Professional Documents
Culture Documents
PEKERJAAN KAYU
HARGA
KODE
INDEK SAT URAIAN HARGA SATUAN (Rp) BAHAN UPAH JUMLAH HARGA (Rp)
ANALISA
( Rp ) ( Rp )
A. PEKERJAAN PONDASI KAYU
A.1.BOW SEBUAH TONGKAT ULIN UK.10/10 CM TINGGI 2,00 M
DICINCIN, DILANCIP DAN DITUMBUK
0.0200 M3 Balok ulin @ 4,500,000.00 90,000.00
0.5100 OH tukang kayu @ 98,000.00 49,980.00
0.8750 OH pekerja @ 79,000.00 69,125.00
0.0510 OH kepala tukang @ 110,000.00 5,610.00
0.0440 OH mandor @ 110,000.00 4,840.00
JUMLAH 90,000.00 129,555.00 219,555.00
A.2 SEBUAH TONGKAT ULIN UK.12/12 CM TINGGI 8,00 M
2 SAMBUNGAN DGN PIPA GALVANIS
0.0800 M3 Balok ulin @ 4,500,000.00 360,000.00
0.5100 OH tukang kayu @ 98,000.00 49,980.00
0.8750 OH pekerja @ 79,000.00 69,125.00
0.0510 OH kepala tukang @ 110,000.00 5,610.00
0.0440 OH mandor @ 110,000.00 4,840.00
JUMLAH 360,000.00 129,555.00 489,555.00
A.3 SEBUAH TONGKAT ULIN UK.10/10 CM TINGGI 4,00 M'
0.0400 M3 Balok ulin @ 4,500,000.00 180,000.00
0.5100 OH tukang kayu @ 98,000.00 49,980.00
0.8750 OH pekerja @ 79,000.00 69,125.00
0.0510 OH kepala tukang @ 110,000.00 5,610.00
0.0440 OH mandor @ 110,000.00 4,840.00
JUMLAH 180,000.00 129,555.00 309,555.00
A. 4 1 M3 MENGERJAKAN PAPAN SIRING KAYU ULIN
1.1000 M3 papan siring kayu ulin @ 5,300,000.00 5,830,000.00
3.0000 kg paku ulin @ #REF! #REF!
15.0000 OH tukang kayu @ 98,000.00 1,470,000.00
4.0000 OH pekerja @ 79,000.00 316,000.00
1.5000 OH kepala tukang @ 110,000.00 165,000.00
0.2000 OH mandor @ 110,000.00 22,000.00
JUMLAH #REF! 1,973,000.00 #REF!
A. 5 1 M3 RANGKA BAWAH KAYU ULIN ( tiang + kalang, sunduk )
1.1000 M3 balok ky ulin @ 4,500,000.00 4,950,000.00
15.0000 OH tukang kayu @ 98,000.00 1,470,000.00
5.0000 OH pekerja @ 79,000.00 395,000.00
1.5000 OH kepala tukang @ 110,000.00 165,000.00
0.2500 OH mandor @ 110,000.00 27,500.00
JUMLAH 4,950,000.00 2,057,500.00 7,007,500.00
B. PEKERJAAN LANTAI KAYU
B. 1 1 M3 MENGERJAKAN SLOOF DAN GELAGAR KY ULIN
1.1000 M3 balok ky ulin @ 4,500,000.00 4,950,000.00
10.0000 Kg paku ulin @ #REF! #REF!
15.0000 OH tukang kayu @ 98,000.00 1,470,000.00
5.0000 OH pekerja @ 79,000.00 395,000.00
1.5000 OH kepala tukang @ 110,000.00 165,000.00
0.2500 OH mandor @ 110,000.00 27,500.00
JUMLAH #REF! 2,057,500.00 #REF!
B. 2 1 M2 LANTAI PAPAN KAYU ULIN DIKETAM
0.0254 M3 papan kayu ulin @ 5,300,000.00 134,620.00
0.2500 Kg paku ulin @ #REF! #REF!
0.8000 OH tukang kayu @ 98,000.00 78,400.00
0.2800 OH pekerja @ 79,000.00 22,120.00
0.0800 OH kepala tukang @ 110,000.00 8,800.00
0.0140 OH mandor @ 110,000.00 1,540.00
JUMLAH #REF! 110,860.00 #REF!
B. 3 1 M2 LANTAI PAPAN KAYU MERANTI DIKETAM
0.0254 M3 papan kayu meranti klas 1 @ 2,920,320.00 74,176.13
0.2500 Kg paku biasa @ 20,500.00 5,125.00
0.8000 OH tukang kayu @ 98,000.00 78,400.00
0.2800 OH pekerja @ 79,000.00 22,120.00
0.0800 OH kepala tukang @ 110,000.00 8,800.00
0.0140 OH mandor @ 110,000.00 1,540.00
JUMLAH 79,301.13 110,860.00 190,161.13
B. PEKERJAAN DINDING KAYU
B. 4 1 M3 MENGERJAKAN RANGKA RUMAH KAYU ULIN (termasuk kusen)
1.1000 M3 balok ky ulin @ 4,500,000.00 4,950,000.00
5.0000 Kg paku ulin @ #REF! #REF!
20.0000 OH tukang kayu @ 98,000.00 1,960,000.00
10.0000 OH pekerja @ 79,000.00 790,000.00
2.0000 OH kepala tukang @ 110,000.00 220,000.00
0.5000 OH mandor @ 110,000.00 55,000.00
JUMLAH #REF! 3,025,000.00 #REF!
B. 5 1 M3 MENGERJAKAN RANGKA RUMAH KAYU MERANTI (termasuk kusen)
1.1000 M3 balok ky meranti @ 2,650,000.00 2,915,000.00
5.0000 Kg paku biasa @ 20,500.00 102,500.00
20.0000 OH tukang kayu @ 98,000.00 1,960,000.00
10.0000 OH pekerja @ 79,000.00 790,000.00
2.0000 OH kepala tukang @ 110,000.00 220,000.00
0.5000 OH mandor @ 110,000.00 55,000.00
JUMLAH 3,017,500.00 3,025,000.00 6,042,500.00
B Harga Bahan
1
2 Ampelas Lbr 3,000.00 - 3,000.00
5 Atap Metal Berkualitas ( 2 ssn, 8 daun ) Lbr 87,000.00 - 87,000.00
25 Balok Klas I Ulin M3 4,500,000.00 - 4,500,000.00
26 Balok Kayu Meranti M3 2,650,000.00 - 2,650,000.00
29 Batu Bata Bh 1,000.00 - 1,000.00
30 Batu apung Kg 950.00 - 950.00
31 Batu Gunung M3 220,000.00 - 220,000
35 Besi Beton Polos Kg 10,500.00 - 10,500.00
47 Cat Air / tembok Kg 75,000.00 - 75,000.00
48 Cat Air / tembok ex.setara ICI,dulux,mowilex Kg 110,000.00 110,000.00
50 Cat Dasar / plamir Kg 21,000.00 - 21,000.00
51 Cat Kilap / Kayu Kg 37,800.00 - 37,800.00
52 Cat Menie kayu Kg 21,600.00 - 21,600.00
57 Daun Jendela Uk. Besar (Fabrikasi) Kc 5 mm Bh 337,500.00 - 337,500.00
58 Daun Jendela Uk. Kecil (Fabrikasi) Kc 5 mm Bh 298,600.00 - 298,600.00
61 Dempul Halus ( INFRA ) Kg 45,000.00 - 45,000.00
62 Dempul kayu Kg 27,500.00 - 27,500.00
63 Dempul Politur Kg 32,500.00 - 32,500.00
64 Engsel Jendela Lokal 3 " Bh 28,500.00 - 28,500.00
65 Engsel Pintu Lokal 5 " Bh 38,750.00 - 38,750.00
HARGA DASAR
NO URAIAN SAT SUN BIAYA ANGKUT KETERANGAN
SATUAN
1 2 3 4 5 6 7
71 Grendel Jendela Bh 27,500.00 - 27,500.00
72 Grendel Pintu Bh 23,400.00 - 23,400.00
73 Grendel tanam Pintu Bh 65,000.00 - 65,000.00
75 Hak Angin Bh 18,750.00 - 18,750.00
76 Handle Jendela putih Bh 23,500.00 - 23,500.00
77 Handle Pintu Bh 27,500.00 - 27,500.00
78 Jalusi Atap Bh 365,000.00 - 365,000.00
85 Kaca polos 5 mm M2 35,000.00 - 35,000.00
88 Kawat Bendrat / Beton Kg 22,000.00 - 22,000.00
94 Kayu Klas 2 M3 2,900,000.00 - 2,900,000.00
95 Kayu galam dia 10 - 12 cm Btg 25,000.00 - 25,000.00
98 Keramik 20 x 20 cm M2 65,000.00 - 65,000.00
99 Keramik 40 x 40 cm Halus M2 72,300.00 - 72,300.00
100 Keramik 40 x 40 cm Kasar M2 72,300.00 - 72,300.00
104 Batu Split ( ukuran 2-3 cm/1-2 )Ex. Krayan M3 425,000.00 - 425,000.00
106 Koral (ex.Lokal) M3 425,000.00 - 425,000.00
109 Kuas 3 " Bh 23,500.00 - 23,500.00
110 Kunci Pintu 2 Slag berkualitas Bh 145,000.00 - 145,000.00
111 Kunci Pintu Double Ex Cisa Bh 165,000.00 - 165,000.00
116 Kuda-kuda baja ringan modern trus m2 187,000.00 - 187,000.00
123 Lampu Pijar 18 Watt Bh 47,500.00 - 47,500.00
138 List Plafond Plywood M' 33,500.00 - 33,500.00
149 Minyak cat Ltr 9,500.00 - 9,500.00
150 Minyak bekisting Ltr 10,800.00 - 10,800.00
159 Nok Model U ukuran 110 x 5 x 6 cm M' 33,750.00 - 33,750.00
168 Paku Genteng metal Kg 27,500.00 - 27,500.00
169 Paku Kayu / biasa Kg 20,500.00 - 20,500.00
174 Paku Sekrup Kg 3,000.00 - 3,000.00
175 Papan Kayu Bangkirai M3 6,500,000.00 - 6,500,000.00
176 Papan Kayu Ulin M3 5,300,000.00 - 5,300,000.00
177 Papan Kayu kelas 2 M3 2,920,320.00 - 2,920,320.00
178 Papan Kayu Meranti M3 2,920,320.00 - 2,920,320.00
179 Papan Nama Proyek Bh 550,000.00 - 550,000.00
183 Pasir Beton Ex. Lokal samuntai M3 365,000.00 - 365,000.00
184 Pasir Beton (sepaku) M3 477,000.00 - 477,000.00
185 Pasir Pasang sungai ex. Kandilo M3 365,000.00 - 365,000.00
186 Pasir pasang putih M3 87,000.00 - 87,000.00
188 Pasir Urug M3 87,000.00 - 87,000.00
190 Pasangan Jendela rangka alumunium + kaca 5 mm Bh 345,000.00 - 345,000.00
191 Pasangan Kusen Almunium Jendela m' 120,000.00 - 120,000.00
196 Pintu Panel kayu Ulin Ukuran Besar L 80 cm Bh 620,000.00 - 620,000.00
212 Plamir Kg 16,650.00 - 16,650.00
213 Plitur Kg 17,500.00 - 17,500.00
219 Plywood 9 mm Lbr 185,000.00 - 185,000.00
224 Rangka besi hollow M' 23,500.00 - 23,500.00
227 Roster beton 20 x 20 cm Bh 19,000.00 - 19,000.00
231 Saklar Ganda Bh 27,500.00 - 27,500.00
232 Saklar Tunggal Bh 19,500.00 - 19,500.00
233 Sekering Kas 3 Group + Instalasi Unit 245,000.00 - 245,000.00
234 Semen Abu - Abu / PC ( 50 kg/Zak ) Zak 66,000.00 - 66,000.00
235 Semen Warna Kg 9,000.00 - 9,000.00
236 Semen putih Kg 1,600.00 - 1,600.00
246 Stop Kontak Bh 22,500.00 - 22,500.00
249 Tanah Urug M3 87,000 - 87,000.00
266 Titik Mata Lampu Ttk 160,000.00 - 160,000.00
272 Pasir beton Exs. Palu m3 490,000.00 490,000.00
275 Kalsiboard 4 mm Lbr 85,000.00 85,000.00
276 Washtafel Unit - -
Catatan :
1. Harga diatas adalah harga disumber material ( disungai, dilokasi penggalian) khusus utk bahan lokal
2. Untuk bahan-bahan non lokal harga tersebut adalah harga toko / harga yang berlaku dipasaran
3. Harga sudah terrmasuk keuntungan kontraktor dan ongkos angkut
4 Harga belum termasuk PPn
Daftar Analisa Satuan Pekerjaan ( SNI )
A Pekerjaan Persiapan
3 1 m' Pengukuran dan pemasangan bouwplank
0.0120 m3 Kayu meranti 2,650,000.00 31,800.00
0.0200 kg Paku kayu 20,500.00 410.00
0.0070 m3 Papan kayu meranti 3/20 2,920,320.00 20,442.24
0.1000 Tukang kayu 98,000.00 9,800.00
0.1000 Pekerja 79,000.00 7,900.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0050 Mandor 110,000.00 550.00
Jumlah 19,350.00 52,652.24 72,002.24
B Pekerjaan Tanah
1 1 m3 Galian tanah biasa sedalam 1 meter
0.4000 Pekerja 79,000.00 31,600.00
0.0400 Mandor 110,000.00 4,400.00
Jumlah 36,000.00 36,000.00
9 1 m3 Pemadatan tanah
0.5000 Pekerja 79,000.00 39,500.00
0.0500 Mandor 110,000.00 5,500.00
Jumlah 45,000.00 - 45,000.00
10 1 m3 Urugan tanah
1.2000 m3 Tanah 87,000.00 104,400.00
0.2500 Pekerja 79,000.00 19,750.00
0.0250 Mandor 110,000.00 2,750.00
1.0000 ls Biaya pemadatan 45,000.00 45,000.00
Jumlah 67,500.00 104,400.00 171,900.00
11 1 m3 Mengurug tanah kembali
0.1920 Pekerja 79,000.00 15,168.00
0.0190 Mandor 110,000.00 2,090.00
Jumlah 17,258.00 17,258.00
12 1 m3 Urugan pasir
1.2000 m3 Pasir urug 87,000.00 104,400.00
0.3000 Pekerja 79,000.00 23,700.00
0.0100 Mandor 110,000.00 1,100.00
1.0000 ls Biaya pemadatan 45,000.00 45,000.00
