You are on page 1of 15

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/296348325

Current Status of Micro Hydro Technology in Nepal

Conference Paper · November 2013

CITATIONS READS
5 5,268

2 authors, including:

Tri Ratna Bajracharya


Tribhuvan University
94 PUBLICATIONS   440 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Modeling the Impacts of Climate Change on Water Resources with Competing Demands: A Case Study of Kaligandaki Gorge Hydropower Project View project

Pelton turbine erosion study project. View project

All content following this page was uploaded by Tri Ratna Bajracharya on 01 March 2016.

The user has requested enhancement of the downloaded file.


Current Status of Micro Hydro Technology in Nepal
Khemraj Acharya, Triratna Bajracharya
Department of Mechanical Engineering, IOE, Central Campus, Pulchowk, Tribhuvan University, Nepal
khemraj.acharya@gmail.com

Abstract: Installation of the Micro Hydro Power (MHP) began in Nepal around fifty years ago and around
23 MW of micro hydro schemes have been installed in the country and around 250,000 households in the
rural area are electrified by the micro hydropower plants. Since micro hydro has lot of positive socio
economic impacts, it has been well accepted by our society in this period. The pace of installation has
increased from few kW per years to around 5 MW per year in fifty years. This research aimed at finding
the current technological status of the micro hydro in Nepal and find out the areas for future improvement.
For this purpose Power Output Verification (POV) reports of 19 micro hydro were collected and data from
these reports were analysed. The results obtained suggest that Nepalese micro hydro have on average
59.8% water to wire efficiency which is well below the average efficiency of the micro hydro in developed
countries. The lower efficiency was found to be caused by lower turbine efficiency. Nepalese micro hydro
with Cross Flow turbines have higher efficiency as compared with the Pelton turbines. Efficiency of Pelton
turbine installations was found to increase slightly with size of micro hydro while that of Cross Flow
turbine installations remained indifferent. Efficiency of the Cross Flow turbine installations was found to
decrease with increase in net head. It was found that Nepalese micro hydro have nearly same penstock
efficiency as that in developed countries. Nepalese micro hydro in average supply 90W per household
connected. In average turbine and generator each has below four per cent share in total cost but efficiency
of these components determine the power output from the micro hydro. Reduction in cost of electrification
through micro hydro system is possible only through improvement in performance of turbine and
generator and use of local materials for civil works and electrical works.

Keywords: water to wire efficiency, electromechanical efficiency, electrification, cost share

firewood as usual source of fuel for cooking followed by


1. INTRODUCTION liquefied petroleum gas (LPG) (21.03 per cent), cow
dung (10.38 per cent), Bio-gas (2.43%), and kerosene
In the fiscal year 2008/09 total energy consumption in (1.03%). Very few households (0.08 per cent) use
Nepal was estimated to be 401 million GJ among which electricity as usual fuel for cooking. In urban area, more
77.7% was contributed by fuel wood followed by than two third (67.68 per cent) of the total households use
petroleum 8.2%, animal dung 5.7%, agro residue 3.7%, LPG as their usual fuel for cooking [3]. There is strong
electricity 2%, and other renewable sources including need for substituting the kerosene from lighting and
micro hydro, biogas and solar total 1% of the total energy traditional fuel from cooking by other renewable energy
consumption. In the same year 89.1% of total energy sources.
consumption was on household sector, followed by
transport 5.2%, industrial 3.3%, commercial 1.3%, Nepal had per capita electricity consumption of 93kWH
agricultural 0.9%, and other 0.2% respectively [1]. This in the year 2010. Total primary energy supply in the same
shows the energy consumption in Nepal is based on year was 14.28GJ/capita while average of the world was
traditional fuels like fuel wood and agro residue. Nepal 78.12 GJ/capita [4]. Energy poverty is the situation in
has per capita Gross National Income (GNI) of US$ 540 which there is lack of modern energy source sufficient for
which is less than average of low income countries US$ cooking and electricity for lighting which means, there is
571 and far less than world average US$ 9514 for the large dependency on traditional fuels for cooking and
year 2011 [2]. lighting as is the case of our country [5]. Energy poverty
has serious and growing public health concerns related to
Population of Nepal was 26.5 million on June 2011 and is indoor air pollution. Energy poverty affects both the
increasing with an annual average growth rate of 1.35 gender roles within society and the educational
percent [3]. About 17 % of the total population reside in opportunities available to children and adults [6]. The
urban area while remaining in rural area. The average estimated households living in energy poverty in
household size is 4.88 in 2011 at the national level. Only cooking, lighting, and drinking water boiling was 51%,
about two third (67.26%) of the total households in Nepal 60%, 88% with overall end uses combining 68% in Nepal
use electricity as main source of lighting. Kerosene is still in year 2006 [7]. Micro hydro schemes can be adapted as
being used by 18.28 per cent of total households for the most economical option for rural electrification than
lighting. Solar is being used by 7.44 per cent and bio-gas any other available renewable energy sources such as
by 0.28 per cent of the total households for lighting. solar and wind [8].
Similarly, about 64% of the total households use

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 1


Micro hydro power plants (MHPs) are one of the structure of Nepalese micro hydro detailed feasibility
promising technologies that use small river water study reports of five different micro hydro of different
resources for generating electricity. A lot of work is being size were referred.
carried out by different government and non-government
bodies for installation and operation of such MHPs. 2. LITERATURE REVIEW
MHPs are being installed in Nepal by different
organization like Remote Area Development Committee A. Micro Hydropower Plant
under Ministry of Local Development, GIZ, and private
entrepreneurs. AEPC is the coordinating and regulating Micro hydro power plants are the small scale hydro
body for renewable energy sector in Nepal. Among the power plants of the sizes in between 5 kW and 100kW
renewable energy technologies promoted by AEPC for [10]. In general, micro hydro does not need dams and a
rural electrification to meet the need of the people, micro reservoir as water is diverted and then conducted in a
hydropower is the most prominent one. penstock to a lower elevation and the water turbine. In
most cases, the end production is the generation of
Two main programs of AEPC had been actively working electricity. There are thought to be tens of thousands of
for the development of micro hydropower plants. The micro hydro plants in China and significant numbers in
UNDP and the World Bank funded Renewable Energy Nepal, Sri Lanka, Pakistan, Vietnam, and Peru. The
for Rural Livelihood Program (RERL) and the Denmark estimate for China was about 500 MW at the end of 2008
and Norway funded Mini Grid Support Program under [11]. Micro hydro is in most cases “run-of-river”, with no
Energy Sector Assistance Program (MGSP/ESAP). dam or water storage, and is one of the most cost-
ESAP completed its second phase by 2012 and new effective and environmentally benign energy
program has been designed named National Rural and technologies to be considered for rural electrification.
Renewable Energy Program. In 2011, the Government of Studies in Nepal have shown that rural electrification
Nepal and development partners jointly agreed to support alone has had minimal impact on agricultural or industrial
formulation of a National Rural and Renewable Energy production. The most cost-effective use of hydropower in
Program (NRREP). NRREP expects to install 25 MW of Nepal has been through mechanical end-uses [12]. From
mini and micro hydro benefitting 150,000 households life cycle assessment of micro hydro in rural Thailand for
from community electrification component during its five twenty years it was concluded that smaller hydro power
year implementation period starting from 2012 [9]. systems have a greater environmental impact per kWh,
The micro hydro installation procedure begins with the perform less well environmentally than larger systems.
request for potential micro hydro and is completed after Placed within a rural electrification context, however, the
one year check and payment of the retained 10% amount. micro hydropower system yields better environmental
Among the subsidy provide by the AEPC about 10% of and financial outcomes than diesel generator and grid
the total subsidy amount is held by the AEPC until one connection alternatives [13].
year guarantee period is completed and installation passes Conventionally micro hydro is being promoted by
the power output verification process. Power Output government sectors through community participation as a
Verification (POV) is a type of third party auditing of the part of rural electrification where national grid is not
micro hydro power plant installation to ascertain that the likely to reach in near future. But in recent time some
installation meets performance limitations as specified by effort is being made for private sector participation for
the AEPC. commercialisation of this sector. An innovative private
sector participation project is in implementation in
A. Methodology Rwanda named ‘Private Sector Participation in Micro
Calculation of different parameters of micro hydro Hydro Development in Rwanda’ which has motivated
components are based on data obtained from the power private sectors to invest in micro hydro sector with their
output verification reports of micro hydro from AEPC. own loan and equity with support from project [14].
Data of 19 different micro hydro power plants whose
installation was completed in year 2012 were collected B. Cost of Electrification from the Micro Hydro
from their respective Power Output Verification (POV) Nouni, M.R. et al. [15] studied techno-economics of
reports. From the processed data, efficiency of different micro hydro projects in India and showed that cost per
components of micro hydro including penstock, kW of the MHP vary with site due to different size of the
electromechanical (combined efficiency of turbine and scheme, specific nature of civil work at required site,
generator and drive system), and water to wire efficiency varying length of transmission and distribution network,
of the system were calculated. Results from the possibility of procuring equipment from local as well as
calculations were analysed to find out trends and to find foreign suppliers etc. Cost per unit power output of the
out the future improvement possibilities in the micro hydro schemes decreases when micro hydro are
performance. Data obtained was analysed using simple promoted with day time productive end use and social
excel model for different results. To study the cost infrastructures along with electrification of the village

