Professional Documents
Culture Documents
BI-21-00097
METHOD OF STATEMENT
REVISION RECORD
MANAGER
Table Of Contents
Content
s
1. Scope.......................................................................................................................................................................4
2. Purpose...................................................................................................................................................................4
3. Definition.................................................................................................................................................................4
4. References & Industry codes...................................................................................................................................5
5. Roles and responsibilities........................................................................................................................................6
5.1 QA / QC Engineer.............................................................................................................................................6
5.2 Construction Manager.....................................................................................................................................6
5.3 Site Engineer....................................................................................................................................................6
5.4 Site Supervisor.................................................................................................................................................7
5.5 Safety Officer...................................................................................................................................................7
6. Sequence of work....................................................................................................................................................7
6.1 Preparation......................................................................................................................................................7
6.2 Communication system installation procedure................................................................................................7
6.3 CCTV Central cabinet installation.....................................................................................................................9
6.4 DESK TOP Type operator console installation..................................................................................................9
6.5 CCTV Camera installation...............................................................................................................................10
6.6 Fiber Optic Cable Installation.........................................................................................................................11
7. TOOLS AND EQUIPMENT........................................................................................................................................12
8. Health, Safety & Environment...............................................................................................................................12
SALES GAS FUEL SUPPLY SYSTEM FOR
NEW SALINE WATER CONVERSION
CORPORATION
1. Scope
This method statement defines the type and extent of the installation and inspection to be carried out
for Instrumentation works, as follows, Installation of Instrument cables, conduits, instrument junction
boxes (AJB and DJB), Installation of instrument cable and Grounding cable, RTU system, structural
support, testing and termination of cables and Testing, are in conformance to the specified standards
and requirements.
2. Purpose
The purpose of this method statement is to ensure that the Instrumentation works including testing
and inspection are carried out in accordance with the project specifications and manufacturer’s
recommendations as well as to meet acceptance workmanship and Saudi Aramco installation
standards.
3. Definition
5.1 QA / QC Engineer
The Contractor/Sub-contractor’s QA/QC engineer shall be responsible for the following:
5.1.1 Ensure that the approved method and materials to be used are in conformance with the
project specifications.
5.1.2 Organize inspections and surveillance in accordance with ITPs and ensure that the quality
of work will be in accordance with the project specifications.
5.1.3 Conducts inspection duties to make sure that the work is performed in accordance with
the applicable standards and specifications and drawings as specified in thecontract.
5.1.4 Prepares the applicable SATIP /SAIC /SATR and issues Request for Inspection (RFI).
Ensures that all the pre-requisite works prior to raising an RFI are completed by the
construction department.
5.1.5 Marks up field changes on the drawings and updates and redlines drawing that has
changed during the installation of the work. Submits the redlined drawings to the Project
Manager / Construction Manager for further actions.
5.1.6 Reviews records and test results as proof that the work inspected conforms to
specifications and keeps an efficient record of all RFI's and test results.
execution of the complete activities at site including, but not limited to;
5.3.1 Confirming the Installation locations from schedule of approved construction drawings.
5.3.2 Organizing tools and equipment required to be used at the work site.
5.3.3 Assigning work crew.
5.3.4 Plan, Monitor and advice about the activities to be carried out at site as per this Method
statement & ITP.
6. Sequence of work
6.1 Preparation
6.4.1 Survey and study the designed location of console desk top in the control room.
6.4.2 Check locations and provide markings to which elevations, mounting height and
orientations should conform in the latest issued Approved for Construction drawings.
6.4.3 Fabrication and installation of support for patch panel shall be as per installation
detail. Ensure that the orientation shall comply with the drawing layout.
6.4.4 Install local junction box/patch panel and conduits, routed from wall to ceiling down
to desk top with complete fittings and accessories.
6.4.5 Install/assemble console desk top and accessories.
6.4.6 Cable interconnection (patch cord cable), from data Telecommunication panel to
patch panel down to console desk top by plugging in the patch.
