You are on page 1of 3

St.

Anthony’s College
ENGINEERING AND TECHNOLOGY DEPARTMENT
San Angel, San Jose, Antique

MASONRY WORKS for SECOND FLOOR


(Phase 1 & Phase 2)

Number
SECOND FLOOR Length Height Area
of Units

14 4m 3.00m 168 m2

4 20m 3.00m 240 m2


4"x 8"x 16"CHB
2 21m 3.00m 126 m2

1 25m 1.70m 42.5 m2

AREA (A1) 576.50 m2

LESS Doors & Windows

Doors 21 0.90m 2.10m 39.69 m2

Bathroom Doors 11 0.80m 2.10m 18.48 m2

Window 2 14 1.60m 1.20m 26.88 m2

Window 3 2 2.40m 1.20m 5.76 m2

AREA (A2) 87.81 m2

Total Area = A1 −¿ A2

TOTAL AREA 488.69 m2

A. MATERIALS
FOR CHB MORTAR per m2
Class A
Multiplier Quantity
Mixture
Portland Cement 0.792 387.04 say 388 bags
Washed Sand 1:02:04 0.0435 21.26 say 22 m3
4"x 8"x 16"CHB 12.5 6108.63 say 6109 pcs.

262
St. Anthony’s College
ENGINEERING AND TECHNOLOGY DEPARTMENT
San Angel, San Jose, Antique

FOR CHB PLASTER per sq. m.


Class A
2 sides using 12mm thickness plaster Multiplier Quantity
Mixture
Portland Cement 0.216 105.56 say 106 bags
1:02:04
Washed Sand 0.012 5.86 say 6m3

REINFORCEMENT FOR CHB per sq. m.


No. of 6m
Spacing @ 60cm Area Multiplier Length Weight
Length
10mm horizontal bar
2.13 1040.91m 173.49 say 174 643.8 kg
(W = N x 3.70)
10 mm vertical bar
488.69 m2 2.15 1050.68m 175.11 say 176 651.2 kg
(W = N x 3.70)
#16 GI tie wire (30 cm
0.032 15.64 kg
tie)
TOTAL 350 bars 1310.64 kg

B. LABOR Data Unit


Laying of 4" CHB
MH
Average Productivity Rate 1.06
m2
Laborers 20 persons
25.90 hours
DURATION
4 days

Ave . Productivity Rate ×total area 1.06 (488.69)


= =25.90 hrs
Laborers 20

1 working day
25.90 hrs × =3.24 say 4 days
8 hrs

263
St. Anthony’s College
ENGINEERING AND TECHNOLOGY DEPARTMENT
San Angel, San Jose, Antique

Placing of Reinforcement bars


MH
Average Productivity Rate 0.70
kg
Laborers 20 persons
45.87 hours
DURATION
6 days

Ave . Productivity Rate ×total weight 0.70 (1310.64)


= =45.87 hrs
Laborers 20

1 working day
45.87 hrs× =5.73 say 6 days
8 hrs

Plastering of CHB
MH
Average Productivity Rate 2.40
m2
Laborers 20 persons
58.64 hours
DURATION
8 days

Ave . Productivity Rate ×total area 2.40 (488.69)


= =58.64 hrs
Laborers 20

1 working day
58.64 hrs × =7.33 say 8 days
8 hrs

TOTAL DURATION 18 days

264

You might also like