preservation of material as specified in all applicable
specifications, manufacturer recommendations, and Company’s standards.
b) Contractor shall issue a Materials Status report monthly, or as otherwise requested, reporting on the status of
preservation.
General Requirements
1) Storage and preservation of HVAC equipment and materials shall be in accordance with the manufacturer
recommendations but not limited to the following:
i. Identification and description of initial and any additional preservation requirements.
ii. Performing initial preservation.
iii. Performing preservation maintenance.
iv. Filling out preservation tracking sheets and fix it to the equipment.
v. Documenting preservation activities on preservation records.
vi. Preparation of a procedure for storage of the skid / equipment and for maintenance preservation during the
construction period. This procedure shall also include method for removal of the preservation used on the skid /
equipment, and shall be included in the preservation dossier.
2) All equipment shall be checked, on delivery with respect to the condition of the preservation. Any defects shall be
HVAC-R rectified according to requirements. For equipment packages supplied internally preserved, no further action except
EQUIPMENT external inspection is required during storage period.

AND 3) All exposed unpainted machined surfaces shall be coated with rust preventive wax.
4) The Contractor shall be solely responsible for the care and cleanliness of the equipment during off-loading, handling,
FANS
storage and construction period and shall ensure a standard of care and cleanliness appropriate to the type and duty
of the equipment. Outdoor storage is only acceptable for equipment prepared for it by the supplier.
5) Maintenance preservation shall be performed during storage period. For special or sensitive equipment, designated
store rooms shall be vented and clean. The storage environment shall have to fulfil manufacturer’s requirements.
6) A temporary protective slanting roof with sidings shall be erected around equipment skids and such special
equipment as inline instr. valves, pumps, electric motors, etc. This temporary protection shall be non-flammable.
7) All in/outlets from units/skids shall be plugged/blanked. Flanges shall be blanked with oil resistant rubber gaskets
and steel or water resistant plywood plate with galvanized bolts sufficient to provide mechanical protection and
water/dust tight sealing.
8) Lubricate door hinges, grease nipples, and fastener as required.
9) General clean up routine and good housekeeping is a prerequisite for successful execution of preservation.
10) Packing of equipment for transportation and under erection shall protect the equipment against humidity, dust, and
mechanical strain which may occur during outdoor storage, loading and construction. The enclosure used for this
purpose shall allow access for stripping down the unit, enable receipt control, maintenance preservation and be
provided with hatches for lifting, hook-up of piping, electrical/instrument cables and tubing without removing the entire
enclosure.
11) Sensitive equipment shall be stored indoors in temperature controlled storage areas as recommended by manufacturer.
Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
SAES-K-101
6000014429
vapor compression SAES-K-001
Limitations per 6000014872
(Offshore, Data Processing, SAES-K-001 SATIP-K-001-05
Chillers SAES-K-001 6000001828 a
Industrial, General 27-SAMSS-006 SAIC-K-4002
Section 7 tables 4 & 5 6000001883
Application) 27-SAMSS-001
6000001885
6000014460

Page 37 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Absorption SAES-K-101
(General Application) 6000012733
SAES-K-101
Direct Expansion Offshore, Data Processing, 6000001882
System General Application 6000013333 SATIP-K-001-06
6000001881 SATIP-K-001-011
SAIC-K-4004
SAES-K-101
Split System General Application SAIC-K-4037
6000001862
Package System General Application SAES-K-001
SATIP-K-001-005
Cooling Tower Forced Draft Per Design 27-SAMSS-003
SAIC-K-4002
AHRI 430
SATIP-K-001-02
Air Handling Units General Application ≥ 5000 CFM Per SAES-K-001
SAIC-K-4004
section 4.8.8.9
SATIP-K-001-005
Fan Coil Units General Application Per Design
SAIC-K-4038
Exhaust Fans General Application ASHRAE 62 SATIP-K-001-01
SAES-K-001 SAIC-K-4001
Supply Fans General Application ASHRAE 62
Electric Duct Heaters General Application Per Design SATIP-K-001-03
Duct Humidifiers General Application Per Design SAIC-K-4011
Battery Exhaust ASHRAE 62/ SAES-P- SAES-K-002 SATIP-K-001-01
Corrosive Environment SAES-K-100
Fans 103 SAES-P-103 SAIC-K-4001
ASHRAE STD 52/
Pre/Final Filter Hepa Filters SATIP-K-001-08
Air Filters Varies SAES-K-101 SAES-K-001
ULPA (MERV17 and above) SAIC-K-4028
6000013331
Expansion Tank -
SAES-K-100 SATIP-K-001-05
Chilled Water, HVAC General Application Per Design SAES-K-001
6000014442 SAIC- K-4022
System
Air and Dirt SAES-K-100 SATIP-K-001-05
General Application Per Design SAES-K-001
Separators 6000014911 SAIC- K-4022
Refrigeration
Equipment and Blast General Application
Freezers

Table A-4005 Documentation Requirements


a) Contractor shall include procedures for handling, storage, and preservation of material as specified in all applicable
specifications, manufacturer recommendations, and Company’s standards.
b) Contractor shall issue a Materials Status report monthly, or as otherwise requested, reporting on the status of
preservation
General Requirements
AIR 1) Storage and preservation of HVAC insulation materials shall be in accordance with the manufacturer
DUCT recommendations.
2) The Contractor shall be solely responsible for the care and cleanliness of the air ducts during off-loading, handling,
storage and construction period.
3) Outdoor storage is only acceptable for ducts prepared for it by the supplier. Maintenance preservation shall be
performed during storage period.
4) General clean up routine and good housekeeping is a prerequisite for successful execution of preservation.

Page 38 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
Duct Sections
ASTM A653 /
Duct Fittings
A653M-03
Volume Damper SMACNA

Sound Attenuator ASTM E477 SAES-K-001


Accessories G− 90
Per SAES-K-001 SATIP-K-001-03
Registers and Grilles Aluminum
Section 4.4.2.2 SATIP-K-001-08
VAV / CAV VAV Box Varies SAES-K-001 a
SAIC-K-4011
Flexible Duct UL181 UMC 2009 SAIK-K-4028
Battery Room Ducts,
SS316/ anti- Per SAES-K-100
Accessories,
corrosive coating Section 603
Registers and Grilles
SAES-K-100
SAES-K-101
Fire, Smoke, 6000013336
General Application
Combination Fire- 6000001863
UL555/555S
Smoke Dampers 6000014320
NFPA 92

Table A-4006 Documentation Requirements


a) Contractor shall include procedures for handling, storage, and preservation of material as specified in all applicable
specifications, manufacturer recommendations, and Company’s standards.
b) Contractor shall issue a Materials Status report monthly, or as otherwise requested, reporting on the status of
preservation
General Requirements
INSULATION 1) Storage and preservation of HVAC insulation materials shall be in accordance with the manufacturer recommendations.
MATERIAL 2) The Contractor shall be solely responsible for the care and cleanliness of the equipment during off-loading, handling,
storage and construction period.
3) Outdoor storage is only acceptable for insulation materials prepared for it by the supplier. Maintenance
preservation shall be performed and maintained during storage period.
4) The storage environment shall have to fulfil manufacturer’s requirements.
Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
ASTM C553
External
Duct Insulation ASTM E 2231
SATIP-K-001-03
Internal Varies NFPA rated closed cell material SAES-K-001 a
SAIC-K-4011
closed cell type PVC nitrile rubber
Pipe Insulation External
insulation

