You are on page 1of 2

DAFTAR KUANTITAS DAN HARGA

KEGIATAN : GEDUNG DPD DEMOKRAT JAWA BARAT


LOKASI : JL. SOEKARNO HATTA NO. 163
PROV / KAB : JAWA BARAT / BANDUNG
THN. KEGIATAN : 2020

HARGA SATUAN JUMLAH HARGA SUB TOTAL


NO. URAIAN DIVISI SAT. VOLUME
(Rp) (Rp) (Rp)

a b c d e f = (d x e) g=f
PEKERJAAN PLUMBING
A INSTALASI PLUMBING
uPVC AW 0.5" M' 48 55,000.00 2,640,000.00 2,640,000.00
uPVC AW 0.75" M' 52 65,000.00 3,380,000.00 3,380,000.00
uPVC AW 1" M' 90 80,000.00 7,200,000.00 7,200,000.00
uPVC AW 1.25" M' 66 105,000.00 6,930,000.00 6,930,000.00
uPVC AW 1.5" M' 20 140,000.00 2,800,000.00 2,800,000.00
uPVC AW 2" M' 90 195,000.00 17,550,000.00 17,550,000.00
uPVC AW 3" M' 30 385,000.00 11,550,000.00 11,550,000.00
uPVC AW 4" M' 98 590,000.00 57,820,000.00 57,820,000.00
Gate Valve 1.25" Nos 7 425,000.00 2,975,000.00 2,975,000.00
Gate Valve 2" Nos 6 755,000.00 4,530,000.00 4,530,000.00
Gate Valve 2.5" Nos 6 1,590,000.00 9,540,000.00 9,540,000.00
Floating Valve 2" Nos 1 1,290,000.00 1,290,000.00 1,290,000.00
Foot Valve 2.5" Nos 2 1,355,000.00 2,710,000.00 2,710,000.00
Check Valve 2" Nos 2 833,000.00 1,666,000.00 1,666,000.00
Check Valve 2.5" Nos 2 140,000.00 280,000.00 280,000.00
Clem Briket (Untuk Semua Instalasi) Ls 1 0.00 0.00
Clean Out ( CO ), 4" Nos 4 180,000.00 720,000.00 720,000.00
Clean Out 4" Nos 7 55,000.00 385,000.00 385,000.00
Clean Out 2" Nos 4 35,000.00 140,000.00 140,000.00
Roof drain 4" Nos 8 145,000.00 1,160,000.00 1,160,000.00
WLC / Elektrode Nos 1 30,000.00 30,000.00 30,000.00
Flexible Joint 2" Nos 4 515,000.00 2,060,000.00 2,060,000.00
Flexible 2.5" Nos 4 623,500.00 2,494,000.00 2,494,000.00
Strainer 2" Nos 2 1,055,000.00 2,110,000.00 2,110,000.00
Strainer 2.5 Nos 2 2,825,000.00 5,650,000.00 5,650,000.00
Water Level Control Nos 2 105,000.00 210,000.00 210,000.00
Pressuere Gauge ( scala 25 Kg/cm2 ) Nos 2 950,000.00 1,900,000.00 1,900,000.00
Header 4" Nos 1 1,050,000.00 1,050,000.00 1,050,000.00
Toren VP 1500 (RoofTank) bh 4 345,000.00 1,380,000.00 1,380,000.00
Pompa dorong bh 2 785,000.00 1,570,000.00 1,570,000.00
Pompa hisap bh 1 555,000.00 555,000.00 555,000.00
Testing and Commisioning Ls 1 5,100,000.00 5,100,000.00 5,100,000.00

Jumlah Pekerjaan Instalasi Plumbing 159,375,000.00


B PEKERJAAN SANITASI DALAM GEDUNG
1 Closet duduk unt 12.00 2,700,000.00 32,400,000.00 32,400,000.00
2 Jet washer bh 12.00 385,000.00 4,620,000.00 4,620,000.00
3 Wastafel unt 11.00 1,485,000.00 16,335,000.00 16,335,000.00
4 Kran wastafel bh 11.00 655,000.00 7,205,000.00 7,205,000.00
5 Urinoir unt 4.00 2,600,000.00 10,400,000.00 10,400,000.00
6 Skat urinoir bh 4.00 1,350,000.00 5,400,000.00 5,400,000.00
7 Kran dinding bh 11.00 105,000.00 1,155,000.00 1,155,000.00
8 Floor drain bh 11.00 165,000.00 1,815,000.00 1,815,000.00
9 Cermin polos t: 5 mm m2 5.00 205,000.00 1,025,000.00 1,025,000.00
10 Stop kran bh 8.00 105,000.00 840,000.00 840,000.00

Jumlah Pekerjaan Sanitasi Dalam Gedung 81,195,000.00


SUB TOTAL PEKERJAAN PLUMBING 240,570,000.00
DAFTAR KUANTITAS DAN HARGA

KEGIATAN : GEDUNG DPD DEMOKRAT JAWA BARAT


LOKASI : JL. SOEKARNO HATTA NO. 163
PROV / KAB : JAWA BARAT / BANDUNG
THN. KEGIATAN : 2020

HARGA SATUAN JUMLAH HARGA SUB TOTAL


NO. URAIAN DIVISI SAT. VOLUME
(Rp) (Rp) (Rp)