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 2


than electrification of the village alone due to high plant targeted to complete installation of 4.5 MW of micro
load factor in former case [16]. The cost of mini hydro hydro schemes within current fiscal year 2070/71 [22].
electrification can be in the range of $2500-3000/kW, but This signifies that installation capacity per annum in
for small schemes may reach up to $10,000/kW micro hydro sector is reaching around 5kW. The private
depending upon specific site. Cost can be reduced by sector was a key implementing partner of the mini grid
using indigenous technology below $1000/kW [12]. component of ESAP. Private companies were involved in
Mainali and Silveira [17] studied off grid rural site identification, installation and repair and
electrification of Nepal and showed that cost per kW of maintenance. AEPC has separate lists of Pre-Qualified
installation decreases with size of installation. (PQ) companies to conduct Detail Feasibility Studies
(DFS) and to install micro-hydro plants. To be eligible
C. Micro Hydro in Nepal for subsidy, communities have to choose a PQ company.
There were 57 installation firms and 52 surveying firms
Nepalese micro hydro powers are sustainable in three in operation which were prequalified by AEPC by the
dimensions of sustainability framework: ecology, end of the year 2009 [23].
economy and social. Ecologically, MHP are causing no
significant negative impacts but improvement in some On average, it takes 8 months to start construction once
cases. Economically, the broader benefit of MHP the project is approved and 19 months to complete the
technology in Nepal is the creation of industrial base of construction once it is started. There is declining trend in
hydropower development in the long-term [18]. Micro project completion time in recent years. Average number
hydro have positive socio-economic impact in the rural of end use applications per micro hydro system is two,
communities like lower consumption of firewood, while the highest number of end use applications in one
extended study time for children, reduced drudgery for micro hydro is 28. On average, each end use application
women, increased economic activity due to productive provides three direct employment opportunities. Among
end use, and social participation [19]. Micro hydropower different end use applications of MHPs agro processing is
should be given precedence to solar PV for lighting since most frequent one, followed by poultry farming, saw mill
solar lighting is costlier than micro hydropower projects and rural carpentry and computer institutes [23].
in terms of unit costs and carbon abatement [20]. One of
the major hindrances to the development of micro D. Previous Research in Nepalese MHPs
hydropower project in Nepal is being costly. There is
Parajuli [24] studied on the cost reduction possibilities in
inconsistency in price and quality of construction
the civil components of the Nepalese MHP systems based
materials and electro-mechanical equipment in the
on the questionnaire survey among the stakeholders and
country [21].
suggested different methods based on the same.
20 According to his findings cost of the MHPs are site
Micro hydro installation (kW)
Hundreds

specific and varied within range of Rs. 150,000 and NRs


170,000 per kW of installation capacity at that time. He
15
also concluded that cost breakdown of the Nepalese
micro hydro sector shows electrical components cost
10 40%, civil components cost 30%, mechanical
components 23%, and transportation cost 7% in average
for Nepalese MHP systems. The study suggested that
5
among the civil component there is a greater cost
reduction possibility in canal. Gyanwali [25] studied on
0 cost reduction possibilities in mechanical components of
MHP systems in Nepal based on the questionnaire survey
Year
among the stakeholders and suggested different methods
based on the same. According to his findings most of the
Figure 1: Micro hydro installations by AEPC/ESAP turbines in Nepalese MHPs were oversized and that’s
(Source: AEPC, 2012) why turbines were found to be relatively costly.
Figure 1 above shows the micro hydro installation by According to his findings most of the turbines are not
AEPC/ESAP on annual basis from 2001 to 2011. This designed as per the required parameters but are selected
chart shows increasing trend of micro hydro installation from already designed templates, which are near about
per year from year 2007 to 2011. In average per kW cost the requirements. This may be one of the reasons for stall
is around Rs. 430,646 among which 26% is contributed in the performance improvement in the MHPs. Aryal
by the AEPC as subsidy 247 Nepalese MHPs [23]. [26] studied on the cost reduction possibilities in
AEPC has recently completed implementation of ESAP electrical components of the Nepalese MHP systems
phase II and till mid July 2013 around 23 MW of MHP based on the questionnaire survey among the
has been installed in Nepal. Nepal government has stakeholders and suggested different methods based on