Page 39 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Table A-4007 Documentation Requirements


a) Contractor shall include procedures for handling, storage, and preservation of material as specified in all applicable
specifications, manufacturer recommendations, and Company’s standards.
b) Contractor shall issue a Materials Status report monthly, or as otherwise requested, reporting on the status of
preservation
General Requirements
1) Storage and preservation of Fire Protection equipment, instruments, and materials shall be in accordance with the
FIRE manufacturer recommendations.
PROTECTION 2) The Contractor shall be solely responsible for the care and cleanliness of the equipment during off-loading, handling,
SPRINKLERS storage and construction period and shall ensure a standard of care and cleanliness appropriate to the type and duty
of the equipment. Outdoor storage is only acceptable for equipment prepared for it by the supplier. Maintenance
AND preservation shall be performed during storage period. For special or sensitive equipment, designated store rooms
STAND PIPES shall be, vented and clean. The storage environment shall have to fulfil manufacturer’s requirements
3) A temporary protective slanting roof with sidings shall be erected around equipment skids and such special
equipment as inline instr. valves, pumps, electric motors, etc. This temporary protection shall be non-flammable.
4) All valves spindles exposed shall be covered with grease tape.
5) General clean up routine and good housekeeping is a prerequisite for successful execution of preservation.
6) Sensitive equipment shall be stored indoors, temperature and humidity controlled storage areas.
Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
S/S, brass (Upright,
Sprinkler Heads 1/2” ANSI/UL 199
pendent, sidewall)
Carbon Steel 1” and above
UL/FM Valves UL 262
Bronze (class 150 min) SAES-S-050
Inspector’s Test NFPA-13
Bronze 1” UL 262
Valve
4” and above
Alarm Check Valve Carbon Steel FM 1041
(class 150 min) SATIP-S-050-01
Fire Department a
SAIS-S-4022
Bronze 2(3) x2-1/2” X 4”
Connection (FDC)
AWWA C-503-88
Fire Hydrant Cast Iron 4- 4-1/2”x 2-1/2”
AWWA C502 SAES-S-050
Fire Hose and Fire NFPA-14
Class 2, Class 3 1-1/2 NFPA 1962
Hose Cabinet (FHC)
Post Indicator Valve
Carbon Steel 4” (Class 150 min) UL 789
(PIV)

Table A-4008 Documentation Requirements


a) Contractor shall include procedures for handling, storage, and preservation of material as specified in all applicable
specifications, manufacturer recommendations, and Company’s standards.
b) Contractor shall issue a Materials Status report monthly, or as otherwise requested, reporting on the status of
OTHER preservation
EQUIPMENT
AND General Requirements
1) Storage and preservation of miscellaneous plumbing and HVAC equipment and materials shall be in accordance
MATERIALS with the manufacturer recommendations.
2) The Contractor shall be solely responsible for the care and cleanliness of the equipment during off-loading,
handling, storage and construction period and shall ensure a standard of care and cleanliness appropriate to the

Page 40 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

type and duty of the equipment. Outdoor storage is only acceptable for equipment prepared for it by the supplier.
Maintenance preservation shall be performed during storage period. For special or sensitive equipment, designated
store rooms shall be, vented and clean. The storage environment shall have to fulfil manufacturer’s requirements.
3) A temporary protective slanting roof with sidings shall be erected around equipment skids and such special
equipment as inline instr. valves, pumps, electric motors, etc. This temporary protection shall be non-flammable.
4) All valves spindles exposed shall be covered with grease tape.
5) Sensitive equipment shall be stored indoors in temperature and humidity controlled storage areas.
6) Drain out ensuring that no water is trapped in system
Standards Quality
Material/Equipment Type Size Specification Notes
Requirements SATIP/Checklist
Emergency ANSI Z358.1 SATIP-B-069-01
9COM Specs SAES-B-069
Eyewash/Shower ISEA Z358.1 SAIC-B-4001
UL 1206-2003 SATIP-S-060-01
Electric Water Heater 9COM Design SAES-S-060
UL 174-2004 SAIC-S-4027
SATIP-S-060-02
Drinking Fountain 9COM Design UL 399-1993 SAES-S-060
SAIC-S-4030
Skid Mounted RO Water WQA S-300-2000 SATIP-S-060-03
175-325400 32-SAMSS-033 SAES-S-060 a
Treatment System NSF 58-2007 SAIC-S-4033
Plumbing Fixture and SATIP-S-060-04
9COM Design IAMPO SAES-S-060
Fittings SAIC-S-4036
SATIP-J-100
Field Sensors and SATIP-J-300
175-030100 34-SAMSS-913 SAES-J-100 SAES-J-100
Devices SATIP-J-400
SAIC-T-5001

COMMUNICATIONS
Table A-5001 Documentation Requirements
a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment, including partially fabricated assemblies, shall be provided and approved as part of project quality
planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions, and recommendations. The I&T procedure shall address both permanent and
temporary identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the
equipment, on equipment packaging and in documentation. The SH&P procedure shall address preservation
requirements ex-works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
COMMUNICATIONS traceability, and quality of indoor electronic equipment in shipping, handling, customs clearance, delivery,
storage, assembly, installation, inspection, testing, and reinstatement.
ELECTRONIC
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
EQUIPMENT acceptance of required QA/QC activities.
General Requirements
1) Prior to shipping, equipment is suitably packaged with compliant packing materials for handling, water, humidity,
condensation, dust, chemical contaminates, solar radiation and ambient temperature.
2) Equipment (including packaging and documentation) are labeled and identified in compliance with requirements
of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for both
temporary and permanent identification.
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state
storage conditions, date of shipment, and the date beyond which the equipment must not be stored.

Page 41 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed.
5) Equipment is handled, placed, and stored in accordance with manufacturer requirements for ready access,
foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration and impact.
6) Equipment is stored in a secured area that is in compliance with requirements of the approved QC procedure,
manufacturer’s instructions, project specifications, and MSAER’s.
7) Equipment is not stored in an area with water sources, flammable materials, chemical vapors, construction
equipment, road traffic, falling or flying objects, and where there is a risk of flooding or physical damage.
8) Equipment and accessories are readily traceable and verifiable to the manufacturer through shipping, handling,
customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment packaging that is damaged or disturbed (e.g., for customs clearance, receiving inspection, etc.) is
timely repaired and fully reinstated for subsequent shipping, handling, storage and preservation. Desiccant
packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment shall be inspected for visible damage by Contractor QC prior to acceptance of shipment, unloading
and handling.
11) Equipment in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
Indoor electronic equipment shall be stored indoors; with environmental controls provided for water, humidity,
condensation, dust, solar radiation, and ambient temperature.

Standards
Material/Equipment Type Size Specification Quality SATIP/Checklist Notes
Requirements
SAES-P-100
Direct Current Power Battery SATIP-T-151-01, SAIC-T-5001
SAES-P-103 (A)
Systems Charger SAIC-P-3002, SAIC-P-3112
NFPA 70 (NEC)
SATIP-T-481-01, SAIC-T-5001
Powered In-Plant Page Party SAES-P-100 SAIC-P-3002, SAIC-T-5203
Communication Handstation, LBA, SAES-T-481 SAIC-T-5204, SAIC-T-5205 (A)
Systems and PA Speaker NFPA 70 (NEC) SAIC-T-5206, SAIC-T-5207
SAIC-T-5208
RF / Wireless Equipment,
Wired Distribution SATIP-T-492-01, SATIP-T-916-01
SAES-P-100
Equipment, SAIC-T-5001, SAIC-P-3002
Communication SAES-T-492
Wired Transmission SAIC-T-5302, SAIC-T-5304 (A)
Systems SAES-T-916
Equipment, SAIC-T-5305, SAIC-T-5306
NFPA 70 (NEC)
Building PDS SAIC-T-5909, SAIC-T-5910
Equipment

Table A-5002 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of
project quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
DC POWER manufacturer instructions and recommendations. The I&T procedure shall address both permanent and
EQUIPMENT temporary identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the
AND equipment, on equipment packaging and in documentation. The SH&P procedure shall address preservation
requirements ex-works; by distributors, vendors, Contractors and in shipping.
MATERIALS c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of indoor electronic equipment in shipping, handling, customs clearance, delivery,
storage, assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and

Page 42 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

acceptance of required QA/QC activities.

