Professional Documents
Culture Documents
Objective:
The objective of this manual is,
1. To provide an easy to follow, step-by-step, comprehensive guide to assist in performing safe tanker
operations.
2. To assist newly joined and trainees to familiarize with vessel’s arrangements and procedures.
General:
The vessel is supplied with shipbuilder’s plans and manufacturer’s instruction manuals, there is no
single document which gives guidance on operating complete systems as installed on board. The
purpose of this manual is to assist, inform and guide competent vessel’s staff and trainees in the
operation of the systems and equipment on board and to provide additional information that may
not be otherwise available. In some cases, the competent vessel’s staff and trainees may be initially
unfamiliar with this vessel and the information in this manual is intended to accelerate the
familiarization process. This manual is intended as a guide and to be used in conjunction with
shipyard drawings, manufacturer’s instruction manuals and iDMS. This manual in no way replaces or
supersedes these publications, all of which take precedence over this manual.
Issue and Update
Introduction
Issue and Update
Index of Sections (Page 1 to 6)
Section 1 – Ship’s Equipment and Arrangements (Page 1 to 9)
1.1. Principal Particulars of Ship
1.2. Cargo Tank Groups and Layout
1.3. Cargo Piping
1.3.1. Loading
1.3.2. Discharging
1.3.3. Bellmouth Arrangement
Diagram
1.3.i. Cargo Piping
1.4. Cargo Pump Details
1.5. Cargo Stripping and Draining Arrangement
1.5.1. Automatic Unloading System
1.5.2. Cargo Eductor
1.5.3. Stripping Pump
1.6. Venting System
1.6.1. Venting Arrangement
1.6.2. Primary and Secondary Venting Arrangement
1.7. Inert Gas Plant
1.8. Cargo Transfer Limitations
1.8.1. Max Loading Rate
1.8.2. Max Un-loading Rate
1.9. Trim and Stability Restrictions
1.10. Tank Cleaning System
1.11. Heating System
1.12. Ballast System
1.12.1. Ballast Tank Layout
1.12.2. Ballast Pump and Piping Arrangement
1.13. Valve Remote Control System
1.14. High Level and Overfill Alarm System
1.15. Pump Room Ventilation System
Section 2 – Procedures
2.1. Loading – Single Grade (Page 1 to 9)
2.1.1. Initial Preparation
2.1.2. Starting Procedure
2.1.3. Procedure and Precautions During Bulk Stage
2.1.4. Procedure for Topping-Off Tanks
Rev. 0.0 1
Index of Sections
Section 3 - Annexure
3.1. Vapor Emission Control System (Page 1 to 4)
3.1.1. Requirement
3.1.2. Initial Preparation
3.1.3. Procedure and Precautions at Load Port
3.1.4. Procedure and Precautions While Discharging at Off-Shore Lightering Area
3.2. Management of Heated Cargo (Page 1 to 8)
3.2.1. Initial Preparation
3.2.2. Starting Procedure
3.2.3. Stopping Procedure
3.2.4. Procedure and Precaution During Voyage
3.2.5. General Precautions
3.3. Disposal of Pump Room Bilges (Page 1 to 3)
3.3.1. Requirement
3.3.2. Disposal Procedure
3.4. Management of Low Sulphur Wax Residue (LSWR) (Page 1 to 3)
3.4.1. Initial Preparation
3.4.2. Procedures and Precautions During Loading
3.4.3. Procedures and Precautions During Voyage
3.4.4. Procedures and Precautions During Discharging
3.5. Shore Line Flushing (Page 1 to 8)
3.5.1. Requirement and Method
3.5.2. Method 1 - By Pumping Sea Water Stored in Either Slop Tank or any Cargo Tank
Rev. 0.0 5
Index of Sections
3.5.3. Method 2 - By Pumping Sea Water Directly from Cargo Sea Chest
3.6. Management of High-Density Cargo (Page 1)
3.7. Blending and Comingling (Page 1 to 8)
3.7.1. Definition and Statutory Regulation
3.7.2. In-Line Mixing Method
3.7.3. Weighted Mixing Method
3.7.4. Internal Transfer Method
3.8. Internal Transfer of Cargo (Page 1 to 5)
3.8.1. Initial Preparation
3.8.2. Method 1 – Transfer by Gravity
3.8.3. Method 2 – Transfer using Cargo Pump and Drop Line
Diagram
3.8.i. Line Diagram for Method 2 – Transfer using Cargo Pump and Drop Line
3.9. Cargo Handling in Cold Climate (Page 1 to 2)
3.9.1. Preparation Prior Arrival Cold Climate Area
3.9.2. Precautions while Handling Cargo in Cold Climate
3.9.3. Precautions while Handling Ballast in Cold Climate
3.10. Cargo Calculation (Single Grade and Comingled Cargo) (Page 1 to 6)
3.10.1. Formulas and Terminology
3.10.2. Procedure for Calculating Weight of Cargo
3.10.3. Procedure for Calculating Draft
3.10.4. Procedure for Calculating Maximum Loadable
3.10.5. Procedure for Calculating Approximate Density of Commingled Cargo
3.10.6. Wedge Formula for Calculation of ROB
3.11. Precautions During Ballast Water Exchange Process (Page 1)
3.12. Precautions During Heavy Weather Ballasting (Page 1)
3.13. Sample Tank Cleaning Plan (Page 1 to 3)
3.14. Standard Port Log Entry Format (Page 1 to 6)
3.14.1. Standard Entries in Port Log
3.14.2. Port Log Sample
3.15. Alarms and Actions (Page 1 to 3)
3.16. Additional Notes to Reader (Page 1 to 2)
3.16.1. Free Surface Effect and Cargo Sloshing
3.16.2. Navigation Bridge Visibility (Blind Distance)
3.16.3. Difference between HVV and PV valve
Rev. 0.0 6
Section 1
Ship’s Equipment
and Arrangements
Section 1 - Ship’s Equipment & Arrangements
Slp No 6 No 5 No 4 No 3 No 2
No 1
(Port) (Port) (Port) (Port) (Port) (Port)
(Port)
Slp No 6 No 5 No 4 No 3 No 2 No 1
(Stbd) (Stbd) (Stbd) (Stbd) (Stbd) (Stbd) (Stbd)
Rev. 0.0 1
Section 1 - Ship’s Equipment & Arrangements
225 mm
30 mm
COT bell-mouth arrangement (Fig-1) Slop Tank cross section (Fig-2)
Rev. 0.0 2
Section 1 - Ship’s Equipment & Arrangements
Rev. 0.0 3
Section 1 - Ship’s Equipment & Arrangements
Rev. 0.0 4
Section 1 - Ship’s Equipment & Arrangements
Scanjet
24 mm 8 Kg/cm2 60 m3 /hr 1 per tank
Slop Tank SC90T2
(P & S) Scanjet
2 x 16 mm 8 Kg/cm2 30 m3 /hr 3 per tank
SC 45TW
Scanjet
Retention Tank 2 x 16 mm 8 Kg/cm2 30 m3 /hr 1 Unit
SC 45TW
Rev. 0.0 5
Section 1 - Ship’s Equipment & Arrangements
Rev. 0.0 6
Section 1 - Ship’s Equipment & Arrangements
Maker Damcos
Pump Capacity 9.5 L/min
No. of Pumps 2
Working Pressure 135 Bar
Tank Capacity 200 L
Ambient Working
0-45o C
Temperature
Low Oil Pressure 130 Bar
Valve Remote Control System details (Fig-8)
Rev. 0.0 7
Section 1 - Ship’s Equipment & Arrangements
Rev. 0.0 8
Section 1 - Ship’s Equipment & Arrangements
Rev. 0.0 9
Section 2
Procedures
2.1. Loading – Single Grade
2.1. Loading – Single Grade
Conduct DRA
Risk Involved:
a. Excess loading/ Inter-tank
migration
b. Toxic exposure/ Oil Spill
c. Fire and explosion
Associated Procedural Hazards: iDMS – Cargo instructions and vessel’s
a. Damage due to pressure surge Ship stability- loading manual instructions
b. Tank overflow
must be adhered while referring to
Responsible Authority: following:
a. Chief Officer
a. Cargo nomination as per Charterers
Task Performer: instruction.
a. Chief Officer overall in charge
(Supervising)
b. Calculate cargo for highest loading
Planning temperature for the voyage and/or any
b. Duty Officer (Monitoring)
c. Deck crew (Assisting) heating instruction during voyage
c. Satisfy IMO Stability criteria *
d. Stresses (SF and BM in sea going
Prepare stowage and loading
condition) limits as per iDMS
plan
e. Draft restriction at load port, discharge
port or during the voyage due transiting
Verify initial loading rate, seasonal zones. **
topping-off rate, maximum f. List and trim correction tanks ^
loading rate and venting rate g. Topping off sequence
from loading manual and h. Restriction on Cargo Density
VECS manual. i. Air Draft restriction***
Note:
* - Please refer MARPOL Annex 1, Regulation 27
for Intact stability criteria.
** - Check Draft restriction from load port and
discharge port agent/guide to port entry/with
business unit/same must be confirmed during
ship shore key meeting.
*** - Check air draft restriction with load port
and discharge port agent, confirm same during
Tanks are inerted with ship shore key meeting.
positive pressure & Oxygen For calculation of Air Draft, refer iDMS section
Tank content below 8% by volume. “IMS-MO-NAV-NS-ADC-Sec 4.4”
Preparation ^ - Cargo tanks shall be selected basis reserve
ullage space, trimming and listing moment of the
Vapor tight integrity verified tank. Tanks positioned amidships are most
suited trimming tanks and these shall be loaded
towards the end. In some cases where vessel
has no draft restriction, ballast tanks can be used
for trim and list correction in order to
accommodate the entire nominated cargo
Rev. 0.0 1
2.1. Loading – Single Grade
Alarm &
Tank high level (95%) and independent overfill/high high-
Gauging
level alarm tested.
System
Tank pre high-pressure, high-pressure, pre low-pressure
and low-pressure alarm tested.
Refer – SOLAS chapter 2-II, Regulation 11 and VIQ chapter
8
Emergency
Readiness All firefighting equipment in a state of readiness.
For the purpose of these procedures it is taken that vessel is loading via port manifold using three connections in all
cargo tanks.
Zero Check
Shut all cargo valves including
drain valves on deck and in Pump
room as listed in line-up checklist
Manifold valves (Fig-4)
Rev. 0.0 4
2.1. Loading – Single Grade
Note:
Open two forward most tank Opening forward most tank valves will
ensure that entire air in the bottom line
main bell mouth valve (1W COT, will escape and the bottom lines will fill up
Valve CL201 & CL203) completely prior filling up tank.
!
Inform terminal and increase to CAUTION
agreed loading rate. Remember, it is very important to
ensure that enough cargo tanks are
open prior increasing loading rate.
Rev. 0.0 5
2.1. Loading – Single Grade
Rev. 0.0 6
2.1. Loading – Single Grade
For the purpose of these procedures it is taken that vessel is loading via port manifold using three connections in all
cargo tanks.
!
CAUTION
Bottom line in cargo tanks are not designed to
withstand high pressure, Keep sufficient tanks open to
Keep enough tanks open to avoid avoid pressure build up in bottom lines.
any back pressure at manifold. Example- If you are having a back pressure of 0 Kg/cm2
at manifold, there is about 2 Kg/cm2 of pressure at
bottom line if tank height is 20 mtr.
Therefore, it is important to have no pressure at
manifold. Monitor manifold pressure closely, in case of
any manifold pressure developing, open more tanks or
reduce loading rate to reduce the manifold pressure.
Rev. 0.0 7
2.1. Loading – Single Grade
For the purpose of these procedures it is taken that vessel is loading via port manifold using three connections in all
cargo tanks.
Note:
Inform terminal and reduce rate As best practice topping-off rate
to agreed topping-off rate. shall not be more than maximum
loading rate of one tank.
Maximum loading rate of one tank
(except slop tank) is 1800 m3/hr
Reduce IG pressure in tank (keep
between 300-400 mmWG) to
facilitate use of portable tank
gauging unit.
Note:
Keep last tank open to drain While draining the lines, monitor
down the lines. ullage of the drain tank
Rev. 0.0 8
2.1. Loading – Single Grade
For the purpose of these procedures it is taken that vessel is loading via port manifold using three connections in all
cargo tanks.
Note:
Upon confirmation with terminal On completion of loading, the vapor pressure in tank will rise,
shut the manifold valves (CL304, the rate of rise of vapor pressure mainly depend on the
CL305 & CL306) following factors,
1. Rise in atmospheric temperature
2. Rise in cargo temperature
The officer of the watch shall monitor the cargo tank pressure
Shut mast riser valve or Vapor closely and vent tank pressure to atmosphere in a controlled
manifold valve. manner prior the tank pressure reaching HVV lift setting.
The maximum atmospheric temperature in a day is around
1400 hrs.
Shut last tank main and stripping
bell mouth valve and ensure all
other tanks main and stripping
bell mouth valves are shut.
Note:
* - Please refer MARPOL Annex 1, Regulation 27 for
Intact stability criteria.
** - Check Draft restriction from load port and
discharge port agent/guide to port entry/with
business unit/same must be confirmed during ship
shore key meeting.
Tanks are inerted with *** - Check air draft restriction with load port and
discharge port agent, confirm same during ship shore
Tank positive pressure & Oxygen
key meeting.
Preparation content below 8% by volume. For calculation of Air Draft, refer iDMS section “IMS-
MO-NAV-NS-ADC-Sec 4.4”
Vapor tight integrity verified ^ - Cargo tanks shall be selected basis reserve ullage
space, trimming and listing moment of the tank.
Tanks positioned amidships are most suited trimming
tanks and these shall be loaded towards the end.
In some cases where vessel has no draft restriction,
ballast tanks can be used for trim and list correction
in order to accommodate the entire nominated cargo
Rev. 0.0 1
2.2. Loading – Multiple Grade
Alarm &
Tank high level (95%) and independent overfill/high high-
Gauging
level (98%) alarm tested.
System
Tank pre high-pressure, high-pressure, pre low-pressure
and low-pressure alarm tested.
Refer – SOLAS chapter 2-II, Regulation 11 and VIQ chapter
8
Emergency
Readiness All firefighting equipment in a state of readiness.
The procedure to load multiple grades is very similar to that of loading a single grade. The difference
is in the cargo and vapor line setup and loading rate.
Cargo and vapor line setup for loading depends upon the following points.
1. Number and rotation of load port.
2. Segregation required between grades, single valve or double valve.
3. Number of shore connection available.
4. Concurrent loading permissible.
5. Vapor segregation requirement.
The maximum loading rate while loading multiple grades will depend on the number of tanks being
loaded and number of manifold connections being used.
Rev. 0.0 4
2.2. Loading – Multiple Grade
Note:
loading sequence of group 3 – group 1 – group 2 is advisable
Commence loading with group 3. as,
Open No 3 manifold valve 1. loading group 3 first will ensure vessel has trim required
(CL306) and open 3W COT main for educting ballast tanks till last stage of loading operation
2. Group 2 tanks are equidistant from amidships, therefore
and stripping bell mouth valve they can be used for correcting trim towards the end
(CL209, CL210, CL211 & CL212 )
Note:
Communicate to terminal and Initial loading rate is calculated basis the number of tanks
commence loading cargo in open initially. As best practice initial rate shall not be more
group 3 at the agreed initial rate than maximum loading rate of one tank.