6.4.7 QC shall inspect the completed activity for console desktop and patch panel, conduits
and patch cord installation. Mock-up installation shall be requested and recorded
using appropriate and approved forms reflected on SATIP.
6.5.1 Check locations and provide markings to which elevations, mounting height and
orientations should conform in the latest issued Approved for Construction
drawings.
6.5.2 Camera shall be installed, in placed manually taking into consideration all necessary
precaution to prevent material damages due to poor handling, lack of information
and manual installation
6.5.3 Support for camera base shall be fabricated and installed as per approved detailed
drawing.
6.5.4 Brackets (vendor supply) for camera shall be available for mounting.
6.5.5 Enclosure type patch panel junction box shall be installed as per vendor
recommendation and latest issued approved for construction
6.5.6 Supports for conduits shall be fabricated and installed as per site
6.5.7 Conduits shall be installed as per latest issued approved for construction drawing.
6.5.8 For touch up painting for every steel surface, edging caused by cutting, drilling,
welding and grinding, refer to project spec.
6.5.9 QC shall inspect the completed activity for CCTV Camera, junction boxes and
SALES GAS FUEL SUPPLY SYSTEM FOR
NEW SALINE WATER CONVERSION
CORPORATION
peripherals installed and its supports. Mock-up installation shall be requested and
recorded using appropriate and approved forms reflected on SATIP.
6.6.1 Site plan, cable specifications, drawings and related documents shall be prepared and
reviewed with regards to respective areas and tackled all aspects to consider logistic
and resources
6.6.2 For underground cable installation, ensure that trenches are of proper route, width,
depth and sand bedding dimensions as shown on approved for construction drawings.
Compaction requirement shall be as per Saudi Aramco standard. QC inspection
shall be requested and recorded using appropriate and approved forms reflected on
SATIP.
6.6.3 Sand bedding/sand filling materials to be used shall be as per SAES-T-928 of the
approved type of cable use and free from any sharp stones, debris and contaminant
materials.
6.6.4 When communication, signal and power cable run in parallel at underground,
segregation distance shall be followed and maintained.
6.6.5 For above ground cable installation, cable tray and conduit shall be free from sharp
edges, foreign objects and unnecessary bends. Before installing cables, remove
foreign object, burrs and moisture from conduit and equipment enclosures.
6.6.6 Provide earth bonding between junction boxes and trays as well as conduits and shall
be connected to the allocated grounding bus.
6.6.7 Cable management in-charge shall confirm that the individual cable lengths are taken
from the designated cable drums.
6.6.8 Cable pulling tension and bending radius shall not exceed the limitations
recommended by the cable manufacturer. Refer to SAES-T-481Sec. 6 paras. 6.11.
6.6.9 Cable pulling for fiber optic cable shall be conducted manually. It shall be secured and
protected from falling objects, debris and should be avoided to cross in the walk
way without any cover for
6.6.10 Prior to fit up of cable glands, check the cable gland schedule to conform to the
correct size, type and area classification. Where glands are to be installed in
hazardous areas, the certification of the gland shall be verified.
6.6.11 Before tightening the cable gland ensure that the cable tails are of correct tails and
SALES GAS FUEL SUPPLY SYSTEM FOR
NEW SALINE WATER CONVERSION
CORPORATION
undamaged during stripping, earth is terminated and tagged as required, and the
outer sheath of the cable is contained within the gland.
6.6.12 Fiber optic fibers shall be spliced using fusion splicing equipment or approved
mechanical splices. Refer to SAES-T- 624 Sec. 4 sub-4.7.5.
6.6.13 Terminate all wiring or cable connections according to the wiring diagram, installing all
termination requirements including identification required to which non-corroding
material with cable reference numbers.
All tools utilized in a classified area should be intrinsically safe and suitable for hazardous areas.
8.1 Secure the approved work permit from the concerned company Representative before starting any
work.
8.2 Fire Watcher with Fire Extinguisher shall be assigned at work area whenever there is hot work.
SALES GAS FUEL SUPPLY SYSTEM FOR
NEW SALINE WATER CONVERSION
CORPORATION
****************************************END**********************************************