General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state
storage conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for ready
access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration and
impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications and MSAER’s
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving
inspection, etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and
preservation. Desiccant packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Nickel-cadmium cells shall be shipped empty and electrically uncharged. The electrolyte shall
be shipped in solid or liquid form in a separate container.
(B) Vented lead-acid cells shall be shipped in dry charged condition (without electrolyte). A local representative of the
battery manufacturer shall supply the electrolyte and fill the battery.
(C) Valve-regulated cells and modules shall be shipped in a fully charged condition.
(D) If battery cells are delivered in a dry-charged or fully-charged condition, the Manufacturer shall provide
instructions for maintaining cell charge until the battery is commissioned.
(E) Batteries / cells must be stored inside a dry room, and the top protected from falling moisture, dirt and dust.
The temperature of the room must be maintained between 10°C and 30°C.
(F) The shelf life of vented lead-acid and nickel-cadmium battery cells shall be a minimum of two (2) years when
stored at 35°C room temperature.
(G) Battery cells must be fitted with transport plugs. Transport plugs remain in place until filling and charging activities
are ready to start.
(H) Aqueous Sulfuric Acid - Hazardous Material - Special procedures and training are required. Store in a cool, dry,
well-ventilated storage area with acid resistant floors and good drainage. Protect from physical damage and
freezing. Keep out of direct sunlight and away from heat and incompatible materials.
(I) Dry Potassium or Sodium Hydroxide - Hazardous Material - Special procedures and training are required.
Minimize amount of corrosive material in storage. Inspect storage areas regularly for any deficiencies, including
corrosion damage, leaking containers, or poor housekeeping. Correct all deficiencies as soon as possible.
(J) Indoor equipment shall be stored indoors; with environmental controls provided for water, humidity,
condensation, dust, solar radiation, and ambient temperature.

Page 43 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


Stationary Vented SAES-P-100, SAES-P-103 SATIP-T-151-01, SAIC-P-3002
Direct Current Power (A), (E),
Storage Ni-Cad SAES-P-104, 17-SAMSS-511 SAIC-P-3101, SAIC-P-3113
Systems (F), (G)
Battery Wet Cell NFPA 70 (NEC) SATR-P-3113
Stationary Vented SAES-P-100, SAES-P-103 SATIP-T-151-01, SAIC-P-3002 (B), (D),
Direct Current Power
Storage Lead-Acid SAES-P-104, 17-SAMSS-511 SAIC-P-3102, SAIC-P-3114 (E), (F),
Systems Battery Wet Cell NFPA 70 (NEC) SATR-P-3103, SATR-P-3114 (G)
Stationary Valve Regulated SAES-P-100, SAES-P-103 SATIP-T-151-01, SAIC-P-3002 (C), (D),
Direct Current Power
Storage Lead-Acid (VRLA) SAES-P-104, 17-SAMSS-511 SAIC-P-3103, SAIC-P-3115 (E), (F),
Systems Battery Gelatin Cell NFPA 70 (NEC) SATR-P-3104, SATR-P-3115 (G)
DC Switchboard, SAES-P-100, SAES-P-101
Direct Current Power SATIP-T-151-01, SAIC-P-3002
Electrical Panelboard, 16-SAMSS-519, 16-SAMSS-518 (J)
Systems SAIC-P-3122, SAIC-P-3123
Equipment DC MCCB NFPA 70 (NEC)
DC
Direct Current Power Aqueous Sulfuric SAES-P-100, SAES-P-103 SATIP-T-151-01, SAIC-P-3104
Electrical (H)
Systems Acid Electrolyte SAES-P-104, NFPA 70 (NEC) SAIC-P-3116 (MSDS)
Materials
DC Dry Potassium or
Direct Current Power SAES-P-100, SAES-P-103 SATIP-T-151-01, SAIC-P-3105
Electrical Sodium Hydroxide (I)
Systems SAES-P-104, NFPA 70 (NEC) SAIC-P-3117 (MSDS)
Equipment Electrolyte

Table A-5003 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment, including partially fabricated assemblies, shall be provided and approved as part of project quality
planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and
temporary identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the
equipment, on equipment packaging and in documentation. The SH&P procedure shall address preservation
requirements ex-works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of indoor electronic equipment in shipping, handling, customs clearance, delivery, storage,
assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
COMMUNICATION
General Requirements
TOWERS 1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
AND water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
FACILITIES 2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state
storage conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for
ready access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration
and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications, and MSAER’s.
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,

Page 44 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical
damage.
8) Equipment and materials are readily traceable and verifiable to the manufacturer through shipping, handling,
customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment packaging that is damaged or disturbed (e.g., for customs clearance, receiving inspection, etc.) is timely
repaired and fully reinstated for subsequent shipping, handling, storage and preservation. Desiccant packing
materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
N/A
Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes
Self-Supporting
SAES-T-744, 12-SAMSS-007 SATIP-T-744-01, SAIC-T-5601
Communication Tower
Guyed Steel
SAES-T-744, 12-SAMSS-007 SATIP-T-744-01, SAIC-T-5602
Communication Tower

Table A-5004 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of
project quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and
temporary identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the
equipment, on equipment packaging and in documentation. The SH&P procedure shall address preservation
requirements ex-works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of indoor electronic equipment in shipping, handling, customs clearance, delivery,
storage, assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
FIBER OPTIC General Requirements
COMMUNICATIONS 1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
CABLE
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
3) Shipping crates and reels shall be marked with handling and storage instructions. Labels on shipping crates shall
state storage conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for
ready access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration
and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved
QC procedure, manufacturer’s instructions, project specifications and MSAER’s
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,

Page 45 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical
damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving
inspection, etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and
preservation. Desiccant packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Cable reels shall be shipped, handled and stored on edges of flanges only (not on flat side of flanges). Reels shall
be chocked to prevent damage from rolling or shifting.
(B) Cable reels shall be shipped with a cable protective covering. Lifting equipment, tools, rope, slings, personnel
and soil shall not contact the cable or cable protective covering during shipping and handling. Mechanical force
or pressure shall not be applied to the cable surface during handling.
(C) Cables with an exposed metal sheath or armor shall be stored indoors.
(D) Cable jacket material not tested and rated for exposure to sunlight shall be stored under a sunshade or indoors.
(E) Cable ends shall be sealed for water and dust, and firmly secured during shipping and storage. If cable ends are
exposed for on-reel testing or sampling, they shall be re-sealed and firmly secured for subsequent storage and
handling.
(F) Cable reels shall be supported off the ground and provided with a weatherproof, rain-tight, and dust-tight cover.
(G) Indoor equipment and materials shall be stored indoors; with environmental controls provided for water,
humidity, condensation, dust, solar radiation, and ambient temperature.
(H) Cables shall be tested on-the-reel, after delivery and prior to installation in accordance with SAES-T-624 and
SAES-T-634.