Maximum loading rate of one tank is 1800 m3/hr
!
Open No 1 manifold valve WARNING
(CL3040) and open 1W COT main On observing change in ullage of Non-nominated
and stripping bell mouth valve tank/tanks, inform Chief Officer and Master
immediately.
(CL201, CL202, CL203 & CL204)
Rev. 0.0 5
2.2. Loading – Multiple Grade
Rev. 0.0 6
2.2. Loading – Multiple Grade
Rev. 0.0 7
2.2. Loading – Multiple Grade
For the purpose of these procedures an example of loading three grades simultaneously with double valve segregation via
port manifold, without vapor segregation is considered.
Rev. 0.0 8
2.2. Loading – Multiple Grade
Note:
Inform terminal and reduce rate As best practice topping-off rate
to agreed topping-off rate. shall not be more than maximum
loading rate of one tank.
Maximum loading rate of one tank
(except slop tank) is 1800 m3/hr
Reduce IG pressure in tank (keep
between 300-400 mmWG) to
facilitate use of portable tank
gauging unit.
!
On reaching the nominated CAUTION
quantity of cargo, stop loading.
Ensure that the correct grade is stopped. Clear and
precise instructions should be passed to the terminal
!
Monitor these tanks whilst WARNING
loading other grades On observing change in ullage of Non-nominated
tank/tanks, inform Chief Officer and Master
immediately.
Rev. 0.0 9
2.2. Loading – Multiple Grade
For the purpose of these procedures an example of loading three grades simultaneously with double valve segregation via
port manifold, without vapor segregation is considered.
The process used for draining and clearing shore loading arms
Shut last tank main and stripping will depend on the draining arrangement available on shore
bell mouth valve and ensure all arms and cargo compatibility.
other tanks main and stripping The process of draining mentioned below should be used to
bell mouth valves are shut. avoid any cargo contamination.
During Loading
1. Loading multiple grade with single valve segregation is a critical process with high risk of inter-tank
migration and inadvertent comingling resulting in cargo claims. While loading multiple grades with
single valve segregation the officer in-charge must have undivided attention in CCR.
2. Use a color code system to identify grade and tanks nominated for that grade. Where possible
same color-coding shall be used as given in the loadicator for different grades of cargo.
3. When loading multiple grades at same load port, the tanks being loaded at any time shall have a
prominent display of “In Use” on CCR control panel and on tank gauges
4. Main and stripping bell mouth valve of non-nominated tanks shall be LOTO in shut position.
5. Ullage/Sounding of non-nominated tanks shall be checked using UTI/Sounding rod on hourly basis.
6. Ullage/Sounding of non-nominated tanks shall be prominently displayed near tank gauges for
ready reference. Trim and List corrections shall be readily available and posted in CCR for reference.
7. Record the observed ullages and volumes of the non-nominated tank in the hourly monitoring
record.
During Voyage
1. In case of multiple load ports, 24 hrs prior arrival port, the officer in-charge shall carry out manual
ullaging of all loaded and empty tanks to identify any migration. In case of migration, office must be
informed.
2. Daily check and record ullage and temperature of all cargo tanks including empty tanks. Compute
volume of cargo and verify with loaded quantity.
3. Keep all bottom crossover valves shut
4. Keep main and stripping bell mouth valve of empty tanks LOTO in shut position.
5. Twice a day start hydraulic pump of valve remote control system and pressurize the line, while
doing so, turn controllable valve knob to shut position. Keep the pump running for at least 15 min.
This is to avoid creeping of valves.
Rev. 0.0 11
2.3. Discharging
2.3.1. Cargo Oil Pump Operating Procedure
2.3.1.1. Principle
Rev. 0.0 1
2.3.1. Cargo Oil Pump Operating Procedure
Head
Head is the height to which a pump can raise liquid up.
Total static head is the difference between discharge and
suction static head.
Discharge head
Discharge head is equal to total head + suction head.
Suction head
It is a measure of the maximum depth from which a
pump can raise liquid via suction. Pump head (Fig-3)
Velocity head
Velocity head is the pressure which is needed to increase
the speed at which a liquid flows.
Rev. 0.0 2
2.3.1. Cargo Oil Pump Operating Procedure
A pump curve is a graphical representation of a pump’s performance based on testing using sea water
conducted by the manufacturer. Each pump has its own pump performance curve and it varies from
pump to pump. This is based on the pump’s horsepower and the size and shape of the impeller.
Understanding any given pump’s performance curve enables you to understand the limitation of that
pump. Operating a pump above its given range can cause damage to the pump.
A pump curve shows two vital performance factors – head and quantity. By reading the H-Q curve the
operator can obtain approximate discharge rate if head is known and vice-versa. The actual rate will
differ due to difference in viscosity of fluid being pumped and frictional losses.
Rev. 0.0 3
2.3.1. Cargo Oil Pump Operating Procedure
Hazards
1. Oil Spill
2. Equipment damage
3. Damage due to fluid hammering
4. Equipment damage due to dry running
Precautions
3. Never operate the pump for more than three minutes with discharge valve completely closed.
When Centrifugal pumps is operated without discharge, most of the power changes into heat and as
a result temperature of the liquid in the pump casing rises to the boiling point causing seizure of the
interior of the pump. Accident may occur, when dangerous liquids are pumped.
4. For steam driven pump, Keep the discharge valve full open. Adjust discharge flow by changing
speeds of the pump. Throttling of discharge valve is not recommended as it results in loss of energy.
5. When operating more than two pumps in parallel, keep the discharge pressure of each pump
equal. Example, if one pump pressure drops below the discharge pressure of the remaining pumps,
the pump will be working at Zero flow even though discharge valve is open. It will result in heating up
of pump casing.
6. As cargo is discharged, the NPSH decreases with the decreasing level of cargo in tank, this may
results in pump cavitation. Lower the speed of the pump without throttling the discharge valve as the
liquid level in the tank drops to avoid cavitation.
7. When liquid level decreases in the tank, suction pressure approaches the vapor pressure of the
liquid and vapor develops in the suction line. In this situation, the role of AUS (auto un-loading
system) is crucial which acts as vapor and gas extractor from the pump suction.
8. If cavitation occurs even when the pump speed is minimum, decrease the discharge rate by
throttling the discharge valve to avoid cavitation.
Rev. 0.0 4
2.3.1. Cargo Oil Pump Operating Procedure
Components
1. Separator Unit: This is a tank placed before the suction side of COP. In separator unit, gas
separates from cargo oil.
2. Vacuum pump Unit: It comprises of two water ring type vacuum pumps and a sealing tank. The
separated gas in the separator unit is discharged to slop tank using vacuum pump. The vacuum pump
starts and stops by preset value of separator level.
3. Discharge Control Valve Unit: It is a pneumatic actuator controlled butterfly valve to regulate
discharge capacity, present at the discharge side of COP. The valve can be operated either manual or
automatic. Automatic operation of valve is linked to separator level.
4. Gas Extraction Valve: This is a piston operated pneumatic valve, the valve opens and closes at
preset value of separator level.
5. Control Unit: A unit present in CCR for operating all components of AUS/AVSS. It also indicates
separator level, discharge valve opening, vacuum pressure and alarms.
Operation
1. As the liquid level in cargo tank reduces, the suction pressure of COP decreases and approaches
the vapor pressure of cargo oil. This results in production of vapors, the vapors separate and
accumulate at the top of separator unit as a result the separator level begins to fall.
2. As the separator level lowers to 50% , the gas extraction valve opens and the vacuum pump runs
and extracts the vapors from separator unit. The extracted vapors are discharged to slop tank. If the
discharge valve is operated automatic, at this time the discharge valve is automatically throttled.
3. As the vapor is extracted, the separator level rises again. As the separator level becomes 70% or
higher, the gas extraction valve closes and 20 sec later the vacuum pump stops. If the discharge valve
is operated automatic, at this time the discharge valve opens full.
4. This process ensures a cavitation free condition for COP and helps in achieving a near zero ROB of
cargo.
Important
As the level of cargo in cargo tank reduces, the COP RPM shall be reduced and discharge valve
operated in automatic mode to increase the efficiency of AUS/AVSS system.
Caution
When cargo tanks are full, Do not use vacuum pump to fill empty separator. This may result in
carryover of cargo to sealing tank.
Rev. 0.0 5
2.3.1. Cargo Oil Pump Operating Procedure
Rev. 0.0 6
2.3.1. Cargo Oil Pump Operating Procedure
Rev. 0.0 7
2.3.1. Cargo Oil Pump Operating Procedure
Confirm flow present at desired While the duty engineer is gradually increasing the
RPM of COP to minimum RPM, If the pump discharge
manifold pressure rises above 4 Kg/cm2, gradually open the
pump discharge valve.
Rev. 0.0 8
2.3.1. Cargo Oil Pump Operating Procedure
Rev. 0.0 9
2.3.2. Cargo Eductor Operating Procedure
2.3.2.1. Principle
SUCTION DISCHARGE
DRIVING
FLUID
*In fluid dynamics, Bernoulli’s principle states that, an increase in the speed of a fluid occurs
simultaneously with a decrease in static pressure or a decrease in the fluid’s potential energy.
Cargo Eductor
Maker KI-WON
No. of sets 2
Capacity 500 m3/hr
Drive fluid 12 Kg/cm2
Discharge Head 25 M Aq
Suction Head -5 M Aq
Rev. 0.0 1
2.3.2. Cargo Eductor Operating Procedure
For the purpose of explanation an example of educting No 6P COT using No 1 COP and No 1 Eductor is
considered.
The eductor shall be operated in closed cycle mode using either single Slop tank or both Slop tanks
Case 1 – Using only slop S tank Case 2 – Using both slop tanks
Line up No 1 COP and No 1 eductor Line up No 1 COP and No 1 eductor
as follows: as follows:
a. Shut No 1 COP suction valve a. Shut No 1 COP suction valve
(CL107) and open crossover valve (CL107) and open crossover valve
(CL131 & CL132) (CL131 & CL132)
b. Check No 2 & 3 COP crossover b. Check No 2 & 3 COP crossover
valves are shut (CL135, CL136, CL137 valves are shut (CL135, CL136, CL137
& CL138) & CL138)
c. Check Slop Port high suction c. Check Slop Port high suction
valves (CL133 & CL134) are shut valves (CL133 & CL134) are shut
d. Open Slop Stbd high suction valve OR d. Open Slop Stbd high suction valve
(CL129 & CL130) (CL129 & CL130)
e. Check eductor discharge non- e. Check eductor discharge non-
return valve by-pass (CL110) is shut return valve by-pass (CL110) is shut
f. Open eductor drive inlet valve f. Open eductor drive inlet valve
(CL121) and discharge to slop S (CL121) and discharge to slop P
valves (CL146) valves (CL148)
g. Check eductor discharge line g. Open eductor discharge line
isolation valve (CL154 & CL158) and isolation valve (CL154 & CL158) and
discharge to Slop P valve (CL148) are check discharge to Slop S valve
shut (CL146) is shut
h. Open eductor suction valve h. Open eductor suction valve
(CL123) and suction to No 3 line (CL123) and suction to No 3 line
valves (CL125, CL126 & CL141) valves (CL125, CL126 & CL141)
i. Check stripping pump suction valve i. Check stripping pump suction valve
(CL159) is shut (CL159) is shut
j. Open No 3 line bulkhead master j. Open No 3 line bulkhead master
valve (CL106) and check No 3 COP valve (CL106) and check No 3 COP
suction valve (CL109) is shut suction valve (CL109) is shut
k. Open Slop tank equalizing valves
(CL150 & CL151)
Station crew in pump room
Note:
1. Refer “Cargo Oil Pump Operating Procedures” for
detailed guidance on filling and operating a COP
Start No. 1 COP at minimum 2.The slop tank shall have enough liquid level to
RPM feed the COP and enough ullage space to
accommodate liquid quantity educted from tanks
Rev. 0.0 2
2.3.2. Cargo Eductor Operating Procedure
On completion of educting
operation, shut 6P COT stripping
bellmouth valve (CL224)
Rev. 0.0 3
2.3.2. Cargo Eductor Operating Procedure
2.3.2.i. Line Diagram for Use of Eductor Using Single Slop Tank
For the purpose of explanation an example of educting No 6P COT using No 1 COP, No 1 Eductor and Slop Stbd tank is marked.
Rev. 0.0 4
2.3.2. Cargo Eductor Operating Procedure
2.3.2.ii. Line Diagram for Use of Eductor Using Both Slop Tanks
For the purpose of explanation an example of educting No 6P COT using No 1 COP and No 1 Eductor is marked.
Rev. 0.0 5
2.3.3. Stripping Pump Operating Procedure
2.3.3.1. Principle
A positive displacement pump moves a fluid by repeatedly enclosing a fixed volume and moving it
mechanically through the system.
Stripping Pump
Maker Shinko Ind. Ltd.
No. of sets 1
Model KPH-275
Capacity 240 m3/hr
Discharge Head 135 m
No of Strokes 27 strokes per min
Safety valve setting 14.85 Kg/cm2
Rev. 0.0 1
2.3.3. Stripping Pump Operating Procedure
Rev. 0.0 2
2.3.3. Stripping Pump Operating Procedure
Rev. 0.0 3
2.3.3. Stripping Pump Operating Procedure
For the purpose of explanation an example of discharging Slop tanks via No 1 Port manifold is considered.
Line up as follows,
a. Open stripping pump suction
valve (CL159)
b. Open stripping pump suction
valve from slop tanks (CL152 &
CL144) and isolation valves
(CL125 & CL126)
c. Open discharge valve (CL156)
d. Open MARPOL port manifold
valve (CL379), MARPOL manifold
drain valve (CL381) and No 1
maniflod drain valve (CL313)
e. Check stripping pump
discharge to ODME line is shut
(CL161)
f. Check re-circulation valve
(CL157) is shut
g. Check No 1 manifold valve
(CL304) is shut
h. Check port manifold drain to
4P COT (CL321 & CL325) is shut
i. Check MARPOL stbd manifold
valve (CL378) is shut
!
Start stripping pump from CCR CAUTION
with minimum strokes Do not start stripping pump with discharge valve shut, this will
result in immediate build of pressure which can cause
structural damage
Rev. 0.0 4
2.3.3. Stripping Pump Operating Procedure
Rev. 0.0 5
2.3.3. Stripping Pump Operating Procedure
For the purpose of explanation an example of discharging Slop tanks via No 1 Port manifold is considered.
!
Shut pump discharge valve CAUTION
(CL156) Do not shut discharge valve prior stopping stripping pump, this
will result in immediate build of pressure which can cause
structural damage
Rev. 0.0 6
2.3.4. Crude Oil Washing
CRUDE OIL
WASHING
Crude oil washing is washing out the residue from tanks of oil tanker using its crude oil cargo, after
the cargo tanks have been emptied. Due to the property and nature of crude oil, during voyage, oil
clings to the tank walls and dissolved sediments settle at tank bottom. This clingage and settled
sediments add to the cargo 'remaining on board' (ROB). Crude oil is sprayed via high pressure nozzles
mounted in the cargo tank onto the walls of the tank to remove clingage and settled sediments, this
significantly reduces ROB on completion of discharging operation.
MARPOL 73/78 has made COW equipment mandatory for all oil tankers of 20,000 tons or greater
deadweight.