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 3


the same. Ghimire [27] studied on end use promotions in Thus, power output from micro hydro power plant
the MHP sector in Nepal. Most of the research works depends upon available head, flow rate and the efficiency
stated are based on the questionnaire survey among the of the different components of the scheme. For given
stakeholders and therefore there is need to find out the specific site with given flow rate and gross head the
current status of the efficiency of the MHP components power that can be harnessed can vary slightly with
and find out the area for the future improvement efficiency of the components.
possibilities based on the test data obtained from the
The overall system efficiency, ηo, is the ratio of useful
MHP installations.
power output to hydraulic power input. It is the product
A number of literatures are available as guidelines for of separate efficiencies for several components of the
development of micro hydro power plants [27, 28, 29, 30, system [30].
31, 32, 33] but very few were available which shows the
ηo = ηp ηt ηg ηtr (3)
current technological status of the Nepalese MHPs. This
paper tries to present the current technological status of Where,
the Nepalese micro hydro power plants.
ηp is the penstock efficiency, typically 0.90 - 0.95,
E. Efficiency of the Micro Hydro Power Plants ηt is the turbine efficiency, typically 0.65 - 0.80
depending on turbine type,
Hydro turbines convert energy available in water into
mechanical shaft power, which can be used to drive an ηg is the generator efficiency, typically 0.65 - 0.90
electric generator, or other machinery. The power depending on size,
available is proportional to the product of head and flow
ηtr is the transmission efficiency including transformers if
rate. The gross head (H) is the maximum available
used, typically 0.85 - 0.90.
vertical fall in the water, from the upstream level to the
downstream level. The actual head seen by a turbine will Holland [27] suggested that the efficiency of a small
be slightly less than the gross head due to losses incurred turbine is typically 75% and generator efficiency is
when transferring the water into and away from the 80%. Paish [12] suggested micro hydro systems tend to
machine. This reduced head after subtracting losses from be in the range 60 to 80% efficient. If we take 70% as a
gross head is known as the net head. The flow rate (Q) in typical water-to-wire efficiency for the whole system,
the river, is the volume of water passing per second, then power equation simplifies to:
measured in m3/sec. For small schemes, the flow rate
P (kW) = 7 x Q (m3/s) x H (m) (4)
may also be expressed in litres/second where 1000
litres/sec is equal to 1m3/sec.
F. Efficiency of Different Components of Micro
The mechanical power output from hydropower system is Hydro
given by,
P=ηρgQH (1) Penstock Efficiency
Where, Penstock efficiency is the ratio of the net head of the
P is the mechanical power produced at the turbine shaft micro hydro to the gross head of the micro hydro scheme.
(Watts), Higher efficiency signifies lower friction loss in the
η is the hydraulic efficiency of the turbine, penstock. Penstocks in micro hydro have typical
ρ is the density of water (1000 kg/m3), efficiency of 96% [29]. There is trade off to be made
g is the acceleration due to gravity (9.81m/s2), between cost of the penstock and the efficiency. For
Q is the volume flow rate passing through the turbine lower friction loss and hence higher efficiency smooth
(m3/s), surface and larger penstock size is required.
H is the effective pressure head of water across the
turbine (m). Turbine Efficiency
The best turbines can have hydraulic efficiencies in the
range 80 to over 90% which is higher than all other prime Turbine efficiency is its ability to convert available
movers, although this will decrease with size. energy in water at turbine inlet to mechanical energy to
Electrical power output generated from hydroelectric drive the generator. Efficiency of the turbines varies with
power plants like micro hydro power (MHP) is given by, its type and size of the plant. Pelton turbine and Cross
flow turbines are most widely used in Nepalese MHPs.
P = ηo ρ g Q H (2) Pelton turbines have best efficiency of 89% with single
Where, jet and 90% in multi jet configuration [29]. Cross Flow
turbines have lower efficiency as compared with Pelton
P is the electric power output from the scheme. turbines. Cross Flow turbines have good part load
ηo is the overall efficiency of the scheme. efficiency as compared with Pelton turbine. Best

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 4


efficiency achieved with Cross Flow turbine is 78.6%,  Maximum voltage drop permissible at the farthest
this value was obtained when tested in a laboratory in end of the distribution line is 10% of the nominal
2008 in Norway [34]. Efficiency of Cross Flow turbine value.
can reach 79% for size 100 kW for model T15. Cross
Flow turbine efficiency slightly decreases with head due Assuming generator efficiency to be 85%, minimum
to increased friction loss in turbine blades [35]. Drive efficiency required for the installations with Pelton
system efficiency for belt drive of the generator is turbine are 47.2%, 52.5%, 58.3% in overall, water to wire
normally 98% [29]. and electromechanical efficiency. Making the same
assumption in generator efficiency to be 85%, minimum
Generator Efficiency efficiency required for the installations with Cross Flow
turbine are 40.5%, 45%, and 50% in overall, water to
The efficiency of the generator is defined as the ratio of wire and electromechanical efficiency. Below these
the electric power output from generator to the input efficiency levels the project does not meet the national
mechanical power. Efficiency of the generator is less than standard for efficiency.
one due to five major losses which are friction loss, core
loss, field copper loss, armature copper loss, and stray H. Measurement of Efficiency of Different
loss or load loss. First two of these are fixed losses which Components
are independent of load whereas remaining three are
variable losses which vary with change in load [36]. Efficiency of the penstock can be determined by
Typical efficiency of generator ranges from 91% for rated measuring gross head and net head of the micro hydro.
power of 10kW to 95% for 100kW rated power [29]. The Gross head is the vertical height level difference between
efficiency of the generator is almost independent of the forebay water level and the turbine nozzle centreline for
load on the generator. impulse turbine where as it is the vertical height
difference between forebay water level and water level at
Assuming transmission and distribution efficiency to be draft tube discharge tail race reservoir water level for
90%, maximum efficiencies possible from Pelton turbine reaction turbine. The gross head can be measured by
installations are 68.57%, 76.2%, 79.4% in overall, water using Abney level and tape method with less than 5%
to wire, and electromechanical. Similarly, for Cross Flow error [28]. Net head available can be directly read from
turbine installations maximum efficiencies achievable are the pressure gauge fitted at the turbine intake. If gauge is
60.10%, 66.77%, 69.5% in overall, water to wire and properly calibrated this method gives less than 5% error.
electromechanical. Where, electromechanical efficiency
is the combined efficiency of the drive transmission Except for the thermodynamic method, determination of
system with efficiency of turbine and generator. the turbine efficiency requires measurement of discharge
Q, mechanical power available at the shaft Pm, electrical
G. Component Efficiency Limitations in Design power as well as net and gross head. Combined efficiency
Standards of MHP in Nepal of the turbine generator unit can be determined by
measuring the electrical power output from the micro
The following are the minimum limitations on hydro, discharge and net head. If efficiency of the
component efficiencies stated in the Nepal Micro Hydro turbine is determined with thermodynamic method then
Standards prepared by AEPC [37]: efficiency of the generator can be determined by dividing
combined turbine generator efficiency by the turbine
 Total headloss including losses in bends and valves
efficiency. Thermodynamic method is one of the methods
on Penstock at design flow rate should not exceed
for field performance testing of hydropower system,
10% of the gross head.
which can give satisfactory results by measuring the
 Turbine efficiency limitations temperature and pressure of water before entry to the
turbine and after discharge from the turbine in the tail
 Pelton turbines 5kW to 30 kW, 70% to 80%
race canal about four runner diameters downstream of the
 Pelton turbines above 30 kW, 75% to 85% discharge from the runner. Temperature measurement
instrument should be capable of measuring temperature
 Cross Flow turbines 5kW to 30 kW, 60% to 70%
change in milliKelvin [38]. But this method cannot be
 Cross Flow turbines above 30kW, 65% to 78% used for low head site since it gives higher uncertainty
level with decrease in head. Below 100m head
 No limitation for generator efficiency but should uncertainty reaches to higher value making this method
meet manufacturer’s efficiency specification. unsatisfactory for efficiency measurement [39].
 Ballast load should be at least 20% higher than the Discharge measurement can be carried out with salt
plant capacity in thyristor type controller. dilution method with error less than 7% [28]. In pressure
time method (Gibson method) flow is derived from
change in pressure when the mass of water decelerates to