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


SAES-T-624, SAES-T-634
Fiber Optic OSP SATIP-T-624-01, SAIC-T-5501
SAES-T-920, 18-SAMSS-625 (A) - (H)
Cable Single-mode SAIC-T-5401, SAES-T-634
NFPA 70 (NEC)
Building SAES-T-625, SAES-T-634
Fiber Optic SATIP-T-624-01, SAIC-T-5501
Inter-Building SAES-T-920, 18-SAMSS-625 (A) - (H)
Cable SAIC-T-5403, SAES-T-634
Single-mode NFPA 70 (NEC)
SAES-T-625, SAES-T-634
Fiber Optic SATIP-T-916-01, SAIC-T-5906
Building PDS SAES-T-920, 18-SAMSS-625 (A) - (H)
Cable SAES-T-634
NFPA 70 (NEC)
SAES-T-919, SAES-T-634
Fiber Optic SAES-T-920, 18-SAMSS-006 SATIP-T-624-01, SAIC-T-5501
Submarine (A) - (H)
Cable 18-SAMSS-008, 15-SAMSS-503 SAIC-T-5403, SAES-T-634
15-SAMSS-504, NFPA 70 (NEC)
SAES-T-624, SAES-T-625
SATIP-T-624-01,
SAES-T-632, SAES-T-634
Fiber Optic SATIP-T-938-01
SAES-T-919, 18-SAMSS-625
Cable SAIC-T-5501, SAIC-T-5405 (G)
18-SAMSS-006, 18-SAMSS-008
Accessories SAIC-T-5406, SAIC-T-5407
15-SAMSS-503, 15-SAMSS-504
SAIC-T-5801
NFPA 70 (NEC)

Page 46 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Table A-5005 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of
project quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and
temporary identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the
equipment, on equipment packaging and in documentation. The SH&P procedure shall address preservation
requirements ex-works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of indoor electronic equipment in shipping, handling, customs clearance, delivery,
storage, assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state
storage conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
COPPER handling. Special handling instructions shall be followed.
COMMUNICATIONS 5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for
CABLE ready access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration
and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved
QC procedure, manufacturer’s instructions, project specifications and MSAER’s
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical
damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving
inspection, etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and
preservation. Desiccant packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Cable reels shall be shipped, handled and stored on edges of flanges only (not on flat side of flanges). Reels shall
be chocked to prevent damage from rolling or shifting.
(B) Cable reels shall be shipped with a cable protective covering. Lifting equipment, tools, rope, slings, personnel
and soil shall not contact the cable or cable protective covering during shipping and handling. Mechanical force
or pressure shall not be applied to the cable surface during handling.
(C) Cables with an exposed metal sheath or armor shall be stored indoors.

Page 47 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

(D) Cable jacket material not tested and rated for exposure to sunlight shall be stored under a sunshade or indoors.
(E) Cable ends shall be sealed for water and dust, and firmly secured during shipping and storage. If cable ends are
exposed for on-reel testing or sampling, they shall be re-sealed and firmly secured for subsequent storage and
handling.
(F) Cable reels shall be supported off the ground and provided with a weatherproof, rain-tight, and dust-tight cover.
(G) Indoor equipment and materials shall be stored indoors; with environmental controls provided for water,
humidity, condensation, dust, solar radiation, and ambient temperature.
(H) Cables shall be tested on-the-reel, after delivery and prior to installation in accordance with SAES-T-629,
SAES-T-916, and SAES-T-634.
Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes
Copper OSP SAES-T-629 SATIP-T-628-01, SAIC-T-5501 (A) - (H)
Cable SAES-T-634, SAES-T-920 SAIC-T-5502, SAES-T-634
NFPA 70 (NEC)
Copper Building SAES-T-916 SATIP-T-628-01, SAIC-T-5501 (A) - (H)
Cable SAES-T-634,SAES-T-920 SAIC-T-5504,SAES-T-634
NFPA 70 (NEC)
Copper Building PDS Category 6 SAES-T-916, SAES-T-634 SATIP-T-916-01, SAIC-T-5501 (A) - (H)
Cable UTP/STP SAES-T-920, NFPA 70 (NEC) SAIC-T-5905, SAES-T-634
Copper SAES-T-916 SATIP-T-628-01, SATIP-T-916-01 (G)
Cable SAES-T-632, SAES-T-634 SATIP-T-938-01, SAIC-T-5501
Accessories SAES-T-920, NFPA 70 (NEC) SAIC-T-5505, SAIC-T-5907
SAIC-T-5908, SAIC-T-5909
SAIC-T-5910, SAIC-T-5801

Table A-5006 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of
project quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and
temporary identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the
equipment, on equipment packaging and in documentation. The SH&P procedure shall address preservation
requirements ex-works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
COMMUNICATIONS traceability, and quality of indoor electronic equipment in shipping, handling, customs clearance, delivery,
RACEWAY, storage, assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
CONDUIT,
acceptance of required QA/QC activities.
CABLE TRAY
AND General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
RACKING water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state
storage conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for

Page 48 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

ready access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration
and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved
QC procedure, manufacturer’s instructions, project specifications and MSAER’s
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical
damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving
inspection, etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and
preservation. Desiccant packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Indoor equipment and accessories shall be stored indoors; with environmental controls provided for water,
humidity, condensation, dust, solar radiation, and ambient temperature.
(B) Handling and storage of NEMA TC conduit and accessories shall be in accordance with manufacturers’ directions
and NEMA TC-B2.

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


SAES-T-916, SAES-P-104
Cable Tray BICSI TDMM, NFPA 70 (NEC), SATIP-T-916-01, SAIC-T-5901
NEMA VE2
SATIP-T-916-01, SAIC-T-5907
Equipment Racking SAES-T-916, BICSI TDMM
SAIC-T-5908, SAIC-T-5909 (A)
Cable Racking NFPA 70 (NEC), EIA/TIA
SAIC-T-5910
Conduit
SAES-T-911, SAES-T-624 SATIP-T-911-01, SAIC-T-5701
Ductbank
Cable Raceway Underground NEMA TC-B2, BICSI OSP DRM SAIC-T-5703, SAIC-T-5704 (B)
Innerduct
NFPA 70 (NEC) SAIC-T-5907
Manholes
Conduit
Above SAES-T-916, SAES-P-104 SATIP-T-916-01, SAIC-T-5902
Cable Raceway Wireway (A), (B)
Ground BICSI TDMM, NFPA 70 (NEC) SAIC-T-5903, SAIC-T-5904
Floor Duct
SATIP-T-911-01, SATIP-T-916-01
SAES-T-916, SAES-T-911 SAIC-T-5501, SAIC-T-5505
Accessories and SAES-P-104, BICSI TDMM SAIC-T-5705, SAIC-T-5707
(A)
Fittings BICSI OSP DRM, NFPA 70 SAIC-T-5708, SAIC-T-5907
(NEC) SAIC-T-5908, SAIC-T-5909
SAIC-T-5910

Page 49 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

INSTRUMENTATION
Table A-6001 Documentation Requirements
a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of project
quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and temporary
identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the equipment, on
equipment packaging and in documentation. The SH&P procedure shall address preservation requirements ex-
works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of equipment and materials in shipping, handling, customs clearance, delivery, storage,
assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
e) Handling, storage, and preservation data for equipment and materials shall be included in monthly Materials
Procurement Status reports and shall be available prior to shipping.
General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
INSTRUMENT
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
CONTROL requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
PANELS both temporary and permanent identification.
AND 3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state storage
CABINETS conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed. Personnel responsible for special handling, storage, and
preservation shall be fully qualified to do so, and supplied with predetermined work and inspection instructions.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for ready
access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications and MSAER’s
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving inspection,
etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and preservation. Desiccant
packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.

Page 50 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Specific Requirements
(A) All control panels and cabinets shall be stored indoors; with environmental controls provided for water, humidity,
condensation, dust, solar radiation, and ambient temperature.
(B) All control panel and cabinet openings shall be sealed. Threaded connections shall be protected with molded plastic
screwed plugs or caps.
(C) All control panels and cabinets shall be boxed or covered with a suitable plastic sheet.
Quality
Material/Equipment Type Size Specification Standards Requirements Notes
SATIP/Checklist
SAES-J-902, SAES-Z-001,
NFPA 70, NEC Art. 110.3(B) SATIP-J-902-05
34-SAMSS-820, 23-SAMSS-010 SATIP-J-902-06
Instrument Control SAES-J-505, SAES-J-510, SAIC-T-5001
All
Panels and Cabinets SAES-J-601, SAES-J-602, SAIC-P-3002
SAES-J-603, SAES-J-604, SAIC-J-6802
SAES-J-607, SAES-Z-003, SAIC-J-6803
SAES-Z-004, SAES-Z-008

Table A-6002 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of project
quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and temporary
identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the equipment, on
equipment packaging and in documentation. The SH&P procedure shall address preservation requirements ex-
works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of equipment and materials in shipping, handling, customs clearance, delivery, storage,
assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
e) Handling, storage, and preservation data for equipment and materials shall be included in monthly Materials
Procurement Status reports and shall be available prior to shipping.
FLOW
INSTRUMENTS General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state storage
conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed. Personnel responsible for special handling, storage, and
preservation shall be fully qualified to do so, and supplied with predetermined work and inspection instructions.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for ready
access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration, and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications, and MSAER’s.

