1 1.2 Mobilisasi
ASPHALT MIXING PLANT Unit 10.000.000,00 20.000.000,00 15.000.000,00
ASPHALT FINISHER Unit 5.000.000,00 10.000.000,00 7.500.000,00
ASPHALT SPRAYER Unit 5.000.000,00 10.000.000,00 7.500.000,00
BULLDOZER 100-150 HP Unit 7.500.000,00 15.000.000,00 10.000.000,00
COMPRESSOR 4000-6500 L\M Unit 250.000,00 250.000,00 250.000,00
CONCRETE MIXER 0.3-0.6 M3 Unit 250.000,00 250.000,00 250.000,00
CRANE 10-15 TON Unit 10.000.000,00 20.000.000,00 15.000.000,00
DUMP TRUCK 3.5 TON Unit 250.000,00 250.000,00 250.000,00
DUMP TRUCK 10 TON Unit 250.000,00 250.000,00 250.000,00
EXCAVATOR 80-140 HP Unit 7.500.000,00 15.000.000,00 10.000.000,00
EXCAVATOR LONG ARM Unit 7.500.000,00 15.000.000,00 10.000.000,00
FLAT BED TRUCK 3-4 M3 Unit 250.000,00 250.000,00 250.000,00
GENERATOR SET Unit 250.000,00 250.000,00 250.000,00
MOTOR GRADER >100 HP Unit 7.500.000,00 15.000.000,00 10.000.000,00
TRACK LOADER 75-100 HP Unit 7.500.000,00 15.000.000,00 10.000.000,00
WHEEL LOADER 1.0-1.6 M3 Unit 7.500.000,00 15.000.000,00 10.000.000,00
THREE WHEEL ROLLER 6-8 T Unit 7.500.000,00 15.000.000,00 10.000.000,00
TANDEM ROLLER 6-8 T. Unit 7.500.000,00 15.000.000,00 10.000.000,00
TIRE ROLLER 8-10 T. Unit 5.000.000,00 10.000.000,00 7.500.000,00
VIBRATORY ROLLER 5-8 T. Unit 7.500.000,00 15.000.000,00 7.500.000,00
CONCRETE VIBRATOR Unit 250.000,00 250.000,00 250.000,00
WATER PUMP 70-100 mm Unit 250.000,00 250.000,00 250.000,00
WATER TANKER 3000-4500 L. Unit 250.000,00 250.000,00 250.000,00
PEDESTRIAN ROLLER Unit 2.000.000,00 2.500.000,00 2.500.000,00
TAMPER Unit 250.000,00 250.000,00 250.000,00
JACK HAMMER Unit 250.000,00 250.000,00 250.000,00
FULVI MIXER Unit 10.000.000,00 20.000.000,00 10.000.000,00
CONCRETE PUMP Unit 5.000.000,00 10.000.000,00 5.000.000,00
TRAILER 20 TON Unit 2.500.000,00 2.500.000,00 3.500.000,00
PILE DRIVER + HAMMER Unit 2.500.000,00 5.000.000,00 2.500.000,00
CRANE ON TRACK 35 TON Unit 2.500.000,00 5.000.000,00 2.500.000,00
WELDING SET Unit 250.000,00 250.000,00 250.000,00
TRONTON Unit 1.500.000,00 5.000.000,00 1.000.000,00
ROCK DRILL BREAKER Unit 5.000.000,00 10.000.000,00 5.000.000,00
ASPHALT DISTRIBUTOR Unit 500.000,00 1.000.000,00 500.000,00
SLIP FORM PAVER Unit 250.000,00 250.000,00 250.000,00
CONCRETE PAN MIXER Unit 10.000.000,00 20.000.000,00 10.000.000,00
TRUK MIXER (AGITATOR) Unit 250.000,00 250.000,00 250.000,00
CRANE ON TRACK 75-100 TON Unit 10.000.000,00 10.000.000,00 5.000.000,00
MESIN POTONG RUMPUT Unit 250.000,00 250.000,00 250.000,00
DIVISI 2. DRAINASE
2 2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 53.607,31 48.698,27 55.379,26
3 2.2.(1) Pasangan Batu dengan Mortar M3 1.189.978,52 1.593.955,55 1.192.025,13
4 2.3.(14) Pasangan Batu tanpa Adukan (Aanstamping) M3 770.407,00 747.202,50 757.838,40
5 2.4.(2) Anyaman Filter Plastik M2 67.164,35 73.274,07 67.164,36
DIVISI 3. PEKERJAAN TANAH
6 3.1.(1a) Galian Biasa M3 84.711,33 76.574,80 87.565,72
3
7 3.1.(1b) Galian Batu Lunak M 119.087,45 106.122,04 121.592,96
8 3.1.(2) Galian Batu M3 179.671,78 165.784,85 183.702,10
9 3.1.(3) Galian Struktur dengan kedalaman 0 - 2 meter M3 56.759,88 102.822,76 99.381,26
10 3.1.(4) Galian Struktur dengan kedalaman 2 - 4 meter M3 462.537,78 659.168,46 551.758,33
