Engineering and Technology Department: Masonry Works For Second Floor (Phase 1 & Phase 2)
Engineering and Technology Department: Masonry Works For Second Floor (Phase 1 & Phase 2)
Anthony’s College
ENGINEERING AND TECHNOLOGY DEPARTMENT
San Angel, San Jose, Antique
Number
SECOND FLOOR Length Height Area
of Units
14 4m 3.00m 168 m2
Total Area = A1 −¿ A2
A. MATERIALS
FOR CHB MORTAR per m2
Class A
Multiplier Quantity
Mixture
Portland Cement 0.792 387.04 say 388 bags
Washed Sand 1:02:04 0.0435 21.26 say 22 m3
4"x 8"x 16"CHB 12.5 6108.63 say 6109 pcs.
262
St. Anthony’s College
ENGINEERING AND TECHNOLOGY DEPARTMENT
San Angel, San Jose, Antique
1 working day
25.90 hrs × =3.24 say 4 days
8 hrs
263
St. Anthony’s College
ENGINEERING AND TECHNOLOGY DEPARTMENT
San Angel, San Jose, Antique
1 working day
45.87 hrs× =5.73 say 6 days
8 hrs
Plastering of CHB
MH
Average Productivity Rate 2.40
m2
Laborers 20 persons
58.64 hours
DURATION
8 days
1 working day
58.64 hrs × =7.33 say 8 days
8 hrs