Page 51 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving inspection,
etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and preservation.
Desiccant packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Flow instruments shall be stored indoors; with environmental controls provided for water, humidity, condensation,
dust, solar radiation, and ambient temperature.
(B) Flow instrument openings shall be sealed. Threaded connections shall be protected with molded plastic screwed
plugs or caps.
(C) Flow instruments shall be dried and cleaned after hydrostatic pressure testing.
(D) Flow instruments shall be prepared for shipping and storage by including desiccant with air-tight plastic shrink-
wrapping or equivalent.

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


SAES-J-100, API RP 551, SATIP-J-100-01,
Orifice Plate SAES-Y-101, 34-SAMSS-112, SAIC-T-5001, All
34-SAMSS-010 SAIC-J-6101
SAES-J-100, API RP 551, SATIP-J-100-01,
Orifice Flow Meter SAES-Y-101, 34-SAMSS-112, SAIC-T-5001, All
34-SAMSS-010 SAIC-J-6102
SATIP-J-100-01,
SAES-J-100, API RP 551,
Flow Nozzle SAIC-T-5001, All
34-SAMSS-010
SAIC-J-6103
SATIP-J-100-01,
SAES-J-100, API RP 551,
Venturi Tube SAIC-T-5001, All
34-SAMSS-010
SAIC-J-6104
SATIP-J-100-01,
Averaging SAES-J-100, API RP 551,
SAIC-T-5001, All
Pitot Element 34-SAMSS-010
SAIC-J-6105
SATIP-J-100-01,
SAES-J-100, API RP 551,
Integral Orifice SAIC-T-5001, All
34-SAMSS-010
SAIC-J-6106
SAES-J-100, API RP 551 SATIP-J-100-01,
Turbine Meter SAES-Y-103, 34-SAMSS-117, SAIC-T-5001, All
34-SAMSS-010 SAIC-J-6107
SAES-J-100, API RP 551 SATIP-J-100-01,
Positive
SAES-Y-103, 34-SAMSS-117, SAIC-T-5001, All
Displacement Meter 34-SAMSS-010 SAIC-J-6108
SATIP-J-100-01,
Magnetic Flow SAES-J-100, API RP 551,
SAIC-T-5001, All
Meter 34-SAMSS-010
SAIC-J-6109
SAES-J-100, API RP 551
Mass Meter SATIP-J-100-01,
SAES-Y-101, SAES-Y-103,
(Coriolis and SAIC-T-5001 All
34-SAMSS-112, 34-SAMSS-117,
Thermal) SAIC-J-6110
34-SAMSS-010
Ultrasonic SAES-J-100, API RP 551 SATIP-J-100-01, All

Page 52 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

(Transit Time and SAES-Y-101, SAES-Y-103 SAIC-T-5001,


Doppler) 34-SAMSS-112, 34-SAMSS-114, SAIC-J-6111
34-SAMSS-010
SATIP-J-100-01,
Vortex Shedding SAES-J-100, API RP 551,
SAIC-T-5001, All
Meter 34-SAMSS-010
SAIC-J-6112
SATIP-J-100-01,
Variable Area Meter SAES-J-100, API RP 551
SAIC-T-5001, All
(Rotameter) 34-SAMSS-117, 34-SAMSS-010
SAIC-J-6113
SAES-J-100, API RP 551
SATIP-J-100-01,
Flow Computer, MSC SAES-Y-101, SAES-Y-103, SABP-Y-856
SAIC-T-5001, All
Recorder/Indicator 34-SAMSS-841, 34-SAMSS-846,
SAIC-J-6016
34-SAMSS-851

Table A-6003 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of project
quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and temporary
identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the equipment, on
equipment packaging and in documentation. The SH&P procedure shall address preservation requirements ex-
works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of equipment and materials in shipping, handling, customs clearance, delivery, storage,
assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
e) Handling, storage, and preservation data for equipment and materials shall be included in monthly Materials
Procurement Status reports and shall be available prior to shipping.
General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
PRESSURE water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
INSTRUMENTS 2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state storage
conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed. Personnel responsible for special handling, storage, and
preservation shall be fully qualified to do so, and supplied with predetermined work and inspection instructions.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for ready
access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications and MSAER’s
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving inspection,

Page 53 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and preservation. Desiccant
packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Pressure instruments shall be stored indoors; with environmental controls provided for water, humidity,
condensation, dust, solar radiation, and ambient temperature.
(B) Pressure instrument openings shall be sealed. Threaded connections shall be protected with molded plastic screwed
plugs or caps.
(C) Pressure instruments shall be dried and cleaned after hydrostatic pressure testing.
(D) Pressure instruments shall be prepared for shipping and storage by including desiccant with air-tight plastic shrink-
wrapping or equivalent.

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


Pressure Gauges SAES-J-100, API RP 551 SATIP-J-200-01, SAIC-T-5001, SAIC-J-6201 All

Pressure Switches SAES-J-100, API RP 551 SATIP-J-200-01, SAIC-T-5001, SAIC-J-6202 All


Pressure SATIP-J-200-01,
SAES-J-100, API RP 551 All
Transmitters SAIC-T-5001, SAIC-J-6203
Differential Pressure SATIP-J-200-01,
SAES-J-100, API RP 551 All
Transmitter SAIC-T-5001, SAIC-J-6204
Recorder/Indicator SAES-J-100, API RP 551 SATIP-J-200-01, SAIC-T-5001, SAIC-J-6017 All

Table A-6004 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of project
quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and temporary
identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the equipment, on
equipment packaging and in documentation. The SH&P procedure shall address preservation requirements ex-
LEVEL works; by distributors, vendors, Contractors and in shipping.
INSTRUMENTS c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of equipment and materials in shipping, handling, customs clearance, delivery, storage,
assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
e) Handling, storage, and preservation data for equipment and materials shall be included in monthly Materials
Procurement Status reports and shall be available prior to shipping.

Page 54 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state storage
conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed. Personnel responsible for special handling, storage, and
preservation shall be fully qualified to do so, and supplied with predetermined work and inspection instructions.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for ready
access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications, and MSAER’s.
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving inspection,
etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and preservation.
Desiccant packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Level instruments shall be stored indoors; with environmental controls provided for water, humidity, condensation,
dust, solar radiation, and ambient temperature.
(B) Level instrument openings shall be sealed. Threaded connections shall be protected with molded plastic screwed
plugs or caps.
(C) Level instruments shall be dried and cleaned after hydrostatic pressure testing.
(D) Level instruments shall be prepared for shipping and storage by including desiccant with air-tight plastic shrink-
wrapping or equivalent.
Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes
Sight Glass SAES-J-100, API RP 551 SATIP-J-300-01,
All
Gauges/Switches 34-SAMSS-010 SAIC-T-5001, SAIC-J-6301
Magnetic SAES-J-100, API RP 551 SATIP-J-300-01,
All
Gauges/Switches 34-SAMSS-010 SAIC-T-5001, SAIC-J-6302
Displacement SAES-J-100, API RP 551 SATIP-J-300-01,
All
Instruments 34-SAMSS-010 SAIC-T-5001, SAIC-J-6303
Automatic Tank SAES-J-100, API RP 551, SAES-Y-301, SATIP-J-300-01,
All
Gauging (ATG) 34-SAMSS-319, 34-SAMSS-321 SAIC-T-5001, SAIC-J-6304
Ball Float SATIP-J-300-01,
SAES-J-100, API RP 551 All
Instrument SAIC-T-5001, SAIC-J-6305
Diff. Pressure SAES-J-100, API RP 551 SATIP-J-300-01,
All
Instruments 34-SAMSS-010 SAIC-T-5001, SAIC-J-6306

