Trishuli 3A 60 Medium,
Capacity (completed)
Large
Small
7%
20%
Large
Medium
Medium Small
73%
Among the completed hydropower projects, most of them are medium capacity
hydropower project which has capacity ranging 10-100 MW.
Capacity (ongoing)
1%
23% 30%
Large
Medium
Small
46%
Mini
Among the ongoing work of Hydropower projects, we mostly are working under the
completion of medium capacity hydropower projects. This will be a huge addition to
overall hydroelectric power generation in Nepal.
Head (completed)
High
14%
High
Medium Medium
86%
HEAD (ONGOING)
High
23%
Medium
77%
We can clearly conclude from the above pie-chart that most of the completed as well as
ongoing hydropower projects use medium head (30-300 m) whereas some of them use high
head (>300 m).