11 3.1.(5) Galian Struktur dengan kedalaman 4 - 6 meter M3 431.322,98 590.674,07 486.654,65
12 3.1.(7) Galian Perkerasan Beraspal tanpa Cold Milling Machine M3 1.048.255,85 1.048.817,09 1.101.854,87
3
13 3.1.(8) Galian Perkerasan berbutir M 184.980,65 192.965,40 192.682,27
3
14 3.1.(9). Galian Perkerasan Beton M 216.933,66 222.254,44 226.956,80
15 3.2.(1) Timbunan Biasa M3 62.101,35 100.651,39 87.431,94
16 3.2.(2) Timbunan Pilihan M3 124.372,93 183.067,29 143.695,91
17 3.3.(1) Penyiapan Badan Jalan M2 3.808,62 3.732,75 3.862,23
18 3.4.(1) Pembersihan dan Pengupasan Lahan M2 3.009,48 3.394,34 3.062,12
19 3.4.(2) Pemotongan Pohon Pilihan diameter 15 – 30 cm Bh 148.696,65 159.219,30 155.273,45
20 3.4.(3) Pemotongan Pohon Pilihan diameter 30 – 50 cm Bh 230.135,78 242.934,71 240.004,91
21 3.4.(4) Pemotongan Pohon Pilihan diameter 50 – 75 cm Bh 433.150,56 474.454,59 448.108,07
22 3.4.(5) Pemotongan Pohon Pilihan diameter > 75 cm Bh 801.331,94 817.615,91 824.177,96
23 3.5.(3) Geotekstil Stabilisator (Kelas 1) M2 38.584,38 31.558,24 37.721,02
DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN
24 4.2.(1) Lapis Pondasi Agregat Kelas A M3 778.119,30 814.006,74 713.751,95
25 4.2.(2a) Lapis Pondasi Agregat Kelas B M3 711.321,12 744.075,97 693.959,43
DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
26 5.1.(1) Lapis Pondasi Agregat Kelas A M3 780.381,31 816.206,49 716.124,55
27 5.1.(2) Lapis Pondasi Agregat Kelas B M3 712.327,72 745.027,36 695.029,73
SA REGION I REGION II REGION III
NO. MATA
NO URAIAN PEKERJAAN TU (TENGAH) (ULU) (PESISIR)
PEMBAYARAN
AN (Rp) (Rp) (Rp)
3
28 5.3.(1) a Perkerasan Beton Semen M 2.707.107,94 3.156.905,65 2.704.697,12
29 5.3.(1) b Perkerasan Beton Semen (Semi Mekanis) M3 3.120.621,00 3.673.459,00 3.135.701,00
3
30 5.3.(1) c Perkerasan Beton Semen Ready Mix M 2.988.735,32 3.732.535,42 3.066.141,67
3
31 5.3.(1) d Perkerasan Beton Semen (Semi Mekanis) Ready Mix M 3.415.284,00 4.276.664,00 3.511.511,00
3
32 5.3.(3) Lapis Pondasi bawah Beton Kurus M 1.836.681,80 2.382.555,56 1.708.192,16
33 SKh-2.5.4.(1) Semen Ton 1.736.040,00 2.580.600,00 1.656.276,00
34 SKh-2.5.4.(2) Lapis Pondasi Semen Komposit Tanah M3 117.302,00 307.873,00 145.735,00
3
35 SKh-2.5.4.(2) Lapis Pondasi Semen Komposit Tanah (Rotavator) M 122.152,00 311.118,00 151.191,00
36 SKh-2.5.4.(3) Bahan Tambah (Additive ) Kg 198.940,00 200.712,00 198.940,00
37 SKh-1.5.9 (1) Perkerasan Telford M3 973.673,27 906.360,43 948.359,67
38 SKh-1.5.9 (2) Lapis Pasir Urug M3 185.880,23 280.945,24 241.477,12
DIVISI 6. PERKERASAN ASPAL
39 6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair Ltr 15.871,94 16.438,28 15.818,58
40 6.1 (2)(a) Lapis Perekat - Aspal Cair Ltr 16.449,58 17.684,59 16.372,71
41 6.2 (1) Agregat Penutup BURTU M2 34.829,08 34.753,51 35.177,59
42 6.2 (2) Agregat Penutup BURDA M2 38.561,96 38.767,03 38.985,58
43 6.2 (3a) Bahan Aspal untuk Pekerjaan Pelaburan Ltr 16.636,20 17.423,51 16.540,63
44 6.3(5a) Laston Lapis Aus (AC-WC) (gradasi halus/kasar) Ton 2.782.627,06 3.473.902,67 2.964.182,78
45 6.3(6a) Laston Lapis Antara (AC-BC) (gradasi halus/kasar) Ton 2.621.104,17 3.272.891,79 2.644.115,76
46 6.3(7a) Laston Lapis Pondasi (AC-Base) (gradasi halus/kasar) Ton 2.619.646,38 3.271.489,15 2.619.989,16
DIVISI 7. STRUKTUR