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 5


zero velocity. Ultrasonic flow meters use Doppler Effect and water heating type ballast load. Most of the micro
to estimate the velocity of flow. Current meters measure hydro are using three phase four wire transmission
velocity at specific points in a defined cross section and is system with single phase supply to individual
integrated with area by area velocity method. Pressure households. From the collected data it was found that
time method and ultrasonic method requires penstock to there was significant error on head measurement at the
be fabricated with provision for installing instrument time of designing. Most of the micro hydro reported
probes. All of these methods can give less than 2% error design gross head to be less than the actual gross head.
[40]. This may be due to lack of confidence in the designer for
design output. Also most of the micro hydro reported
Since mechanical power available in the turbine shaft can
power output from the scheme to be higher than the
only be measured with dynamometers, it cannot be
design power output value. While going through the
measured at site conditions. Hence, turbine efficiency and
different POV reports some MHPs were reported to have
generator efficiency cannot be measured at site
trouble with their ELC and at least one MHP reported
conditions and therefore combined turbine and generator
that design flow was not possible to pass through the
efficiency is to be measured. Efficiency of the generator
given scheme but power output from the same scheme
remains almost constant around its full load efficiency.
was higher than the design power output because of the
Though efficiency of the generator varies slightly with
error in the head measurement before design. Only one
temperature and altitude, it can be corrected for such
out of nineteen MHP has reported to have productive end
variations. Efficiency be assumed to be constant for
use application at the time before POV test, while none of
specific test condition for given altitude, temperature and
the others have any end use application except lighting.
installation. Efficiency of the turbine can be
approximated by using generator efficiency and
combined efficiency of turbine and generator. B. Calculated Parameters
Overall efficiency is the ratio of power available at the
I. Provisions Related with Efficiency Measurement location of the user to the hydraulic energy available in
in POV Guideline [42] the site. It is the product of water to wire efficiency with
transmission and distribution efficiency. In actual
Gross head measurement with Abney level and tape practice transmission and distribution efficiency is less
method. Net head is to be measured with pressure gauge than 95%. Overall efficiency is calculated as:
at end of the penstock.
Overall efficiency = Electric power output available at
Flow measurement using salt dilution method or area end use/Power available in water (1)
velocity method to be carried out at the headwork site.
Stream flow measurement at intake is to be carried out Power available in water at given site = ρgHQ (2)
using salt dilution method or area velocity method. Where,
Voltage, current and power factor in each phase, and ρ is the density of water (1000 kg/m3),
frequency is to be measured using RMS meters. Ballast
voltage and power to be measured in each phase of the g is the acceleration due to gravity (9.81m/s2),
ballast load. Each parameter is to be measured with
Q is the volume flow rate passing through the turbine
variation of load at various position of the valve for flow
(m3/s),
variation.
H is the actual gross head of water at given site (m).
3. CALCULATIONS AND RESULTS Water to wire efficiency is the ratio of power output
measured at the powerhouse to the power available in the
A. Observations water. Water to wire efficiency is obtained by dividing
From collected data it was found that most of the micro overall efficiency with transmission efficiency.
hydro is community owned and operated. Similarly, Water to wire efficiency = Electric power output / Power
almost all the Nepalese micro hydro schemes used available in water (3)
temporary weir for diverting water. There is variation in
the canal type, some use stone masonry, some cemented Design HH/kW is the ratio of targeted number of
lined and few have used high density polythene pipes. All households at the design time to the design power output.
of the micro hydro use mild steel penstock pipe. Many of It shows the targeted power supply to the each household
the micro hydro use stepped thickness in penstock design. of the scheme.
All micro hydro with net head lower than 50m used Cross Actual HH/kW is the ratio of actual number of households
Flow turbines while above 50m used Pelton turbines. connected to the scheme to the actual power output. It
Almost all of the micro hydro used synchronous three shows the actual power supply to the each household of
phase generators with Electronic Load Controller (ELC) the scheme.

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 6


Penstock efficiency is the ratio of the actual net head of Actual/design power is the ratio of the actual power
the scheme to the actual gross head of the scheme. output of the scheme to the design power output assumed
at the time of design of the same scheme.
Electromechanical efficiency is the combined efficiency
of the electromechanical components of the MHP. It is Ballast load/design power is the ratio of the ballast load
the product of the turbine efficiency, drive system installed at the plant to the design power output.
efficiency and the generator efficiency. Since efficiency
Ballast load/actual power is the ratio of the ballast load
of the turbine and generator was not possible to be
installed at the plant to the actual power output measured
calculated from the obtained data combined efficiency
at the plant.
was calculated as:
Results from Analysis of POV Data
Electromechanical efficiency = power output from the
scheme/power available at turbine inlet (4) From results obtained after calculation it can be seen that
the Nepalese MHP have water to wire efficiency of
Power available at turbine inlet = ρgHnQ (5)
59.8% on average with minimum value of 39.7% and
Where, Hn is the net head of the scheme. maximum value of 73.5%. Schemes with Pelton turbines
have average efficiency of 57.4% while that with cross
Actual/design gross head is the ratio of the actual head of
flow turbines have 63.1% average efficiency. Detail
the scheme to the gross head assumed at the time of
results obtained are shown on the Table 1.
design of the same scheme.
Table 1: Different parameters calculated for the all mhps at a time
Standard
Parameter Mean Median Min Max Skewness Kurtosis
Deviation
Water to wire Efficiency 59.80% 60.30% 39.70% 73.50% 8.70% -0.41 0.2
Penstock efficiency 94.70% 95% 90% 98% 2% -0.49 0.32
Electromechanical efficiency 62.20% 64% 43% 77% 10% -0.43 -0.45
Design HH/kW 10.4 10.02 7.89 13.95 1.66 0.42 -0.37
Actual HH/kW 10.16 10.38 5.8 16.96 2.77 0.53 0.67
Actual/Design Gross Head 105.50% 107% 93% 119% 7% 0.06 0.09
Actual/Design Power 109.00% 109% 78% 138% 17% 0.01 -0.81
Ballast load/Design Power 127.90% 123% 118% 157% 11% 1.59 2.16
Ballast load/Actual Power 120.10% 115% 87% 157% 21% 0.08 -0.97
Actual/Design Discharge 101.9% 100% 75% 137% 16% 0.41 -0.32
Generator oversizing 171.90% 173.90% 133.30% 220.00% 18.70% 0.64 1.81

average Nepalese MHPs have ballast load of 127.9% of


Similarly Nepalese MHPs have penstock efficiency on
design power output. Considering power factor to be 0.8
average of 94.8% with minimum value of 90% and
Nepalese MHPs have generator oversized by 171.9% in
maximum value of 98% which is quite good. Nepalese
average.
MHPs are designed with 10.7 HH/kW but are actually
11.2 households are connected per kW of the power Figure 2 below shows the variation of water to wire
output i.e. each household gets around 90W. Schemes efficiency with size of the MHP. The correlation
with Pelton turbines have electromechanical efficiency of coefficient between water to wire efficiency and size of
60.5% on average while schemes with Cross Flow the micro hydro was calculated to be 0.358 which shows
turbine have average electromechanical efficiency of slight correlation between water to wire efficiency and
64.5%. About 73% of Nepalese MHPs have actual gross size of the MHP. Scatter plot shows that water to wire
head higher than design gross head where few schemes efficiency varies widely with site location even the size
have more than 10 m error in head measurement. Actual of the micro hydro is nearly of the same size. Variation of
power output of 68.4% of Nepalese MHPs is higher than water to wire efficiency with size of micro hydro is given
design power output. Due to discrepancies in the design by the regression equation:
power output and actual power output 21% of the
ηww = 0.5476+0.0019P (106)
Nepalese MHPs have ballast load less than the actual
power output at design flow rate of the scheme. On