WASHING REQUIREMENT
Prior departure from discharge port following tanks shall be crude oil washed
a. Heavy Weather ballast tanks
b. For sludge control, In addition to heavy weather ballast tanks, 25% of tanks in which cargo is
carried on rotational basis, however no tank need to be crude oil washed more than once in four
months
METHOD
Rev. 0.0 2
2.3.4. Crude Oil Washing
Rev. 0.0 3
2.3.4. Crude Oil Washing
Rev. 0.0 4
2.3.4. Crude Oil Washing
For the purpose of explanation an example of 4W COT washing using No. 1 COP is considered.
Rev. 0.0 5
2.3.4. Crude Oil Washing
Concurrently keep discharging Tank cleaning line fwd pressure gauge (Fig - 8)
4W COT using No. 2 and 3 COP
Rev. 0.0 6
2.3.4. Crude Oil Washing
Rev. 0.0 7
2.3.4. Crude Oil Washing
Rev. 0.0 8
2.3.4. Crude Oil Washing
For the purpose of explanation an example of 4W COT washing using No. 1 COP is considered.
Rev. 0.0 9
2.3.4. Crude Oil Washing
Case 1 – Using only slop S tank Case 2 – Using both slop tanks
Line up No 1 COP and No 1 eductor as Line up No 1 COP and No 1 eductor as
follows: follows:
a. Shut No 1 COP suction valve a. Shut No 1 COP suction valve
(CL107) and open crossover valve (CL107) and open crossover valve
(CL131 & CL132) (CL131 & CL132)
b. Check No 2 & 3 COP crossover b. Check No 2 & 3 COP crossover
valves are shut (CL135, CL136, CL137 valves are shut (CL135, CL136, CL137
& CL138) & CL138)
c. Check Slop Port high suction valves c. Check Slop Port high suction valves
(CL133 & CL134) are shut (CL133 & CL134) are shut
d. Open Slop Stbd high suction valve d. Open Slop Stbd high suction valve
(CL129 & CL130) (CL129 & CL130)
e. Check eductor discharge non- e. Check eductor discharge non-
return valve by-pass (CL110) is shut OR return valve by-pass (CL110) is shut
f. Open eductor drive inlet valve f. Open eductor drive inlet valve
(CL121) and discharge to slop S valves (CL121) and discharge to slop P valves
(CL146) (CL148)
g. Check eductor discharge line g. Open eductor discharge line
isolation valve (CL154 & CL158) and isolation valve (CL154 & CL158) and
discharge to Slop P valve (CL148) are check discharge to Slop S valve
shut (CL146) is shut
h. Open eductor suction valve (CL123) h. Open eductor suction valve (CL123)
and suction to No 1 line valves and suction to No 1 line valves
(CL139) (CL139)
i. Check isolation valve (CL125) on i. Check isolation valve (CL125) on
suction line is shut suction line is shut
j. Open No 1 line bulkhead master j. Open No 1 line bulkhead master
valve (CL129) valve (CL129)
k. Open Slop tank equalizing valves
(CL150 & CL151)
Station crew in pump room and
on deck
Note:
Conduct prior starting checks as 1. Refer “COW Operations and Equipment Manual”
per COW checklist CL-C-06 2. Maximum trim basis regulation 18 of MARPOL is 3.58
meter. Do not exceed this trim at any time.
3. Give due regard to berth safety and hull stresses while
conducting COW operation.
Make 3.58 meter trim by astern
and slight list to port
Rev. 0.0 10
2.3.4. Crude Oil Washing
Continuously monitor Slop tank 1. Do not increase pressure beyond 12 Kg/cm2. The machines are
designed for an operating pressure between 6 - 12 Kg/cm2
level.
2. Tank cleaning line pressure below 8 Kg/cm2 would
considerably reduce the effectiveness of the washing operation
On completing the desired wash 3. While carrying out bottom wash, utmost care shall be
cycle, reduce No 1 COP RPM to exercised to ensure that no oil is accumulated on tank top. Oil
minimum. accumulated on tank top reduces the effectiveness of COW.
Rev. 0.0 11
2.3.4. Crude Oil Washing
Rev. 0.0 12
2.3.4. Crude Oil Washing
Rev. 0.0 13
2.3.4. Crude Oil Washing
Rev. 0.0 14
2.3.4. Crude Oil Washing
Rev. 0.0 15
2.3.5. Discharging – Single Grade
Rev. 0.0 1
2.3.5. Discharging – Single Grade
Rev. 0.0 2
2.3.5. Discharging – Single Grade
Alarm &
Tank high level (95%) and independent overfill/high high-
Gauging
level (98%) alarm tested.
System
Tank pre high-pressure, high-pressure, pre low-pressure
and low-pressure alarm tested.
Refer – SOLAS Ch 2-II, reg 11 and VIQ Chapter 8 “Venting Arrangements”
Alarm Trip
COP emergency trip tested COP Casing 75o C 80o C
from all locations (Manifold, Top bearing 85o C 90o C
Bottom bearing 85o C 90o C
pump-room entrance, pump- Stuffing Box 85o C 90o C
room bottom, CCR and Over speed trip - 113 +0/-2%
(Electric) Rated Speed
engine room . Over speed trip - 115 +0/-3%
(Mechanical) Rated Speed
Pump discharge - 16.0 Kg/cm2
COP temperature and pressure trip
Vibration 0.5 +/- 0.1 0.7 +/- 0.1
vibration alarm and trip mm mm
simulation test carried out L.O low pressure 0.6 +/- 0.1
Kg/cm2
0.5 +/- 0.1
Kg/cm2
High back 0.9 +/- 0.1
pressure (By Air) - Kg/cm2
1. Test run vacuum pump COP temp and vibration alarm (Fig–2)
2. Ensure vacuum pump seal
COP & tank is free of oil and filled
Stripping with water.
System 3. Line up Auto Unloading
Oil/Water
System as follows, Gas
a. Open all separator suction
valve (AU001, AU002 &
AU003)
b. Open vacuum pump
suction valves
c. Open seal tank discharge
valve (AU008) to slop P
d. Shut seal tank drain and
line drains and drain tank
filling valve (C20, C35, C43 &
AU015)
e. Open IG line to AUS re-
circulation line manual valve
(IG056)
f. Check AUS drain tank
suction valve (AU009) is shut
Vacuum pump unit (Fig–9)
Emergency All oil spill containment & fire fighting equipment in a state
Readiness of readiness. SOPEP emergency coastal contact list
updated and readily available.
Rev. 0.0 3
2.3.5. Discharging – Single Grade
For the purpose of these procedures it is taken that vessel is discharging from all tanks via port manifold using three
connections.
IMPORTANT
Prior carrying out discharge operation, Officer in-charge shall make himself familiar with the following ship specific
procedures,
1. Operation of COP
2. Operation of eductor
3. Operation of Stripping pump
4. COW procedure
Zero Check
Shut all cargo valves including
drain valves on deck and in Pump Deck cross-over valves (Fig-4)
room as listed in line-up checklist
Rev. 0.0 4
2.3.5. Discharging – Single Grade
Rev. 0.0 5
2.3.5. Discharging – Single Grade
Rev. 0.0 6
2.3.5. Discharging – Single Grade
Rev. 0.0 7
2.3.5. Discharging – Single Grade
For the purpose of these procedures it is taken that vessel is discharging from all tanks via port manifold using three
connections.
Note:
For the purpose of these procedures,
Stagger tanks as per discharge
the discharge sequence is taken as
sequence Group 1 – Group 2 – Group 3.
Note:
Cavitation is the formation of bubbles or cavities in liquid,
developed in areas of relatively low pressure around an
impeller. The imploding or collapsing of these bubbles trigger
intense shockwaves inside the pump, causing significant
damage to the impeller and/or the pump
Rev. 0.0 8
2.3.5. Discharging – Single Grade
Rev. 0.0 9
2.3.5. Discharging – Single Grade
Rev. 0.0 10
2.3.5. Discharging – Single Grade
On completion of COW
operation, educt all tanks
Note:
Ensure main and stripping bell As best practice ensure tank valve is
mouth valve of all tanks are shut closed prior reducing COP RPM to avoid
prior stopping eductor. back filling of the tank
Rev. 0.0 11
2.3.5. Discharging – Single Grade
Rev. 0.0 12
2.3.5. Discharging – Single Grade
On completion of stripping,
a. Stop stripping pump
b. Shut Slop tank bell mouth
valve (CL144 & CL152) and shut
stripping pump suction line
isolation valves (CL125 & CL126)
c. Open line drain, COP drain and
separator drain of COP’s &
(CL155) suction to stripping
pump
d. Ensure all line master valves
and deck crossover valves are
open
e. Open Hydraulic and pneumatic
discharge valve of COP’s
f. Open air escape valves (CL334
& CL335)
!
CAUTION
Start stripping pump from CCR
with minimum strokes (8 to 10 Do not start stripping pump with discharge
strokes) valve shut, this will result in immediate build
of pressure which can cause structural
damage to pump and pipeline.
Confirm flow in MAPOL line
Rev. 0.0 13
2.3.5. Discharging – Single Grade
Inform terminal
Rev. 0.0 14
2.3.6. Discharging – Multiple Grade
Note:
Tanks are inerted with * - Refer MARPOL Annex 1, Regulation 27 for Intact
positive pressure & Oxygen stability criteria.
content below 8% by volume. ** - Draft restriction shall be verified from port
Tank authorities of discharge port. Same shall be confirmed
Preparation during ship shore key meeting.
If circumstances permit, the arrival draft of vessel
shall not be exceeded during any stage of discharge
Vapor tight integrity verified operation.
*** - During discharge operation ballast tanks shall be
used for making trim and list to facilitate discharge.
**** - Check air draft restriction with discharge port
agent, confirm same during ship shore key meeting.
If vessel is carrying slops in For calculation of Air Draft, refer iDMS section “IMS-
slop tank and load on top is MO-NAV-NS-ADC-Sec 4.4”
not permitted. Lock out-tag ^ - The tank sequence will depend on cargo and vapor
segregation requirement, number of connections and
out all suction and discharge any restriction at discharge port.
valves of the tank.
Rev. 0.0 1
2.3.6. Discharging – Multiple Grade
Rev. 0.0 2
2.3.6. Discharging – Multiple Grade
Alarm &
Tank high level (95%) and independent overfill/high high-
Gauging
level (98%) alarm tested.
System
Tank pre high-pressure, high-pressure, pre low-pressure
and low-pressure alarm tested.
Refer – SOLAS Ch 2-II, reg 11 and VIQ Chapter 8 “Venting Arrangements”
1. Test run vacuum pump COP temp and vibration alarm (Fig–2)
2. Ensure vacuum pump seal
COP & tank is free of oil and filled
Stripping with water.
System 3. Line up Auto Unloading Oil/Water
System as follows, Gas
a. Open all separator suction
valve (AU001, AU002 &
AU003)
b. Open vacuum pump
suction valves
c. Open seal tank discharge
valve (AU008) to slop P
d. Shut seal tank drain and
line drains and drain tank
filling valve (C20, C35, C43 &
AU015)
e. Open IG line to AUS re-
circulation line manual valve
(IG056)
f. Check AUS drain tank
suction valve (AU009) is shut Vacuum pump unit (Fig–9)
Emergency All oil spill containment & fire fighting equipment in a state
Readiness of readiness. SOPEP emergency coastal contact list
updated and readily available.
Rev. 0.0 3
2.3.6. Discharging – Multiple Grade
The procedure to discharge multiple grades is very similar to that of discharging a single grade.
The variable factors in multiple grade discharging are cargo and vapor line setup, number of pumps
for operation, use of slop tank and terminal’s COW requirement. These factors will vary from
terminal to terminal and charterer to charterer.
The variable factors for discharging will further depends upon the following points.
1. Cargo compatibility and Segregation required between grades (single valve or double valve)
2. Number of shore connection available.
3. Concurrent discharging requirement.
4. Vapor segregation requirement.
5. Any terminal restriction or special requirement (example – Grade for educting and COW etc.)
The officer-in-charge shall use his prudent judgement and optimize all available resources to the
fullest to carry out a safe operation.
For the purpose of these procedures an example of discharging three grades, one grade at a time, via port manifold is
considered. The grades are stowed group wise.
IMPORTANT
Prior carrying out discharge operation, Officer in-charge shall make himself familiar with the following ship specific procedures,
1. Operation of COP
2. Operation of eductor
3. Operation of Stripping pump
4. COW procedure
Rev. 0.0 4
2.3.6. Discharging – Multiple Grade
Rev. 0.0 5
2.3.6. Discharging – Multiple Grade
Note:
1. Refer “Procedures for operation of COP” for
Fill up the pumps using 1W COT, detailed steps on filling empty COP.
fill pumps one by one.
!
Start IG plant and maintain tank CAUTION
pressure between 500 to 700 Filling up an empty COP is a critical process, Follow
mmWG. the steps in the same order. Failure in following the
steps in the same order may cause fluid hammering
and result in damage to COP and its associated
equipment
Start No 1 COP at minimum
RPM, once at minimum RPM
open hydraulic discharge valve
!
(CL113), pneumatic discharge
CAUTION
valve (CL065) and commence
While starting COP do not keep the
discharge discharge valve of other non operational
COP open, this is to avoid reverse
rotation of the impeller which may
damage the prime mover.
Once shore confirms receiving
cargo, and directs to increases
Note:
discharge rate, start remaining Discharge using one COP at minimum RPM for a
pumps in the same manner and minimum of 15 min to confirm that correct tanks are
keep them at minimum RPM. being discharged.
Note:
Increase pump RPM gradually to The maximum discharge rate will depend on the
achieve the desired discharge number of tanks being discharged and pumps being
used.
rate or manifold pressure.
Rev. 0.0 6
2.3.6. Discharging – Multiple Grade
!
Carry out safety and integrity CAUTION
check of pumps and lines
A starving pump i.e. a pump with -ve
suction pressure will develop cavitation.
Cavitation can cause pitting in pump
casing
Keep all tank valves of grade 1
open to provide positive feed to
pump. Note:
In case the tanks are unable to provide
sufficient feed to pumps, reduce RPM of pumps
or reduce the number of pumps.
Once the cargo level in 1W COT
reduces to 1mtr or the suction
pressure of COP reduced to zero.
Gradually start reducing RPM of
all COPs.
Note:
Switch on vacuum pump from Vacuum pump can be controlled either manually by
AUS panel. operator or automatically. Automatic function is
linked with COP seperator level.
Rev. 0.0 7
2.3.6. Discharging – Multiple Grade
Rev. 0.0 8
2.3.6. Discharging – Multiple Grade
Rev. 0.0 9
2.3.6. Discharging – Multiple Grade
Rev. 0.0 10
2.3.6. Discharging – Multiple Grade
Rev. 0.0 11
2.3.6. Discharging – Multiple Grade
Rev. 0.0 12
2.3.6. Discharging – Multiple Grade
During Discharging
1. Discharging multiple grade with single valve segregation is a critical process with high risk of inter-
tank migration and inadvertent discharge resulting in cargo claims. While discharging multiple grades
with single valve segregation the officer in-charge must have undivided attention in CCR.
2. 24 hrs prior arrival discharge port, the officer in-charge shall carry out manual ullaging of all loaded
and empty tanks to identify any migration. In case of migration, office must be informed.