47 7.1 (2) a Beton mutu tinggi fc’=45 Mpa M3 3.725.715,62 4.557.656,84 3.680.749,54
48 7.1 (4) a Beton mutu tinggi fc’=35 Mpa M3 3.599.598,27 4.341.322,52 3.561.998,18
49 7.1 (5) a Beton mutu sedang fc’=30 MPa M3 3.518.144,24 4.281.034,02 3.487.324,43
50 7.1 (6) a Beton mutu sedang fc’= 25 Mpa M
3
3.076.544,29 3.741.899,12 3.043.697,55
51 7.1 (7) a Beton mutu sedang fc’= 20 MPa M3 2.495.024,80 3.239.708,46 2.094.468,77
52 7.1 (8) a Beton mutu rendah fc’= 15 MPa M3 2.035.469,65 2.596.908,28 1.554.968,98
53 7.1 (10) a Beton mutu rendah fc’= 10 Mpa M3 1.798.053,46 2.303.462,74 1.318.289,97
54 7.1 (2) b Beton mutu tinggi fc’=45 Mpa (Ready Mix) M3 4.317.338,14 5.419.041,12 4.463.756,00
55 7.1 (4) b Beton mutu tinggi fc’=35 Mpa (Ready Mix) M3 4.192.985,37 5.257.382,51 4.261.502,62
56 7.1 (5) c Beton mutu sedang fc’=30 MPa (Ready Mix) M
3
4.029.604,87 5.095.698,26 4.084.032,32
57 7.1 (6) b Beton mutu sedang fc’= 25 Mpa (Ready Mix) M3 3.466.568,87 4.397.545,28 3.526.965,48
58 7.1 (7) a Beton mutu sedang fc’= 20 MPa (Ready Mix) M
3
2.814.608,72 3.788.481,69 3.021.332,00
59 7.1 (8) b Beton mutu rendah fc’= 15 MPa (Ready Mix) M3 2.175.679,38 2.901.256,02 2.379.079,46
60 7.1 (10) b Beton mutu rendah fc’= 10 Mpa (Ready Mix) M3 1.846.227,38 2.480.821,77 2.069.514,41
61 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 90 cm, Bentang 10 m Bh 49.793.420,49 58.959.352,90 46.493.031,83
62 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 90 cm, Bentang 11 m Bh 56.753.737,26 61.489.954,96 48.963.581,71
63 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 90 cm, Bentang 12 me Bh 62.828.600,03 68.494.954,02 55.908.517,09
64 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 90 cm, Bentang 13 me Bh 70.919.102,29 79.574.253,58 61.067.145,97
65 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 90 cm, Bentang 14 me Bh 69.369.329,99 83.067.055,90 64.740.139,33
66 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 90 cm, Bentang 15 m Bh 76.532.227,83 90.668.001,19 72.040.777,73
67 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 90 cm, Bentang 16 m Bh 86.207.395,60 93.411.928,25 74.724.629,61
68 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 125 cm, Bentang 16 m Bh 88.369.729,10 101.971.182,75 83.283.884,11
69 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 125 cm, Bentang 17 m Bh 91.373.712,37 105.294.111,81 86.546.749,49
70 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 125 cm, Bentang 18 m Bh 94.653.281,63 108.342.777,36 89.535.351,37
71 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 125 cm, Bentang 19 m Bh 98.541.016,90 111.667.028,92 92.799.539,25
72 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 125 cm, Bentang 20 m Bh 101.697.375,17 115.599.446,48 96.671.893,13
73 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 125 cm, Bentang 21 m Bh 106.879.584,94 118.800.487,03 99.812.870,01
74 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 125 cm, Bentang 22 m Bh 110.645.420,21 124.027.379,09 104.979.698,39
75 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 125 cm, Bentang 23 m Bh 148.295.809,97 127.837.896,65 108.730.152,27
76 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 160 cm, Bentang 22 m Bh 150.804.995,71 163.211.777,59 144.164.096,89