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 7


From results of regression analysis, at 10% level of Variation of electromechanical efficiency with size of
significance tcritical = 1.771, tstatistic = 1.65, null hypothesis micro hydro is given by the regression equation:
is accepted since tstatistic is less than tcritical, and it can be
ηem = 0.5837+0.0017P (11)
concluded that size of the micro hydro does not influence
the water to wire efficiency. From results of regression analysis, at 10% level of
significance tcritical = 1.771, tstatistic = 1.39, null hypothesis
80%
is accepted since tstatistic is less than tcritical, and it can be
concluded that size of the micro hydro does not influence
the electromechanical efficiency.
70%
Figure 4 below shows the relationship between water to
wire efficiency with size of the micro hydro with Pelton
Water to wire efficiency

60% turbine installation. Coefficient of correlation calculated


between water to wire efficiency of Pelton turbine
installations and size was found to be 0.59. This signifies
50% there is linear relationship between water to wire
efficiency and size of the micro hydro with Pelton turbine
installation. Positive value of correlation coefficient
40% signifies that these two variables vary in the same
direction. That means larger size micro hydro will tend to
have higher efficiency compared with that of the smaller.
30% Variation of water to wire efficiency with size of micro
0 20 40 60 80 100
hydro is given by the regression equation:
Design power output (kW)

Figure 2: Variation of water to wire efficiency with size of


ηww = 0.515 + 0.0023P (12)
MHPs From results of regression analysis, at 10% level of
Figure 3 below shows the variation of electromechanical significance tcritical = 1.833, tstatistic = 2.07, null hypothesis
efficiency of the micro hydro with size of the micro is rejected since tstatistic exceeds tcritical, and it can be
hydro. From the scatter plot it is clear that the concluded that size of the micro hydro influences the
electromechanical efficiency varies widely with specific water to wire efficiency for Pelton turbine installation.
installation. Regression line plotted shows the increasing Similarly, test statistic exceeds the critical value of the F
trend of the micro hydro with slight correlation between distribution at the 10% significance level, so the
electromechanical efficiency and size with Carl Pearson regression as a whole is significant.
coefficient of correlation 0.342. Since correlation
80%
coefficient is positive with small value close to zero than
to one, these two values vary together but with slight 70%
degree only.
Water to wire efficiency

60%
80%
50%

70% 40%
Electromechanical efficiency

30%
60%
20%

10%
50%
0%
0 20 40 60 80 100
40% Design power output (kW)

Figure 4: Variation of water to wire efficiency with size of


30% MHPs with Pelton turbine
0 20 40 60 80 100
Design power output (kW)
Figure 5 below shows the relationship between
electromechanical efficiency with the size of the
Figure 3: Variation of electromechanical efficiency with size of Nepalese MHPs having Pelton turbine installation.
MHP Coefficient of correlation between electromechanical
efficiency and size of the micro hydro with Pelton turbine

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 8


is 0.56, which is close to 1 than to zero meaning that 80%
there is slight linear relationship between 75%
electromechanical efficiency of the micro hydro with its

Electromechanical efficiency
70%
size. The positive value of correlation coefficient
65%
signifies that with increase in size of micro hydro tends to
cause an increase in electromechanical efficiency of the 60%
installation. Variation of electromechanical efficiency 55%
with size of micro hydro with Pelton turbine is given by 50%
the regression equation: 45%
ηem = 0.547+0.0023P (13) 40%
35%
From results of regression analysis, at 10% level of
significance tcritical = 1.833, tstatistic = 2.04, null hypothesis 30%
55 75 95 115 135
is rejected since tstatistic exceeds tcritical, and it can be Actual net head (m)
concluded that size of the micro hydro influences the
electromechanical efficiency for Pelton turbine Figure 6: Variation in electromechanical efficiency with net
installation. Similarly, test statistic exceeds the critical head for MHPs with Pelton turbines
value of the F distribution at the 10% significance level,
so the regression as a whole is significant. Figure 7 below shows the relationship between the
electromechanical efficiency of the micro hydro with
90% Pelton turbines with flow rate. The coefficient of
80% correlation between these two variables is calculated to
be 0.24 which means there is very slight amount of linear
Electromechanical efficiency

70%
relationship between electromechanical efficiency with
60% the discharge available at sites for Pelton turbine
50% installations. This signifies that there is no sufficient
evidence that micro hydro with Pelton turbine having
40% high flow rates will have higher efficiency than that have
30% lower flow rate. Variation of electromechanical
efficiency with discharge of micro hydro with Pelton
20%
turbines is given by the regression equation:
10%
ηem = 0.5783 + 0.0005Q (8)
0%
0 20 40 60 80 100 From results of regression analysis, at 10% level of
Design power output (kW)
significance tcritical = 1.833, tstatistic = 0.755, null hypothesis
Figure 5: Variation of electromechanical efficiency with size for is accepted since tstatistic is less than tcritical, and it can be
MHPs with Pelton turbines concluded that there is not sufficient evidence to claim
that the electromechanical efficiency is influenced by the
Figure 6 below shows the relationship of electro-
discharge for Pelton turbine installation.
mechanical efficiency of the micro hydro with the net
head of the installations with Pelton turbines. The
coefficient of correlation between these two variables 80%
was determined to be 0.30, which means there is weak
correlation between these two variables. From scatter plot
Electromechanical efficiency

70%
it can be clearly seen that electromechanical efficiency of
the micro hydro is more dependent on site of installation
60%
than its net head due to scattering of the points far away
from the regression line. Variation of electromechanical
efficiency with net head of micro hydro with Pelton 50%
turbine is given by the regression equation:
40%
ηem = 0.501+0.0011Hn (7)
From results of regression analysis, at 10% level of 30%
significance tcritical = 1.833, tstatistic = 0.94, null hypothesis 10 30 50 70 90 110 130 150
is accepted since tstatistic is less than tcritical, and it can be Actual flow (litres/sec)
concluded that the electromechanical efficiency is
Figure 7: Variation of electromechanical efficiency with
independent of the net head for Pelton turbine discharge for MHPs with Pelton turbines
installation.