3. Use a color code system to identify grade and tanks loaded with the grade. Where possible same
color-coding shall be used as given in the loadicator for different grades of cargo.
4. When discharging multiple grades at same discharge port, the tanks being discharged at any time
shall have a prominent display of “In Use” on CCR control panel and on tank gauges
5. Main and stripping bell mouth valve of non-nominated tanks shall be LOTO in shut position.
6. Ullage/Sounding of non-nominated tanks shall be checked using UTI/Sounding rod on hourly basis.
7. Ullage/Sounding of non-nominated tanks shall be prominently displayed near tank gauges for
ready reference. Trim and List corrections shall be readily available and posted in CCR for reference.
8. Record the observed ullages and volumes of the non-nominated tank in the hourly monitoring
record.
9. 6 hours prior completing discharge, all cargo tanks shall be manually gauged to ascertain the exact
grade and quantity discharged and balance cargo to discharge.
Rev. 0.0 13
2.4. Pressure Test
2.4.1. Cargo Line Pressure Test
1. Pollution incident often been caused due to leakage from Cargo lines, dresser couplings, valve
flanges, faulty pressure gauge connections, associated drains and other parts of the cargo piping
system on deck. Thus Periodic pressure testing of pipelines carrying hydrocarbons at high pressure is
essential to ensure their integrity during operations and service.
2. As per 33 CFR 156.170, static liquid pressure test is required for marine transportation related
pipelines handling oil to ensure their integrity and safety. The actual testing of the oil transfer lines
must be a hydrostatic test. That is a pressure test using a liquid medium. Air testing of the lines is not
acceptable.
3. Vessel's 'Oil Transfer System' includes the discharge pump and piping between the pump and the
vessel's manifold, excluding any non-metallic hoses.
IMPORTANT
The bottom lines are designed for a lower pressure rating and are inaccessible during normal course
of operation, therefore, it’s testing shall only be carried out in dry dock.
Rev. 0.0 1
2.4.1. Cargo Line Pressure Test
Terminology
Maximum Allowable Working Pressure (MAWP) is the maximum pressure that the weakest
component of the cargo system can withstand.
The MAWP of cargo system shall be the lowest pressure value of the following pressure ratings.
1. Maximum rated/Design pressure as per ship’s piping diagram
2. Cargo pump’s maximum discharge pressure (the head developed at zero flow condition as given in
the pump curve)
3. Pressure setting of pump overpressure trip (if fitted)
Refer iDMS- Cargo section (IMS-MO-CGO-CS), Appendix-C1.2 for detailed guidance on MAWP.
Working Pressure (WP) is the normal pressure that would be experienced by the cargo system during
cargo transfer.
Working pressure shall be the lowest pressure value of the following pressure ratings.
1. Maximum operating pressure of cargo pump (Which is the total head of cargo pump as per pump
curve)
2. 85% of MAWP of cargo system
Refer iDMS- Cargo section (IMS-MO-CGO-CS), Appendix-C1.2 for detailed guidance on MAWP.
Formula
Formula to convert cargo pump’s discharge head (in meter) to pressure in (Kg/cm2)
Pressure = 0.1 x head x Specific Gravity of liquid
Rev. 0.0 2
2.4.1. Cargo Line Pressure Test
Rev. 0.0 3
2.4.1. Cargo Line Pressure Test
Rev. 0.0 4
2.4.1. Cargo Line Pressure Test
For the purpose of explanation an example of testing No. 2 line using No. 2 pump with feed from 4P COT is considered.
IMPORTANT
Prior carrying out pressure testing, Officer in-charge should be familiar with the following ship specific procedures and test
plan,
a. Operation of COP
b. Operation of Stripping pump
c. IMS-MO-CGO-CS-Template -C1.1 - “Pipeline pressure test plan”
Zero Check
Shut all cargo valves including
drain valves on deck and in Pump
room as listed in line-up checklist
Line up as follows
a. Shut all three drop valves
(CL326, CL327 & CL328)
b. Shut No1 & 3 line deck
crossover valves (CL307, CL309,
CL390 & CL392) and open No 2
line crossover valves (CL308 & Drop valves (Fig-2)
CL391)
c. Open No. 2 Line master valve
(CL330)
d. Open No. 2 port and stbd side
manifold valves (CL302 & CL305)
e. Shut No. 2 port and stbd
manifold drain valves (CL311 &
CL314)
f. Shut port and stbd side Air escape valves (Fig-3)
manifold drain valves leading to
4W COT (CL320, CL321, CL324 &
CL325)
g. Open both side manifold
pressure gauge valve
h. Open air escape valves (CL334
& CL335)
Rev. 0.0 5
2.4.1. Cargo Line Pressure Test
Rev. 0.0 6
2.4.1. Cargo Line Pressure Test
!
Open pneumatic discharge valve CAUTION
(CL066) 10% and fill-up No. 2 Air and liquid are immiscible fluids with different compression
line, displace air into 4P COT via ratios, if same amount of force is applied on both fluid, air gets
air escape valves compressed more than liquid and exerts a higher pressure on
pipeline. The compressed air tries to de-compress and causes a
pressure wave within the pipe. Therefore, it is important that all
air is displaced prior increasing COP RPM.
Rev. 0.0 7
2.4.1. Cargo Line Pressure Test
Rev. 0.0 8
2.4.1. Cargo Line Pressure Test
For the purpose of explanation an example of testing No. 2 line using No. 2 pump with feed from 4P COT is marked.
Rev. 0.0 9
2.4.1. Cargo Line Pressure Test
IMPORTANT
Do not strip bottom lines (cargo tank section of line) in loaded condition,
1. An empty cargo line can suffer structural damage due to constant pressure being exerted by liquid
head.
2. On stripping cargo lines air gets filled in the bottom pipeline, this pocket of air, if not vented
properly can cause pressure wave/shock wave and result in structural damage.
Rev. 0.0 10
2.4.1. Cargo Line Pressure Test
!
CAUTION
Increase stripping pump strokes
Do not start stripping pump with discharge
to 27 strokes per min
valve shut, this will result in immediate build
of pressure which can cause structural
damage to pump and pipeline.
Rev. 0.0 11
2.4.1. Cargo Line Pressure Test
For the purpose of explanation an example of stripping No 2 line to 4P COT using Stripping pump is marked.
Rev. 0.0 12
2.4.2. Tank Cleaning Line Pressure Test
1. Pollution incident often been caused due to leakage from tank cleaning lines, dresser couplings,
valve flanges, faulty pressure gauge connections, associated drains and other parts of the tank
cleaning piping on deck. Thus Periodic pressure testing of tank cleaning pipelines at high pressure is
essential to ensure their integrity during operations.
2. As per 33 CFR 156.170, static liquid pressure test is required for marine transportation related
pipelines handling oil to ensure their integrity and safety. The actual testing of the oil transfer lines
must be a hydrostatic test. That is a pressure test using a liquid medium. Air testing of the lines is not
acceptable.
Terminology
Maximum Allowable Working Pressure (MAWP) is the maximum pressure that the weakest
component of the cargo system can withstand.
The MAWP of cargo system shall be the lowest pressure value of the following pressure ratings.
1. Maximum rated/Design pressure as per ship’s piping diagram
2. Cargo pump’s maximum discharge pressure (the head developed at zero flow condition as given in
the pump curve)
3. Pressure setting of pump overpressure trip (if fitted)
Refer iDMS- Cargo section (IMS-MO-CGO-CS), Appendix-C1.2 for detailed guidance on MAWP.
Rev. 0.0 1
2.4.2. Tank Cleaning Line Pressure Test
Working Pressure (WP) is the normal pressure that would be experienced by the cargo system during
cargo transfer.
Working pressure shall be the lowest pressure value of the following pressure ratings.
1. Maximum operating pressure of cargo pump (Which is the total head of cargo pump as per pump
curve)
2. 85% of MAWP of cargo system
Refer iDMS- Cargo section (IMS-MO-CGO-CS), Appendix-C1.2 for detailed guidance on MAWP.
Formula
Formula to convert cargo pump’s discharge head (in meter) to pressure in (Kg/cm2)
Pressure = 0.1 x head x Specific Gravity of liquid
Rev. 0.0 2
2.4.2. Tank Cleaning Line Pressure Test
Note:
Connect manifold pressure
Calibrate COW line pressure gauge build pressure using
gauges. pump and compare it with
calibrator gauge.
Rev. 0.0 3
2.4.2. Tank Cleaning Line Pressure Test
Rev. 0.0 4
2.4.2. Tank Cleaning Line Pressure Test
For the purpose of explanation an example of testing tank cleaning line using No. 1 pump with feed from 4P COT is considered.
IMPORTANT
Prior carrying out pressure testing, Officer in-charge should be familiar with the following ship specific procedures and test
plan,
a. Operation of COP
b. Operation of Stripping pump
c. IMS-MO-CGO-CS-Template -C1.1 - “Pipeline pressure test plan”
Zero Check
1. Shut all cargo valves including
drain valves on deck and in Pump
room as listed in line-up checklist
2. Shut all tank cleaning machine
valves and branch valves
Line up as follows
a. Shut tank cleaning heater inlet
and outlet valve (TC061 & Tank cleaning heater (Fig - 3)
TC062)
b. Open tank cleaning line
master valve (TC063)
c. Open forward drain valves
(TC085)
d. Open master valve of all COT
(No 1 COT to Slp COT)
e. Open tank cleaning line fwd
pressure gauge valve.
Rev. 0.0 5
2.4.2. Tank Cleaning Line Pressure Test
Rev. 0.0 6
2.4.2. Tank Cleaning Line Pressure Test
Rev. 0.0 7
2.4.2. Tank Cleaning Line Pressure Test
Rev. 0.0 8
2.4.2. Tank Cleaning Line Pressure Test
Rev. 0.0 9
2.4.2. Tank Cleaning Line Pressure Test
Rev. 0.0 10
2.4.2. Tank Cleaning Line Pressure Test
!
CAUTION
Start stripping pump from CCR
with minimum strokes (8 to 10 Do not start stripping pump with discharge
strokes) valve shut, this will result in immediate build
of pressure which can cause structural
damage to pump and pipeline.
Rev. 0.0 11
2.4.2. Tank Cleaning Line Pressure Test
Rev. 0.0 12
2.4.2. Tank Cleaning Line Pressure Test
Rev. 0.0 13
2.4.3. Ballast Line Integrity Test
6 Monthly or after completion Visual inspection of filled ballast line Chief Officer Master
of any repair work
Conduct DRA
Risk Involved:
a. Increase in draft
b. Enclosed space
Responsible Authority:
a. Chief Officer
Task Performer:
a. Chief Officer overall in charge
(Supervising)
b. Duty Officer (Assisting)
c. Deck crew (Assisting)
Note:
1. Testing shall be carried out in loaded passage
2. Coincide test with routine ballast tank
Prepare test plan inspection
Rev. 0.0 1
2.4.3. Ballast Line Integrity Test
Zero check
Check all ballast line and tank
valves are shut
Note:
The inspection shall include the piping, flanges,
Visually inspect ballast pipe in
dresser coupling and valves for any leakage.
pump room and inside ballast Particular attention shall be given at the bend, cross
tank section and bottom of the ballast pipes
On completion of visual
inspection, open empty ballast
tank valve and drain ballast line
Rev. 0.0 2
2.4.3. Ballast Line Integrity Test
Rev. 0.0 3
2.5. Tank Cleaning
2.5. Tank Cleaning
TANK
CLEANING
Generally cold water is used for cleaning tanks, however hot water may be used for washing if sludge
build-up has been detected and proven difficult to remove by cold water washing or if required by
charterers.
METHOD
Closed cycle washing using both slop tanks is preferred method of water washing. This method helps
in containing oil retrieved from cargo tank in dirty slop tank and provides clean water for washing
from clean slop tank.
Rev. 0.0 1
2.5. Tank Cleaning
Rev. 0.0 2
2.5. Tank Cleaning
Conduct DRA
Risk Involved:
a. Fire and explosion
b. Oil pollution Be guided by iDMS – Cargo section (IMS-
c. Equipment damage
MO-CGO-TC) and approved Crude oil
Associated Procedural Hazards: washing manual.
a. Damage due to fluid hammering a. Identify tanks to be washed
Responsible Authority: b. Identify “dirty” and “clean” slop tank
a. Chief Officer c. Method of washing (cold water or hot
Task Performer water wash)
a. Chief Officer overall in charge d. Use of Slop tank
(Supervising) e. Amount of water required for closed
b. Duty Officer (Monitoring)
cycle washing
c. Deck crew (Assisting)
f. Use of tank cleaning heater
g. Pattern of washing and number of
wash cycles
Prepare Tank cleaning plan h. Emergency preparedness
i. Identify key personnel and their duties
Rev. 0.0 3
2.5. Tank Cleaning
Rev. 0.0 4
2.5. Tank Cleaning
For the purpose of explanation an example of line flushing and 4W COT washing using No. 1 COP and both slop tanks is
considered.
IMPORTANT
Prior carrying out tank cleaning operation, Officer in-charge should be familiar with the following ship specific procedures,
a. Operation of COP
b. Operation of Eductor
c. Operation of Stripping pump
Zero Check
Shut all cargo valves including
drain valves on deck and in Pump
room as listed in line-up checklist
Rev. 0.0 5
2.5. Tank Cleaning
Observe flow in stripping pump Prior opening cargo sea chest valve ensure the pump
room crossover section is completely empty and the
discharge line to slop P
line is under vacuum
Rev. 0.0 6
2.5. Tank Cleaning
Rev. 0.0 7
2.5. Tank Cleaning
Rev. 0.0 8
2.5. Tank Cleaning
Rev. 0.0 9
2.5. Tank Cleaning
Rev. 0.0 10
2.5. Tank Cleaning
Rev. 0.0 11
2.5. Tank Cleaning
Rev. 0.0 12
2.5. Tank Cleaning
Rev. 0.0 13
2.6. Tank Atmosphere Control
Operation
2.6.1. Inerting
INERTING
The cargo tanks have abundance of hydrocarbon (fuel) and source of ignition (static charge), therefore
by reducing the oxygen content in the tank fire can be prevented. The process of reducing oxygen
content of cargo tank to below 8% by volume is known as inerting.
Method
Dilution Displacement
Inert gas is introduced at high velocity in the Inert gas is introduced at slow velocity in the tank
tank to form a homogeneous mixture, this forming a stable horizontal interface between
mixture is vented via purge pipe. As the process inert gas and air-hydrocarbon mixture. Air-
continues, the concentration of the original gas hydrocarbon mixture is displaced from the tank
decreases progressively. As entry of inert gas is through suitable piping.
required at high velocity, therefore only a
This method requires low entry velocity of inert
limited number of tanks can be inerted
gas, therefore more tanks can be inerted
simultaneously.
simultaneously.
Dilution Method: IG entry from IG branch line
and vent via purge pipe Displacement Method: IG entry from bottom
cargo line and vent via purge pipe
As ships are not fitted with a purge pipe that extends till the bottom of the tank, a combination of
dilution and displacement method is used for inerting. In this method IG is introduced in one tank and
vented from another.
Example: 1P and 1S tank can be inerted simultaneously by introducing IG in 1P tank via main IG line,
connecting 1P and 1S tank via bottom cargo line and venting from 1S tank purge stack of HVV valve.
Combination method is more efficient than dilution method as by using this method 4 wing tanks can
be inerted at the same time.
