Professional Documents
Culture Documents
Relative Humidity % 76 80 98
Following Coal Analysis has been considered for the Plant Design (the fuel
analysis is same as being fired in the existing Plant):
Ultimate Analysis
Carbon (C) (%d.a.f 60 88.5
)
Hydrogen (H) (%d.a.f 3 10
)
Nitrogen (N) (%d.a.f 0.5 2.0
)
Oxygen (O) (%d.a.f 5.0 27.5
)
Note: We refer to the Ash Analysis provided in Exhibit A of the Term Sheet.
While the individual constituents “minimum” and “maximum” limits are specified,
this does not provide the actual “Ash Composition” with the total leading upto
100%. In order to understand the ash characteristics and the corresponding coal
behaviour, it is necessary to have the correct ash composition totalling to 100%. As
the basis of our proposal, we have provided in this Design Criteria the typical “Ash
Composition” considered for the boiler design.
Limestone composition % by wt
Calcium carbonate % 95
Magnesium carbonate % 1.5
Inert / SiO2 % 3.25
Moisture % 0.25
Limestone properties
Reactivity >3.3
Attrition Index <2.6
Nature Soft,
powdery
Bulk Density Kg/m3 1100 - 1300
140 100 10 – 15
200 75 0
During normal operation, considering low ash fuel, continuous addition of bed
material / limestone is required to maintain the bed inventory.
Instruments 230 1 50 z
The following DM water quality shall be supplied from the existing Plant:
Parameter Quality
pH 7.0 – 7.5
Dissolved Organic Carbon (DOC) 200 µg/kg max
Total Suspended Solids Nil
Hardness Nil
Conductivity @ 25degC 0.1 µS/cm max
Silica (SiO2) 0.01 mg/l max
Total Iron (Fe) 0.01 mg/l max
Total Copper (Cu) 0.003 mg/l max
Sodium (Na) 0.01 mg/l max
Oil Nil
pH value 8 ~ 10
Turbidity, NTU 3 max
Hardness, mg/L as CaCO3 48 ~108
TDS, mg/L 100
Iron, Fe, mg/L <0.3
Residual Chlorine, mg/l <0.5
O&G, mg/l <2
Fire water storage tank and this will be used for the following
applications:
The facility, under scope of supply, will be designed and constructed to meet the
noise emission limit of 85 dB (A) at normal, continuous and stable operating
conditions, under 100% base load operation, measured in accordance with DIN
45635 and ISO 3746, at a distance of 1 meter from each equipment / enclosure
surface, and height of 1.5 meter above the ground level. During abnormal
operation cases, such as opening of safety valves / start-up vent, turbine bypass
operation, start up and shut down, EDG and diesel fire pump operation, the noise
levels will be higher (about 115dBA), but such operations are expected to be only
for a short duration.
The back ground noise level is assumed to be zero for such guarantees.
Conditions for normal cubic meters (Nm3) are 0 degC and 760mm of Hga.
Conditions for standard cubic feet (SCF) are 15degC and 760mm of Hga
The SOx emissions will depend on the sulphur content in the fuel.
The Facility will be designed in accordance with the following list of codes and
standards. The Facility must also comply with Cambodia national standards as may be
approved by Ministry (or any other approved Governmental Authority) from time to time.
The codes and standards utilized will be the latest editions in effect on the date of
this proposal.
In the event these codes and standards are subsequently modified by their issuing
agency, and should such modifications be required to be incorporated into the
Facility, then any resulting additional cost, project delays, changes in
performance guarantees, etc., will be considered as a change in the work scope.
For packaged equipment supplies, the manufacturer’s codes and standards, as per
their standard engineering practices, will be followed. The surface preparation
and painting for such equipment shall follow their recommended procedures.