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 9


Figure 8 below show the relationship between size and with increase in net head for Cross Flow turbine
water to wire efficiency for micro hydro with Cross Flow installations. Similarly, test statistic exceeds the critical
turbine installation. Calculation of correlation coefficient value of the F distribution at the 10% significance level,
resulted in the value of negative 0.05, which is almost so the regression as a whole is significant.
zero. This signifies that there is no direct relationship
80%
between size of micro hydro and its water to wire
efficiency. From the scatter diagram it can be seen that 75%
the points are very scattered and have no definite trend

Electromechanical efficiency
pattern. Variation of water to wire efficiency with size of 70%
micro hydro with Cross Flow turbine is given by the
regression equation: 65%

ηww = 0.6038 + 0.0008P (9) 60%


From results of regression analysis, at 10% level of 55%
significance tcritical = 1.943, tstatistic = 0.22, null hypothesis
is accepted since tstatistic is less than tcritical, and it can be 50%
concluded that size of the micro hydro does not influence
the water to wire efficiency for Cross Flow turbine 45%
installation.
40%
80% 15 25 35 45 55
Actual net head (m)

70%
Figure 9: Variation of electromechanical efficiency with net
head for MHPs with Cross Flow turbines
Water to wire efficiency

60% After calculation of different parameters of MHPs for


separate turbine type installation and all considered at a
50% time, MHPs were grouped according to size into four
groups size less than 10 kW, size between 10 kW and 20
kW, size between 20kW and 30 kW, and size between 30
40%
kW and 40 kW. Among MHPs of size between 5 kW and
10 kW, one has water to wire efficiency calculated of
30% 51.5% while other has 63.1% with average efficiency of
0 10 20 30 40 57.3%. Among six MHPs of size between 10 kW and 20
Design power output (kW)
kW, one has water to wire efficiency of 39.7% which is
Figure 8: Variation of water to wire efficiency with size for the lowest while another one has 66.5% with average
MHPs with Cross Flow turbines efficiency of 56.5%. This group has average
electromechanical efficiency value of 59.9%. Six MHPs
Figure 9 below shows the relationship between
of size between 20 kW and 30 kW have lowest water to
electromechanical efficiency of the micro hydro with net
wire efficiency of 49% and highest 73.5% with average
head for Cross Flow type installations. Carl Pearson
efficiency of 60.5%. Similarly, this group has average
correlation coefficient between electromechanical
electromechanical efficiency of 64.1%. Three MHPs
efficiency and net head was found to be -0.695. The
among 19 are of size between 30 kW and 40 kW. This
negative value close to minus one than zero means the
group has lowest water to wire efficiency of group is
electromechanical efficiency decreases with increase in
39.7% and highest is the 60.4 with average of 60.4%.
net head of the micro hydro for Cross Flow turbine type
Micro hydro of size between 30kW and 40kW has in
installation in fair amount. Which signifies that micro
average electromechanical efficiency value 62.5%. One
hydro with Cross Flow turbine installations are more
of the micro hydro among 19 was of size 88 kW (Bhuwa
efficient in low head installation compared with high
Khola MHP) with actual net head of 85.30 m which uses
head installations. Variation of electromechanical
2 jet Pelton turbine to electrify 882 HHs with 96 kW
efficiency with net head of micro hydro with Cross Flow
measured power output which has water to wire
turbine is given by the regression equation:
efficiency of 72.8% with penstock efficiency of 95.2%
ηem = 0.848-0.0054Hn (17) and electromechanical efficiency of 76%.
From results of regression analysis, at 10% level of Figure below shows the mean water to wire efficiency of
significance tcritical = 1.943, tstatistic = 2.37, null hypothesis each group plotted in bar chart which shows slight
is rejected since tstatistic exceeds tcritical, and it can be increasing trend in efficiency of the micro hydro with
concluded that the electromechanical efficiency decreases size. From the bar chart micro hydro of size less than 20

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 10


kW have water to wire efficiency of around 57% while
between 20 and 40 kW size have water to wire efficiency Cost Structure of Nepalese MHP
around 60% and 88 kW MHP has efficiency of 72%. It Share of different sectors in installation of micro hydro
signifies increasing efficiency trend but has low certainty was found to vary according to size of installation, and
for this result since the values are average of number of location as shown in Figure on next page. These costs
data. are as estimated in detailed feasibility reports of Suntale
Khola MHP (100 kW) Taplejung, Nurkhuwa Khola MHP
75%
(31kW) Khotang, Yari Khola MHP (23kW) Udayapur,
70% Chima Khola MHP (13kW) Khotang, and Rumrunga
Khola MHP Khotang in DECEEC [42], DATECPL [44],
65% HSCPL [44], DATECPL [45], and DATECPL [47]
Water to wire efficiency

respectively. Percentages share of electrical, mechanical


60%
and civil work varies from 30% to 47%, 7% to 13% and
55% 16% to 28% respectively. Share of mechanical and civil
works in total installation cost increases with decrease in
50% size of the MHP and cost of the electrical works increases
45%
with increase in size of the micro hydro. This increase in
electrical cost is mainly due to increase in transmission
40% and distribution cost of the micro hydro. The
<10 kW 10 to 20 20 to 30 30 to 40 88 kW transmission and distribution cost of micro hydro with
kW kW kW larger capacity is high due to involvement of transformer
Size of the MHP
and steel poles for high voltage transmission. Cost of
Figure 10: Variation of average efficiency of MHP with size installation, commissioning and testing increase in slight
group amount with increase in size but percentage share of total
Figure 11 below shows the average component cost decreases with increase in size of the micro hydro.
efficiencies of the different size group of micro hydro. Miscellaneous cost component includes tax paid on
From this chart it is clear that penstock efficiency varies purchase of nonlocal material and contingency expenses
only around within 3% range while electromechanical which remains almost constant at around 12 to 13% even
efficiency and water to wire efficiency varies widely, in with variation in size of the micro hydro.
micro hydro. Average efficiency of the penstock is Rumrunga MHS (11kW) Chima MHS (13kW)
satisfactory as compared with results from other countries Yari MHS (23kW) Nurkhuwa MHS (31kW)
while that of electromechanical efficiency is below Suntale MHS (100kW)
average range as suggested in literature. This is the main 50%
reason of low water to wire efficiency on average. There
45%
Percentage of th total investment cost

is place for improvement in electromechanical efficiency


which will improve the water to wire efficiency of the 40%
micro hydro. 35%
30%
<10 kW 10 to 20 kW 20 to 30 kW 30 to 40 kW 88 kW
100% 25%

20%
90%
Average efficiency (%)

15%
80%
10%

70% 5%
0%
60%

50%

40%
Cost components
Water to Wire Penstock Electromechanical
Efficiency component
Figure 12: Relative cost contribtion of different components in
Figure 11: Variation of average component efficiency with size MHP in Nepal
group
Figure 13 shows variation of cost per kW of installation
for micro hydro with its size.

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 11


lower efficiency due to lower efficiency of the Cross
Rumrunga MHS (11kW) Chima MHS (13kW) Yari MHS (23kW)
Flow turbine as compared with the Pelton turbine
Nurkhuwa MHS (31kW) Suntale MHS (100kW)
installations. Either the Pelton turbines are operating in
500
part load condition due to oversizing or there are some
Thousands

450 problems in design or fabrication in the Pelton turbines


400
for having lower efficiency. Performance testing of
Pelton turbines is needed to determine the exact cause of
350
lower efficiency. Every effort should be made in
Cost per kW (Rs.)