Rev. 0.0 1
2.6.1. Inerting
CARGO LINE
Rev. 0.0 2
2.6.1. Inerting
Conduct DRA
Risk Involved:
a. Personal Injury due to toxicity of
Inert Gas
Associated Procedural Hazards:
a. Tank subject to excess pressure
b. Re-entry of oxygen in tank
Responsible Authority:
a. Chief Officer
Task Performer
a. Chief Officer overall in charge
(Supervising)
b. Deck crew (Assisting)
Rev. 0.0 3
2.6.1. Inerting
Rev. 0.0 4
2.6.1. Inerting
Method - IG entry from IG branch line and vent via purge stack/HVV Valve
For the purpose of explanation an example of inerting 1W COT using Dilution Method is considered.
Start IG plant
Rev. 0.0 5
2.6.1. Inerting
SAMPLE POINT
Note:
On completion, open IG branch valves of all COT’s and check
all gas freeing covers are shut.
Rev. 0.0 6
2.6.1. Inerting
Method - IG entry from IG branch line and vent via purge stack/HVV Valve
For the purpose of explanation an example of inerting 1W COT using Dilution Method is marked. Yellow color represents the flow of inert gas.
Vent
Vent
Rev. 0.0 7
2.6.1. Inerting
Method - IG entry from bottom cargo line and vent via purge stack/HVV Valve
For the purpose of explanation an example of inerting 1W COT using Displacement Method is considered.
Start IG plant
Rev. 0.0 8
2.6.1. Inerting
Note:
Maintain low pressure setting of Low entry velocity of inert gas can also be achieved by
regulating valve to ensure inerting multiple tanks simultaneously
delivery of IG at low velocity
Note:
Stop inerting once tank oxygen On completion, open IG branch valves of all COT’s and check
content is below 8% by volume all gas freeing covers are shut.
On completion of inerting
disconnect IG line from cargo line
(remove spool piece) and shut IG
valve (IG060 & IG0601)
Rev. 0.0 9
2.6.1. Inerting
Method - IG entry from bottom cargo line and vent via purge stack/HVV Valve
For the purpose of explanation an example of inerting 1W COT using Displacement Method is marked. Yellow color represents the flow of inert gas.
Rev. 0.0 10
2.6.1. Inerting
Vent
Vent
Rev. 0.0 11
2.6.1. Inerting
For the purpose of explanation an example of inerting 1W COT using Combination method is considered
Start IG system
Rev. 0.0 12
2.6.1. Inerting
Note:
On completion, open IG branch valves of all COT’s and check
Stop inerting once tank oxygen all gas freeing covers are shut.
content is below 8% by volume
Rev. 0.0 13
2.6.1. Inerting
Vent
Rev. 0.0 14
2.6.2. Purging
PURGING
It is the process of reducing concentration of hydrocarbon, hydrogen sulphide or other toxic gas
(example: mercaptan, mercury vapour etc.) in an inerted cargo tank using inert gas.
Method
Dilution Displacement
Inert gas is introduced at high velocity in the Inert gas is introduced at slow velocity in the tank
tank to form a homogeneous mixture, this forming a stable horizontal interface between
mixture is vented via purge pipe. As the process inert gas and hydrocarbon-toxic gas mixture.
continues, the concentration of the original gas Hydrocarbon-toxic gas mixture is displaced from
decreases progressively. As entry of inert gas is the tank through suitable piping.
required at high velocity, therefore only a
This method requires low entry velocity of inert
limited number of tanks can be purged
gas, therefore more tanks can be inerted
simultaneously.
simultaneously.
Dilution Method: IG entry from IG branch line
and vent via purge pipe Displacement Method: IG entry from bottom
cargo line and vent via purge pipe
Rev. 0.0 1
2.6.2. Purging
As ships are not fitted with a purge pipe that extends till the bottom of the tank, a combination of
dilution and displacement method is used for purging. In this method IG is introduced in one tank and
vented from another.
Example: 1P and 1S tank can be purged simultaneously by introducing IG in 1P tank via main IG line,
connecting 1P and 1S tank via bottom cargo line and venting from 1S tank purge pipe.
Combination method is more efficient than dilution method as by using this method 4 tanks can be
purged at the same time.
CARGO LINE
Rev. 0.0 2
2.6.2. Purging
Conduct DRA
Risk Involved:
a. Personal Injury due to toxicity
b. Fire and explosion
Rev. 0.0 3
2.6.2. Purging
!
Shut all doors and natural vents CAUTION
leading to accommodation
It is important that all HVV valves are operating freely, as HVV
valve will act as a safety barrier and prevent over pressure in
case of leaking IG valve of tank not being purged
Air Condition on partial re-
circulation.
Rev. 0.0 4
2.6.2. Purging
Method - IG entry from IG branch line and vent via purge stack/HVV Valve
For the purpose of explanation an example of purging 1W COT using Dilution Method is considered.
Start IG plant
Rev. 0.0 5
2.6.2. Purging
Note:
Stop purging once required gas On completion, open IG branch valves of all COT’s and check
concentration (hydrocarbon or all gas freeing covers are shut.
toxic gas) achieved
Rev. 0.0 6
2.6.2. Purging
Method - IG entry from IG branch line and vent via purge stack/HVV Valve
For the purpose of explanation an example of purging 1W COT using Dilution Method is marked. Yellow color represents the flow of inert gas.
Vent
Vent
Rev. 0.0 7
2.6.2. Purging
Method - IG entry from bottom cargo line and vent via purge stack/HVV Valve
For the purpose of explanation an example of purging 1W COT using Displacement Method is considered.
Start IG plant
Rev. 0.0 8
2.6.2. Purging
Regularly take sample of gas Monitor Individual tank pressure of all tanks throughout the
operation
being vented to check the
progress of process
Note:
Refer “Gas Sampling” procedures given in Inerting
section 2.6.1.3.
Carry out exchange till
concentration of gas
(hydrocarbon or toxic gas) in
escaping mixture is less than
required value Note:
1. The time required to reduce the concentration of gas
will depend on various factors as initial concentration of
gas, properties of previous cargo carried, any cargo
On completion, switch over to residue present in tank, whether tank washed etc.
next set of tanks as follows
a. Open main bellmouth valve 2. The concentration of hydrocarbon gas is measured in
and HVV valve gas freeing cover %Vol or % LEL and of toxic gas in PPM.
of next tank 3. If purging a tank for gas freeing operation the
b. Shut main bellmouth valve and concentration of hydrocarbon should be reduced below
HVV valve gas freeing cover of 1% vol and toxic gas below TLV.
completed tank
Rev. 0.0 9
2.6.2. Purging
Note:
Stop purging once required gas On completion, open IG branch valves of all COT’s and check
concentration (hydrocarbon or all gas freeing covers are shut.
toxic gas) achieved
On completion of purging
disconnect IG line from cargo line
(remove spool piece) and shut IG
valve (IG060 & IG0601)
Rev. 0.0 10
2.6.2. Purging
Method - IG entry from bottom cargo line and vent via purge stack/HVV Valve
For the purpose of explanation an example of purging 1W COT using Displacement Method is marked. Yellow color represents the flow of inert gas.
Rev. 0.0 11
2.6.2. Purging
Vent
Vent
Rev. 0.0 12
2.6.2. Purging
For the purpose of explanation an example of purging 1W COT using Combination method is considered
Start IG system
Rev. 0.0 13
2.6.2. Purging
Note:
1. The time required to reduce the concentration of gas
Carry out exchange till will depend on various factors as initial concentration of
concentration of gas gas, properties of previous cargo carried, any cargo
residue present in tank, whether tank washed etc.
(hydrocarbon or toxic gas) in
escaping mixture is less than 2. The concentration of hydrocarbon gas is measured in
required value %Vol or % LEL and of toxic gas in PPM.
Note:
Stop purging once required gas On completion, open IG branch valves of all COT’s and check
concentration (hydrocarbon or all gas freeing covers are shut.
toxic gas) achieved
Rev. 0.0 14
2.6.2. Purging
Vent
Rev. 0.0 15
2.6.3. Gas Freeing
GAS
FREEING
The process of replacing inert and toxic atmosphere of a tank with oxygen rich atmosphere is called
gas freeing.
METHOD
Dilution Displacement
Gas freeing of a tank by dilution method can be Gas freeing of a tank by displacement method can
done by two method be done by using a portable blower (water driven
1. Using portable blower (water driven or air or air driven) running in exhaust mode connected
driven) in supply mode to a portable flexible duct extending till the
2. Using IG plant in gas freeing mode bottom of the tank
Conduct DRA
Risk Involved:
a. Personal Injury due to toxicity
Responsible Authority:
a. Chief Officer
Task Performer
a. Chief Officer overall in charge
(Supervising)
b. Deck crew (Assisting)
Rev. 0.0 2
2.6.3. Gas Freeing
Rev. 0.0 3
2.6.3. Gas Freeing
!
Shut bottom line crossovers CAUTION
(CL229, CL230, CL233, CL234,
CL245 & CL246) and maintain Maintain double valve segregation to avoid any accidental
double valve segregation ingress of hydrocarbon rich atmosphere or inert gas into the
between tanks tank from cargo line
Rev. 0.0 4
2.6.3. Gas Freeing
Rev. 0.0 5
2.6.3. Gas Freeing
For the purpose of explanation an example of gas freeing 1W COT using Dilution Method 2 is considered
Shut tank IG valve and rotate It is important that the spectacle blank of remaining tanks are
swung to shut position to avoid any accidental ingress of air in
spectacle blank to blank position hydrocarbon rich atmosphere due to leaking tank IG valve
of all other COT’s
Note:
Refer “Gas Sampling” procedures given in Inerting
Regularly take sample of gas section 2.6.1.3.
being vented at tank opening to
check the progress of process
Rev. 0.0 6
2.6.3. Gas Freeing
Rev. 0.0 7
2.6.3. Gas Freeing
For the purpose of ease of understanding an example of gas freeing 1P and 1S is illustrated
Rev. 0.0 8
2.6.3. Gas Freeing
Vent
Vent
Rev. 0.0 9
2.6.3. Gas Freeing
!
Shut tank IG valve and rotate CAUTION
spectacle blank to shut position It is important that the spectacle blank is rotated to shut
position to avoid any accidental ingress of hydrocarbon rich
atmosphere or inert gas into the tank due to leaking tank IG
valve
Shut tank main and stripping bell
mouth valve and LOTO
!
CAUTION
Shut bottom line crossovers Maintain double valve segregation to avoid any accidental
(CL229, CL230, CL233, CL234, ingress of hydrocarbon rich atmosphere or inert gas into the
CL245 & CL246) and maintain tank from cargo line
double valve segregation
between tanks
!
CAUTION
Rig the portable blower along Ground portable blower and flexible duct to deck
with a portable flexible duct structure
extending till 1 mtr above tank
top
Rev. 0.0 10
2.6.3. Gas Freeing
Rev. 0.0 11
2.7. Ballast Handling
2.7.1. Ballasting
Conduct DRA
Consider these points in addition to the guidance
Risk Involved: given in iDMS -Ballast process.
a. Structural damage a. Ballast Quantity*
Associated Procedural Hazards: b. IMO Stability criteria**
a. Damage due to pressure surge/water c. Stresses (SF and BM in sea going condition) limits
hammer as per iDMS
b. Structural damage due to over flow e. Draft restriction at discharge port, including any
of ballast tank
restriction due to tidal variation
Responsible Authority: f. Tanks for List and trim correction
a. Chief Officer g. Air Draft restrictions.
h. Manifold height restriction
Task Performer:
a. Chief Officer overall in charge
(Supervising) Note
b. Duty Officer (Monitoring)
* - Capacity of the segregated ballast is determined by
c. Deck crew (Assisting)
lightweight of vessel and the requirement to comply with
below mentioned ship’s draught and trim requirement,
a. Draft midship = 2m + 0.02 x Length between the
perpendiculars.
Prepare ballast plan b. Trim by astern shall not be greater than 0.015 x Length
between the perpendiculars.
c. Propeller shall have 100 % immersion.(Upper tip of the
propeller is immersed just to the water line or more)
Check ballast tank Fixed Gas (Refer MARPOL Annex 1 - Regulation 18 Segregated Ballast
Detection panel for tanks)
hydrocarbon alarm
** - Please refer MARPOL Annex 1, Regulation 27 for Intact
stability criteria.
Rev. 0.0 1
2.7.1. Ballasting
Rev. 0.0 2
2.7.1. Ballasting
Zero check
Check all ballast line and tank
valves are shut
Note:
Ballast will fill in by gravity till the ballast tank level is
lower that vessels draft
Rev. 0.0 3
2.7.1. Ballasting
Rev. 0.0 4
2.7.1. Ballasting
Note:
Open tank valve of 4W WBT 1. Open at least 4 ballast tanks when running both ballast
(BA416, BA417, BA418 & pumps.
BA419) & check line isolation 2. During final stage use single pump to top off ballast tanks.
valve (BA506) is open
!
CAUTION
Ballast tank as per ballast plan
Do not overflow ballast tanks while ballasting, this
can result in structural damage to ballast tank and
its fittings
Rev. 0.0 5
2.7.1. Ballasting
Zero check
Check all ballast line and tank
valves are shut
Note:
It is important to remove air from pump casing and fill pump
Open No 2 Ballast pump casing prior starting ballast pump. Opening discharge valve of
suction valve from sea chest pump facilitates in removal of air.
(BA503) and discharge valve
(BA523)
Rev. 0.0 6
2.7.1. Ballasting
Note:
During the start up of a centrifugal pump, prior to the time
Start No. 2 Ballast pump at that normal flow is reached, these transient conditions can
minimum RPM with discharge generate heads and input torques (stress) that are much
higher than design on prime movers, A closed discharge valve
valve (BA523) shut creates a minimum load on prime movers.
Rev. 0.0 7
2.7.1. Ballasting
On completion of ballasting
change over pump sea to sea as
follows,
a. Open discharge to overboard
line valve (BA512 & BA530)
b. Shut discharge to ballast tank
valve (BA520)
Rev. 0.0 8
2.7.1. Ballasting
Rev. 0.0 9
2.7.1. Ballasting
Rev. 0.0 10
2.7.1. Ballasting
Rev. 0.0 11
2.7.2. De-Ballasting
Compare fixed pneumatic level (Refer MARPOL Annex 1 - Regulation 18 Segregated Ballast
tanks)
gauges of ballast tank with
manual soundings ** - The de-ballasting and loading operation, should at all
time satisfy Intact stability criteria (MARPOL Annex 1,
Regulation 27)
- The de-ballast plan should include steps to minimize Free
Surface effect due to slack ballast and cargo tanks.
Verify functioning of local
pressure/suction gauge and
CCR gauges of ballast pump and
ballast eductor
Rev. 0.0 1
2.7.2. De-Ballasting
Rev. 0.0 2
2.7.2. De-Ballasting
Zero check
Check all ballast line and tank
valves are shut
Note
1. De-ballasting by gravity will happen till the tank
level equals vessels draft.
De-Ballast desired quantity by
gravity 2. Once the tank level is close to vessel draft, the de-
ballasting rate will reduce.
3. It is advisable to start ballast pump once the de-
ballasting rate by gravity has fallen below pumps
discharge rate.