77 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 160 cm, Bentang 23 m Bh 154.525.773,97 167.997.472,15 148.889.727,77
78 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 160 cm, Bentang 24 m Bh 158.732.829,74 171.762.932,71 152.595.124,65
79 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 160 cm, Bentang 25 m Bh 163.122.712,51 176.014.670,76 156.786.799,03
80 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 160 cm, Bentang 26 m Bh 167.802.774,78 180.449.235,82 161.161.311,91
81 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 160 cm, Bentang 27 m Bh 173.548.105,05 185.173.980,38 165.825.981,29
82 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 160 cm, Bentang 28 m Bh 177.984.367,31 190.963.992,94 171.555.930,17
83 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 160 cm, Bentang 29 m Bh 185.101.026,58 195.444.937,49 175.976.811,05
84 7.2 (1).c Penyediaan Unit Pracetak Gelagar Tipe I, H = 160 cm, Bentang 30 m Bh 189.901.654,85 202.606.279,05 183.078.088,93
85 7.2 (2).c Pemasangan Unit Pracetak Gelagar Tipe I Bh 7.758.433,28 7.667.339,65 7.776.580,98
86 7.2.(10) Beton Diafragma fc’ 30 MPa termasuk stressing (post tension) H = 90 cm Bh 4.699.906,37 6.107.019,05 4.448.451,40
87 7.2.(10) Beton Diafragma fc’ 30 MPa termasuk stressing (post tension) H = 125 cm Bh 5.454.559,37 7.428.507,05 5.100.156,40
88 7.2.(10) Beton Diafragma fc’ 30 MPa termasuk stressing (post tension) H = 160 cm Bh 6.161.257,37 8.631.177,05 5.716.763,40
89 7.3 (1) Baja Tulangan U 24 Polos Kg 24.413,22 26.576,24 24.075,51
90 7.3 (2) Baja Tulangan U 32 Polos Kg 26.228,64 29.574,26 26.212,24
91 7.3 (3) Baja Tulangan U 32 Ulir Kg 24.240,35 29.349,62 26.034,01
92 7.3 (4) Baja Tulangan U 39 Ulir Kg 33.592,76 35.852,40 33.569,27
93 7.3 (5) Baja Tulangan U 48 Ulir Kg 35.490,26 38.192,65 33.569,27
94 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) Kg 51.744,76 55.190,59 51.172,90
95 7.4 (1) b Penyediaan Baja Struktur BJ 37 (Titik Leleh 240 MPa) Kg 51.997,76 55.443,59 51.425,90
96 7.4 (1) c Penyediaan Baja Struktur BJ 55/Grade 345 (Titik Leleh 345-360 MPa) Kg 52.946,51 56.392,34 52.374,65
97 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) Kg 8.493,53 8.557,83 8.470,44
98 7.4 (2) b Pemasangan Baja Struktur BJ 37 (Titik Leleh 240 MPa) Kg 8.493,53 8.557,83 8.470,44
99 7.4 (2) c Pemasangan Baja Struktur BJ 55/Grade 345 (Titik Leleh 345-360 MPa) Kg 8.493,53 8.557,83 8.470,44
100 7.6 (1) Fondasi Cerucuk Penyedian dan Pemancangan Cerucuk M1 93.287,84 82.112,05 94.813,39
101 7.6 (4) Dinding Turap Baja M2 5.027.937,65 5.223.775,27 4.621.023,93
SA REGION I REGION II REGION III
NO. MATA
NO URAIAN PEKERJAAN TU (TENGAH) (ULU) (PESISIR)
PEMBAYARAN
AN (Rp) (Rp) (Rp)
102 7.6 (5) Dinding Turap Beton M2 2.496.060,59 3.036.885,92 2.461.596,17
103 7.6 (8) b Penyediaan Tiang Pancang Baja Diameter 500 mm dengan tebal 12 mm M1 2.920.963,17 3.534.895,26 4.809.760,16
104 7.6 (8) c Penyediaan Tiang Pancang Baja Diameter 600 mm dengan tebal 12 mm M1 3.509.591,24 4.250.093,97 2.461.596,17
105 7.6 (11) a Penyediaan Tiang Pancang Beton Pratekan Pracetak uk. 400 mm x 400 mm M1 1.271.642,27 1.258.432,38 1.457.922,45