Jumlah 69,800.00 104,400.00 174,200.00
C Pekerjaan Pondasi
1 1 m3 Pasang pondasi batu kosong/Aanstamping
1.2000 m3 Batu gunung 220,000.00 264,000.00
0.3000 m3 Pasir urug 87,000.00 26,100.00
0.7800 Pekerja 79,000.00 61,620.00
0.3900 Tukang Batu 98,000.00 38,220.00
0.0390 Kepala Tukang 110,000.00 4,290.00
0.0390 Mandor 110,000.00 4,290.00
Jumlah 108,420.00 290,100.00 398,520.00
3 1 m3 Pasang pondasi batu gunung 1 : 4
1.1000 m3 Batu gunung 220,000.00 242,000.00
3.2600 zak Semen PC 50 kg 66,000.00 215,160.00
0.5200 m3 Pasir pasang 87,000.00 45,240.00
1.5000 Pekerja 79,000.00 118,500.00
0.6000 Tukang batu 98,000.00 58,800.00
0.0600 Kepala Tukang 110,000.00 6,600.00
0.0750 Mandor 110,000.00 8,250.00
Jumlah 192,150.00 502,400.00 694,550.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
D Pekerjaan Struktur
1 1 m2 pasang bekisting untuk pondasi
0.0400 m3 Papan kayu kelas 2 2,920,320.00 116,812.80
0.3000 kg Paku kayu 20,500.00 6,150.00
0.1000 lt minyak bekisting 10,800.00 1,080.00
0.3000 Pekerja 79,000.00 23,700.00
0.2600 Tukang kayu 98,000.00 25,480.00
0.0260 Kepala Tukang 110,000.00 2,860.00
0.0050 Mandor 110,000.00 550.00
Jumlah 52,590.00 124,042.80 176,632.80
2 1 m2 pasang bekisting untuk sloof
0.0450 m3 Papan kayu kelas 2 2,920,320.00 131,414.40
0.3000 kg Paku kayu 20,500.00 6,150.00
0.1000 lt minyak bekisting 10,800.00 1,080.00
0.3000 Pekerja 79,000.00 23,700.00
0.2600 Tukang kayu 98,000.00 25,480.00
0.0260 Kepala Tukang 110,000.00 2,860.00
0.0050 Mandor 110,000.00 550.00
Jumlah 52,590.00 138,644.40 191,234.40
3 1 m2 pasang bekisting untuk kolom
0.0400 m3 Papan kayu kelas 2 2,920,320.00 116,812.80
0.4000 kg Paku kayu 20,500.00 8,200.00
0.2000 lt minyak bekisting 10,800.00 2,160.00
0.0150 m3 Balok kayu meranti 2,650,000.00 39,750.00
0.3500 lbr plywood tebal 9 mm 185,000.00 64,750.00
2.0000 btg kayu galam 25,000.00 50,000.00
0.3000 Pekerja 79,000.00 23,700.00
0.3300 Tukang kayu 98,000.00 32,340.00
0.0330 Kepala Tukang 110,000.00 3,630.00
0.0060 Mandor 110,000.00 660.00
Jumlah 60,330.00 281,672.80 342,002.80
E Pekerjaan Dinding
1 1 m2 Pasangan batu bata tebal 1/2 bata 1 : 2
60.0000 bh Batu bata 1,000.00 60,000.00
0.3790 zak Semen PC 50 kg 66,000.00 25,014.00
0.0380 m3 Pasir pasang putih 87,000.00 3,306.00
0.3200 Pekerja 79,000.00 25,280.00
0.1000 Tukang batu 98,000.00 9,800.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0150 Mandor 110,000.00 1,650.00
Jumlah 37,830.00 88,320.00 126,150.00
2 1 m2 Pasangan batu bata tebal 1 bata 1 : 2
120.0000 bh Batu bata 1,000.00 120,000.00
0.8700 zak Semen PC 50 kg 66,000.00 57,420.00
0.0800 m3 Pasir pasang putih 87,000.00 6,960.00
0.6500 Pekerja 79,000.00 51,350.00
0.2000 Tukang batu 98,000.00 19,600.00
0.0200 Kepala Tukang 110,000.00 2,200.00
0.0300 Mandor 110,000.00 3,300.00
Jumlah 76,450.00 184,380.00 260,830.00
3 1 m2 Pasangan batu bata tebal 1/2 bata 1 : 4
60.0000 bh Batu bata 1,000.00 60,000.00
0.2300 zak Semen PC 50 kg 66,000.00 15,180.00
0.0430 m3 Pasir pasang putih 87,000.00 3,741.00
0.3200 Pekerja 79,000.00 25,280.00
0.1000 Tukang batu 98,000.00 9,800.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0150 Mandor 110,000.00 1,650.00
Jumlah 37,830.00 78,921.00 116,751.00
4 1 m2 Pasang dinding roster 20 x 20
26.0000 bh Roster 19,000.00 494,000.00
0.2560 zak Semen PC 50 kg 66,000.00 16,896.00
0.0350 m3 Pasir pasang putih 87,000.00 3,045.00
0.3000 Pekerja 79,000.00 23,700.00
0.1000 Tukang batu 98,000.00 9,800.00
0.0150 Kepala Tukang 110,000.00 1,650.00
0.0150 Mandor 110,000.00 1,650.00
Jumlah 36,800.00 513,941.00 550,741.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
F Pekerjaan Plesteran
2 1 m2 Plesteran tebal 15 mm dengan 1 : 2
0.1704 zak Semen PC 50 kg 66,000.00 11,246.40
0.0170 m3 Pasir pasang putih 87,000.00 1,479.00
0.2000 Pekerja 79,000.00 15,800.00
0.1500 Tukang batu 98,000.00 14,700.00
0.0150 Kepala Tukang 110,000.00 1,650.00
0.0100 Mandor 110,000.00 1,100.00
Jumlah 33,250.00 12,725.40 45,975.40
L Pekerjaan Cat-catan
1 1 m2 Mendempul
0.0800 kg Dempul 27,500.00 2,200.00
0.0200 liter Minyak cat 9,500.00 190.00
0.0100 Kg Batu apung 950.00 9.50
0.0400 Pekerja 79,000.00 3,160.00
0.0400 Tukang cat 98,000.00 3,920.00
0.0040 Kepala Tukang 110,000.00 440.00
0.0025 Mandor 110,000.00 275.00
Jumlah 7,795.00 2,399.50 10,194.50
2 1 m2 Mengecat tembok yang baru
( 1 lapis plamir, 1 lapis cat dasar, dan
2 lapis cat penutup )
0.1000 kg Plamir 16,650.00 1,665.00
0.1000 kg Cat dasar 21,000.00 2,100.00
0.2600 kg Cat tembok ( Cat Penutup ) 2x 110,000.00 28,600.00
0.0200 Pekerja 79,000.00 1,580.00
0.0630 Tukang cat 98,000.00 6,174.00
0.0063 Kepala Tukang 110,000.00 693.00
0.0025 Mandor 110,000.00 275.00
Jumlah 8,722.00 32,365.00 41,087.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
3 1 m2 Pekerjaan cat kilap ( 1 lapis plamir ;
1 lapis cat dasar ; 2 lapis cat penutup )
0.2000 kg Cat meni 21,600.00 4,320.00
0.1500 kg Plamir 16,650.00 2,497.50
0.1700 kg Cat dasar 21,000.00 3,570.00
0.2600 kg Cat penutup 2 kali 110,000.00 28,600.00
0.0700 Pekerja 79,000.00 5,530.00
0.0090 Tukang cat 98,000.00 882.00
0.0060 Kepala Tukang 110,000.00 660.00
0.0025 Mandor 110,000.00 275.00
Jumlah 7,347.00 38,987.50 46,334.50
4 1 m2 Pekerjaan cat kilap ( 1 lapis plamir ;
1 lapis cat dasar ; 3 lapis cat penutup )
0.2000 kg Cat meni 21,600.00 4,320.00
0.1500 kg Plamir 16,650.00 2,497.50
0.1700 kg Cat dasar 21,000.00 3,570.00
0.3500 kg Cat penutup 3 kali 110,000.00 38,500.00
0.0700 Pekerja 79,000.00 5,530.00
0.1050 Tukang cat 98,000.00 10,290.00
0.0040 Kepala Tukang 110,000.00 440.00
0.0025 Mandor 110,000.00 275.00
Jumlah 16,535.00 48,887.50 65,422.50
5 1 m2 Plituran
0.5220 kg Politur 17,500.00 9,135.00
2.0000 lbr Ampelas 3,000.00 6,000.00
0.0600 Tukang cat 98,000.00 5,880.00
0.0160 Kepala Tukang 110,000.00 1,760.00
0.0025 Mandor 110,000.00 275.00
Jumlah 7,915.00 15,135.00 23,050.00
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV.KARYA SEJATI UTAMA
Pekerjaan : Pembangunan RKB SDN 009 Waru Konsultan Pengawas : CV. ARDHIA ASRI
Lokasi : Kec. Babulu Kab. Penajam Paser Utara Minggu : I ( Pertama )
Tahun : 2014 Periode : 15 Agustus 2014 - 17 Agustus 2014
LAPORAN MINGGUAN
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV.KARYA SEJATI UTAMA
Pekerjaan : Pembangunan RKB SDN 009 Waru Konsultan Pengawas : CV. ARDHIA ASRI
Lokasi : Kec. Babulu Kab. Penajam Paser Utara Minggu : I ( Pertama )
Tahun : 2014 Periode : 15 Agustus 2014 - 17 Agustus 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : II ( Kedua )
Tahun : 2014 Periode : 23 Juni 2014 - 30 Juni 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : III ( Ketiga )
Tahun : 2014 Periode : 1 Juli 2014 - 6 Juli 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : IV ( Keempat )
Tahun : 2014 Periode : 07 Juli 2014 - 13 Juli 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : V ( Lima )
Tahun : 2014 Periode : 14 Juli 2014 - 16 Juli 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Bulan : I ( Pertama )
Tahun : 2014 Periode : 18 Juni 2014 - 30 Juni 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : II ( Kedua )
Tahun : 2014 Periode : 01 Juli 2014 - 16 Juli 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. BUANA UMAR
Pekerjaan : Pembangunan RKB SDN 010 Waru Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Waru Kab. Penajam Paser Utara Minggu : I ( Pertama )
Tahun : 2014 Periode : 17 Agust. 2014 - 24 Agust. 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. BUANA UMAR
Pekerjaan : Pembangunan RKB SDN 010 Waru Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Waru Kab. Penajam Paser Utara Minggu : II ( Dua )
Tahun : 2014 Periode : 25 Agust. 2014 - 31 Agust. 2014
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 - - - - - - - 0.00% - - - 0%
0%
Jumlah A 500,000.00 0.03 - - - - - - - 0%
0%
B PEKERJAAN PEMBONGKARAN 0%
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 - - - - - - - 0.00% - - - 0.00%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 465.52 12,000.00 5,586,240.00 0.33 - - - - - - - 0.00% - - - 0.00%
3 Pembongkaran Plafond Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 - - - - - - - 0.00% - - - 0%
4 Pembongkaran Lisplank Atap Eksisting M² 570.57 20,000.00 11,411,400.00 0.68 - - - - - - - 0.00% - - - 0%
0%
Jumlah B 19,812,840.00 1.18 - - - - - -
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 84.00 211,490.00 17,765,160.00 1.06 - - - - - - - 0.00% - - - 0%
2 Plafond Calciboard (3,5mm) M² 84.00 73,279.00 6,155,436.00 0.37 - - - - - - - 0.00% - - - 0%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 - - - - - - - 0.00% - - - 0%
- Cat Tembok Interior M² 2,023.34 34,980.00 70,776,293.28 4.20 - - - - - - - 0.00% - - - 0%
- Cat Plafond M² 1,406.75 34,980.00 49,208,115.00 2.92 - - - - - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 684.00 7,500.00 5,130,000.00 0.30 - - - - - - - 0.00% - - - 0%
2 Lantai 2
- Cat Tembok Exterior Weather Shield M² 1364.72 38,340.00 52,323,364.80 3.11 - - - - - - - 0.00% - - - 0%
- Cat Tembok Interior M² 2,075.30 34,980.00 72,593,854.08 4.31 - - - - - - - 0.00% - - - 0%
- Cat Plafond M² 1,410.93 34,980.00 49,354,331.40 2.93 - - - - - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 579.20 7,500.00 4,344,000.00 0.26 - - - - - - - 0.00% - - - 0%
