Professional Documents
Culture Documents
KONTRAK 45,240,101,225.00
ASSUMSI PRODUKSI 13,572,030,367.50 18,096,040,490.00 13,572,030,367.50
SISA 21,869,125,225.00
Loss/profit Terhadap kontrak 48.34%
Modal kerja 23,370,976,000.00
Profit terhadap modal 93.57%
Resume Analisa biaya pekerjaan Well Pad Paket 1 RESUME COST 23,370,976,000.00
BULAN PERTAMA BULAN KEDUA BULAN KETIGA
Biaya Biaya Biaya
8,122,210,000.00 7,642,983,000.00 7,605,783,000.00
Rental Crane Piping dan JWDD 35 ton 240,000,000.00 1 1 1 Rp240,000,000 Rp240,000,000 Rp240,000,000
Rental DT 30,000,000.00 28 28 28 Rp840,000,000 Rp840,000,000 Rp840,000,000
Rental Excavator 50,000,000.00 4 4 4 Rp200,000,000 Rp200,000,000 Rp200,000,000
Rental Dozer D6 64,000,000.00 2 2 2 Rp128,000,000 Rp128,000,000 Rp128,000,000
Rental Smooth Drum 44,000,000.00 2 2 2 Rp88,000,000 Rp88,000,000 Rp88,000,000
Rental sheep foot 44,000,000.00 2 2 2 Rp88,000,000 Rp88,000,000 Rp88,000,000
Rental Grader 60,000,000.00 2 2 2 Rp120,000,000 Rp120,000,000 Rp120,000,000
Fuel Tank 5.000 Liters 47,200,000.00 1 1 1 Rp47,200,000 Rp47,200,000 Rp47,200,000
Water Tank 10.000 Liters 45,400,000.00 2 2 2 Rp90,800,000 Rp90,800,000 Rp90,800,000
Hand compactor 3,500,000.00 1 1 1 Rp3,500,000 Rp3,500,000 Rp3,500,000
Bus 12,000,000.00 6 6 6 Rp72,000,000 Rp72,000,000 Rp72,000,000
Lowboy 65,000,000.00 2 2 2 Rp130,000,000 Rp130,000,000 Rp130,000,000
Crane 50 TON 160,000,000.00 1 1 1 Rp160,000,000 Rp160,000,000 Rp160,000,000
Foco Truck 15 TON 40,000,000.00 2 2 2 Rp80,000,000 Rp80,000,000 Rp80,000,000
Welding Mechine 8,500,000.00 4 4 4 Rp34,000,000 Rp34,000,000 Rp34,000,000
Double Cabin 12,500,000.00 8 8 8 Rp100,000,000 Rp100,000,000 Rp100,000,000
Light Vehicle 6,500,000.00 2 2 2 Rp13,000,000 Rp13,000,000 Rp13,000,000
Sub total Rp2,434,500,000 Rp2,434,500,000 Rp2,434,500,000
Project Construction Cordinator 30,000,000.00 1 1 1 Rp30,000,000 Rp30,000,000 Rp30,000,000
Site Manager 24,000,000.00 1 1 1 Rp24,000,000 Rp24,000,000 Rp24,000,000
Project Control Leader 14,000,000.00 1 1 1 Rp14,000,000 Rp14,000,000 Rp14,000,000
HRD Supervisor 7,000,000.00 1 1 1 Rp7,000,000 Rp7,000,000 Rp7,000,000
Payroll staff 6,500,000.00 1 1 1 Rp6,500,000 Rp6,500,000 Rp6,500,000
Construction Supervisor 8,500,000.00 2 2 2 Rp17,000,000 Rp17,000,000 Rp17,000,000
QC Supervisor 8,000,000.00 1 1 1 Rp8,000,000 Rp8,000,000 Rp8,000,000
QC admin 5,500,000.00 1 1 1 Rp5,500,000 Rp5,500,000 Rp5,500,000
CEM Inspector 7,000,000.00 1 1 1 Rp7,000,000 Rp7,000,000 Rp7,000,000
HES Corporate Coordinator 16,000,000.00 1 1 1 Rp16,000,000 Rp16,000,000 Rp16,000,000
HES Supervisor 6,500,000.00 1 1 1 Rp6,500,000 Rp6,500,000 Rp6,500,000
Scheduler & Estimator 8,000,000.00 0 0 0 Rp0 Rp0 Rp0
