Pipe

The document outlines the steps for mud circulation, pressure testing, pumping various fluids, dropping plugs to land on collars, displacing fluids, waiting on cement, and ensuring circulation for single and two stage cementing jobs.

Uploaded by

Mostafa Ibrahim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views1 page

Pipe

The document outlines the steps for mud circulation, pressure testing, pumping various fluids, dropping plugs to land on collars, displacing fluids, waiting on cement, and ensuring circulation for single and two stage cementing jobs.

Uploaded by

Mostafa Ibrahim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Summery

1. Mud circulation 1. Mud circulation


2. Pressure test 2. Pressure test
3. Pumping wash 3. Pumping wash
4. Pumping spacer 4. Pumping spacer
5. Drop bottom plug to land on the float collar 5. Pumping slurry
6. Pump lead slurry 6. Drop first-stage plug (Indicating Plug) to land on the float collar
7. Pump tail slurry 7. Displacement
8. Drop top plug to land on the Bottom plug 8. Bleed off & check returns
9. Displacement 9. Drop opening bomb (trip plug) to land on the D.V
10. Bleed off & check returns 10. Establish circulation
11. WOC (12 hrs.) 11. WOC and Keep circulation (12 hrs)
12. Pump wash
13. Pump slurry
Single Stage 14. Drop closing plug (Shutt off Plug) to land on the Opening Bomb
15. Displacement
16. Bleed off & check returns
17. WOC (12 hrs)
Two Stages
WOC for production cementing: 24 hrs.
1