J. PEKERJAAN SANITASI
Roof Tank Air Bersih Type: Silinder Kapasitas: 5m3 Unit 2.00 10,084,500.00 20,169,000.00 1.20 - - - - - - - 0.00% - - - 0%
Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO bh 4.00 4,951,184.00 19,804,736.00 1.18 - - - - - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 4.00 822,269.00 3,289,076.00 0.20 - - - - - - - 0.00% - - - 0%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - - - - - 0.00% - - - 0%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - - - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - - - - - 0.00% - - - 0%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO bh 6.00 4,951,184.00 29,707,104.00 1.76 - - - - - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 2.00 822,269.00 1,644,538.00 0.10 - - - - - - - 0.00% - - - 0%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - - - - - 0.00% - - - 0%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - - - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - - - - - 0.00% - - - 0%
Instalasi Pemipaan Site
- GIP dia. 50 (Dari Gedung Utama ke Sumur Pompa) m 150.00 165,000.00 24,750,000.00 1.47 - - - - - - - 0.00% - - - 0%
- Gate valve dia 50mm bh 2.00 470,000.00 940,000.00 0.06 - - - - - - - 0.00% - - - 0%
- Gate valve dia 40mm bh 2.00 320,000.00 640,000.00 0.04 - - - - - - - 0.00% - - - 0%
- Gate valve dia 32mm bh 2.00 250,000.00 500,000.00 0.03 - - - - - - - 0.00% - - - 0%
Instalasi Air Bersih
Lantai 1
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - - - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - - - - - 0.00% - - - 0%
- Dia .25 m 10.00 35,000.00 350,000.00 0.02 - - - - - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - - - - - 0.00% - - - 0%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - - - - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd
SAT VOLUME VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) pek. ( Rp. ) (%) pek. ( Rp. ) (%) pek.
Lantai 2
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - - - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - - - - - 0.00% - - - 0%
- Dia .25 m 20.00 35,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - - - - - 0.00% - - - 0%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - - - - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 250.00 105,000.00 26,250,000.00 1.56 - - - - - - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - - - - - 0.00% - - - 0%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 70.00 105,000.00 7,350,000.00 0.44 - - - - - - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - - - - - 0.00% - - - 0%
Instalasi Air Bekas
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- dia. 80 m 160.00 65,000.00 10,400,000.00 0.62 - - - - - - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - - - - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
Lantai 2
- dia. 80 m 30.00 65,000.00 1,950,000.00 0.12 - - - - - - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - - - - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
Instalasi Pipa Ventilasi
Pipa PVC Kelas D (Incl. Fitting & Accessories)
Lantai 1
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - - - - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
Lantai 2
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - - - - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres Ls 1.00 18,000,000.00 18,000,000.00 1.07 - - - - - - - 0.00% - - - 0%
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
1 Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
2
3 - - 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
0 9 - - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
0 10 - - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
0 12 - #REF! 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
14 - - 12 : 09 NOVEMBER 2015 s/d 15 NOVEMBER 2015
15 - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
0 18 - - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
0 19 - - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
0 20 - - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - -
0 22 - -
23 - -
24 - -
0 25 - -
0 26 - -
27 - -
0 28 - -
29 - -
30 - -
31 - -
0 32 - -
0 33 - -
0 34 - -
0 35 - -
36 - -
0 37 - -
0 38 - -
0 39 - -
0 40 - -
41 - -
0 42 - -
43 - -
44 - -
0 45 - -
0 46 - -
0 47 - -
0 48 - -
0 49 - #REF!
52 - -
0 53 - -
54 - -
55 - -
56 - -
0 57 - -
0 58 - -
0 59 - #REF!
0 61 - -
0 62 - #REF!
0 64 - -
0 65 - #REF!
67 - -
0 68 - -
1 Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
69 - -
70 - -
71 - -
72 - -
0 73 - -
74 - -
0 75 - -
76 - -
0 77 - -
78 - -
0 79 - -
0 80 - -
0 81 - -
82 - -
0 83 - -
0 84 - -
0 85 - -
0 86 - -
0 87 - -
0 88 - -
0 89 - -
0 90 - -
91 - -
0 92 - -
93 - -
94 - -
0 95 - -
0 96 - -
0 97 - -
0 98 - -
0 99 - -
0 100 - -
0 101 - -
0 102 - -
0 103 - #REF!
105 - -
0 106 - -
107 - -
108 - -
0 109 - -
110 - -
111 - -
0 112 - -
0 113 - -
0 114 - -
0 115 - -
0 116 - -
117 - -
0 118 - -
0 119 - -
0 120 - -
0 121 - -
0 122 - -
123 - -
0 124 - -
0 125 - -
0 126 - -
0 127 - -
128 - -
129 - -
130 - -
0 131 - -
0 132 - -
0 133 - -
0 134 - -
0 135 - -
0 136 - -
137 - -
0 138 - -
1 Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
139 - -
140 - -
0 141 - -
0 142 - -
0 143 - -
0 144 - -
0 145 - -
0 146 - -
147 - -
0 148 - -
149 - -
150 - -
151 - -
0 152 - -
0 153 - -
154 - -
0 155 - -
0 156 - -
157 - -
158 - -
159 - -
0 160 - -
0 161 - -
0 162 - -
163 - -
0 164 - -
0 165 - -
0 166 - -
167 - -
168 - -
169 - -
0 170 - -
171 - -
0 172 - -
173 - -
0 174 - -
175 - -
0 176 - -
177 - -
0 178 - -
179 - -
180 - -
0 181 - #REF!
183 - -
0 184 - -
- -
RINCIAN PROGRES MINGGUAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 - - - - 1.00 500,000.00 0.03 100.00% 1.00 500,000.00 0.03 100%
0%
Jumlah A 500,000.00 0.03 - - - 500,000.00 0.03 500,000.00 0.03 0%
0%
B PEKERJAAN PEMBONGKARAN 0%
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 - - - - - - - 0.00% - - - 0.00%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 465.52 12,000.00 5,586,240.00 0.33 - - - - - - - 0.00% - - - 0.00%
3 Pembongkaran Plafond Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 - - - - - - - 0.00% - - - 0%
4 Pembongkaran Lisplank Atap Eksisting M² 570.57 20,000.00 11,411,400.00 0.68 - - - - - - - 0.00% - - - 0%
0%
Jumlah B 19,812,840.00 1.18 - - - - - -
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 84.00 211,490.00 17,765,160.00 1.06 - - - - - - - 0.00% - - - 0%
2 Plafond Calciboard (3,5mm) M² 84.00 73,279.00 6,155,436.00 0.37 - - - - - - - 0.00% - - - 0%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 - - - - - - - 0.00% - - - 0%
- Cat Tembok Interior M² 2,023.34 34,980.00 70,776,293.28 4.20 - - - - - - - 0.00% - - - 0%
- Cat Plafond M² 1,406.75 34,980.00 49,208,115.00 2.92 - - - - - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 684.00 7,500.00 5,130,000.00 0.30 - - - - - - - 0.00% - - - 0%
2 Lantai 2
- Cat Tembok Exterior Weather Shield M² 1364.72 38,340.00 52,323,364.80 3.11 - - - - - - - 0.00% - - - 0%
- Cat Tembok Interior M² 2,075.30 34,980.00 72,593,854.08 4.31 - - - - - - - 0.00% - - - 0%
- Cat Plafond M² 1,410.93 34,980.00 49,354,331.40 2.93 - - - - - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 579.20 7,500.00 4,344,000.00 0.26 - - - - - - - 0.00% - - - 0%
J. PEKERJAAN SANITASI
Roof Tank Air Bersih Type: Silinder Kapasitas: 5m3 Unit 2.00 10,084,500.00 20,169,000.00 1.20 - - - - - - - 0.00% - - - 0%
Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO bh 4.00 4,951,184.00 19,804,736.00 1.18 - - - - - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 4.00 822,269.00 3,289,076.00 0.20 - - - - - - - 0.00% - - - 0%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - - - - - 0.00% - - - 0%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - - - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - - - - - 0.00% - - - 0%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO bh 6.00 4,951,184.00 29,707,104.00 1.76 - - - - - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 2.00 822,269.00 1,644,538.00 0.10 - - - - - - - 0.00% - - - 0%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - - - - - 0.00% - - - 0%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - - - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - - - - - 0.00% - - - 0%
Instalasi Pemipaan Site
- GIP dia. 50 (Dari Gedung Utama ke Sumur Pompa) m 150.00 165,000.00 24,750,000.00 1.47 - - - - - - - 0.00% - - - 0%
- Gate valve dia 50mm bh 2.00 470,000.00 940,000.00 0.06 - - - - - - - 0.00% - - - 0%
- Gate valve dia 40mm bh 2.00 320,000.00 640,000.00 0.04 - - - - - - - 0.00% - - - 0%
- Gate valve dia 32mm bh 2.00 250,000.00 500,000.00 0.03 - - - - - - - 0.00% - - - 0%
Instalasi Air Bersih
Lantai 1
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - - - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - - - - - 0.00% - - - 0%
- Dia .25 m 10.00 35,000.00 350,000.00 0.02 - - - - - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - - - - - 0.00% - - - 0%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - - - - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd
SAT VOLUME VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) pek. ( Rp. ) (%) pek. ( Rp. ) (%) pek.