106 7.6 (11) b Penyediaan Tiang Pancang Beton Pratekan Pracetak uk. 500 mm x 500 mm M1 1.874.719,70 2.174.167,30 2.153.795,58
107 7.6 (11) b Penyediaan Tiang Pancang Beton Pratekan Pracetak uk. 450 mm x 450 mm M1 1.777.874,01 1.602.166,55 2.001.279,10
108 7.6 (11) b Penyediaan Tiang Pancang Beton Pratekan Pracetak uk. 350 mm x 350 mm M1 1.010.520,30 984.133,68 1.150.396,88
109 7.6 (11) b Penyediaan Tiang Pancang Beton Pratekan Pracetak uk. 300 mm x 300 mm M1 803.911,95 848.409,00 905.817,58
110 7.6 (11) b Penyediaan Tiang Pancang Beton Pratekan Pracetak uk. 250 mm x 250 mm M1 461.218,54 718.310,66 531.479,05
111 7.6 (11) b Penyediaan Tiang Pancang Beton Pratekan Pracetak uk. 200 mm x 200 mm M1 489.621,62 2.328.790,15 474.717,86
112 7.6 (12) a Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 450 mm M1 1.159.701,24 1.413.828,70 1.143.017,21
1
113 7.6 (12) b Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 600 mm M 1.796.214,68 2.265.577,04 1.764.888,79
114 7.6 (12) b Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 500 mm M1 1.377.786,66 1.707.866,95 1.355.933,68
115 7.6 (12) b Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 400 mm M1 997.077,64 1.220.215,86 982.486,57
116 7.6 (12) b Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 350 mm M1 879.556,93 1.042.527,52 869.060,13
117 7.6 (12) b Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 300 mm M1 788.771,42 913.774,19 780.863,28
118 7.6 (14) a Pemancangan Tiang Pancang Baja Diameter 500 mm M1 474.834,88 476.032,61 480.360,56
119 7.6 (14) b Pemancangan Tiang Pancang Baja Diameter 600 mm M1 494.027,60 495.270,26 499.745,71
1
120 7.6 (17) a Pemancangan Tiang Pcg. Beton Pratekan Pracetak uk. 400 mm x 400 mm M 322.179,93 328.194,12 326.204,94
121 7.6 (17) b Pemancangan Tiang Pcg. Beton Pratekan Pracetak uk. 500 mm x 500 mm M1 357.414,38 364.092,23 361.851,76
122 7.6 (17) b Pemancangan Tiang Pcg. Beton Pratekan Pracetak uk. 450 mm x 450 mm M1 339.797,15 346.143,18 344.028,35
123 7.6 (17) b Pemancangan Tiang Pcg. Beton Pratekan Pracetak uk. 350 mm x 350 mm M1 304.562,70 310.245,07 308.381,54
124 7.6 (17) b Pemancangan Tiang Pcg. Beton Pratekan Pracetak uk. 300 mm x 300 mm M1 286.161,50 291.503,78 289.711,41
1
125 7.6 (17) b Pemancangan Tiang Pcg. Beton Pratekan Pracetak uk. 250 mm x 250 mm M 250.927,05 255.605,68 254.064,59
126 7.6 (17) b Pemancangan Tiang Pcg. Beton Pratekan Pracetak uk. 200 mm x 200 mm M1 233.309,83 237.656,63 236.241,18
127 7.6 (18) a Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 450 mm M1 286.161,50 291.503,78 289.711,41
1
128 7.6 (18) b Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 600 mm M 322.179,93 328.194,12 326.204,94
129 7.6 (18) b Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 500 mm M1 303.778,73 309.452,83 307.534,81
130 7.6 (18) b Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 400 mm M1 268.544,28 273.554,73 271.888,00
131 7.6 (18) b Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 350 mm M1 250.927,05 255.605,68 254.064,59
132 7.6 (18) b Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 300 mm M1 233.309,83 237.656,63 236.241,18
Pengujian Pembebanan Dinamis Jenis PDA (Pile Dynamic Analysis) pada Tiang
133 7.6 (27) a Bh 19.000.000,00 20.900.000,00 19.000.000,00
ukuran / diameter ....