During de-ballasting, frequently
monitor water surface on stbd
side for signs of contamination
Rev. 0.0 3
2.7.2. De-Ballasting
Rev. 0.0 4
2.7.2. De-Ballasting
Rev. 0.0 5
2.7.2. De-Ballasting
Note:
As the level of ballast in ballast Hunting ampere meter and a reduction in discharge and
tanks reduces, the WBP will suction pressure indicate cavitation in ballast pump
cavitate
Rev. 0.0 6
2.7.2. De-Ballasting
Rev. 0.0 7
2.7.2. De-Ballasting
Rev. 0.0 8
2.7.2. De-Ballasting
Rev. 0.0 9
2.7.2. De-Ballasting
Rev. 0.0 10
Section 3
Annexure
3.1. Vapor Emission Control System
3.1.1. Requirement
Legislation in some ports and offshore lightering area prohibits release of volatile organic compound (VOC)
from ship’s cargo tank into atmosphere. In these ports vessel needs to carry out cargo operation using Vapor
Emission Control System (VECS). This operation involves connecting a vapor return arm or hose to dedicated
vapor manifold. The vapor manifold line is connected to main Inert Gas line, Therefore during cargo operation
the entire displaced cargo oil tank atmosphere containing VOC is discharged ashore rather than being vented
directly to atmosphere, or in case of a lightering operation returned to the discharging vessel.
The vessel is fitted with two vapor manifold on each side. The VECS is also equipped with IG line pressure and
oxygen monitoring and alarm system to ensure that the tank pressure and oxygen content remains within the
operational parameters.
Rev. 0.0 1
3.1. Vapor Emission Control System
Rev. 0.0 2
3.1. Vapor Emission Control System
Note:
If vessel has a long stay at berth after completion of loading,
Disconnect shore vapor recovery do not disconnect vapor arm on completion of loading as it
arm or hose may be required to pass vapor ashore if tank vapor pressure
increases due to thermal variation
Rev. 0.0 3
3.1. Vapor Emission Control System
Note:
Monitor Oxygen content of It is advisable that the service ship arrives with high tank
pressure, this is to facilitate flow of vapor from service
vapor being received from ship to STBL
service ship
On completion of discharging,
shut vapor manifold valve
Rev. 0.0 4
3.2. Management of Heated Cargo
Note:
Conduct DRA Be guided by iDMS section: IMS-MO-CGO-CG-HEAT, in
Risk Involved: addition pay special attention to,
a. Personnel Injury / Burns a. Charterer’s request of,
b. Structural damage due to thermal The cargo to be heated throughout the voyage to a
shock certain temperature.
The vessel to arrive at the discharging port with a certain
Associated Procedural Hazards: temperature and maintain it throughout discharging.
a. Introduction of free water in cargo
tanks The cargo to be heated throughout the voyage to a
certain temperature which should be increased to a
b. Introduction of oil in cascade tank
higher temperature before arrival.
Responsible Authority: b. Cargo tank coating and tank valve seat ring tolerable limit
for temperature
1. Chief Officer and Chief Engineer
c. The property of cargo as,
Task Performer: Heating of viscous cargoes such as heavy fuels is
1. Chief Officer overall in charge necessary in order to facilitate pumping and draining
(Supervising) Heating of cargo reduces the delivery pressure on the
2. Duty Engineer (Monitoring) ship's pumps and facilitates stripping and subsequent
3. Pump man and Deck crew (Assisting) cleaning of the tanks
Rev. 0.0 1
3.2. Management of Heated Cargo
Rev. 0.0 2
3.2. Management of Heated Cargo
Zero Check
Shut all valves of steam main
supply line, main return line,
branch supply line and branch
return line including drain valves
Rev. 0.0 3
3.2. Management of Heated Cargo
Rev. 0.0 4
3.2. Management of Heated Cargo
Note:
Main steam line pressure will 1. The steam pressure to maintain in main steam line will
drop with every tank being depend on weather condition, cargo loading
started, regulate main steam temperature, heating instructions from charterer etc.
line pressure from engine room 2. Monitor cargo temperature regularly to check the
progress of process
accordingly.
Rev. 0.0 5
3.2. Management of Heated Cargo
Non-Heating
1. Allow cargo temperature to cool down to
lowest allowable temperature
2. In case of carrying cargo with high wax content,
do not allow temperature to fall below cloud
point.
Depending upon the duration of
voyage and charterer’s heating
instructions, break heating Maintaining
schedule in to three phases. In this period heat cargo to maintain the minimum
allowable temperature or loading temperature.
Heating-Up
In this period, heat up cargo from the lowest
allowable temperature to the temperature
needed to discharge the cargo.
Note:
1. Do not overheat cargo, overheating results in
Periodically drain main steam
excess consumption of bunker.
supply line and supply branch 2. Do not heat cargo beyond cargo tank coating and
line to avoid steam hammering tank valve seat ring tolerable temperature limit.
Note:
Monitor observation tank and External factors which will affect heating,
cascade tank for sign of oil when 1. Sea water Temperature
cargo heating is underway 2. Air Temperature
3. Sea Conditions and Movement of the Ship
4. Weather
Rev. 0.0 7
3.2. Management of Heated Cargo
LOADING OPERATION
1. Vessel shall not load cargo having temperatures higher than 150°F unless specific instructions to
the contrary are received from the Charterers and confirmed by commercial operations and Marine /
Vessel Superintendent.
2. Load very slowly for the first two meters before gradually raising the rate to the required full. This
allows the structure to adapt slowly to the temperature variation.
3. The temperature of the incoming cargo should be checked periodically as too high a temperature
may cause undue strain on the ship's structure, damage tank coating, valve seat ring and wedge ring
of expansion joints.
4. In case of loading heated cargo with high pour point in extremely cold condition, the loading lines
shall be immediately drained once loading is completed or suspended.
5. In case of loading heated cargo in extremely cold condition, steam line shall be warmed up and
kept ready prior arrival load port.
DISCHARGING OPERATION
1. While discharging the temperature of cargo shall not rise excessively, at high temperature cargo
will gas up and cause cavitation
2. Strip each tank immediately after completing bulk discharge, do not postpone stripping. When the
level of the cargo falls below the heating coils its temperature falls rapidly and if not stripped at once,
it might solidify.
3. If a heated cargo is discharged in very cold weather and the discharge is temporarily stopped,
every effort should be made to drain all cargo lines and main pumps by stripping them dry into a tank
containing oil. This must be carried out immediately after the main pumps are stopped in order to
prevent oil solidifying in the exposed pipelines on deck and in the pumproom.
4. If a fairly lengthy stop occurs after the level of cargo in a tank has fallen below the heating coils, the
level should be raised by gravitating cargo from another tank. Pumping should recommence only
after the temperature has been raised to the permissible maximum. Overheating on such occasions
may easily occur, therefore, frequently check the temperature.
Rev. 0.0 8
3.3. Disposal of Pump Room Bilges
3.3.1. Requirement
The pumproom is provided with a fixed bilge disposal arrangement capable of transferring
pumproom bilge content to cargo tank, slop tank or other containment tank without risk of pollution.
In emergency, the bilge disposal system is capable of being operated from outside the pumproom
without exposing operator to toxic environment.
Arrangement
IMPORTANT
1. Pumproom bilge suction valves are non-return valves. Keep both bilge suction valves (CL198 &
CL199) open at all times.
2. Keep stripping pump, manual operated steam inlet and return line valves (SC534 & SC536) open at
all times.
3. Keep stripping pump, steam inlet line drain (SC531 & SC539), return line drain (SC540) and pump
steam chest drains shut at all times.
4. Keep steam inlet to return line by-pass valves (SC538, SC535 & SC537) shut at all times.
5. Keep stripping pump re-circulation valve (CL157) shut at all times.
Rev. 0.0 1
3.3. Disposal of Pump Room Bilges
Rev. 0.0 2
3.3. Disposal of Pump Room Bilges
For the purpose of explanation an example of pumproom bilge disposal to Retention tank is explained.
Rev. 0.0 3
3.4. Management of L.S.W.R Cargo
L.S.W.R Cargo
Low Sulphur Waxy Residue Cargo (L.S.W.R) is a residual product of fractional distillation. It is a
mixture of long residue and vacuum residue with diesel to meet specification. It has low sulphur and
high wax content and has high cloud point and pour point, hence, requires extreme care while
carriage.
Conduct DRA
Risk Involved:
a. Toxic exposure
b. Oil Spill
c. Fire and Explosion
Note:
Associated Procedural Hazards: Be guided by iDMS section: IMS-MO-CGO-CG-LSWR, in
a. Cooling of cargo below cloud point
addition pay special attention to,
Responsible Authority: a. The property of cargo
a. Chief Officer Cloud Point (Temperature below which wax forms a
cloudy appearance)
Task Performer: Pour Point
a. Chief Officer overall in charge b. Loading temperature
(Supervising)
c. Tank pre-heating requirement prior loading
b. Duty Officer (Monitoring)
d. De-ballasting and ballasting plan
c. Deck crew (Assisting)
e. Charterer’s heating requirement
f. Availability of cutter stock at discharge port
!
CAUTION
Prepare detailed heating plan To avoid clogging of lines, the cargo shall be loaded at a
minimum of 20oF above pour point
Rev. 0.0 1
3.4. Management of L.S.W.R Cargo
1. Restrict the number of tanks being loaded together and de-ballast the adjacent ballast tank as fast
as possible, keeping draft, trim and stability of vessel in consideration.
2. Obtain permission from charterers and start heating cargo during loading operation.
3. On completion of loading or in the case of temporary stoppage, every effort should be made to
drain exposed section of cargo lines into a tank containing oil. This must be carried out immediately.
4. On completion of cargo arm draining and disconnection, the manifold drain line section shall be
immediately cleared by steam blowing.
1. Do not stop heating, if temperature of the cargo is increasing beyond charterers requirement,
regulate heating by reducing the number of heating coils. Discontinuing heating will stop the
convection circulation and help in settling of cargo (wax formation) on the bulkheads and bottom
forming a blanket. If the blanket hardens, it will be extremely difficult to melt and result in high
clingage ROB.
2. Prior arrival discharge port, full open heating to each tank, this will increase the convection
circulation and melt any solidified cargo that may have formed during the voyage.
1. Continue heating through out the discharge, do not stop heating till the tank is stripped.
2. In case of partial discharge, plan to discharge entire tank at once, if the quantity does not permit
entire tank discharge, leave at least 1 mtr of cargo in tank. Super heat the remaining cargo to 50oF
above pour point till discharging resume and the tank is completely empty.
3. Delay ballasting as far as possible and practical keeping draft, trim and stability of vessel in
consideration. As practical ballast tanks adjacent to cargo tanks being discharged.
5. If receiver or charterer permits and provides, load about 5000 Bbls of cutter stock and wash tanks
with cutter stock during discharge.
Rev. 0.0 2
3.4. Management of L.S.W.R Cargo
6. If the discharge is temporarily stopped, every effort should be made to drain all cargo lines and
main pumps by stripping them dry into a tank containing oil. This must be carried out immediately
after the main pumps are stopped in order to prevent oil solidifying in the exposed pipelines on deck
and in the pumproom.
7. On completion of cargo arm draining and disconnection, the manifold drain line section shall be
immediately cleared by steam blowing.
Rev. 0.0 3
3.5. Shore Line Flushing
Sea water flushing/plugging of SBM and SPM shore line is carried out to eliminate risk of pollution in
case:
1. SBM, SPM or the shore line is scheduled for maintenance or renewal
2. Approaching severe weather with potential to cause destruction
METHOD
Sea water flushing of shore line can be carried out by the following two methods,
Method 1 - By pumping sea water stored in either slop tank or any cargo tank
Method 2 - By pumping sea water directly from cargo sea chest
Conduct DRA
Risk Involved:
a. Oil pollution
b. Cargo contamination
c. Electrostatic generation
Associated Procedural Hazards:
a. Excess or short intake of water
b. Pump room flooding
Responsible Authority:
a. Chief Officer
Task Performer Be guided by iDMS – Cargo section (IMS-
a. Chief Officer overall in charge MO-CGO-CS) and in addition, the
(Supervising) following points shall be taken in
b. Duty Officer (Monitoring)
account.
c. Deck crew (Assisting)
a. Identify tanks to be filled with water
b. Method of filling sea water in tank
Prepare shore line flushing plan c. Exact volume of water required
d. Identify pumps, lines and manifolds
being used for flushing
Conduct ship-shore key meeting,
discuss plan with shore
representative and complete
“Ship-shore key meeting form
FR-C01 “
Rev. 0.0 1
3.5. Shore Line Flushing
Case 1 – Using Tank Cleaning Line Case 2 – Using Cargo Sea Chest
For the purpose of explanation an example of For the purpose of explanation an example of
filling Slop Port is considered filling Slop Port is considered
Open Slop Port machine valve (TC054), Open sea chest valve
check Slop Stbd machine valves (TC053,
TC055, TC056 & TC057), Residual oil tank
valve (TC066), Slop port bottom machine Observe flow in stripping pump discharge
valves (TC058, TC059 & TC060) and Slop line to Slop Port
tank master valve (TC051) are shut
Rev. 0.0 2
3.5. Shore Line Flushing
Start Fire/GS pump and start filling Slop Observe COP discharge to Slop Port
Port
On reaching the desired volume, stop Monitor Slop Port level and fill desired
Fire/GS pump volume of water
Shut angle valve (TC082) and fire hydrant Stop COP on reaching desired volume
Dis-connect portable hose to angle valve Shut cargo sea chest valve and Swing
(TC082) and rotate spectacle blank to shut cargo sea chest blank to shut position
position
Rev. 0.0 3
3.5. Shore Line Flushing
On completion of cargo
operation, await instruction of
terminal for flushing
Rev. 0.0 4
3.5. Shore Line Flushing
Conduct DRA
Risk Involved:
a. Oil pollution
Associated Procedural Hazards:
a. Pollution through cargo sea chest
b. Pump room flooding
Responsible Authority:
a. Chief Officer
Task Performer
a. Chief Officer overall in charge
(Supervising)
b. Duty Officer (Monitoring)
c. Deck crew (Assisting) Note:
Be guided by iDMS – Cargo section (IMS-
MO-CGO-CS) and local port regulations
Prepare shore line flushing plan
For the purpose of explanation an example of shore line flushing using No 1 COP and all manifolds is considered
On completion of cargo
operation thoroughly strip
pumproom pipelines, COP and
separator
Rev. 0.0 5
3.5. Shore Line Flushing
Rev. 0.0 6
3.5. Shore Line Flushing
Rev. 0.0 7
3.5. Shore Line Flushing
3.5.i. Method 2 - By Pumping Sea Water Directly from Cargo Sea Chest
For the purpose of explanation an example of shore line flushing using No 1 COP and all manifolds is marked
Rev. 0.0 8
3.6. Management of High Density Cargo
Note:
Obtain density information of
Due to their high kinematic viscosity, bitumen, tar and their
nominated cargo from charterers emulsions require very high temperature to facilitate loading
and discharging. Therefore, they are carried on special ships
capable of handling very high temperatures.
Note:
1. Heating reduces viscosity of cargo and facilitates in
its loading and discharging
2. Be guided by Annex 2 of this section “Management
of heated cargo”
Loading, discharging and carriage of high density cargo is similar to that of other oil cargoes, the
procedures and precautions present in section 2 of this manual shall be followed when carrying high
density cargo.