Lantai 2
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - - - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - - - - - 0.00% - - - 0%
- Dia .25 m 20.00 35,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - - - - - 0.00% - - - 0%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - - - - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 250.00 105,000.00 26,250,000.00 1.56 - - - - - - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - - - - - 0.00% - - - 0%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 70.00 105,000.00 7,350,000.00 0.44 - - - - - - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - - - - - 0.00% - - - 0%
Instalasi Air Bekas
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- dia. 80 m 160.00 65,000.00 10,400,000.00 0.62 - - - - - - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - - - - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
Lantai 2
- dia. 80 m 30.00 65,000.00 1,950,000.00 0.12 - - - - - - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - - - - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
Instalasi Pipa Ventilasi
Pipa PVC Kelas D (Incl. Fitting & Accessories)
Lantai 1
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - - - - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
Lantai 2
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - - - - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - - - - - 0.00% - - - 0%
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres Ls 1.00 18,000,000.00 18,000,000.00 1.07 - - - - - - - 0.00% - - - 0%
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
2
3 - - 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
1 4 1 1.00 - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
0 9 - - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
0 10 - - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
0 12 - #REF! 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
14 - - 12 : 09 NOVEMBER 2015 s/d 15 NOVEMBER 2015
15 - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
0 18 - - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
0 19 - - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
0 20 - - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - -
0 22 - -
23 - -
24 - -
0 25 - -
0 26 - -
27 - -
0 28 - -
29 - -
30 - -
31 - -
0 32 - -
0 33 - -
0 34 - -
0 35 - -
36 - -
0 37 - -
0 38 - -
0 39 - -
0 40 - -
41 - -
0 42 - -
43 - -
44 - -
0 45 - -
0 46 - -
0 47 - -
0 48 - -
0 49 - #REF!
52 - -
0 53 - -
54 - -
55 - -
56 - -
0 57 - -
0 58 - -
0 59 - #REF!
0 61 - -
0 62 - #REF!
0 64 - -
0 65 - #REF!
67 - -
0 68 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
69 - -
70 - -
71 - -
72 - -
0 73 - -
74 - -
0 75 - -
76 - -
0 77 - -
78 - -
0 79 - -
0 80 - -
0 81 - -
82 - -
0 83 - -
0 84 - -
0 85 - -
0 86 - -
0 87 - -
0 88 - -
0 89 - -
0 90 - -
91 - -
0 92 - -
93 - -
94 - -
0 95 - -
0 96 - -
0 97 - -
0 98 - -
0 99 - -
0 100 - -
1 101 1 1.00 -
2 102 1 1 2.00 -
0 103 - #REF!
105 - -
0 106 - -
107 - -
108 - -
0 109 - -
110 - -
111 - -
0 112 - -
0 113 - -
0 114 - -
0 115 - -
0 116 - -
117 - -
0 118 - -
0 119 - -
0 120 - -
0 121 - -
0 122 - -
123 - -
0 124 - -
0 125 - -
0 126 - -
0 127 - -
128 - -
129 - -
130 - -
0 131 - -
0 132 - -
0 133 - -
0 134 - -
0 135 - -
0 136 - -
137 - -
0 138 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
139 - -
140 - -
0 141 - -
0 142 - -
0 143 - -
0 144 - -
0 145 - -
0 146 - -
147 - -
0 148 - -
149 - -
150 - -
151 - -
0 152 - -
0 153 - -
154 - -
0 155 - -
0 156 - -
157 - -
158 - -
159 - -
0 160 - -
0 161 - -
0 162 - -
163 - -
0 164 - -
0 165 - -
0 166 - -
167 - -
168 - -
169 - -
0 170 - -
171 - -
0 172 - -
173 - -
0 174 - -
175 - -
0 176 - -
177 - -
0 178 - -
179 - -
180 - -
0 181 - #REF!
183 - -
0 184 - -
- -
TIME SCHEDULE
NAMA KEGIATAN : PENGEMBANGAN WILAYAH STRATEGI DAN CEPAT TUMBUH BULAN KE : II ( KEDUA )
KEGIATAN : PEMBANGUNAN POS PELAYANAN PERIODE :
PEKERJAAN : PEMBANGUNAN POS PELAYANAN POLRES KAB. PPU LOKASI : KOMPLEKS MAPOLRES PENAJAM PASER UTARA
NOMOR KONTRAK : 765/449/DPU/PPU/2016 TAHUN ANGGARAN : 2016
TANGGAL : 14 JUNI 2016
NILAI KONTRAK : RP. 1.608.641.100
KONTRAKTOR : CV. SINAR PRIMA KARYA
TAHUN 2016
154(Seratus Lima Puluh Empat) Hari Kalender
BOBOT BULAN / MINGGU KE-
NO. JENIS PEKERJAAN (%) KET
JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
100%
A PEKERJAAN PERSIAPAN #REF! #REF! #REF!
B PEKERJAAN STRUKTUR #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
C PEKERJAAN ARSITEKTUR #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
D PEKERJAAN MEKANIKAL DAN ELEKTRIKAL #REF! #REF! #REF! #REF! #REF! #REF!
E PEKERJAAN LAIN - LAIN #REF! #REF! #REF! #REF! #REF! #REF! #REF!
0%
JUMLAH TOTAL BOBOT FISIK #REF!
PROGRESS RENCANA MINGGUAN CCO-01 (%) - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
PROGRESS RENCANA KOMULATIF CCO-01 (%) - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
PROGRESS REALISASI MINGGUAN (%) - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
PROGRESS REALISASI KOMULATIF (%) - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
DEVIASI (+/-) #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
KETERANGAN :
: Rencana Kontrak CCO-01
: Realisasi Progres
KONTRAK CCO - 01 S/d Minggu Lalu Minggu Ini S/d Bulan Ini
NO URAIAN
HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT thd
SAT VOLUME ( Rp. ) ( Rp. ) (%) VOLUME ( Rp. ) ( % ) thd pek. VOLUME ( Rp. ) ( % ) thd pek. VOLUME ( Rp. ) (%) pek.
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bouwplank M¹ 80.00 63,207.20 5,056,576.00 0.34 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
2 Papan Nama Proyek Bh 1.00 500,000.00 500,000.00 0.03 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
Jumlah 5,556,576.00 0.38 #REF! #REF! - - #REF! #REF!
Sub Total I 5,556,576.00 0.38 #REF! #REF! - - #REF! #REF!
II PEKERJAAN STRUKTUR
A Struktur Pondasi
1 Pekerjaan Pondasi Setempat
- K-225 M³ 7.04 1,692,376.90 11,920,679.76 0.81 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
- Pembesian Ulir Kg 1,089.90 20,348.50 22,177,725.29 1.51 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
- Bekisting M² 12.10 232,417.92 2,811,327.16 0.19 #REF! #REF! #REF! #REF! - - 0% #REF! #REF! #REF! #REF!
#REF!
2 Pekerjaan Pondasi Batu Kali M³ 97.92 1,029,922.88 100,850,048.41 6.86 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3 Tie Beam / Sloof TB1 15 x 25cm #REF!
- K-225 M³ 3.60 1,692,376.90 6,092,556.83 0.41 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Pembesian Polos Kg 699.13 18,466.90 12,910,738.01 0.88 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Bekisting M² 48.00 248,769.92 11,940,956.16 0.81 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
4 Galian tanah Pondasi M³ 95.04 79,884.00 7,592,175.36 0.52 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
5 Galian Tanah Siring Selasar M³ 29.74 79,884.00 2,375,430.62 0.16 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
6 Urug pasir dibawah Pondasi M³ 10.56 147,806.40 1,560,835.58 0.11 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
7 Urugan Pasir Bawah Siring Selasar M³ 4.25 147,806.40 627,881.59 0.04 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
8 Lantai kerja t=10 cm #REF!
- Dibawah pondasi batu kali M² - - - #REF!
- Dibawah pondasi setempat M² 2.74 1,222,641.28 3,354,927.67 0.23 #REF! #REF! #REF! #REF! - - 0% #REF! #REF! #REF! #REF!
9 Tanah urug peninggian lantai t=1.25 m (dalam bangunan) M³ 230.86 232,881.60 53,763,744.82 3.66 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
10 Tanah urug peninggian lantai t=1.10 m (Selasar) M³ 53.38 232,881.60 12,431,965.03 0.85 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
11 Pekerjaan Selasar Siring Batu Kali M³ 53.81 1,029,922.88 55,418,090.33 3.77 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
12 Cor beton lantai dasar Camp. 1:3:5 t=7 cm M³ 17.96 1,222,641.28 21,964,506.07 1.49 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
13 Pembesian Pelat (Wiremesh M6 2 layer) M² - - - #REF!
Jumlah 327,793,588.69 22.30 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF!
B Struktur Atas #REF!
1 Kolom 25x25, 10 Unit #REF!
- K-225 M³ 2.50 1,692,376.90 4,230,942.24 0.29 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Pembesian Polos Kg 416.18 18,466.90 7,685,587.64 0.52 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Bekisting M² 40.00 110,076.96 4,403,078.40 0.30 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
2 Kolom Praktis : 10x10, 13 Unit #REF! -
- K-225 M³ 0.52 1,692,376.90 880,035.99 0.06 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Pembesian Polos Kg 165.98 18,466.90 3,065,200.05 0.21 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Bekisting M² 10.40 110,076.96 1,144,800.38 0.08 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
3 Kolom 12x25, 14 Unit #REF! -
- K-225 M³ 1.55 1,692,376.90 2,629,953.70 0.18 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Pembesian Polos Kg 304.51 18,466.90 5,623,310.15 0.38 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Bekisting M² 38.33 110,076.96 4,219,470.03 0.29 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
4 Meja Beton POS Pelayanan - #REF! -
- K-225 M³ 0.82 1,692,376.90 1,389,102.96 0.09 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Pembesian Polos Kg 112.58 18,466.90 2,078,963.12 0.14 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Bekisting M² 5.28 110,076.96 581,206.35 0.04 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
5 Gawang Pintu Utama (PU) #REF! -
- K-225 M³ 0.68 1,692,376.90 1,150,816.29 0.08 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Pembesian Polos Kg 79.02 18,466.90 1,459,227.00 0.10 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
- Bekisting M² 10.20 110,076.96 1,122,784.99 0.08 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
Jumlah 41,664,479.28 2.83 #REF! #REF! #REF! - - #REF! #REF!
#REF!
KONTRAK CCO - 01 S/d Minggu Lalu Minggu Ini S/d Bulan Ini
NO URAIAN
SAT VOLUME HARGA SAT JUMLAH HARGA BOBOT VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT thd
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) pek.
NO URAIAN
SAT VOLUME HARGA SAT JUMLAH HARGA BOBOT VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT thd
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) pek.