Page 55 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Capacitance SAES-J-100, API RP 551 SATIP-J-300-01,


All
Instruments 34-SAMSS-010 SAIC-T-5001, SAIC-J-6307
Nuclear Level SATIP-J-300-01,
SAES-J-100, API RP 551 All
Transmitters SAIC-T-5001
SATIP-J-300-01,
Level Switches SAES-J-100, API RP 551 All
SAIC-T-5001

Table A-6005 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of project
quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and temporary
identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the equipment, on
equipment packaging and in documentation. The SH&P procedure shall address preservation requirements ex-
works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of equipment and materials in shipping, handling, customs clearance, delivery, storage,
assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
e) Handling, storage, and preservation data for equipment and materials shall be included in monthly Materials
Procurement Status reports and shall be available prior to shipping.
General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
TEMPERATURE requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
INSTRUMENTS
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state storage
conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed. Personnel responsible for special handling, storage, and
preservation shall be fully qualified to do so, and supplied with predetermined work and inspection instructions.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for ready
access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications and MSAER’s
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving inspection,
etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and preservation. Desiccant
packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.

Page 56 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Specific Requirements
(A) Temperature instruments shall be stored indoors; with environmental controls provided for water, humidity,
condensation, dust, solar radiation, and ambient temperature.
(B) Temperature instrument openings shall be sealed. Threaded connections shall be protected with molded plastic
screwed plugs or caps.
(C) Temperature instruments shall be dried and cleaned after hydrostatic pressure testing.
(D) Temperature instruments shall be prepared for shipping and storage by including desiccant with air-tight plastic
shrink-wrapping or equivalent.

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


Temperature
SAES-J-100, API RP 551 SATIP-J-400-01, SAIC-T-5001 (A) (B) (D)
Transmitters
SAES-J-100, API RP 551 SATIP-J-400-01,
Thermowells All
34-SAMSS-010 SAIC-J-6401, SAIC-T-5001
Type E, Type J, SATIP-J-400-01,
Thermocouples SAES-J-100, API RP 551 (A) (B) (D)
and Type K SAIC-J-6402, SAIC-T-5001
Resistance
SATIP-J-400-01,
Temperature SAES-J-100, API RP 551 (A) (B) (D)
SAIC-J-6403, SAIC-T-5001
Detectors
Filled System SATIP-J-400-01,
SAES-J-100, API RP 551 (A) (B) (D)
Instruments SAIC-J-6404, SAIC-T-5001
Bimetallic SATIP-J-400-01,
SAES-J-100, API RP 551 (A) (B) (D)
Instruments SAIC-J-6405, SAIC-T-5001
SATIP-J-400-01,
Infrared Instruments SAES-J-100, API RP 551 (A) (B) (D)
SAIC-J-6406, SAIC-T-5001
Temperature SATIP-J-400-01,
SAES-J-100, API RP 551 (A) (B) (D)
Switches SAIC-T-5001
Multipoint
SATIP-J-400-01,
Indicators and SAES-J-100, API RP 551 (A) (B) (D)
SAIC-T-5001
Multiplexers

Table A-6006 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of project
quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
COMBUSTIBLE manufacturer instructions and recommendations. The I&T procedure shall address both permanent and temporary
identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the equipment, on
GAS AND equipment packaging and in documentation. The SH&P procedure shall address preservation requirements ex-
HYDROGEN works; by distributors, vendors, Contractors and in shipping.
SULFIDE c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
DETECTION traceability, and quality of equipment and materials in shipping, handling, customs clearance, delivery, storage,
assembly, installation, inspection, testing, and reinstatement.
SYSTEMS
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
e) Handling, storage, and preservation data for equipment and materials shall be included in monthly Materials
Procurement Status reports and shall be available prior to shipping.

Page 57 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state storage
conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed. Personnel responsible for special handling, storage, and
preservation shall be fully qualified to do so, and supplied with predetermined work and inspection instructions.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for ready
access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications and MSAER’s
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving inspection,
etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and preservation. Desiccant
packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Detection systems and instrumentation shall be stored indoors; with environmental controls provided for water,
humidity, condensation, dust, solar radiation, and ambient temperature.
(B) Detection system openings shall be sealed. Threaded connections shall be protected with molded plastic screwed
plugs or caps.
(C) Detection systems and instrumentation shall be prepared for shipping and storage by including desiccant with air-
tight plastic shrink-wrapping or equivalent.
(D) Detection instrumentation and components typically have a finite lifespan (expiration date) from the date of
manufacture. Manufacturer and Vendor requirements for product expiration date shall be addressed by Contractor
in scheduling procurement, shipping, delivery, storage, installation, and commissioning.
(E) Manufacturer requirements for detection system, test gas expiration date shall be followed.

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


SATIP-J-505-01,
Detection Systems SAES-J-505, 34-SAMSS-514 All
SAIC-J-6921, SAIC-T-5001
Detection SATIP-J-505-01,
SAES-J-505, 34-SAMSS-514 All
Instruments SAIC-J-6921, SAIC-T-5001

Page 58 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Table A-6007 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of project
quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and temporary
identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the equipment, on
equipment packaging and in documentation. The SH&P procedure shall address preservation requirements ex-
works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of equipment and materials in shipping, handling, customs clearance, delivery, storage,
assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
e) Handling, storage, and preservation data for equipment and materials shall be included in monthly Materials
Procurement Status reports and shall be available prior to shipping.
General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
CONTROL 3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state storage
conditions, date of shipment, and the date beyond which the equipment must not be stored.
VALVES
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
AND handling. Special handling instructions shall be followed. Personnel responsible for special handling, storage, and
ACTUATORS preservation shall be fully qualified to do so, and supplied with predetermined work and inspection instructions.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for ready
access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications and MSAER’s
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving inspection,
etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and preservation.
Desiccant packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Actuators, positioners and other accessories shall be procured as part of the valve purchase order. Control valve
manufacturers shall be responsible for packaging and guaranteeing assembly.
(B) All machined or threaded surfaces subject to atmospheric corrosion during shipment or storage shall be treated with
easily removable rust preventive. Flange protectors shall fully cover gasket contact surfaces.
(C) Tubing systems shall be protected to prevent any damage during shipment. Actuator enclosures, tube-end openings,

Page 59 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

threaded connections and fittings shall be sealed by molded plastic plugs, plastic caps, or PVC tape.
(D) Control valves, actuators and accessories shall be stored in an enclosed building that provides protection from blown
dust, mud, rain, etc. Valves and actuators with electronic components shall be stored indoors; with environmental
controls provided for water, humidity, condensation, dust, solar radiation, and ambient temperature.
(E) New control valves are hydrostatic pressure tested by the manufacturer. There is no need to hydro-test new control
valves in the field. Control valves shall be dried and cleaned after hydrostatic pressure testing.
(F) Control valves, actuators, and accessories shall be stored above grade or above finished floor using suitable pallets.
(G) Control valve and actuator electrical cabinets, enclosures and junction boxes shall be closed and monitored for
moisture, to ensure dryness. Desiccant bags shall be used inside electrical cabinets, enclosures, and boxes to prevent
damage from moisture.
(H) To prevent moisture condensation in actuators and hydraulic power units with electric motors (stored in
uncontrolled, potentially humid environments) space heating must be utilized. Space heating should maintain motor
winding temperature at a minimum of 5°C above ambient temperature.
i. If factory-installed space heaters are supplied by the manufacturer, they should be energized and monitored
while in storage. Manufacturers shall label enclosures with permanent space heater power, voltage, and current
parameters, to alert personnel to supply electrical power to the heater.
ii. If factory space heaters are not provided, manufacturers may require single-phase "trickle" heating be utilized
(energizing one phase of the motor's winding with a low voltage).
iii. As a third option, manufacturers may require the use of temporary, auxiliary space heaters located inside
packaging or inside the enclosure.
(I) If hydraulic actuators or power units are to be stored for more than three (3) months, then fluid reservoirs shall be
completely filled with hydraulic fluid (per manufacturer’s instructions). Storage fluid shall be tested prior to
commissioning and startup (34-SAMSS-717).
(J) Manufacturer’s special shipping and handling procedures shall be followed for linear actuators equipped with gas
hydraulic tanks (to prevent the loss of hydraulic fluid when shipped in a horizontal position).