300 improvement in turbine efficiency since it increases the


250
efficiency of the whole power plant. Assuming generator
efficiency to be 88% since it varies between 85% to 90%
200 in Nepalese context and transmission drive efficiency to
150 be 98%, turbine efficiency in Pelton installation in
average becomes 67%. Similarly if same assumptions
100
were made to calculate the turbine efficiency of the Cross
50 Flow installations turbine efficiency becomes 71%. This
0
means Pelton turbines are less efficient than the minimum
Total Local Non local standard fixed and Cross Flow turbines barely meet the
Cost components minimum efficiency limitations. It is clearly seen that
Figure 13: Cost per kW of Nepalese MHPs there is lot of space for improvement in turbine efficiency
for both Cross Flow and Pelton turbines. Turbine and
Cost per kW of installation decreases with size from per generator each cost around 4% at maximum of the total
kW cost around Rs. 475,000 for 11kW size to Rs. cost of the installation but have great influence in the
275,000 for 31kW. Cost per kW for 100kW size is higher power output from the scheme. Since all the material cost
due to involvement of high transmission and distribution is already included, slight increase in cost of fabrication
cost for high voltage transmission. Table 2 shows the will increase the cost of turbine only by small amount.
contribution of different components of micro hydro in The cost increment incurred to increase the efficiency of
total installation cost. From this table it can be seen that turbine can be offset by the saving in extra cost that may
turbines cost around four percentage of the total cost and be incurred in generating the power equal to the
generator costs around four percentage of total cost while difference in two cases. Consider a micro hydro site with
both of these have smaller share in larger installations. 10kW gross power available in water. If micro hydro is
installed with water to wire efficiency of 70% it will
Table 2: Relative cost shares of different components of MHP
in total cost generate 7kW of power. If micro hydro has the water to
wire efficiency of 50% then 5kW of power will be
Suntale Nurkhuwa Chima Rumrunga Avg. generated. From analysis carried above cost of generation
Name of
MHS MHS MHS MHS Cost
the scheme
(100kW) (31kW) (13kW) (11kW) share of one kilowatt of electricity from micro hydro is above
Rs. 275,000. Increasing power output by 2kW from the
Head works 3.3% 1.3% 1.6% 1.2% 1.9%
same scheme at least Rs. 550,000 can be saved which can
Headrace canal 12.1% 10.4% 18.6% 14.8% 14.0% electrify extra 20 rural households. If extra cost incurred
Generator 1.2% 3.5% 4.7% 3.9% 3.3% in selecting turbine and generator with more efficiency is
ELC 0.9% 2.9% 2.6% 2.9% 2.4%
less than this amount it should be selected and in most of
the cases which is true. Efficiency of the micro hydro
Transformers 4.8% 4.5% 0.0% 0.0% 2.3% with Pelton turbines is found to increase with size of
Conductors 15.5% 14.8% 12.0% 15.3% 14.4% micro hydro which has also been reported by other
Poles 11.1% 0.6% 2.0% 0.5% 3.5% literatures. Similarly, Cross Flow turbines have
decreasing trend in efficiency with increase in size of the
Turbine 1.4% 4.1% 3.8% 3.9% 3.3%
micro hydro due to increased friction loss in the blades as
Penstock 3.3% 3.0% 2.8% 5.9% 3.7% reported in the literatures. Cost reduction in Nepalese
micro hydro is possible only by combined effort in
4. DISCUSSION improvement in component efficiencies, and use of local
materials in civil works and electrical transmission and
From observations and results it can be seen that the distribution system. First of all resource should be
Nepalese MHPs have average efficiency lower than assessed well before designing of any MHP which will
MHPs in developed countries. From the results of the eliminate the error in head measurement. Well trained
efficiencies of Pelton and cross flow schemes it can be surveyor/technician use of well calibrated proper
seen that cross flow turbines have better efficiencies as instrument will remove such error which will increase the
compared with Pelton schemes in case of Nepalese certainty of the availability of the properly designed
MHPs. In other countries Cross Flow installations have power output from the scheme. There should be end use

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 12


promotion activities at the time of installation of the [10] AEPC, Renewable Energy Data Book 2011.: Alternative Energy
Promotion Centre, Ministry of Environment, Science and
MHP to make sure the sustainability of the scheme. If we
Technology, Government of Nepal, 2011.
can increase the efficiency of these components specially
turbines Nepalese MHPs will be more economic due to [11] V. Nelson, Introduction to Renewable Energy. Boca Raton: CRC
Press, 2011.
lower installation cost per kW power output from the
scheme. ELCs should have rating higher than the actual [12] Oliver Paish, "Small hydro power: technology and current status,"
power output of the scheme otherwise it will be damaged Renewable and Sustainable Energy Reviews 6 (2002), pp. 537–
556., 2002.
while dissipating excess power from the MHP.
[13] Andrew Pascale, Tania Urmee, and Andrew Moore, "Life cycle
assessment of a community hydroelectric power system in rural
5. CONCLUSIONS Thailand," Renewable Energy 36 (2011), pp. 2799-2808, 2011.
From the analysis of the data obtained it is concluded that [14] Maurice Pigaht and Robert J. van der Plas, "Innovative private
Nepalese MHPs have average water to wire efficiency of micro-hydro power development in Rwanda," Energy Policy 37,
pp. 4753–4760, 2009.
59.8% which is well below the average efficiency of the
MHPs in developed countries. Micro hydro with Pelton [15] M.R. Nouni, S. C. Mallic, and T.C. Kandpal, "Techno-economics
turbine installations have in average 57.4% water to wire of micro-hydro projects for decentralized powersupply in India,"
Energy Policy 34 (2006), pp. 1161 – 1174, 2006.
efficiency, and that with Cross Flow turbine installations
have 63.1% water to wire efficiency. Best efficiencies [16] Nicola U. Blum, Ratri Sryantoro Wakeling, and Tobis S. Schmidt,
achieved in other country are 76.2% and 66.8% for "Rural electrification through village grids—Assessing the cost
competitiveness of isolated renewable energy technologies in
Pelton and Cross Flow installations. The lower value of Indonesia," Renewable and Sustainable Energy Reviews 22, pp.
efficiency was found to be mainly caused by lower 482–496, 2013.
turbine efficiency. It can be seen that there is a wide [17] Brijesh Mainali and Semida Silvera, "Financing off-grid rural
space for improvement in efficiency. Though turbine and electrification: Country case Nepal," Energy 36, pp. 2194-2201,
generators in average share around four precent of the 2011.
total cost in average they determine the power output [18] Govinda Raj Pokharel, "Promoting Sustainable Development by
from the scheme so every endeavour is to be made to Creating Enterprises on Renewable Energy Technologies in Nepal
increase the efficiency of these components which is Case Studies Based on Micro Hydropower Projects," University of
causing the micro hydro to have lower efficiency. It was Flensberg, Flensberg, Germany, Ph. D. Dissertation 2006.
found that Nepalese MHPs have in average penstock [19] A. Gurung, I. Bryceson, J. H. Joo, and S. E. Oh, "Socio economic
efficiency of 94.7%, this value can be considered to be impacts of a micro-hydropower plant on rural livelihoods,"
Scientific Research and Essays Vol. 6(19), pp. 3964-3972, 2011.
good. Cost per kW of power was found to decrease with
larger installation, so larger size installations are to be [20] Saligram Pokharel, "Kyoto Protocol and Nepal's energy sector,"
promoted. Energy Policy 35 (2007), pp. 2514-2525, 2007.
[21] Solar Energy Foundation Nepal, "Renewable Energy Policy Gap
REFERENCES Study 2011 Final Report," Solar Energy Foundation Nepal, 2011.
[22] AEPC, Mini Grid Outlook (1999 to 2012). Kathmandu, Nepal:
[1] WECS, "Energy Sector Synopsis Report," Water and Energy
Energy Sector Assistance Programme, Alternative Energy
Commission Secretariat, Kathmandu, Nepal, 2010.
Promotion Centre, Ministry of Environment, Government of
[2] World Bank, "World Development Indicators 2013," Washington, Nepal, 2012.
doi: 10.1596/978-0-8213-9824-1, 2013.
[23] MoF, Budget for Fiscal Year 2070/71.: Ministry of Finance,
[3] CBS, "National Population and Housing Census 2011 (National Government of Nepal, 2013.
Report)," Kathmandu, Nepal, 2012.
[24] R. R. Parajuli, "A Study on Cost Reduction Possibilities in Civil
[4] IEA, "Key World Energy Statistics ," 2012. Components of Micro Hydro Power Systems," Department of
Mechanical Engineering, Department of Mechanical Engineering,
[5] Benjamin K. Sovacool, "The political economy of energy poverty: Pulchowk Campus, Institute of Engineering, Lalitpur, Nepal, M.
A review of key challenges," Energy for Sustainable Development Sc. Thesis report 2004.
16, pp. 272–282, 2012.
[25] P. Gyanwali, "A Study on Cost Reduction Possibilities in
[6] Benjamin K. Sovacool, "Expanding Renewable Energy Access Mechanical Components of Micro Hydro Power System,"
with Pro-Poor Public Private Partnerships in the Developing Department of Mechanical Engineering, Department of
World," Energy Strategy Reviews 1 (2013), pp. 181-192, 2013. Mechanical Engineering, Pulchowk Campus, Institute of
[7] Practical Action Nepal, "Study to Determine Outline Plans for Engineering, M.Sc. Thesis report 2004.
Eliminating Energy Poverty in Nepal," Kathmandu, Nepal, 2009. [26] R. Aryal, "A Study on Cost Reduction Possibilities in Electrical
Components of Micro Hydro Power System," Department of
[8] A. Laghari, H. Mokhlis, A.H.A. Bakar, and M. Hasmaini, "A
comprehensive overview of new designs in the hydraulic, Mechanical Engineering, Department of Mechanical Engineering,
Pulchowk Campus, Institute of Engineering, M.Sc. Thesis report
electrical equipment and controllers of mini hydro power plants
2004.
making it cost effective technology," Renewable and Sustainable
Energy 20, pp. 279–293, 2013. [27] Sujan Ghimire, "A Study on Cost Reduction Possibilities in
Mechanical Components of Micro Hydro Power Systems,"
[9] AEPC, "National Rural and Renewable Energy Program, Nepal
Department of Mechanical Engineering, Department of
Program Document," 2012a.

