PEKERJAAN MEKANIKAL
I PEKERAJAAN MEKANIKAL LANTAI 1
A DEEP WELL
1 Pekerjaan persiapan
- Analisa Geolistrik 1 ls 750,000.00 5,500,000.00 750,000.00 5,500,000.00 6,250,000.00
- Pembersihan Lokasi Kerja 1 ls 250,000.00 1,500,000.00 250,000.00 1,500,000.00 1,750,000.00
- Transportasi Alat alat bor 1 ls 150,000.00 2,000,000.00 150,000.00 2,000,000.00 2,150,000.00
- Tanah Liat/Lempung 15 m3 100,000.00 500,000.00 1,500,000.00 7,500,000.00 9,000,000.00
- Semen Bentonik 10 zak 100,000.00 250,000.00 1,000,000.00 2,500,000.00 3,500,000.00
- Pembuatan Bak Sirkulasi 1 ls 300,000.00 750,000.00 300,000.00 750,000.00 1,050,000.00
Sub Jumlah 1 3,950,000.00 19,750,000.00 23,700,000.00
2 Jasa Pengeboran
- Main Hole dia 4" 180 mtr 75,000 500,000.00 13,500,000 90,000,000.00 103,500,000.00
- Reaming dia 6" 180 mtr 75,000 150,000.00 13,500,000 27,000,000.00 40,500,000.00
- Reaming dia 8" 180 mtr 75,000 150,000.00 13,500,000 27,000,000.00 40,500,000.00
Sub Jumlah 2 40,500,000 144,000,000.00 184,500,000.00
3 Konstruksi
- Analisa Loging 1 ls 650,000.00 6,500,000.00 650,000.00 6,500,000.00 7,150,000.00
- Pipa Casing Conduit Pipa GIP dia 6" 90 mtr 52,000.00 520,000.00 4,056,000.00 40,560,000.00 44,616,000.00
Pipa GIP dia 4" 80 mtr 25,500.00 242,666.67 1,456,000.00 14,560,000.00 16,016,000.00
- Screen Stainless Steel dia 4" 20 mtr 39,000.00 390,000.00 468,000.00 4,680,000.00 5,148,000.00
- Gravel Pack 5 m3 45,500.00 455,000.00 227,500.00 2,275,000.00 2,502,500.00
- Semen 4 zak 9,500.00 91,000.00 36,400.00 364,000.00 400,400.00
- Tutup Sumur dia 6" 1 ls 19,500.00 195,000.00 19,500.00 195,000.00 214,500.00
Sub Jumlah 3 6,913,400.00 69,134,000.00 76,047,400.00
4 Pompa
- Pipa Outlet GIP dia 2" 185 mtr 15,000.00 95,000.00 2,775,000.00 17,575,000.00 20,350,000.00
- Shoch dia 2" 6 buah 2,500.00 19,500.00 15,000.00 117,000.00 132,000.00
- Elbow dia 2" 8 buah 3,500.00 27,300.00 28,000.00 218,400.00 246,400.00
- Cek Valve dia 2" 4 buah 6,500.00 45,500.00 26,000.00 182,000.00 208,000.00
- Get Valve dia 2" 4 buah 9,750.00 46,800.00 39,000.00 187,200.00 226,200.00
- Pompa Sub marsible 4 unit 4,500,000.00 45,000,000.00 18,000,000.00 180,000,000.00 198,000,000.00
- Type SP 17 - - -
- Kapasitas 17 m3/jam - - -
- Total Head 120m - - -
- Power 5,5kw - - -
- Phasa 3 phasa - - -
- Panel Kontrol 2 WLC 2 unit 1,500,000.00 10,000,000.00 3,000,000.00 20,000,000.00 23,000,000.00
- 1 unit Boks Panel Coating - - -
- 1 buah Kontaktor 3 pole 32A LC1 D 40 - - -
- 1 buah Magnetik thermar 25A THN 25 - - -
- 6 buah Pilot lamp - - -
- 1 buah selektor Switch A - O - M Camsco - - -
- 1 buah Volt Meter 500V Camsco - - -
- 1 buah Ampere Meter 50A Camsco - - -
Sub Jumlah 4 23,883,000.00 218,279,600.00 242,162,600.00
Sub Jumlah Pekerjaan Deep Well (A) 75,246,400.00 451,163,600.00 526,410,000.00
B PLUMBING
1 Pompa Transfer Air Bersih ke rooftank & unit gedung 10 Unit 1,150,000.00 22,550,000.00 11,500,000.00 225,500,000.00 237,000,000.00
- Tipe : Centrifugal End Suction
- Kapasitas : 2 x ( 125L/m)
- Total Head : 20 meter
- Power : 2 x 1,5 kW/2900RPM/380V/3Ph/50Hz
- Seal tape : Mekanikal Seal
- Jumlah : 2 Unit Pompa
- Operation : Pararel Alternatif
- Accessories : Lengkap dengan kontrol panel,Presure Tank
Presure Switch, Presure Gauge
2 Pompa Transfer Air Kotor antar bak penampung 6 Unit 1,150,000.00 22,550,000.00 6,900,000.00 135,300,000.00 142,200,000.00
- Tipe : Centrifugal End Suction
- Kapasitas : 2 x ( 125L/m)
- Total Head : 20 meter
- Power : 2 x 1,5 kW/2900RPM/380V/3Ph/50Hz
- Seal tape : Mekanikal Seal
- Jumlah : 2 Unit Pompa
- Operation : Pararel Alternatif
- Accessories : Lengkap dengan kontrol panel,Presure Tank
Presure Switch, Presure Gauge
PEKERJAAN MEKANIKAL
I PEKERJAAN MEKANIKAL LANTAI 1
A DEEP WELL Rp. 526,410,000.00
B PLUMBING Rp. 1,171,113,680.00
C HYDRANT Rp. 1,330,235,315.00
Rp. 3,027,758,995.00
II PEKERAJAAN MEKANIKAL LT 2 DAN LT 3
A PLUMBING Lantai 2 dan Lantai 3 Rp. 418,986,250.00
Rp. 418,986,250.00
III PEKERJAAN GAS MEDIS
Instalasi Gas Medis lantai 1 Rp. 1,081,182,850.00
Instalasi Gas Medis lantai 2 Rp. 1,150,638,500.00
Instalasi Gas Medis lantai 3 Rp. 1,176,571,865.00
Central Gas Medis Rp. 532,500,000.00
Rp. 3,940,893,215.00
IV PEKERAJAAN MEKANIKAL PELENGKAP
A Roof tank
tanki air produk pinguin type stainlessteel Rp. 397,500,000.00
Lengkap denganSBF UNP 120 Manhole, Flange Rp. 14,880,000.00
JIS 10K, dia 3" untuk inlet autlet dan overflow
B Wastafel stanlis setyle Untuk Ruang Operasi Rp. 227,500,000.00
C WTP Water treatmen RO Rp. 1,237,500,000.00
D Bak Penampung Air Bersih dan Sumur/PDAM Rp. 385,000,000.00
E Septck tank Rp. 418,200,000.00
F Bak kontrol limbah transisi Rp. 148,500,000.00
G Sumur Resapan halaman rumah sakit Rp. 605,000,000.00
H Instalasi Pengelolaan Air Limbah ( IPAL ) komplit Rp. 1,680,000,000.00
5,114,080,000.00
Total Jumlah Pekerjaan Rp. 12,501,718,460.00
Ppn Rp. 1,250,171,846.00
Jumlah Rp. 13,751,890,306.00
Jumlah dibulatkan Rp. 13,751,890,000.00