10 Pintu Kayu Ulin Type P3 ( 80 x 270 ) Unit 2.00 2,050,000.00 4,100,000.00 0.28 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
11 Pintu Utama ( PU ) #REF!
a Daun pintu kaca frameless 12mm (tempered glass) m2 4.80 2,771,529.60 13,303,342.08 0.90 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
b Kaca mati frameless 12mm (tempered glass) m2 3.12 2,771,529.60 8,647,172.35 0.59 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
c Bar Handle untuk pintu kaca psg 2.00 1,921,997.28 3,843,994.56 0.26 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
d Floor hinge setara Dekson set 1.00 3,153,997.28 3,153,997.28 0.21 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
e Floor lock utk pintu kaca setara Dekson set 1.00 409,997.28 409,997.28 0.03 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
Jumlah 72,948,503.55 4.96 #REF! #REF! #REF! - - #REF! #REF!
#REF!
D PEKERJAAN PENUTUP ATAP #REF!
1 Atap alumunium spandex M² 303.27 319,471.04 96,886,157.82 6.59 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
2 Nok genteng metal M¹ 44.20 81,263.84 3,591,861.73 0.24 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
3 Lisplank Aluminium Composite Panel t= 30cm M¹ 73.20 579,514.88 42,420,489.22 2.89 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
Jumlah 142,898,508.76 9.72 #REF! #REF! #REF! - - #REF! #REF!
#REF!
E PEKERJAAN SANITAIR #REF!
1 Closed Jongkok Setara TOTO Unit 2.00 857,280.48 1,714,560.96 0.12 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
2 Pasang jet washer (terpasang) Unit 2.00 370,000.00 740,000.00 0.05 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
3 Pasang stop kran di kloset dan bak Unit 2.00 100,000.00 200,000.00 0.01 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
4 Pasang kran Bh 2.00 225,000.00 450,000.00 0.03 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
5 Pasang floor drain Bh 2.00 467,885.60 935,771.20 0.06 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
6 Wastafel Meja Unit 1.00 3,221,141.73 3,221,141.73 0.22 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
7 Wastafel Gantung Unit 1.00 1,161,517.28 1,161,517.28 0.08 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
Jumlah 8,422,991.17 0.57 #REF! #REF! #REF! - - #REF! #REF!
- #REF!
F PEKERJAAN PLAFOND DAN PERAPIHAN BETON EKSPOSE - #REF!
1 Plafond Gypsum Rangka Hollow 40x40 dan 20x40 M² 227.31 384,326.21 87,359,268.71 5.94 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
2 List Gypsum M¹ 246.60 54,176.64 13,359,959.42 0.91 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
Jumlah 100,719,228.13 6.85 #REF! #REF! #REF! - - #REF! #REF!
#REF!
G PEKERJAAN PENGECATAN #REF!
1 Cat Tembok Exterior Weather Shield M² 211.49 59,890.77 12,666,442.26 0.86 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
2 Cat Tembok Interior M² 292.46 52,633.17 15,393,033.15 1.05 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
3 Cat Plafond M² 227.31 21,161.17 4,810,039.29 0.33 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
4 Cat list plafond gypsum M¹ 12.33 21,161.17 260,917.20 0.02 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
Jumlah 33,130,431.91 2.25 #REF! #REF! #REF! - - #REF! #REF!
#REF!
H PEK. PERKERASAN DI DALAM & KELILING BAGIAN LUAR BANG. #REF!
H.1 Pekerjaan Perkerasan di Luar Bangunan #REF!
1 Tanah Urugan M³ - - - - #REF!
Jumlah - #REF!
H.2 Pekerjaan Grill Besi Jalan Masuk ke Bangunan #REF!
1 Pekerjaan Grill besi siku 5 cm diarea entrance, Jalan Masuk Ke Bangu M¹ 36.00 217,800.00 7,840,800.00 0.53 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
Jumlah 7,840,800.00 0.53 #REF! #REF! #REF! - - #REF! #REF!
#REF!
I PEKERJAAN DRAINASE #REF!
I.1 Pekerjaan Drainase Luar / Sekeliling Bangunan #REF!
1 Pasangan bata Saluran Keliling & taman ad 1 Pc : 4 , t=45mm M² 33.75 161,381.58 5,446,501.28 0.37 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
2 Plester aci M¹ 22.62 68,884.03 1,558,156.80 0.11 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
3 Lantai kerja ad. 1:3:5, t = 5 cm M³ 1.13 1,222,641.28 1,382,807.29 0.09 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
4 Pasir urug t = 5 cm M³ 1.13 147,806.40 167,169.04 0.01 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
5 Galian tanah saluran M³ 13.57 79,884.00 1,084,185.65 0.07 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
6 Urugan tanah kembali M³ 4.07 57,848.00 235,533.92 0.02 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
I.2 Pekerjaan Bak Kontrol #REF!
1 Pasangan bata Bak Kontrol ( 6 Unit BK ) ad 1 Pc : 4 Ps M² 3.24 161,381.58 522,876.33 0.04 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
2 Plester + aci M² 2.16 68,884.03 148,789.51 0.01 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
3 Pasir urug t = 5 cm M³ 0.05 147,806.40 7,981.55 0.00 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
4 Lantai kerja ad. 1:3:5 t = 5 cm M³ 0.05 1,222,641.28 66,022.63 0.00 #REF! #REF! #REF! #REF! - - - 0% - - #REF! 0%
5 Galian tanah M³ 0.65 79,884.00 51,764.83 0.00 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
6 Urugan tanah kembali M³ 0.19 57,848.00 11,245.65 0.00 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
Jumlah 10,683,034.47 0.73 #REF! #REF! #REF! - - #REF! #REF!
Sub Total III 601,323,161.14 40.90 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
KONTRAK CCO - 01 S/d Minggu Lalu Minggu Ini S/d Bulan Ini
NO URAIAN
SAT VOLUME HARGA SAT JUMLAH HARGA BOBOT VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT thd
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) pek.
NO URAIAN
SAT VOLUME HARGA SAT JUMLAH HARGA BOBOT VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT thd
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) pek.
#REF!
B.2 PEKERJAAN LISTRIK #REF!
B.2.1 PEKERJAAN PANEL #REF!
1 Lampu TL 1 x 36 W V -SHAPE Bh 6.00 203,900.00 1,223,400.00 0.08 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
2 Lampu TL 2 x 36 W TKI Bh 8.00 290,000.00 2,320,000.00 0.16 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
3 Down LIGHT 18 W Bh 19.00 806,000.00 15,314,000.00 1.04 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
4 Saklar Tunggal Bh 9.00 50,400.00 453,600.00 0.03 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
5 Saklar Double Bh 5.00 70,500.00 352,500.00 0.02 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
6 Stop Kontak 1 Phase Bh 16.00 63,300.00 1,012,800.00 0.07 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
Jumlah 20,676,300.00 1.41 #REF! #REF! #REF! - - #REF! #REF!
#REF!
#REF!
B.2.2 Pekerjaan Kabel #REF!
1 Kabel Distribusi Daya dari MDP Existing : #REF!
Kabel Twisted 4 x 25 mm (Kabel Udara) M¹ 180.00 50,000.00 9,000,000.00 0.61 #REF! #REF! #REF!
#REF!
2 Pekerjaan Instalasi Final #REF!
NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Lampu ttk 33.00 263,700.00 8,702,100.00 0.59 #REF! #REF! #REF!
NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Stop Kontak ttk 16.00 373,700.00 5,979,200.00 0.41 #REF! #REF! #REF! #REF! - - - 0% #REF! #REF! #REF! #REF!
#REF!
3 Pekerjaan Kabel Power VAC #REF!
Kabel NYM 3 x 2,5mm2 dari panel ke indoor unit #REF!
IU-1 M¹ 10.00 16,700.00 167,000.00 0.01 #REF! #REF!
Cap: 22500 buth #REF!
Lokasi Rg. Pelayanan #REF!
#REF!
IU-2 M¹ 14.00 16,700.00 233,800.00 0.02 #REF! #REF!
Cap: 22500 buth #REF!
Lokasi Rg. Pelayanan #REF!
#REF!
IU-3 M¹ 16.00 16,700.00 267,200.00 0.02 #REF! #REF!
Cap: 22500 buth #REF!
Lokasi Rg. Pelayanan #REF!
#REF!
IU-4 M¹ 22.00 16,700.00 367,400.00 0.02 #REF! #REF!
Cap: 18000 buth #REF!
Lokasi Ruangan #REF!
#REF!
IU-5 M¹ 26.00 16,700.00 434,200.00 0.03 #REF! #REF!
Cap: 18000 buth #REF!
Lokasi Ruangan #REF!
#REF!
IU-6 M¹ 22.00 16,700.00 367,400.00 0.02 #REF! #REF!
Cap: 18000 buth #REF!
Lokasi Ruangan #REF!
#REF!
IU-7 M¹ 26.00 16,700.00 434,200.00 0.03 #REF! #REF!
Cap: 18000 buth #REF!
Lokasi Ruangan #REF!
#REF!
IU-8 M¹ 10.00 16,700.00 167,000.00 0.01 #REF! #REF!
Cap: 18000 buth #REF!
Lokasi Ruang Istirahat #REF!
Jumlah 26,119,500.00 1.78 #REF! #REF! #REF! - - #REF! #REF!
Sub Total IV 139,326,490.00 9.48 #REF! #REF! #REF! - - #REF! #REF!
KONTRAK CCO - 01 S/d Minggu Lalu Minggu Ini S/d Bulan Ini
NO URAIAN
SAT VOLUME HARGA SAT JUMLAH HARGA BOBOT VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT thd
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) pek.