Rev. 0.0 1
3.7. Blending and Commingling
Blending Commingling
Physical blending refers to the process whereby The operation of loading in the same cargo
the ship's cargo pumps and pipelines are used space of same specification of cargo from
to circulate two or more different cargoes with different sources such as different shippers or
the intent to achieve a cargo with new product port is known as commingling.
designation. Example – loading fuel oil with density X from
Example – loading heavy crude oil grade A in one load port and fuel oil with density Y from
one set of tank and light crude oil grade B in second load port to achieve fuel oil of
another set of tanks and using ships pumps and homogeneous density without altering any
pipelines to mix both grades of crude oil to other property of cargo as flash point, pour
form medium grade crude oil with altered point, sulphur content etc.
density, viscosity, pour point, flash point etc.
Statutory Regulation
SOLAS Chapter 5 “Carriage of Cargoes” - Regulation 5.2 prohibits blending of bulk liquid cargoes and
production processes during “sea voyages”
Exemptions
1. SOLAS states “This prohibition does not preclude the master from undertaking cargo transfers at
sea for the safety of the ship or protection of the marine environment.”
2. Passing of cargo through external heat exchanger for the purpose of heating is exempted from the
provision of SOLAS Chapter 5 regulation 5.2
Weighted
Mixing
Rev. 0.0 1
3.7. Blending and Commingling
Procedures
Loading while in line mixing is similar to loading single grade cargo. Follow procedures for “loading
single grade cargo” present in section 2 of this manual. In addition, pay attention to the following
points.
For the purpose of explanation an example of loading two grades (A & B) with grade A loading arm connected to No 1
manifold and grade B to No 2 manifold is explained.
Rev. 0.0 2
3.7. Blending and Commingling
Note:
Conduct ship-shore key 1. Verify identity of cargoes and their nominated quantity
meeting and complete “Ship- 2. Agree on maximum loading rate, in such case maximum
shore key meeting form FR- loading rate shall be maximum loading rate of single
segregation
C01”
Precautions
1. The loading rates of both grades shall be same to achieve a homogeneous mixture.
2. There shall be no remains of previous cargo, as remains of previous cargo may alter property of
blend product.
3. The Bill of Lading shall have the correct description and quantity of blended cargo.
Rev. 0.0 3
3.7. Blending and Commingling
In Weighted Mixing two or more grades of cargos are mixed in a cargo tank basis weight percentage.
The grades are loaded sequentially in nominated cargo tanks to obtain desired final product.
Example- Vessel nominated to load a homogenous mixture of 30,000 MT cargo of grade 1 and 20,000
MT cargo of grade 2. On preparing the stowage plan No.1W COT has a loadable quantity of 6000 MT,
both grades shall be loaded in the percentage of their weight to form 6000 MT aggregate.
Total weight of cargo- 50,000 MT
Grade 1- 30,000 MT is 60% of total cargo weight
Grade 2- 20,000 MT is 40% of total cargo weight
Therefore weighted distribution in No.1W COT will be
Grade 1- 6000 X 60/100 = 3600 MT
Grade 2- 6000 X 40/100 = 2400 MT
This process is followed for all other nominated tanks.
Procedures
Follow procedures for “loading single grade cargo” present in section 2 of this manual. In addition the
following points shall be paid special attention.
Note:
Obtain information from 1. Obtain quantity and physical properties of individual
grades and blend product. In certain cases the property of
charterers and terminal of blend product significantly differ from original grades and
cargos being blended may require special attention while handling.
Example – In certain cases of crude oil mixing, wax dropout/
sedimentation occurs, if not handled correctly, it may result
Obtain Letter of indemnity (LOI) in high ROB.
from charterer 2. Obtain MSDS of individual grades and blend product.
Rev. 0.0 4
3.7. Blending and Commingling
Precautions
1. When mixing two grades with significant density difference, grade with higher density shall be
loaded first followed by grade with lower density. Loading lower density grade first, will result in
improper mixing and formation of layers.
2. There shall be no remains of previous cargo, as remains of previous cargo may alter property of
blend product.
3. The Bill of Lading shall have the correct description and quantity of blended cargo.
4. Where grades are loaded from different load ports, the Bill of Lading issued at first load port shall
be surrendered and new Bill of Lading with final product description and quantity obtained at last
load port.
Rev. 0.0 5
3.7. Blending and Commingling
Internal Transfer
Internal transfer is controlled movement of cargo from one tank to another within the ships hull
using ships pumps and pipelines.
As vessels tanks are divided into groups and have a ringmain pipelines system for loading and
discharging, the internal transfer can be carried out using two methods,
Method 1 – By Gravity
Method 2 – Using cargo pump and drop line – Preferred for inter group tanks
Procedure
The detailed procedures and precautions for internal transfer using any of the two methods is given
in Annex 3.8 of this manual. In addition to the procedures present in Annex 3.8, the following points
shall be carried out.
Rev. 0.0 6
3.7. Blending and Commingling
Rev. 0.0 7
3.7. Blending and Commingling
Rev. 0.0 8
3.8. Internal Transfer
Internal Transfer
It is controlled movement of cargo from one tank to another within the ship’s hull.
Internal Transfer is required in the following cases:
1. For the purpose of Blending and Commingling
2. To relocate a parcel on instructions of charterers
3. After incident - For safety of ship and environment
Methods
Method 2
Method 1
Transfer using Cargo Pump
Transfer by Gravity
and Drop Line
Carry out initial preparation as per section 2.3.5.1. – “Discharging – Single Grade”. In addition, carry
out the following points.
Conduct DRA
Risk Involved:
a. Excess transfer
b. Tank overflow
c. Inadvertent transfer
Associated Procedural Hazards:
a. Damage due to pressure surge
b. Bottom cargo lines subject to high
pressure
Responsible Authority:
a. Chief Officer
Task Performer:
a. Chief Officer overall in charge
Note:
(Supervising)
b. Duty Officer (Monitoring) Transfer plan shall cover the following points
a. Identity of nominated feed tanks, cargo grade and quantity
c. Deck crew (Assisting)
for transfer
b. Identity of destination tanks, present ullages and space
available
c. Final ullages and quantity, of feed tanks and destination
Prepare internal transfer plan tanks
d. Identity of pumps and lines required for transfer
e. Stability and stress for all stages of operation
(Avoid transverse asymmetric transfer)
Isolate and LOTO Non-Nominated f. Ballast operation for list and trim correction
tanks
Rev. 0.0 1
3.8. Internal Transfer
IMPORTANT
Transfer by gravity is only possible in cases where the destination tank is either empty or has cargo at
lower level than feed tank
Rev. 0.0 2
3.8. Internal Transfer
IMPORTANT
This method of transfer is only possible in cases where the destination tank and feed tank are from
different cargo groups.
For the purpose of explanation an example of transferring cargo from 6W COT of group 3 to 2W COT of group 2 is
explained.
Zero Check
Shut all cargo valves including
drain valves on deck and in Pump
room as listed in line-up checklist
Line up as follows,
a. Open No 3 line master valve
b. Open No 2 drop
c. Open No 2 and 3 deck
crossover valves
d. Open 2W COT tank main
bellmouth valves
Rev. 0.0 3
3.8. Internal Transfer
!
CAUTION
Open discharge valve and start
transfer The bottom lines are designed for a lower pressure rating.
Therefore, Monitor discharge pressure of COP. Do not exceed
discharge pressure at COP head, more than working pressure
of the suction side of the cargo lines.
Confirm cargo is transferring from
6W COT to 2W COT
Rev. 0.0 4
3.8. Internal Transfer
3.8.i. Line Diagram for Method 2 – Transfer using Cargo Pump and Drop Line
For the purpose of explanation an example of transferring cargo from 6W COT of group 3 to 2W COT of group 2 is marked.
Rev. 0.0 5
3.9. Cargo Handling in Cold Climate
Crude oil is a mixture of volatile liquid hydrocarbons mainly paraffins, naphthenes and aromatics. The
naphthenes form the heavy products and residues of crude oil. Crude oil freezes between -40 to -60
o
F. However, the heavy products and suspended residues in crude oil solidify way above its freezing
point and therefore require special attention while handling in cold climate.
Be guided by iDMS section “IMS-MO-CGO-CS section 5.17” and checklist CL-S12 “Cold Weather
Checklist”
LOADING OPERATION
1. Obtain cargo information from charterers prior arrival, check pour point, cloud point (Temperature
below which wax forms a cloudy appearance) and heating requirement.
2. De-ballasting operation shall be carried out as fast as possible, keeping vessel’s stability, stress and
draft in consideration.
3. In case of loading heated cargo in extremely cold condition, steam line shall be warmed up and
kept ready prior arrival load port.
4. In case of loading heated cargo with high pour point in extremely cold condition, the loading lines
shall be immediately drained once loading is completed or suspended.
5. On completion of draining and disconnecting loading arms, the drain lines shall be cleared using
compressed air or steam and drain valves left open.
DISCHARGING OPERATION
Non-Heated Cargo
1. If cargo property permits, obtain permission form commercials and heat cargo present in slop tank
for back flush use.
2. Strip each tank immediately after completing bulk discharge, do not postpone stripping as this will
allow cargo to cool down and settle residues.
3. In case of high ROB back flush tank with cargo from slop tank and re-strip the tank.
4. If cargo is suitable for COW, carryout COW of tanks with high ROB.
5. Delay ballasting as far as possible and practical keeping draft, trim and stability of vessel in
consideration. As practical ballast tanks adjacent to cargo tanks being discharged.
Heated Cargo
1. In case of discharging heated cargo, the temperature of cargo will fall rapidly once it is below the
heating coils. The tank shall be stripped immediately and heating stopped only on completion of
stripping.
2. If a heated cargo is discharged in very cold weather and the discharge is temporarily stopped,
every effort should be made to drain all cargo lines and main pumps by stripping them dry into a tank
containing oil. This must be carried out immediately after the main pumps are stopped in order to
prevent oil solidifying in the exposed pipelines on deck and in the pumproom.
Rev. 0.0 1
3.9. Cargo Handling in Cold Climate
3. If a fairly lengthy stop occurs after the level of cargo in a tank has fallen below the heating coils, the
level should be raised by gravitating cargo from another tank. Pumping should recommence only
after the temperature has been raised to the permissible maximum.
4. On completion of draining and disconnecting loading arms, the drain lines shall be cleared using
compressed air or steam and drain valves left open.
5. Delay ballasting as far as possible and practical keeping draft, trim and stability of vessel in
consideration. As practical ballast tanks adjacent to cargo tanks being discharged.
1. While handling ballast in sub zero condition, ballast tank vents should be free from ice formation
for free flow of air. Prior arrival port, during port stay and prior departure port, any ice formation on
ballast tank vents should be removed promptly.
2. Sounding pipes shall be covered with canvas to avoid freezing and same removed prior operation.
3. To avoid freezing, salt water should be ballasted, if vessel is trading in fresh water area, the
ballasted fresh water should be replaced with salt water at first opportunity.
4. Periodic lowering and raising of ballast water surface shall be carried out to avoid freezing.
5. Sea chest must be kept free from ice formation by air bubbling or heating.
Rev. 0.0 2
3.10. Cargo Calculation
Volume: The space occupied by a substance is volume. Units of volume are m3, Barrels, Liters etc.
Total Observed Volume (TOV): It is Total Observed Volume of cargo at observed temperature
including free water. The present temperature of oil in tank is observed temperature.
Gross Observed Volume (GOV): TOV – Free Water
Gross Standard Volume (GSV): Gross oil volume at standard temperature. 15 oC and 60 oF are
standard temperature.
Density: It is mass of a unit volume of a substance. Units of density are g/cm3, Kg/m3,T/m3 etc.
For oil calculation, density can be provided by supplier in any of the following formats,
1. Density at 15 oC - This is the mass per unit volume of oil at 15 oC
2. Relative density at 60 oF – This is the density of oil at 60 oF divided by the density of water
3. API Gravity – Mathematical number published by American Petroleum Institute which bears a
mathematical relation to relative density.
API gravity at 60 oF = (141.5/ Relative Density at 60 oF) – 131.5
Volume Correction Factor (VCF): It is the factor obtained from ASTM tables to correct observed
volume to standard volume.
GSV = GOV x VCF
Weight Correction Factor (WCF): It is the factor obtained from ASTM tables to convert standard
volume into mass.
Mass = GSV x WCF
On Board Quantity (OBQ): Quantity of cargo present onboard prior loading operation.
Free Water: It is the water that exists as a separate layer below the oil.
Rev. 0.0 1
3.10. Cargo Calculation
Use ASTM table and obtain Use ASTM table and obtain Use ASTM table and obtain
VCF VCF VCF
Table 6A – For Crude Oil Table 24A – For Crude Oil Table 54A – For Crude Oil
Table 6B – For Product Oil Table 24B – For Product Oil Table 54B – For Product Oil
Use ASTM table and obtain Use ASTM table and obtain
WCF for Long Tons and Use ASTM table and obtain WCF for Long Tons and
Metric Tons WCF for Long Tons Metric Tons
Table – 11 for Long Tons Table – 29 for Long Tons Table – 57 for Long Tons
Table – 13 for Metric Tons Table – 56 for Metric Tons
Weight in Long Tons = GSV x Weight in Long Tons = GSV x Weight in Long Tons = GSV x
WCF (Table 11) WCF (Table 29) WCF (Table 57)
Note:
Table 6A & 6B – These tables are entered using API and Observed Temperature.
Table 24A & 24B – These tables are entered using Relative Density and Observed Temperature.
Table 54A & 54B – These tables are entered using Density at 15oC and Observed Temperature.
Rev. 0.0 2
3.10. Cargo Calculation
Rev. 0.0 3
3.10. Cargo Calculation
Rev. 0.0 4
3.10. Cargo Calculation
For Grade A
Obtain WCFA from ASTM tables
and calculate Weight of Grade A
(WeightA)
WeightA = GSVA x APIA
For Grade B
Obtain WCFB from ASTM tables
and calculate Weight of Grade B
(WeightB)
WeightB = GSVB x APIB
Note:
o
In case the vessel is provided with Density at 15 C, use volume in cubic meters and follow the same
procedure as mentioned above. Use ASTM table 56 to obtain Density at 15oC for corresponding WCFF
Rev. 0.0 5
3.10. Cargo Calculation
CARGO TANK
h S
BTM
WEDGE FORMULA
V = 1 x { ( U – D x F) x F + S}2 x W
(2F)
Where,
V: Volume of liquid (m3)
F: Trim factor (Trim/LBP = h/l )
U: Distance between sounding measuring point and aft bulkhead of the tank (m)
D: Depth of tank at sounding measuring point (m)
S: Sounding measured from sounding measuring point (m)
W: Width of tank bottom at tank’s aft bulkhead position (m)
The volume of liquid obtained from the above formula is approximate volume as, the formula is true
for box shaped cargo tank. Vessel’s tanks are seldom box shape and they contain internal structures,
heating coils, pipelines etc. which result in discrepancies.
Condition of Use:
The cargo in tank in not touching the forward bulkhead of tank resulting in cargo wedge.
Precautions while using Wedge formula:
1. Observe sounding of tank at all available locations to ensure the cargo is not touching the forward
bulkhead of tank.
2. Measure sounding from the aftermost sounding point or sounding point with wedge data
available. Do not use radar gauge/remote gauge to obtain soundings.