3
134 7.9.(1) Pasangan Batu M 1.295.078,28 1.720.680,73 1.293.186,53
135 7.10.(1) Pasangan Batu Kosong yang Diisi Adukan M3 1.433.446,45 1.643.665,37 1.423.543,29
136 7.10.(2) Pasangan Batu Kosong M3 805.425,50 781.166,25 792.285,60
137 7.10.(3) a Bronjong dengan kawat yang dilapisi galvanis M3 1.745.083,31 1.867.398,75 1.382.379,35
138 7.11.(1) a Expansion Joint Asphaltic Plug Tipe Fixed M1 2.606.934,33 2.549.940,31 2.514.080,31
139 7.11.(1) b Expansion Joint Asphaltic Plug Tipe Moveable M1 2.780.871,83 2.856.702,81 2.792.380,31
140 7.11.(6) Expansion Joint Tipe Baja Bersudut M1 11.719.257,70 2.792.000,67 1.429.033,95
141 7.12.(2) Perletakan Elastomerik Alam Ukuran 450 mm x 400 mm x 45 mm Bh 2.337.173,75 1.391.195,25 2.228.107,75
142 7.12.(4) Perletakan Strip M1 1.118.397,18 1.090.428,03 1.071.781,93
143 7.13.(1) Sandaran (Railing) M1 244.543,28 300.150,20 213.665,38
144 7.15.(1) Pembongkaran Pasangan Batu M3 555.856,09 634.225,83 577.124,95
145 7.15.(2) Pembongkaran Beton M3 803.444,50 885.296,47 836.426,94
146 7.15.(5) Pembongkaran Rangka Baja M2 143.451,20 142.084,72 145.498,59
147 7.15.(7) Pembongkaran Lantai Jembatan Kayu M2 138.642,85 147.520,83 142.659,88
2
148 7.15.(8) Pembongkaran Jembatan Kayu M 48.999,58 53.177,44 52.676,36
149 7.16.(1) Deck drain Unt 1.164.892,50 1.218.350,25 1.200.686,25
150 7.16.(2) a Pipa Drainase Baja diameter 75 mm M' 305.481,54 352.088,55 277.782,36
151 7.16.(3).a Pipa Drainase PVC diameter 75 mm M' 61.126,37 83.265,00 88.290,10
SA REGION I REGION II REGION III
NO. MATA
NO URAIAN PEKERJAAN TU (TENGAH) (ULU) (PESISIR)
PEMBAYARAN
AN (Rp) (Rp) (Rp)
DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR
152 8.4.(1) Marka Jalan Termoplastik M2 234.405,85 219.043,26 200.251,11
153 8.4.(2) Marka Jalan Bukan Termoplastik M2 67.581,95 111.341,62 82.817,45
154 8.4.(5) Patok Pengarah Bh 112.682,77 119.076,07 124.344,39
155 8.4.(6).a Patok Kilometer Bh 408.860,19 489.587,46 441.252,09
156 8.4.(6).b Patok Hektometer Bh 187.756,87 211.985,27 204.512,92
157 8.4.(7) Rel Pengaman M1 1.440.171,60 1.487.616,42 957.968,29
158 8.4.(9) Mata Kucing Bh 123.669,19 139.906,27 67.440,98
159 8.4.(10).a Kerb Pracetak Jenis 1 (Peninggi/Mountable) M1 140.558,47 177.897,34 145.733,97
160 8.4.(10).b Kerb Pracetak Jenis 2 (Penghalang/Barrier) M1 187.207,68 238.266,56 195.267,04
161 8.4.(10).c Kerb Pracetak Jenis 3 (Kerb Berparit/Gutter) M1 172.513,08 219.163,57 179.631,64
162 8.4.(10).d Kerb Pracetak Jenis 4 (Penghalang Berparit / Barrier Gutter) t = 20 cm M1 196.579,38 250.106,33 203.723,19
163 8.4.(10).e Kerb Pracetak Jenis 5 (Penghalang Berparit / Barrier Gutter) t = 30 cm M1 240.771,82 307.556,50 250.167,44
164 8.4.(10).f Kerb Pracetak Jenis 6 (Kerb dengan Bukaan) Bh 90.138,79 111.733,56 93.588,68
165 8.4.(10).g Kerb Pracetak Jenis 7a (Kerb pada Pelandaian Trotoar) Bh 99.836,18 124.340,17 105.168,20