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


SATIP-J-700-01,
Motor Operated SAIC-J-6701
All 34- SAMSS-718 (A) – (H)
Valve Actuators SAIC-P-3407
SAIC-T-5001
SATIP-J-700-01,
SAES-J-700
Control Valves All SAIC-J-6701 All
34-SAMSS-711
SAIC-T-5001
Pneumatic On-Off SATIP-J-700-01,
and Hydraulic Valve 34-SAMSS-716 SAIC-J-6701,
All All
Actuators, Hydraulic 34-SAMSS-717 SAIC-P-3407
Power Units SAIC-T-5001

Table A-6008 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of project
quality planning.
PROCESS b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and temporary
ANALYZER identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the equipment, on
SYSTEMS equipment packaging and in documentation. The SH&P procedure shall address preservation requirements ex-
works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of equipment and materials in shipping, handling, customs clearance, delivery, storage,

Page 60 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

assembly, installation, inspection, testing, and reinstatement.


d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
e) Handling, storage, and preservation data for equipment and materials shall be included in monthly Materials
Procurement Status reports and shall be available prior to shipping.
General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state storage
conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed. Personnel responsible for special handling, storage, and
preservation shall be fully qualified to do so, and supplied with predetermined work and inspection instructions.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for ready
access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration, and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications, and MSAER’s.
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving inspection,
etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and preservation.
Desiccant packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Process analyzer systems shall be fabricated, prepared, and packaged for shipping and handling in accordance with
equipment manufacturers and system fabricator instructions, to ensure safe delivery and installation without
internal or external damage.
(B) Installed equipment, fixtures, and components that may move, shift or vibrate during system shipment, handling and
installation shall be braced, secured, and supported prior to shipment.
(C) Manufacturers’ special instructions for fragile or sensitive equipment shall be followed. If required, fragile and
sensitive equipment shall be removed from the system, and packaged and shipped separately.
(D) Desiccant materials shall be placed inside all electronic enclosures prior to packaging and shipping.
(E) All piping and tubing shall be cleaned, dried with instrument air or nitrogen, and plugged or capped prior to shipment.
(F) All valves shall be in the closed position. All flange connections shall be covered with metal cover plates.
(G) Process analyzer systems shall be stored indoors; with environmental controls provided for water, humidity,
condensation, dust, solar radiation and ambient temperature. Process analyzer system HVAC units shall be
temporarily powered and monitored when indoor climate-controlled storage is substandard.
(H) Process analyzer systems shall be prepared, packaged, and protected for extended periods of jobsite storage.
(I) Process analyzer equipment and consumables may have a finite lifespan (expiration date) from the date of
manufacture. Manufacturer requirements for expiration dates shall be addressed by Contractor and Fabricator in
scheduling fabrication, delivery, storage, installation and commissioning.

Page 61 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


SATIP-J-902-03,
SAES-J-902,
SAIC-P-3002
SAES-J-510,
Process Analyzer SAIC-T-5001
34-SAMSS-510, All
Systems SAIC-J-6019
34-SAMSS-514,
SAIC-J-6020
12-SAMSS-014
SAIC-J-6021

Table A-6009 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of
project quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and
temporary identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the
equipment, on equipment packaging and in documentation. The SH&P procedure shall address preservation
requirements ex-works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of equipment and materials in shipping, handling, customs clearance, delivery, storage,
assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
e) Handling, storage, and preservation data for equipment and materials shall be included in monthly Materials
Procurement Status reports and shall be available prior to shipping.
General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
METALLIC 2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
INSTRUMENTATION requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
AND both temporary and permanent identification.

CONTROL CABLE 3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state
storage conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed. Personnel responsible for special handling, storage, and
preservation shall be fully qualified to do so, and supplied with predetermined work and inspection instructions.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for
ready access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration
and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications and MSAER’s
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical
damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving
inspection, etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and preservation.
Desiccant packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,

Page 62 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

unloading and handling.


11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Cable reels shall be packaged and shipped with a weatherproof (rain- and dust-tight) cable protective covering.
Lifting equipment, tools, rope, slings, personnel and soil shall not contact the cable or cable protective covering
during shipping and handling. Mechanical force or pressure shall not be applied to the cable surface during handling.
(B) Cable ends shall be sealed (waterproof and dustproof) and firmly secured during shipping and storage.
(C) Cable reels shall be shipped, handled and stored on edges of flanges only (not on flat side of flanges). Reels shall
be chocked to prevent damage from rolling or shifting.
(D) Cable shall be stored indoors; with environmental controls provided for water, humidity, condensation, dust, solar
radiation, and ambient temperature.
(E) Cable reels shall be stored to provide easy access for lifting and moving.
(F) Cable reels shall be stored away from open flame, fire, arc welding, brazing, grinding, and other sources of high
heat or ignition.
(G) If cable ends are exposed for on-reel testing or sampling, they shall be re-sealed (waterproof and dustproof) and
firmly secured during storage and handling.
Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes
SATIP-J-902-01
Copper Cores in Pairs, Shielded and Twisted and SAES-J-902, NFPA 70 (NEC)
All SAIC-P-3201, SAIC-J-6601, All
Triads or Bundles Unshielded untwisted 34-SAMSS-913
SAIC-J-6602
Metallic Alloys Thermocouple SAES-J-902, NFPA 70 (NEC) SATIP-J-902-01,
All All
other than Copper Extension Cable 34-SAMSS-913 SAIC-P-3201, SAIC-J-6603
Copper Cores in Axial
Coaxial and Twin SAES-J-902, NFPA 70 (NEC) SATIP-J-902-01,
configuration for high All All
axial Data Cable 34-SAMSS-913 SAIC-P-3201, SAIC-J-6604
frequency
Gland connectors,
insulation tubing &
tape; straps & ties; SATIP-J-902-01,
Cable Accessories All SAES-J-902, NFPA 70 (NEC) All
wire connectors; SAIC-J-6805
termination kits;
cable & duct seal

Table A-6010 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of project
quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and temporary
identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the equipment,
FIBER OPTIC on equipment packaging and in documentation. The SH&P procedure shall address preservation requirements
CABLE FOR ex-works; by distributors, vendors, Contractors, and in shipping.
PROCESS c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
CONTROL traceability, and quality of equipment and materials in shipping, handling, customs clearance, delivery, storage,
assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
e) Handling, storage, and preservation data for equipment and materials shall be included in monthly Materials
Procurement Status reports and shall be available prior to shipping.