a b c d e f = (d x e) g=f
XV ELEKTRIKAL
PEKERJAAN KELISTRIKAN DALAM GEDUNG
A Lantai Dasar
1 Down Light LED 25W Philips bh 18.00 185,000.00 3,330,000.00 3,330,000.00
2 Lampu Tl 1 x 36 Watt bh 39.00 175,000.00 6,825,000.00 6,825,000.00
3 Instalasi Penerangan NYM 3x2,5mm +HI Ø20 ttk 129.00 260,000.00 33,540,000.00 33,540,000.00
4 Instalasi Stop Kontak Tunggal 13A / 1P ttk 56.00 260,000.00 14,560,000.00 14,560,000.00
5 Saklar Serie / ganda panasonic bh 14.00 45,000.00 630,000.00 630,000.00
6 Saklar Tunggal bh 8.00 35,000.00 280,000.00 280,000.00
7 Stop Kontak tunggal bh 6.00 25,000.00 150,000.00 150,000.00
8 Kabel NYA 1x6 mm m 105.00 25,000.00 2,625,000.00 2,625,000.00
9 Panel MDP Unit 1.00 21,000,000.00 21,000,000.00 21,000,000.00
10 Panel SDP Unit 1.00 26,000,000.00 26,000,000.00 26,000,000.00
11 Pengadaan & Pemasangan Genset Kap. 100 KV Unit 1.00 380,000,000.00 380,000,000.00 380,000,000.00
12 Sapot / Tray m1 45.00 0.00 0.00
Jumlah Lantai Dasar 488,940,000.00
B Lantai I
1 Down Light LED 25W Philips bh 25.00 185,000.00 4,625,000.00 4,625,000.00
2 Down Light LED 15W Philips bh 86.00 175,000.00 15,050,000.00 15,050,000.00
3 Instalasi Penerangan NYM 3x2,5mm +HI Ø20 ttk 111.00 260,000.00 28,860,000.00 28,860,000.00
4 Instalasi Stop Kontak Tunggal 13A / 1P ttk 48.00 260,000.00 12,480,000.00 12,480,000.00
5 Saklar Serie / ganda panasonic bh 24.00 45,000.00 1,080,000.00 1,080,000.00
6 Saklar Tunggal bh 8.00 35,000.00 280,000.00 280,000.00
7 Stop Kontak tunggal bh 8.00 25,000.00 200,000.00 200,000.00
8 Kabel NYA 1x6 mm m 102.00 25,000.00 2,550,000.00 2,550,000.00
9 Panel SDP Unit 1.00 26,000,000.00 26,000,000.00 26,000,000.00
Jumlah Lantai I 91,125,000.00
C Lantai II
1 Down Light LED 25W Philips bh 36.00 185,000.00 6,660,000.00 6,660,000.00
2 Down Light LED 15W Philips bh 113.00 175,000.00 19,775,000.00 19,775,000.00
3 Instalasi Penerangan NYM 3x2,5mm +HI Ø20 ttk 149.00 260,000.00 38,740,000.00 38,740,000.00
4 Instalasi Stop Kontak Tunggal 13A / 1P ttk 59.00 260,000.00 15,340,000.00 15,340,000.00
5 Saklar Serie / ganda panasonic bh 26.00 45,000.00 1,170,000.00 1,170,000.00
6 Saklar Tunggal bh 12.00 35,000.00 420,000.00 420,000.00
7 Stop Kontak tunggal bh 11.00 25,000.00 275,000.00 275,000.00
8 Kabel NYA 1x6 mm m 120.00 25,000.00 3,000,000.00 3,000,000.00
9 Panel SDP Unit 1.00 26,000,000.00 26,000,000.00 26,000,000.00
Jumlah Lantai II 111,380,000.00
D Lantai III
1 Down Light LED 25W Philips bh 11.00 185,000.00 2,035,000.00 2,035,000.00
2 Down Light LED 15W Philips bh 23.00 175,000.00 4,025,000.00 4,025,000.00
3 Lampu Tl 2 x 36 Watt bh 15.00 0.00 0.00
4 Instalasi Penerangan NYM 3x2,5mm +HI Ø20 ttk 61.00 260,000.00 15,860,000.00 15,860,000.00
5 Instalasi Stop Kontak Tunggal 13A / 1P ttk 38.00 260,000.00 9,880,000.00 9,880,000.00
6 Saklar Serie / ganda panasonic bh 16.00 45,000.00 720,000.00 720,000.00
7 Saklar Tunggal bh 6.00 35,000.00 210,000.00 210,000.00
8 Stop Kontak tunggal bh 6.00 25,000.00 150,000.00 150,000.00
9 Kabel NYA 1x6 mm m 72.00 25,000.00 1,800,000.00 1,800,000.00
10 Panel SDP Unit 1.00 26,000,000.00 26,000,000.00 26,000,000.00
Jumlah Lantai III 60,680,000.00
E Lantai RoofTop
1 Down Light LED 25W Philips bh 7.00 185,000.00 1,295,000.00 1,295,000.00
2 Instalasi Penerangan NYM 3x2,5mm +HI Ø20 ttk 7.00 260,000.00 1,820,000.00 1,820,000.00
3 Instalasi Stop Kontak Tunggal 13A / 1P ttk 8.00 260,000.00 2,080,000.00 2,080,000.00
4 Saklar Serie / ganda panasonic bh 3.00 45,000.00 135,000.00 135,000.00
5 Stop Kontak tunggal bh 4.00 25,000.00 100,000.00 100,000.00
6 Kabel NYA 1x6 mm m 15.00 25,000.00 375,000.00 375,000.00
Jumlah Lantai RoofTop 5,805,000.00
SUB TOTAL PEKERJAAN ELEKTRIKAL 757,930,000.00
TOTAL PEKERJAAN PLUMBING & ELEKTRIKAL 998,500,000.00