REPORT

WFM R14A Deployment Plan Phase2

RPA Go-Live Deployment plan


High level overview

1 Preparation
2 Software installations on the servers
3 Sanity Testing
4 OAT
5 Decision Meetings

Sheet: Deployment Overview1 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2

RPA Deployment plan

Sl No Area Activity
Please note down all the RPA RTR,IC,App servers are
1 Preparation up and running

-To Intimate RPA users/MUs in communications about


the change window.
- All stake holder communication including BPPM and
Service DESK and Incident Manager

2 Communication

RPA team deploy changes in app servers of MSDP 1.0 &


4 Configuration Changes 2.0

6 Testing OAT Test by Ops and MU

7 Go or NO GO Project Team and Ops Team

Change window Start Indian Time


Change window End Indian Time

Sheet: Deployment Plan2 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2

Downtime
Status of the activity Required Duration Owner

1:00 Project Team

0:05 PO

2:00 Project Team

Operations Team
1:00 and MU
All Stake
holders 0:30

30-May-20 00:00
1-Jun-20 22:00

Sheet: Deployment Plan3 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2

India Time

Start DateTime (IST) Finish DateTime (IST)


5/30/2020 0:00 5/30/2020 23:00

5/31/2020 8:00 5/31/2020 8:05

5/31/2020 10:00 5/31/2020 12:00

5/31/2020 14:00 5/31/2020 15:00

6/1/2020 14:00 6/1/2020 20:00

Sheet: Deployment Plan4 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2
RPA Rollback plan
SLNo Activity

Rollback on same day during change window


1 Removed service accounts will be added in Local admin group

Sheet: Rollback Plan5 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2
Indian Time
Resposibility Down Time Effort (Hrs) Start

Project Team 0:30 6/1/2020 19:30:00 PM

Sheet: Rollback Plan6 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2
Indian Time
End

6/1/2020 20:00:00 PM

Sheet: Rollback Plan7 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2

RPA Deployment plan

Total Change Window


Start Date & Time Finish Date & Time Timezone Duration
30-May-20 00:00 1-Jun-20 22:00 IST 22:00

Deployment Change Window


Start Date & Time Finish Date & Time Timezone Duration
30-May-20 00:00 31-May-20 23:00 IST 23:00

Rollback Change Window


Start Date & Time Finish Date & Time Timezone Duration
1-Jun-20 19:30 1-Jun-20 22:00 IST 2:30

Sheet: Summary8 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2

Production Applications
RPA

Sheet: Summary9 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2

Links

Sheet: Summary10 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2

Sheet: Impact Analysis11 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2

No Impact.

Sheet: Impact Analysis12 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2

Name Role Email

Project Team Anup Singh PAM anup.u.singh@ericsson.com

Mayank Tyagi PO mayank.m.tyagi@ericsson.com

Neeraj Kumar SA neeraj.e.kumar@ericsson.com


Satyam Singh SI satyam.s.singh@ericsson.com

Sheet: Contact Details13 (14) © Ericsson AB 2016


Ericsson Internal
REPORT
WFM R14A Deployment Plan Phase2

Phone number

918130600113

918860477790

9654874125

8448833649

Sheet: Contact Details14 (14) © Ericsson AB 2016