3. Keep vessel upright (No list), to avoid list correction.
4. Remnant cargo is liquid. Do not use this formula in case of sludge ROB.
Rev. 0.0 6
3.11. Precautions for Ballast Water Exchange
IMPORTANT
Conduct ballast water exchange as per approved Ballast Water Management Plan
Planning Stage
Conduct DRA
Risk Involved:
a. Personnel Injury due to unsafe access
to deck area
Associated Procedural Hazards:
a. Oil Pollution
b. Structural Damage
c. Freezing of ballast water in sub zero
condition
d. Non- compliance with IMO stability Note:
criteria The plan should be in accordance with approved ballast
Responsible Authority: water management plan and in addition the following
1. Chief Officer points must be taken into account:
1. Stability and strength calculation of each stage
Task Performer: 2. Any stability restriction as per trim and stability manual
1. Chief Officer overall in charge 3. IMO stability and bridge visibility criteria
(Supervising) 4. Number of deck openings for flow through method
2. Duty Engineer and Duty Officer 5. Time required for operation
(Monitoring) 6. Region of water ballast exchange
3. Pump man and Deck crew (Assisting) 7. Traffic density expected during the exchange operation
8. Local regulations for the Ballast Exchange, example - Black
sea countries, Great lakes (Canada) etc.
9. Additional work load of master and crew
Draw ballast water exchange plan
Operation Stage
IMPORTANT
Carry out heavy weather ballasting as per condition given in approved Trim and Stability booklet
Planning Stage
Conduct DRA
Risk Involved:
a. Oil Pollution
Associated Procedural Hazards:
a. Oil Pollution
b. Pressure surge in pipe line
Responsible Authority:
1. Chief Officer
Task Performer:
1. Chief Officer overall in charge Note:
(Supervising) 1. Ship specific plan shall be drawn for Heavy Weather
2. Duty Engineer (Monitoring) Ballasting in accordance with condition given in trim and
3. Pump man and Deck crew (Assisting) stability booklet.
2. If circumstances permit cargo tanks dedicated for heavy
weather ballast shall be crude oil washed.
3. All cargo pumps and associated pipe lines shall be
Precautions prior heavy weather thoroughly drained and stripped.
ballasting
Operation Stage
Rev. 0.0 1
FR-C09-PT
DAY 3 DAY 4
Tank / Line
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1C
1P
1S
2C
2P
2S
3C
3P
3S
4C
4P
4S
5C
5P
5S
SLP P Heating
SLP S Heating
NO 1 LINE
NO 2 LINE
NO 3 LINE
Rev. 0.0 1
IMS-FC-CGO To be filed in File:
FR-C09-PT
DAY 5 DAY 6
Tank / Line
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1C
1P
1S
2C
2P
2S
3C
3P
3S
4C
4P
4S
5C
5P
5S
SLP P
SLP S
NO 1 LINE
NO 2 LINE
NO 3 LINE
Procedure Employed:
1. Person overall incharge of conducting this operation is C/O. He will be assisted by an OOW in CCR and 2 watchkeepers on deck as per duty roster prepared and attached with this plan.
2. Initial stage - Team 1, two members will change over cargo seachest blank. Team 2, two members will swing tankcleaning heater blanks.
3. Check O2 content of all tanks at 3 levels, record same in port log. The O2 content in tanks shall be less than 5% by Vol. Maintain 800 mmWG pressure in all tanks.
4. Line up stripping pump to discharge water to Slop P. Creat a vacuum in sea chest line and open sea chest while the pump is running continiously. Once the line is flushed and is filled with sea water,
start no 1 COP and flush no 1 line P/Rm section, main deck section, drop section and bottom line, returning the water to slop P. Follow the same process for line 2 and 3.
5. Fill approx xxx m3 of water in Slop P (Dirty Slop). Start heating of Slop P to maintain temp of water around 50 deg C.
6. Hot water wash Slop S, 3 cycles of full wash at mininum speed, with suction from and discharge to Slop P. (If provided, use tank cleaning heater for heating water, set TC heater temp at 65 deg C.)
7. Upon completion of Slop S stripping. Open seachest and fill approx xxx m3 of water in Slop P keeping the decanting valve between Slop P and S open.
8. Start heating Slop S to maintain temp of water anound 50 deg C.
9. Line up 1C COT for hot water washing, set machines on full wash cycle at minimum speed. Once ready start No1 COP and start eductor, suction from Slop S and discharge to Slop P.
10. On completion of 3 complete cycles of full wash stop hot water washing of 1C COT, educt the tank and verify using sounding rod.
11. Change over 1C COT for purging using dilution method, For dilution method, open PV valve manually or purge stack, Keep IG branch valve of 1C COT open and shut IG branch valves of all other tanks
except Slop P & S.
12. Line up 1W COT for hot water wash as per directions mentioned in step 9 and 10.
13. On completion of 1W COT hot water washing and 1C COT purging, change over to purging of 1W COT as per directions mentioned in step 11.
14. On completion of purging of 1C COT, shut the IG branch inlet valve to 1C COT and swing the blank on IG branch line to closed position. Open manholes of 1C COT for rigging hydroblower and start
gas freeing 1C COT using hydroblower.
15. Hot water wash, purge and gas free all tanks concurrently as per bar diagram mentioned above following the directions mentioned in steps 9 to 14.
16. For washing group 2 tanks, use of no 2 COP is preffered with suction from Slop S and discharge to Slop P.
17. For washing group 3 tanks, use of no 3 COP is preffered with suction from Slop S and discharge to Slop P.
18. On completion of Hot water washing of 5W COT. Trip the COP and strat stripping pump to educt all lines including COP and seperator.
19. Allow the water in slops to settle for atleast 18 hrs, keep heating for this time period maintain temp of slops around 40 deg C.
20. After 18 hrs of setteling time, obtain the ullage and interface of both tanks. Stop heating for Slop S. Line up ODME for decanting Slop S using No 1 COP or stripping pump.
21. Start CPO or Stripping pump with suction from slop S and discharge overboard using ODME. Dischage Slop S. Keep a continious watch overboard and on the level of slop S using UTI.
22. Line up Slop S for hot water washing, Use no 1 COP with suction from Slop P and discharge to Slop P
23. Once water washing of Slop S is completed, change over tank for purging, followed by gas freeing. Use directions mentioned in step 11 and 14.
24. On completion of washing allow Slop S to settle for atleast 18 hrs, obtain accurate ullage and interface. Stop heating for Slop S. Open IG branch valve of Slop S. Line up ODME for decanting Slop S
using stripping pump.
25. Start Stripping pump with suction from slop P and discharge overboard using ODME. Dischage Slop P till 1.5m of allowance from interface. Keep a continious watch overboard and on the level of slop
S using UTI.
Rev. 0.0 2
IMS-FC-CGO To be filed in File:
FR-C09-PT
S using UTI.
IMPORTANT POINTS:
1. Purged tank shall have HC vol in tank is less than 2% vol and H2S ppm less than 5 PPM.
2. Gas free tank shall have HC vol less than 1% LEL, H2S 0 ppm and O2 20.9% vol.
3. When obtaining gas readings ventilation shall be stopped and tank depressurized. The readings shall be obtained from multiple locationsand at three levels.
4. All ODME operation will be carried out only during daylight, with a watchkeeper standing by at the discharge location.
5. Both IG blowers will be used for purging. Both blowers combined capacity is - xxxx m3/hr
6. For Gas freeing hydro blowers will be used. Individual hydro blower capacity is - xxxx m3/hr at x bar of drive pressure.
Gas freeing using inert gas fans Settling of slop tank Prepared by C/O Verified by Master
Name: Name:
Rev. 0.0 3
IMS-FC-CGO To be filed in File:
3.14. Guidelines for Entries in Port Log
Loading Operation
Additional entries for loading operation.
1. Water ballast surface check prior de-ballasting.
2. Time of commence loading, identity of cargo and identity of tanks being loaded. (Make separate
entry for each parcel)
3. Time when maximum loading rate is achieved and any change of rate.
Rev. 0.0 1
3.14. Guidelines for entries in Port Log
Discharging Operation
Additional entries for discharging operation
1. Testing of emergency shut down system (pump trips).
2. Starting and stopping time of inert gas system including identity of IG blower.
3. Starting and stopping time of cargo pumps including stripping pump.
4. Time of commence discharge, identity of cargo and identity of tanks being discharged. (Make
separate entry for each parcel).
5. Time when maximum rate is achieved.
6. Time of commence ballasting including identity of ballast tanks.
7. Starting and stopping time of ballast pumps.
8. Starting and stopping time of eductor including identity of eductor, feed pump and feed tank.
9. Crude Oil Washing operation including identity of tank, start/stop time, washing pattern and oxygen
content of tank.
10. Status of ballast tank HC detection system.
Special Operation
1. Detailed record of tank cleaning, inerting, purging and gas freeing operation including start/stop
time. Identity of tank, method used etc.
2. SBM operation – The lead and direction of SBM at regular interval.
Rev. 0.0 2
3.14.2. Port Log Sample
Rev. 0.0 3
3.14.2. Port Log Sample
xxxx Vessel request terminal to increase to maximum loading rate of 50,000 Bbls/Hr
xxxx AB xxxx carried out inspection of gangway and mooring lines. Mooring lines tended.
Deck safety and security round completed. Item “R” of ship shore safety checklist complied
with and in order. No breach of security observed.
xxxx Pump room safety round completed, ventilation, illumination and communication. Pump room
xxxx Terminal suspended loading. Tank valves of 1W, 2W, 4W & 5W shut.
xxxx Cargo Figures comparison carried out, Ship Figure xxxx Bbls GSV, Shore Figure xxxx Bbls GSV
xxxx Line checked by C/O and AB, Vessel informed Terminal ready to discharge cargo.
Rev. 0.0 4
3.14.2. Port Log Sample
xxxx Pump room safety round completed, COP casing temperature monitored, no abnormal
xxxx AB xxxx carried out inspection of gangway and mooring lines. Mooring lines tended.
Deck safety and security round completed. Item “R” of ship shore safety checklist complied
with and in order. No breach of security observed.
xxxx No.3 COP started
xxxx AB xxx observed ship side from designated observation area and no oil sheen sighted
xxxx Started No. 1 eductor using No. 1 COP in closed cycle with Slop P tank.
1P COT Upper – 4.2%, Middle – 4.1% & 1S COT Upper – 4.1%, Middle – 4.0%
xxxx Commence bottom wash of 1W COT
Rev. 0.0 5
3.14.2. Port Log Sample
xxxx IG stop
WBT. IG blower 1 in operation. Tank gauging system communication failure alarm received,
system was restarted and working satisfactory since then. Present UKC is xxx m. CL03 and CL04
complied with and in order. Watch handed over to 3rd Officer.
(Signature of Handing over OOW) (Signature of Taking over OOW)
Rev. 0.0 6
3.15. Alarms and Actions
Cargo and ballast handling system is fitted with various safeguards in the form of alarms and trips.
During cargo operation an officer in-charge can encounter these alarms and trips, the way an officer
responds to an alarm or trip will determine the final consequence.
Below is a guidance given to officer in-charge, for his action in case of an alarm.
General Alarms
S. No. Alarm / Trip Action
1 High Wind Alarm (Set as per wind a. Inform terminal
criteria of terminal) a. Stop Cargo operation
2 High-High Wind Alarm (Set as per a. Inform terminal
wind criteria of terminal) a. Disconnect cargo hose and consider
unberthing
3 Remote Valve Operation Hydraulic a. Reduce number of valves operating
System Low Pressure Alarm simultaneously
b. Start stand-by pump
c. Check pipeline for leakages
4 Remote Valve Operation Hydraulic a. Re-fill tank
System Low Level Alarm b. Check pipeline for leakages
5 Pumproom Gas Alarm a. Evacuate pumproom
b. Follow contingency plan
6 Pumproom Bilge Alarm with a. Evacuate pumproom and Follow
Pumproom Gas Alarm contingency plan
7 Pumproom Bilge Alarm a. Check the content of Bilges
b. Check the source of flooding
8 Forepeak Bilge Alarm a. Check the content of Bilges
b. Check the source of flooding
Rev. 0.0 1
3.15. Alarms and Actions
Loading Operation
S. No. Alarm / Trip Action
1 Cargo Tank Overfill Alarm a. Open slack cargo tank valve
b. Shut valve of tank with overfill alarm
c. Monitor level of tank by UTI and tank
gauging system
2 Cargo Tank High Level alarm a. Check the final ullage of tank and
load with caution
b. If final ullage is below tank high level
alarm level, stop loading in tank.
c. Monitor level of tank by UTI and tank
gauging system
3 Cargo Tank Low Pressure Alarm a. Shut mast riser and stop venting
Or
b. In case of using VRS, inform terminal
to reduce vapor recovery rate
4 Cargo Tank High Pressure Alarm a. Open mast riser full
Or
b. In case of using VRS, inform terminal
and increase vapor recovery rate
c. Reduce loading rate
5 High Temperature Alarm (In case of a. Verify cargo temperature with UTI
loading heated cargo or in case of b. If heating, stop heating
heating cargo while loading) c. Inform terminal to reduce loading
rate
d. Fill adjacent ballast tanks
Discharging Operation
S. No. Alarm / Trip Action
1 COP Casing High Temperature a. Open discharge valve full
Alarm b. Reduce COP RPM
c. Stop COP if temperature is still rising
2 COP Bearing High Temperature a. Reduce COP RPM
Alarm b. Stop COP if required
3 Individual Cargo Tank Low Pressure a. Stop discharging from concerned
Alarm tank
b. Check status of IG branch valve
4 Individual Cargo Tank High Pressure a. Compare concern tank pressure with
Alarm other tanks
b. Full open tank valve and confirm
cargo discharging
c. Reduce IG regulating valve setting
Rev. 0.0 2
3.15. Alarms and Actions
Discharging Operation
S. No. Alarm / Trip Action
5 Cargo Tank Low Level Alarm a. Shut tank main bellmouth valve and
keep stripping bellmouth valve open
b. Discharge with caution, once tank
empty, shut stripping bellmouth
valve
6 Cargo Tank High Level Alarm a. Check status of tank valve. Shut both
main and stripping bellmouth valves
if open
b. Verify the ullage of tank using UTI
c. Check for any other source of ingress
as tank cleaning line, drain line,
eductor discharge line or ODME re-
circulating line
7 Stripping Pump – Over Speed Alarm a. Reduce working steam volume by
regulating pneumatic control vlave
8 High Temperature Alarm (In case of a. Verify cargo temperature with UTI
discharging heated cargo) b. If heating, stop or reduce heating
c. Fill adjacent ballast tanks
Rev. 0.0 3
3.16. Additional Notes to Reader
M M
G2
W L W L
G G G1
B B B1
K K
Partially filled tank in upright condition (Fig-1) Partially filled tank in heeled condition (Fig-2)
In figure 2,
BB1 – Shift in center of buoyance
GG1 – Shift in center of gravity
GM – Original metacentric height
GG2 – Virtual loss of center of gravity due to shifting liquid
G2M – Reduced metacentric height
SOLAS chapter 5 – Regulation 22 requires, the view of the sea surface from the conning position shall
not to be obscured by more than 2L (LBP) or 500m, whichever is less, forward of the bow to 100 on
either side for all conditions of draft and trim.
The above requirement shall be maintained at all times i.e. At sea and during port operations.
Rev. 0.0 1
3.16. Additional Notes to Reader
Rev. 0.0 2