Disetujui Oleh,
Pengawas Lapangan
DINAS PEKERJAAN UMUM KAB.PPU
BIDANG CIPTA KARYA Diperiksa Oleh, Dibuat Oleh,
Konsultan Pengawas Kontraktor Pelaksana
1. NUR EFENDI, ST : ............................................... CV. ARDHIA ASRI CV. SINAR PRIMA KARYA
NIP. 19710623 200604 1 008
Hari :
Tanggal : JULI 2019
URAIAN KEGIATAN TENAGA KERJA JUMLAH
A. PEMBANGUNAN KAMAR MANDI/WC SITE MANAGER Orang
PELAKSANA LAPANGAN Orang
MANDOR Orang
KEPALA TUKANG Orang
TUKANG BATU Orang
TUKANG BESI Orang
TUKANG KAYU Orang
TUKANG CAT Orang
PEKERJA Orang
SITE ENGINEER Orang
PENGAWAS LAPANGAN Orang
CUACA
CERAH MENDUNG HUJAN JAM
B. PEMBANGUNAN UKS 07.00 S/D 08.00
08.00 S/D 09.00
09.00 S/D 10.00
10.00 S/D 11.00
11.00 S/D 12.00
12.00 S/D 13.00
13.00 S/D 14.00
14.00 S/D 15.00
15.00 S/D 16.00
16.00 S/D 17.00
CATATAN
C. PEMBANGUNAN PERPUSTAKAAN
MATERIAL MASUK
Jenis Material Jumlah Diterima / Ditolak
Hari :
Tanggal : AGUSTUS 2019
URAIAN KEGIATAN TENAGA KERJA JUMLAH
A. PEMBANGUNAN KAMAR MANDI/WC SITE MANAGER Orang
PELAKSANA LAPANGAN Orang
MANDOR Orang
KEPALA TUKANG Orang
TUKANG BATU Orang
TUKANG BESI Orang
TUKANG KAYU Orang
TUKANG CAT Orang
PEKERJA Orang
SITE ENGINEER Orang
PENGAWAS LAPANGAN Orang
CUACA
CERAH MENDUNG HUJAN JAM
B. PEMBANGUNAN UKS 07.00 S/D 08.00
08.00 S/D 09.00
09.00 S/D 10.00
10.00 S/D 11.00
11.00 S/D 12.00
12.00 S/D 13.00
13.00 S/D 14.00
14.00 S/D 15.00
15.00 S/D 16.00
16.00 S/D 17.00
CATATAN
C. PEMBANGUNAN PERPUSTAKAAN
MATERIAL MASUK
Jenis Material Jumlah Diterima / Ditolak
Hari :
Tanggal : SEPTEMBER 2019
URAIAN KEGIATAN TENAGA KERJA JUMLAH
A. PEMBANGUNAN KAMAR MANDI/WC SITE MANAGER Orang
PELAKSANA LAPANGAN Orang
MANDOR Orang
KEPALA TUKANG Orang
TUKANG BATU Orang
TUKANG BESI Orang
TUKANG KAYU Orang
TUKANG CAT Orang
PEKERJA Orang
SITE ENGINEER Orang
PENGAWAS LAPANGAN Orang
CUACA
CERAH MENDUNG HUJAN JAM
B. PEMBANGUNAN UKS 07.00 S/D 08.00
08.00 S/D 09.00
09.00 S/D 10.00
10.00 S/D 11.00
11.00 S/D 12.00
12.00 S/D 13.00
13.00 S/D 14.00
14.00 S/D 15.00
15.00 S/D 16.00
16.00 S/D 17.00
CATATAN
C. PEMBANGUNAN PERPUSTAKAAN
MATERIAL MASUK
Jenis Material Jumlah Diterima / Ditolak
Hari :
Tanggal : OKTOBER 2019
URAIAN KEGIATAN TENAGA KERJA JUMLAH
A. PEMBANGUNAN KAMAR MANDI/WC SITE MANAGER Orang
PELAKSANA LAPANGAN Orang
MANDOR Orang
KEPALA TUKANG Orang
TUKANG BATU Orang
TUKANG BESI Orang
TUKANG KAYU Orang
TUKANG CAT Orang
PEKERJA Orang
SITE ENGINEER Orang
PENGAWAS LAPANGAN Orang
CUACA
CERAH MENDUNG HUJAN JAM
B. PEMBANGUNAN UKS 07.00 S/D 08.00
08.00 S/D 09.00
09.00 S/D 10.00
10.00 S/D 11.00
11.00 S/D 12.00
12.00 S/D 13.00
13.00 S/D 14.00
14.00 S/D 15.00
15.00 S/D 16.00
16.00 S/D 17.00
CATATAN
C. PEMBANGUNAN PERPUSTAKAAN
MATERIAL MASUK
Jenis Material Jumlah Diterima / Ditolak
TAHUN 2017
154(Seratus Lima Puluh Empat) Hari Kalender
NO. JENIS PEKERJAAN BOBOT (%) BULAN / MINGGU KE- KET
JUNI JULI AGUSTUS SEPTEMBER OKTOBER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
tgl 19-25 26-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-30 1-7 8-16
A PEMBANGUNAN RKB
I PEKERJAAN PERSIAPAN 0.28 0.28 100%
II PEKERJAAN TANAH 3.02 0.50 0.50 0.80 1.22
III PEKERJAAN PONDASI 7.84 1.00 1.00 2.00 3.84
IV PEKERJAAN PASANGAN 8.96 1.00 1.00 1.00 0.50 5.46
V PEKERJAAN KAYU 5.56 0.20 5.00 0.20 0.16
VI PEKERJAAN STRUKTUR 12.86 1.00 2.00 3.00 5.00 1.86 -
VII PEKERJAAN PENUTUP ATAP 11.20 6.00 4.00 1.20 -
VIII PEKERJAAN PLAFOND 8.59 1.00 4.50 3.09 - -
IX PEKERJAAN KUNCI DAN KACA 0.95 0.60 0.35
X PEKERJAAN LANTAI 6.41 1.00 5.00 0.41
XI PEKERJAAN CAT-CATAN 5.35 4.00 1.20 0.15 -
B PEMBANGUNAN PERPUSTAKAAN
I PEKERJAAN PERSIAPAN 0.19 0.19
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
IV PEKERJAAN PASANGAN
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 - - 0% - - 0% - - - 0%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 - - 0% - - 0% - - - 0%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - 0% - - 0% - - - 0%
57,517,398.91 5.34 - - - - - -
V PEKERJAAN KAYU
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 - - 0% - - 0% - - - 0%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 - - 0% - - 0% - - - 0%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - 0% - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - 0% - - 0% - - - 0%
11,660,440.93 1.08 - - - - - -
VI. PEKERJAAN BETON
1 SLOOF 15/20
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% - - - 0% - - - 0%
2 KOLOM PRAKTIS
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 - - 0% - - 0% - - - 0%
5 CANOPY
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - 0% - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - 0% - - 0% - - - 0%
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% - - - 0% - - - 0%
36,932,777.55 3.43 - - - - - -
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
X. PEKERJAAN LANTAI
1 Pasang Lantai Keramik 40x40 cm M2 54.86 251,350.54 13,789,090.62 1.28 - - - 0% - - - 0% - - - 0%
2 Plint Keramik Ruangan M2 29.75 34,103.94 1,014,592.22 0.09 - - - 0% - - - 0% - - - 0%
3 Pasang Lantai Keramik Kasar 40x40 cm Teras M2 4.70 237,639.93 1,117,858.23 0.10 - - - 0% - - - 0% - - - 0%
15,921,541.07 1.48 - - - - - -
Disetujui Oleh,
DINAS PENDIDIKAN PEMUDA DAN OLAHRAGA Diperiksa Oleh, Dibuat Oleh,
KAB. PENAJAM PASER UTARA Konsultan Pengawas Kontraktor Pelaksana
Pengawas Lapangan CV. BUANA LESTARI CV. PRIMA EKA CIPTA
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 - - - 0.00% 1.00 500,000.00 0.03 100.00% 1.00 500,000.00 0.03 100%
0%
Jumlah A 500,000.00 0.03 - - - 500,000.00 0.03 500,000.00 0.03 0%
0%
B PEKERJAAN PEMBONGKARAN 0%
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 - - - 0.00% 7.00 84,000.00 0.00 5.97% 7.00 84,000.00 0.00 5.97%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 465.52 12,000.00 5,586,240.00 0.33 - - - 0.00% - - - 0.00% - - - 0.00%
3 Pembongkaran Plafond Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 - - - 0.00% - - - 0.00% - - - 0%
4 Pembongkaran Lisplank Atap Eksisting M² 570.57 20,000.00 11,411,400.00 0.68 - - - 0.00% - - - 0.00% - - - 0%
0%
Jumlah B 19,812,840.00 1.18 - - 84,000.00 0.00 84,000.00 0.00
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 84.00 211,490.00 17,765,160.00 1.06 - - - 0.00% - - - 0.00% - - - 0%
2 Plafond Calciboard (3,5mm) M² 84.00 73,279.00 6,155,436.00 0.37 - - - 0.00% - - - 0.00% - - - 0%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 - - - 0.00% 360.00 13,802,400.00 0.82 33.87% 360.00 13,802,400.00 0.82 34%
- Cat Tembok Interior M² 2,023.34 34,980.00 70,776,293.28 4.20 - - - 0.00% - - - 0.00% - - - 0%
- Cat Plafond M² 1,406.75 34,980.00 49,208,115.00 2.92 - - - 0.00% - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 684.00 7,500.00 5,130,000.00 0.30 - - - 0.00% - - - 0.00% - - - 0%
2 Lantai 2
- Cat Tembok Exterior Weather Shield M² 1364.72 38,340.00 52,323,364.80 3.11 - - - 0.00% 405.00 15,527,700.00 0.92 29.68% 405.00 15,527,700.00 0.92 30%
- Cat Tembok Interior M² 2,075.30 34,980.00 72,593,854.08 4.31 - - - 0.00% - - - 0.00% - - - 0%
- Cat Plafond M² 1,410.93 34,980.00 49,354,331.40 2.93 - - - 0.00% - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 579.20 7,500.00 4,344,000.00 0.26 - - - 0.00% - - - 0.00% - - - 0%
J. PEKERJAAN SANITASI
Roof Tank Air Bersih Type: Silinder Kapasitas: 5m3 Unit 2.00 10,084,500.00 20,169,000.00 1.20 - - - 0.00% - - - 0.00% - - - 0%
Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO bh 4.00 4,951,184.00 19,804,736.00 1.18 - - - 0.00% - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 4.00 822,269.00 3,289,076.00 0.20 - - - 0.00% - - - 0.00% - - - 0%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - 0.00% - - - 0.00% - - - 0%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - 0.00% - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO bh 6.00 4,951,184.00 29,707,104.00 1.76 - - - 0.00% - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 2.00 822,269.00 1,644,538.00 0.10 - - - 0.00% - - - 0.00% - - - 0%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - 0.00% - - - 0.00% - - - 0%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - 0.00% - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Pemipaan Site
- GIP dia. 50 (Dari Gedung Utama ke Sumur Pompa) m 150.00 165,000.00 24,750,000.00 1.47 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 50mm bh 2.00 470,000.00 940,000.00 0.06 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 40mm bh 2.00 320,000.00 640,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 32mm bh 2.00 250,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Air Bersih
Lantai 1
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - 0.00% - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .25 m 10.00 35,000.00 350,000.00 0.02 - - - 0.00% - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - 0.00% - - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd
SAT VOLUME VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) pek. ( Rp. ) (%) pek. ( Rp. ) (%) pek.
Lantai 2
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - 0.00% - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .25 m 20.00 35,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - 0.00% - - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 250.00 105,000.00 26,250,000.00 1.56 - - - 0.00% - - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - - 0.00% - - - 0%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 70.00 105,000.00 7,350,000.00 0.44 - - - 0.00% - - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Air Bekas
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- dia. 80 m 160.00 65,000.00 10,400,000.00 0.62 - - - 0.00% - - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
Lantai 2
- dia. 80 m 30.00 65,000.00 1,950,000.00 0.12 - - - 0.00% - - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Pipa Ventilasi
Pipa PVC Kelas D (Incl. Fitting & Accessories)
Lantai 1
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - 0.00% - - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
Lantai 2
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - 0.00% - - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres Ls 1.00 18,000,000.00 18,000,000.00 1.07 - - - 0.00% - - - 0.00% - - - 0%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 6,500,000.00 0.39 39,406,060.00 2.34 45,906,060.00 2.73
B. PPN 10 % ( A X 10 % ) 168,363,634.68 650,000.00 3,940,606.00 4,590,606.00
C. JUMLAH (A + B ) 1,851,999,981.45 7,150,000.00 43,346,666.00 50,496,666.00
D. DIBULATKAN 1,851,999,000.00 7,150,000.00 43,346,000.00 50,496,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
2
3 - 1.00 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - (45.00) 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
52 9 - 0 0 0 12.00 14 13 13.00 52.00 (172.00) 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
172 10 42.00 45 44 41.00 172.00 - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
0 12 - #REF! 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
14 - - 12 : 09 NOVEMBER 2015 s/d 15 NOVEMBER 2015
15 - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
0 18 - - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
0 19 - - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
0 20 - - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - -
0 22 - -
23 - -
24 - -
0 25 - -
0 26 - -
27 - -
0 28 - -
29 - -
30 - -
31 - -
360 32 45.00 50 44 40 54 42 41 44.00 360.00 -
0 33 - -
0 34 - -
0 35 - -
36 - -
405 37 55.00 68 48 46 54 44 42 48.00 405.00 -
0 38 - -
0 39 - -
0 40 - -
41 - -
0 42 - -
43 - -
44 - -
0 45 - -
0 46 - -
0 47 - -
0 48 - -
0 49 - #REF!
52 - -
0 53 - -
54 - -
55 - -
56 - -
7 57 1.4 1.5 1.3 1.6 1.20 7.00 -
0 58 - -
0 59 - #REF!
0 61 - -
0 62 - #REF!
0 64 - -
0 65 - #REF!