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 13


Mechanical Engineering, Pulchowk Campus, Institute of Canal Measuring Section," in The 7th International Conference on
Engineering, Lalitpur, Nepal, 2004. Hydraulic Efficiency Measurements, September 2008, Milan,
Italy, 2008, p. 11.
[28] R. Holland, Micro Hydro Electric Power.: Intermediate
Technology Development Group, England, 1983. [40] Harald Hulaas and Leif Vinnogg, "IEC 60041-1991, "Field
Acceptance Tests to Determine Hydraulic Performance of
[29] Adam Harvey, Micro Hydro Design Manual: A Guide to Small Hydraulic Turbines, Pumps and Pump-Turbines" Clause 14
Scale water power schemes.: Intermediate Technology "Thermodynamic Method for Measuring Efficiency" Comments,"
Publications, 1993. in IGHEM-2010, Oct. 21-23, 2010, AHEC, IIT Roorkee, Roorkee,
[30] ESHA, Guide on How to Develop a Small Hydropower Plant. India, 2010, pp. 171-180.
Brussels, Belgium: European Small Hydropower Association, [41] Santosh Ghosh, Sudhir Mali, and Jagadish T. Kshirsagar,
2004. "Performance Testing of a Low Head Small Hydro Power Plant
[31] ITDG, Civil Works Guideline for Micro Hydropower Development Zho Suwei (Taiwan) A Case Study," in IGMEC-2010, IIT
in Nepal.: Intemediate Technology Development Group. Roorkee, India, 2010.

[32] CRT/N, Manual on Microhydro Development. Kathmandu, Nepal: [42] AEPC/ESAP, Micro Hydro Implementation Guidelines.:
Centre for Rural Technology, 2005. Alternative Energy Promotion Centre, Rural Energy Development
Programme, 2010.
[33] Pushpa Chitrakar, Micro Hydro Design Aids Version 2006.05.
Kathmandu: Small Hydropower Promotion Project, GTZ, 2006. [43] DECEEC, "Detailed Feasibility Study Report of Suntale Khola
MHS (100kW) Taplejung," Submitted to District Development
[34] Klaus Jorde, Good and Bad of Mini Hydro Power, Roman Ritter, Committee, District Energy and Environment Section Taplejung,
Ed. Jakarta, Indonesia: The ASEAN Centre for Energy, 2009, vol. Kathmandu, Nepal, Technical Report Vol I 2011.
I & II.
[44] DATECPL, "Detailed Feasibility Study Report of Nurkhuwa
[35] Eve Cathrin Walseth, "Investigation of the flow through the Khola MHS (31kW) Sawakatahare VDC, Khotang," Distict
Runner of a Cross Flow Turbine," Norwegian University of Development Committee, District Energy and Environment
Science and Technology, Faculty of Engineering Science and Section Khotang, Kathmandu, Nepal, Technical Report 2009.
Technology, Department of Energy and Process Engineering,
Trondeheim, Norway, Master's thesis 2009. [45] HSCPL, "Detailed Feasibility Report of Yari Khola Micro Hydro
System (23kW), Ratapur VDC, Udayapur," District Development
[36] Owen Schumacher and Anders Austegard, RHL/IAM Crossflow Committee, District Energy and Environment Section Udayapur,
Turbine from Remote Hydrolight/IAM. Lalitpur, Nepal, Technical Report 2009.
[37] AHEC/MNRE, Standards/Manuals/Guidelines for Small Hydro [46] DATECPL, "Detailed Feasibility Study Report of Chima Khola
Development Version 3, Guideline for Selection of Hydro MHS (13 kW) Kaule VDC, Khotang," District Development
Generator for SHP.: Ministry of New and Renewable Energy, Committee, District Energy and Environment Section Khotang,
Government of India. Kathmandu, Nepal, Technical Report Volume I 2009.
[38] AEPC, National Micro Hydro Standards Nepal.: Alternative [47] DATECPL, "Detailed Feasibility Study Report of Rumranga
Energy Promotion Centre, 2005. Khola MHS (11kW) Kaule VDC, Khotang," District Development
Committee, District Energy and Environment Section Khotang,
[39] Harald Hulaas, Erik Nilsen, and Leif Vinnogg, "Thermodynamic Kathmandu, Nepal, Technical Volume I 2009.
Efficiency Measurements of Pelton Turbines, Experience from
Investigation of Energy/Temperature Distribution in the Discharge

Proceedings of IOE Graduate Conference, Vol. 1, Nov 2013 14

View publication stats

You might also like