Drafter/Enggineering 6,500,000.00 1 1 1 Rp6,500,000 Rp6,500,000 Rp6,500,000
Quantity Surveyor 6,000,000.00 1 1 1 Rp6,000,000 Rp6,000,000 Rp6,000,000
General Admin/Document Control 5,500,000.00 1 1 1 Rp5,500,000 Rp5,500,000 Rp5,500,000
Procurement (Material man) 5,500,000.00 1 1 1 Rp5,500,000 Rp5,500,000 Rp5,500,000
Foreman/Mandor pelaksana 6,500,000.00 4 4 4 Rp26,000,000 Rp26,000,000 Rp26,000,000
Hes man 5,500,000.00 8 8 8 Rp44,000,000 Rp44,000,000 Rp44,000,000
Dump man 5,000,000.00 4 4 4 Rp20,000,000 Rp20,000,000 Rp20,000,000
Spotter 5,000,000.00 12 12 12 Rp60,000,000 Rp60,000,000 Rp60,000,000
Flagman 5,000,000.00 12 12 12 Rp60,000,000 Rp60,000,000 Rp60,000,000
Swamper 4,800,000.00 3 3 3 Rp14,400,000 Rp14,400,000 Rp14,400,000
Load Checker 5,000,000.00 2 2 2 Rp10,000,000 Rp10,000,000 Rp10,000,000
Survey (Foreman) 6,000,000.00 2 2 2 Rp12,000,000 Rp12,000,000 Rp12,000,000
Instrument man Survey 5,500,000.00 2 2 2 Rp11,000,000 Rp11,000,000 Rp11,000,000
Chain man Survey 5,000,000.00 2 2 2 Rp10,000,000 Rp10,000,000 Rp10,000,000
Welder 7,000,000.00 5 5 5 Rp35,000,000 Rp35,000,000 Rp35,000,000
Rigger 5,500,000.00 6 6 6 Rp33,000,000 Rp33,000,000 Rp33,000,000
Office boy 3,500,000.00 1 1 1 Rp3,500,000 Rp3,500,000 Rp3,500,000
Pipe fitter 1 6,500,000.00 4 4 4 Rp26,000,000 Rp26,000,000 Rp26,000,000
Pipe fitter 2 6,000,000.00 4 4 4 Rp24,000,000 Rp24,000,000 Rp24,000,000
Helper piping 5,000,000.00 4 4 4 Rp20,000,000 Rp20,000,000 Rp20,000,000
Material baja 2,000,000.00 1 Rp2,000,000 Rp0 Rp0
Operator 6,000,000.00 9 9 9 Rp72,000,000 Rp72,000,000 Rp72,000,000
Driver DT 5,800,000.00 2 2 24 Rp162,400,000 Rp162,400,000 Rp139,200,000
Driver Bus 5,000,000.00 6 6 6 Rp30,000,000 Rp30,000,000 Rp30,000,000
Chief Security 5,000,000.00 1 1 1 Rp5,000,000 Rp5,000,000 Rp5,000,000
Security 3,500,000.00 8 8 8 Rp28,000,000 Rp28,000,000 Rp28,000,000
Digger man 3,500,000.00 8 8 4 Rp28,000,000 Rp28,000,000 Rp14,000,000
Consumble 30,000,000.00 1 1 1 Rp30,000,000 Rp30,000,000 Rp30,000,000
Engineer Civil 9,000,000.00 1 1 1 Rp9,000,000 Rp9,000,000 Rp9,000,000
Helper JWDD 5,500,000.00 3 3 3 Rp16,500,000 Rp16,500,000 Rp16,500,000
Operator piling 5,800,000.00 1 1 1 Rp5,800,000 Rp5,800,000 Rp5,800,000
Skill 1 piling 5,500,000.00 1 1 1 Rp5,500,000 Rp5,500,000 Rp5,500,000
Kayu meranti sembarang 12000.00 25 Rp300,000 Rp0 Rp0
Papan Meranti ( M2 ) 12000.00 11 Rp132,000 Rp0 Rp0
Helper carpenter 5,000,000.00 1 1 1 Rp5,000,000 Rp5,000,000 Rp5,000,000
Paku 18000.00 1 1 1 Rp18,000 Rp18,000 Rp18,000
Kawat las CS 40000.00 1 1 1 Rp40,000 Rp40,000 Rp40,000
OXI 100000.00 1 1 1 Rp100,000 Rp100,000 Rp100,000
LPG 350000.00 1 1 1 Rp350,000 Rp350,000 Rp350,000
Sub total Rp974,040,000 Rp971,608,000 Rp934,408,000