67 - -
0 68 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
69 - -
70 - -
71 - -
72 - -
0 73 - -
74 - -
0 75 - -
76 - -
0 77 - -
78 - -
0 79 - -
0 80 - -
0 81 - -
82 - -
0 83 - -
0 84 - -
0 85 - -
0 86 - -
0 87 - -
0 88 - -
0 89 - -
0 90 - -
91 - -
0 92 - -
93 - -
94 - -
0 95 - -
0 96 - -
0 97 - -
0 98 - -
0 99 - -
0 100 - -
0 101 0 - -
3 102 1 2.00 3.00 -
0 103 - #REF!
105 - -
0 106 - -
107 - -
108 - -
0 109 - -
110 - -
111 - -
0 112 - -
0 113 - -
0 114 - -
0 115 - -
0 116 - -
117 - -
0 118 - -
0 119 - -
0 120 - -
0 121 - -
0 122 - -
123 - -
0 124 - -
0 125 - -
0 126 - -
0 127 - -
128 - -
129 - -
130 - -
0 131 - -
0 132 - -
0 133 - -
0 134 - -
0 135 - -
0 136 - -
137 - -
0 138 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
139 - -
140 - -
0 141 - -
0 142 - -
0 143 - -
0 144 - -
0 145 - -
0 146 - -
147 - -
0 148 - -
149 - -
150 - -
151 - -
0 152 - -
0 153 - -
154 - -
0 155 - -
0 156 - -
157 - -
158 - -
159 - -
0 160 - -
0 161 - -
0 162 - -
163 - -
0 164 - -
0 165 - -
0 166 - -
167 - -
168 - -
169 - -
0 170 - -
171 - -
0 172 - -
173 - -
0 174 - -
175 - -
0 176 - -
177 - -
0 178 - -
179 - -
180 - -
0 181 - #REF!
183 - -
0 184 - -
- -
LAPORAN BULANAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100%
0%
Jumlah A 500,000.00 0.03 500,000.00 0.03 - - - 500,000.00 0.03 0%
0%
B PEKERJAAN PEMBONGKARAN 0%
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 7.00 84,000.00 0.00 5.97% - - - 0.00% 7.00 84,000.00 0.00 5.97%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 465.52 12,000.00 5,586,240.00 0.33 - - - 0.00% - - - 0.00% - - - 0.00%
3 Pembongkaran Plafond Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 - - - 0.00% - - - 0.00% - - - 0%
4 Pembongkaran Lisplank Atap Eksisting M² 570.57 20,000.00 11,411,400.00 0.68 - - - 0.00% - - - 0.00% - - - 0%
0%
Jumlah B 19,812,840.00 1.18 84,000.00 0.00 - - 84,000.00 0.00
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 84.00 211,490.00 17,765,160.00 1.06 - - - 0.00% - - - 0.00% - - - 0%
2 Plafond Calciboard (3,5mm) M² 84.00 73,279.00 6,155,436.00 0.37 - - - 0.00% - - - 0.00% - - - 0%
-
Jumlah D 23,920,596.00 1.42 - - - - - - - - -
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 360.00 13,802,400.00 0.82 33.87% 290.00 11,118,600.00 0.66 27.28% 650.00 24,921,000.00 1.48 61%
- Cat Tembok Interior M² 2,023.34 34,980.00 70,776,293.28 4.20 - - - 0.00% - - - 0.00% - - - 0%
- Cat Plafond M² 1,406.75 34,980.00 49,208,115.00 2.92 - - - 0.00% - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 684.00 7,500.00 5,130,000.00 0.30 - - - 0.00% - - - 0.00% - - - 0%
2 Lantai 2
- Cat Tembok Exterior Weather Shield M² 1364.72 38,340.00 52,323,364.80 3.11 405.00 15,527,700.00 0.92 29.68% 304.00 11,655,360.00 0.69 22.28% 709.00 27,183,060.00 1.61 52%
- Cat Tembok Interior M² 2,075.30 34,980.00 72,593,854.08 4.31 - - - 0.00% - - - 0.00% - - - 0%
- Cat Plafond M² 1,410.93 34,980.00 49,354,331.40 2.93 - - - 0.00% - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 579.20 7,500.00 4,344,000.00 0.26 - - - 0.00% - - - 0.00% - - - 0%
J. PEKERJAAN SANITASI
Roof Tank Air Bersih Type: Silinder Kapasitas: 5m3 Unit 2.00 10,084,500.00 20,169,000.00 1.20 - - - 0.00% - - - 0.00% - - - 0%
Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO bh 4.00 4,951,184.00 19,804,736.00 1.18 - - - 0.00% - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 4.00 822,269.00 3,289,076.00 0.20 - - - 0.00% - - - 0.00% - - - 0%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - 0.00% - - - 0.00% - - - 0%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - 0.00% - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO bh 6.00 4,951,184.00 29,707,104.00 1.76 - - - 0.00% - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 2.00 822,269.00 1,644,538.00 0.10 - - - 0.00% - - - 0.00% - - - 0%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - 0.00% - - - 0.00% - - - 0%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - 0.00% - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Pemipaan Site
- GIP dia. 50 (Dari Gedung Utama ke Sumur Pompa) m 150.00 165,000.00 24,750,000.00 1.47 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 50mm bh 2.00 470,000.00 940,000.00 0.06 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 40mm bh 2.00 320,000.00 640,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 32mm bh 2.00 250,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Air Bersih
Lantai 1
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - 0.00% - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .25 m 10.00 35,000.00 350,000.00 0.02 - - - 0.00% - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - 0.00% - - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd
SAT VOLUME VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) pek. ( Rp. ) (%) pek. ( Rp. ) (%) pek.
Lantai 2
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - 0.00% - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .25 m 20.00 35,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - 0.00% - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1 -
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 250.00 105,000.00 26,250,000.00 1.56 - - - 0.00% - - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - - 0.00% - - - 0%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 70.00 105,000.00 7,350,000.00 0.44 - - - 0.00% - - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Air Bekas
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- dia. 80 m 160.00 65,000.00 10,400,000.00 0.62 - - - 0.00% - - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
Lantai 2
- dia. 80 m 30.00 65,000.00 1,950,000.00 0.12 - - - 0.00% - - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Pipa Ventilasi
Pipa PVC Kelas D (Incl. Fitting & Accessories)
Lantai 1
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - 0.00% - - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
Lantai 2
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - 0.00% - - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres Ls 1.00 18,000,000.00 18,000,000.00 1.07 - - - 0.00% - - - 0.00% - - - 0%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 45,906,060.00 2.73 84,463,570.00 5.02 130,369,630.00 7.74
B. PPN 10 % ( A X 10 % ) 168,363,634.68 4,590,606.00 8,446,357.00 13,036,963.00
C. JUMLAH (A + B ) 1,851,999,981.45 50,496,666.00 92,909,927.00 143,406,593.00
D. DIBULATKAN 1,851,999,000.00 50,496,000.00 92,909,000.00 143,406,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
2
3 - - 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
0 9 - - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
0 10 - - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
0 12 - #REF! 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
14 - - 12 : 09 NOVEMBER 2015 s/d 15 NOVEMBER 2015
15 - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
0 18 - - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
0 19 - - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
57 20 8 7 8 10 8 6 47.00 - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - -
0 22 - -
23 - -
24 - -
0 25 - -
0 26 - -
0 27 - -
28 - -
29 - -
30 - -
31 - -
290 32 50 56 47 54 42 41 - 290.00 -
0 33 - -
0 34 - -
0 35 - -
36 - -
304 37 68 48 46 54 46 42 - 304.00 -
0 38 - -
0 39 - -
0 40 - -
41 - -
42 - -
43 - -
44 - -
0 45 - -
0 46 - -
0 47 - -
0 48 - -
0 49 - #REF!
52 - -
53 - -
54 - -
55 - -
56 - -
0 57 - -
2 58 1 0 1 0 2.00 -
190 59 30 29 33.00 32 31 35 190.00 #REF!
61 - -
0 62 - #REF!
0 64 - -
0 65 - #REF!
67 - -
68 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
69 - -
70 - -
71 - -
72 - -
0 73 - -
74 - -
0 75 - -
76 - -
0 77 - -
78 - -
0 79 - -
0 80 - -
0 81 - -
82 - -
0 83 - -
0 84 - -
0 85 - -
0 86 - -
0 87 - -
0 88 - -
0 89 - -
0 90 - -
91 - -
92 - -
93 - -
94 - -
0 95 - -
0 96 - -
0 97 - -
0 98 - -
0 99 - -
0 100 - -
0 101 - -
7 102 2 3 2 7.00 -
0 103 - #REF!
105 - -
106 - -
107 - -
108 - -
0 109 - -
110 - -
111 - -
0 112 - -
0 113 - -
0 114 - -
0 115 - -
0 116 - -
117 - -
0 118 - -
0 119 - -
0 120 - -
0 121 - -
0 122 - -
123 - -
0 124 - -
0 125 - -
0 126 - -
0 127 - -
128 - -
129 - -
130 - -
0 131 - -
0 132 - -
0 133 - -
0 134 - -
0 135 - -
0 136 - -
137 - -
0 138 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
139 - -
140 - -
0 141 - -
0 142 - -
0 143 - -
0 144 - -
0 145 - -
146 - -
147 - -
0 148 - -
149 - -
150 - -
0 151 - -
0 152 - -
0 153 - -
154 - -
0 155 - -
0 156 - -
157 - -
158 - -
159 - -
0 160 - -
0 161 - -
0 162 - -
163 - -
0 164 - -
0 165 - -
0 166 - -
167 - -
168 - -
169 - -
0 170 - -
171 - -
0 172 - -
173 - -
0 174 - -
175 - -
0 176 - -
177 - -
178 - -
179 - -
180 - -
0 181 - #REF!
183 - -
184 - -
- -
RINCIAN PROGRES MINGGUAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100%
0%
Jumlah A 500,000.00 0.03 500,000.00 0.03 - - - 500,000.00 0.03 0%
0%
B PEKERJAAN PEMBONGKARAN 0%
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 7.00 84,000.00 0.00 5.97% - - - 0.00% 7.00 84,000.00 0.00 5.97%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 465.52 12,000.00 5,586,240.00 0.33 - - - 0.00% - - - 0.00% - - - 0.00%
3 Pembongkaran Plafond Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 - - - 0.00% - - - 0.00% - - - 0%
4 Pembongkaran Lisplank Atap Eksisting M² 570.57 20,000.00 11,411,400.00 0.68 - - - 0.00% - - - 0.00% - - - 0%
0%
Jumlah B 19,812,840.00 1.18 84,000.00 0.00 - - 84,000.00 0.00
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 84.00 211,490.00 17,765,160.00 1.06 - - - 0.00% - - - 0.00% - - - 0%
2 Plafond Calciboard (3,5mm) M² 84.00 73,279.00 6,155,436.00 0.37 - - - 0.00% - - - 0.00% - - - 0%
-
Jumlah D 23,920,596.00 1.42 - - - - - - - - -
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 650.00 24,921,000.00 1.48 61.15% 412.92 15,831,352.80 0.94 38.85% 1,062.92 40,752,352.80 2.42 100%
- Cat Tembok Interior M² 2,023.34 34,980.00 70,776,293.28 4.20 - - - 0.00% - - - 0.00% - - - 0%
- Cat Plafond M² 1,406.75 34,980.00 49,208,115.00 2.92 - - - 0.00% - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 684.00 7,500.00 5,130,000.00 0.30 - - - 0.00% - - - 0.00% - - - 0%
2 Lantai 2
- Cat Tembok Exterior Weather Shield M² 1364.72 38,340.00 52,323,364.80 3.11 709.00 27,183,060.00 1.61 51.95% 655.72 25,140,304.80 1.49 48.05% 1,364.72 52,323,364.80 3.11 100%
- Cat Tembok Interior M² 2,075.30 34,980.00 72,593,854.08 4.31 - - - 0.00% - - - 0.00% - - - 0%
- Cat Plafond M² 1,410.93 34,980.00 49,354,331.40 2.93 - - - 0.00% - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 579.20 7,500.00 4,344,000.00 0.26 - - - 0.00% - - - 0.00% - - - 0%
J. PEKERJAAN SANITASI
Roof Tank Air Bersih Type: Silinder Kapasitas: 5m3 Unit 2.00 10,084,500.00 20,169,000.00 1.20 - - - 0.00% - - - 0.00% - - - 0%
Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO bh 4.00 4,951,184.00 19,804,736.00 1.18 - - - 0.00% - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 4.00 822,269.00 3,289,076.00 0.20 - - - 0.00% - - - 0.00% - - - 0%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - 0.00% - - - 0.00% - - - 0%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - 0.00% - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO bh 6.00 4,951,184.00 29,707,104.00 1.76 - - - 0.00% - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 2.00 822,269.00 1,644,538.00 0.10 - - - 0.00% - - - 0.00% - - - 0%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - 0.00% - - - 0.00% - - - 0%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - 0.00% - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Pemipaan Site
- GIP dia. 50 (Dari Gedung Utama ke Sumur Pompa) m 150.00 165,000.00 24,750,000.00 1.47 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 50mm bh 2.00 470,000.00 940,000.00 0.06 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 40mm bh 2.00 320,000.00 640,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 32mm bh 2.00 250,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Air Bersih
Lantai 1
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - 0.00% - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .25 m 10.00 35,000.00 350,000.00 0.02 - - - 0.00% - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - 0.00% 20.00 500,000.00 0.03 100.00% 20.00 500,000.00 0.03 100%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - 0.00% - - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd
SAT VOLUME VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) pek. ( Rp. ) (%) pek. ( Rp. ) (%) pek.