Page 63 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s for
both temporary and permanent identification.
3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state storage
conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed. Personnel responsible for special handling, storage, and
preservation shall be fully qualified to do so, and supplied with predetermined work and inspection instructions.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for ready
access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved QC
procedure, manufacturer’s instructions, project specifications, and MSAER’s.
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving inspection,
etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and preservation.
Desiccant packing materials exposed to moisture or humidity shall be replaced with new materials.
10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of shipment,
unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Cable reels shall be packaged and shipped with a weatherproof (rain- and dust-tight) cable protective covering.
Lifting equipment, tools, rope, slings, personnel and soil shall not contact the cable or cable protective covering during
shipping and handling. Mechanical force or pressure shall not be applied to the cable surface during handling.
(B) Cable ends shall be sealed (waterproof and dustproof) and firmly secured during shipping and storage.
(C) Cable reels shall be shipped, handled and stored on edges of flanges only (not on flat side of flanges). Reels shall be
chocked to prevent damage from rolling or shifting.
(D) Cable shall be stored indoors; with environmental controls provided for water, humidity, condensation, dust, solar
radiation, and ambient temperature.
(E) Cable reels shall be stored to provide easy access for lifting and moving.
(F) Cable reels shall be stored away from open flame, fire, arc welding, brazing, grinding, and other sources of high heat
or ignition.
(G) Cables shall be tested on-the-reel, after delivery and prior to installation in accordance with EIA/RS-455. Cable ends
exposed for on-reel testing or sampling shall be re-sealed (waterproof and dustproof) and firmly secured.
Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes
SAES-J-902, NFPA 70 (NEC) SATIP-J-902-04
On-Shore Indoor,
Fiber Optic Cable SAES-Z-020, EIA/RS-455, SAIC-T-5501 All
Single-mode Outdoor
BICSI TDMM, BICSI COOP SAIC-J-6622, SATR-J-6621
SAES-J-902, NFPA 70 (NEC) SATIP-J-902-04
On-Shore Indoor,
Fiber Optic Cable SAES-Z-020, EIA/RS-455, SAIC-T-5501 All
Multimode Outdoor
BICSI TDMM, BICSI COOP SAIC-J-6622, SATR-J-6621

Page 64 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

SAES-J-902, NFPA 70 (NEC) SATIP-J-902-04


Submarine
Fiber Optic Cable SAES-Z-020, EIA/RS-455, SAIC-T-5501 All
Cable
BICSI COOP SAIC-J-6622, SATR-J-6621
Connector and
terminal kits; SAES-J-902, NFPA 70 (NEC)
Fiber Optic SATIP-J-902-04
straps and ties; SAES-Z-020, EIA/TIA-568, All
Cable Accessories SAIC-J-6623
lubricant; cable BICSI TDMM, BICSI COOP
and duct seal.

Table A-6011 Documentation Requirements


a) Quality procedures for Storage, Handling and Preservation (SH&P) and Identification and Traceability (I&T) of
equipment and materials, including partially fabricated assemblies, shall be provided and approved as part of
project quality planning.
b) The procedures shall adopt and implement requirements from applicable MSAER’s, project specifications,
manufacturer instructions and recommendations. The I&T procedure shall address both permanent and
temporary identification requirements (e.g., anti-theft, anti-tampering and anti-counterfeiting devices) – on the
equipment, on equipment packaging and in documentation. The SH&P procedure shall address preservation
requirements ex-works; by distributors, vendors, Contractors and in shipping.
c) The procedures shall schedule required inspections, testing and QA/QC resources for preserving identification,
traceability, and quality of equipment and materials in shipping, handling, customs clearance, delivery, storage,
assembly, installation, inspection, testing, and reinstatement.
d) The procedures shall specify the documentary evidence to be issued and maintained on implementation and
acceptance of required QA/QC activities.
e) Handling, storage, and preservation data for equipment and materials shall be included in monthly Materials
Procurement Status reports and shall be available prior to shipping.
General Requirements
1) Prior to shipping, equipment and materials are suitably packaged with compliant packing materials for handling,
water, humidity, condensation, dust, chemical contaminates, solar radiation and ambient temperature.
INSTRUMENTATION 2) Equipment and materials (including packaging and documentation) are labeled and identified in compliance with
requirements of the approved QC procedure, manufacturer’s instructions, project specifications, and MSAER’s
TUBING for both temporary and permanent identification.
AND FITTINGS 3) Shipping crates shall be marked with handling and storage instructions. Labels on shipping crates shall state
storage conditions, date of shipment, and the date beyond which the equipment must not be stored.
4) Personnel shall be fully aware of manufacturer's special handling instructions prior to shipping, unloading or
handling. Special handling instructions shall be followed. Personnel responsible for special handling, storage,
and preservation shall be fully qualified to do so, and supplied with predetermined work and inspection
instructions.
5) Equipment and materials are handled, placed, and stored in accordance with manufacturer requirements for
ready access, foundation- / floor- / shelf-loading, stacking, orientation, leveling, rigging, lifting, moving, vibration,
and impact.
6) Equipment and materials are stored in a secured area that is in compliance with requirements of the approved
QC procedure, manufacturer’s instructions, project specifications and MSAER’s
7) Equipment and materials are not stored in an area with water sources, flammable materials, chemical vapors,
construction equipment, road traffic, falling, or flying objects, and where there is a risk of flooding or physical
damage.
8) Equipment, materials, and accessories are readily traceable and verifiable to the manufacturer through shipping,
handling, customs clearance, distribution, delivery, storage, assembly, installation, testing, and reinstatement.
9) Equipment and materials packaging that is damaged or disturbed (e.g., for customs clearance, receiving
inspection, etc.) is timely repaired and fully reinstated for subsequent shipping, handling, storage and
preservation. Desiccant packing materials exposed to moisture or humidity shall be replaced with new materials.

Page 65 of 66
Document Responsibility: Project Quality Standards Committee SAEP-385
Issue Date: 25 October 2017
Next Planned Update: 25 October 2020 Preservation of Project Materials and Equipment

10) Equipment and materials shall be inspected for visible damage by Contractor QC prior to acceptance of
shipment, unloading and handling.
11) Equipment and materials in storage shall be inspected by Contractor QC on a weekly basis.
Specific Requirements
(A) Tubing drums, reels and fittings shall be packaged, shipped and stored with a weatherproof (rain- and dust-tight)
protective covering. Lifting equipment, tools, rope, slings, personnel and soil shall not contact the tubing
protective covering during shipping and handling. Mechanical force or pressure shall not be applied to the
tubing during handling.
(B) Tube ends shall be sealed (waterproof and dustproof) and firmly secured during shipping and storage.
(C) Tubing drums and reels shall be shipped, handled and stored on edges of flanges only (not on flat side of
flanges). Drums and reels shall be chocked to prevent damage from rolling or shifting.
(D) Tube fittings shall be protected to prevent any contamination or damage during shipment and storage.
Fitting openings and threaded connections shall be sealed with molded plastic plugs or caps.
(E) Tubing and fittings shall be stored either indoors or under a sunshade. Jacketed and insulated tubing shall not be
stored where exposed to sunlight.
(F) Tube fittings shall be stored above grade or above finished floor using suitable pallets.
(G) Instrument tubing drums and reels shall be stored to provide easy access for lifting and moving.
(H) Instrument tubing and fittings shall be stored away from open flame, fire, arc welding, brazing, grinding, and
other sources of high heat or ignition.
(I) Fabricator or jobsite pressure testing of instrumentation tubing shall be in accordance with SAES-L-150, using dry
instrument air or inert gas.
(J) Hydrostatic pressure testing of instrument air piping and tubing is not permitted.
(K) When pneumatic testing is not practical, testing with liquid is permitted for instrument impulse tubing.
Impulse tubing shall be flushed of all liquid and debris and shall be blown dried. If water is the testing media,
its quality shall not affect the integrity of impulse tubing.

Material/Equipment Type Size Specification Standards Requirements Quality SATIP/Checklist Notes


SAES-J-003, SAES-J-510, SATIP-J-003-01, SAIC-J-6001,
Copper Alloy Tubing All
SAES-J-901 SAIC-J-6002, SAIC-J-6004
Stainless Steel Alloy SAES-J-003, SAES-J-510, SATIP-J-003-01, SAIC-J-6001,
Type 316 SS All
Tubing SAES-J-901 SAIC-J-6002, SAIC-J-6004
SATIP-J-003-01, SAIC-J-6001,
SAES-J-003, SAES-J-510,
Accessories and Fittings SAIC-J-6002, SAIC-J-6003, All
SAES-J-901
SAIC-J-6004, SAIC-J-6005

Page 66 of 66