Lantai 2
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - 0.00% - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .25 m 20.00 35,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - 0.00% - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - - 0%
Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 250.00 105,000.00 26,250,000.00 1.56 - - - 0.00% - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - 0.00% - - - 0%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 70.00 105,000.00 7,350,000.00 0.44 - - - 0.00% - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - 0.00% - - - 0%
Instalasi Air Bekas
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- dia. 80 m 160.00 65,000.00 10,400,000.00 0.62 - - - 0.00% - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - - 0%
Lantai 2
- dia. 80 m 30.00 65,000.00 1,950,000.00 0.12 - - - 0.00% - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - - 0%
Instalasi Pipa Ventilasi
Pipa PVC Kelas D (Incl. Fitting & Accessories)
Lantai 1
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - 0.00% - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - - 0%
Lantai 2
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - 0.00% - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - - 0%
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres Ls 1.00 18,000,000.00 18,000,000.00 1.07 - - - 0.00% - - 0.00% - - - 0%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 130,369,630.00 7.74 90,295,131.60 5.36 220,664,761.60 13.11
B. PPN 10 % ( A X 10 % ) 168,363,634.68 13,036,963.00 9,029,513.16 22,066,476.16
C. JUMLAH (A + B ) 1,851,999,981.45 143,406,593.00 99,324,644.76 242,731,237.76
D. DIBULATKAN 1,851,999,000.00 143,406,000.00 99,324,000.00 242,731,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
2
3 - - 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
0 9 - - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
0 10 - - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
0 12 - #REF! 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
14 - - 12 : 09 NOVEMBER 2015 s/d 15 NOVEMBER 2015
15 - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
0 18 - - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
0 19 - - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
49 20 7 9 6 6 8 6 7 49.00 - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - -
0 22 - -
23 - -
24 - -
0 25 - -
0 26 - -
0 27 - -
28 - -
29 - -
30 - -
31 - -
412.92 32 66.00 63 68 60 62 47.5 46.42 - 412.92 -
0 33 - -
0 34 - -
0 35 - -
36 - -
655.72 37 102.00 110 96 90 80 92 85.72 - 655.72 -
0 38 - -
0 39 - -
0 40 - -
41 - -
42 - -
43 - -
44 - -
0 45 - -
0 46 - -
0 47 - -
0 48 - -
0 49 - #REF!
52 - -
53 - -
54 - -
55 - -
56 - -
0 57 - -
0 58 - -
0 59 - #REF!
61 - -
0 62 - #REF!
16 64 4.00 4 4 4 16.00 -
216 65 24.00 42 25 40 23 38 24 - 216.00 #REF!
67 - -
68 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
69 - -
70 - -
71 - -
72 - -
0 73 - -
74 - -
0 75 - -
76 - -
0 77 - -
78 - -
0 79 - -
0 80 - -
0 81 - -
82 - -
0 83 - -
0 84 - -
0 85 - -
0 86 - -
0 87 - -
0 88 - -
0 89 - -
0 90 - -
91 - -
92 - -
93 - -
94 - -
0 95 - -
0 96 - -
0 97 - -
0 98 - -
0 99 - -
0 100 - -
0 101 - -
0 102 - -
0 103 - #REF!
105 - -
106 - -
107 - -
108 - -
0 109 - -
110 - -
111 - -
0 112 - -
0 113 - -
0 114 - -
0 115 - -
0 116 - -
117 - -
0 118 - -
0 119 - -
0 120 - -
0 121 - -
0 122 - -
123 - -
0 124 - -
0 125 - -
0 126 - -
0 127 - -
128 - -
129 - -
130 - -
0 131 - -
0 132 - -
0 133 - -
0 134 - -
20 135 7 8 5 20.00 -
0 136 - -
137 - -
0 138 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
139 - -
140 - -
0 141 - -
0 142 - -
0 143 - -
0 144 - -
0 145 - -
146 - -
147 - -
148 - -
149 - -
150 - -
151 - -
152 - -
153 - -
154 - -
155 - -
156 - -
157 - -
158 - -
159 - -
160 - -
161 - -
162 - -
163 - -
164 - -
165 - -
166 - -
167 - -
168 - -
169 - -
170 - -
171 - -
172 - -
173 - -
174 - -
175 - -
176 - -
177 - -
178 - -
179 - -
180 - -
181 - #REF!
183 - -
184 - -
- -
RINCIAN PROGRES MINGGUAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100%
0%
Jumlah A 500,000.00 0.03 500,000.00 0.03 - - - 500,000.00 0.03 0%
0%
B PEKERJAAN PEMBONGKARAN 0%
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 7.00 84,000.00 0.00 5.97% - - - 0.00% 7.00 84,000.00 0.00 5.97%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 465.52 12,000.00 5,586,240.00 0.33 - - - 0.00% - - - 0.00% - - - 0.00%
3 Pembongkaran Plafond Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 - - - 0.00% - - - 0.00% - - - 0%
4 Pembongkaran Lisplank Atap Eksisting M² 570.57 20,000.00 11,411,400.00 0.68 - - - 0.00% - - - 0.00% - - - 0%
0%
Jumlah B 19,812,840.00 1.18 84,000.00 0.00 - - 84,000.00 0.00
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 84.00 211,490.00 17,765,160.00 1.06 - - - 0.00% - - - 0.00% - - - 0%
2 Plafond Calciboard (3,5mm) M² 84.00 73,279.00 6,155,436.00 0.37 - - - 0.00% - - - 0.00% - - - 0%
-
Jumlah D 23,920,596.00 1.42 - - - - - - - - -
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42 100%
- Cat Tembok Interior M² 2,023.34 34,980.00 70,776,293.28 4.20 - - - 0.00% - - - 0.00% - - - 0%
- Cat Plafond M² 1,406.75 34,980.00 49,208,115.00 2.92 - - - 0.00% - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 684.00 7,500.00 5,130,000.00 0.30 - - - 0.00% - - - 0.00% - - - 0%
2 Lantai 2
- Cat Tembok Exterior Weather Shield M² 1364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11 100%
- Cat Tembok Interior M² 2,075.30 34,980.00 72,593,854.08 4.31 - - - 0.00% - - - 0.00% - - - 0%
- Cat Plafond M² 1,410.93 34,980.00 49,354,331.40 2.93 - - - 0.00% - - - 0.00% - - - 0%
- Cat list plafond gypsum & kaLsiboard (interior) M' 579.20 7,500.00 4,344,000.00 0.26 - - - 0.00% - - - 0.00% - - - 0%
J. PEKERJAAN SANITASI
Roof Tank Air Bersih Type: Silinder Kapasitas: 5m3 Unit 2.00 10,084,500.00 20,169,000.00 1.20 - - - 0.00% - - - 0.00% - - - 0%
Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO bh 4.00 4,951,184.00 19,804,736.00 1.18 - - - 0.00% - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 4.00 822,269.00 3,289,076.00 0.20 - - - 0.00% 4.00 3,289,076.00 0.20 100.00% 4.00 3,289,076.00 0.20 100%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - 0.00% 10.00 4,664,240.00 0.28 50.00% 10.00 4,664,240.00 0.28 50%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - 0.00% - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO bh 6.00 4,951,184.00 29,707,104.00 1.76 - - - 0.00% - - - 0.00% - - - 0%
- Pemasangan Toilet Jongkok Setara TOTO bh 2.00 822,269.00 1,644,538.00 0.10 - - - 0.00% - - - 0.00% - - - 0%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - 0.00% - - - 0.00% - - - 0%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - 0.00% - - - 0.00% - - - 0%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Pemipaan Site
- GIP dia. 50 (Dari Gedung Utama ke Sumur Pompa) m 150.00 165,000.00 24,750,000.00 1.47 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 50mm bh 2.00 470,000.00 940,000.00 0.06 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 40mm bh 2.00 320,000.00 640,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Gate valve dia 32mm bh 2.00 250,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
Instalasi Air Bersih
Lantai 1
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - 0.00% - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .25 m 10.00 35,000.00 350,000.00 0.02 - - - 0.00% - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 20.0 500,000.00 0.03 100.00% - - - 0.00% 20.00 500,000.00 0.03 100%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - 0.00% - - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd
SAT VOLUME VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) pek. ( Rp. ) (%) pek. ( Rp. ) (%) pek.
Lantai 2
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - 0.00% - - - 0.00% - - - 0%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .25 m 20.00 35,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - - 0%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - 0.00% - - 0.00% - - - 0%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - - 0%
Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 250.00 105,000.00 26,250,000.00 1.56 - - - 0.00% - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - 0.00% - - - 0%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 70.00 105,000.00 7,350,000.00 0.44 - - - 0.00% - - 0.00% - - - 0%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - 0.00% - - - 0%
Instalasi Air Bekas
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- dia. 80 m 160.00 65,000.00 10,400,000.00 0.62 - - - 0.00% - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - - 0%
Lantai 2
- dia. 80 m 30.00 65,000.00 1,950,000.00 0.12 - - - 0.00% - - 0.00% - - - 0%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - 0.00% - - - 0%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - - 0%
Instalasi Pipa Ventilasi
Pipa PVC Kelas D (Incl. Fitting & Accessories)
Lantai 1
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - 0.00% - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - - 0%
Lantai 2
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - 0.00% - - 0.00% - - - 0%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - - 0%
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres Ls 1.00 18,000,000.00 18,000,000.00 1.07 - - - 0.00% - - 0.00% - - - 0%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 220,664,761.60 13.11 77,432,332.00 4.60 298,097,093.60 17.71
B. PPN 10 % ( A X 10 % ) 168,363,634.68 22,066,476.16 7,743,233.20 29,809,709.36
C. JUMLAH (A + B ) 1,851,999,981.45 242,731,237.76 85,175,565.20 327,906,802.96
D. DIBULATKAN 1,851,999,000.00 242,731,000.00 85,175,000.00 327,906,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
2
3 - - 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
0 9 - - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
0 10 - - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - (18.00) 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
18 12 18 18.00 #REF! 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
14 - - 12 : 09 NOVEMBER 2015 s/d 15 NOVEMBER 2015
15 - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
32 18 6 4 8 4 6 4 32.00 - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
0 19 - 3.00 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
52 20 7 9 6 6 8 6 7 49.00 - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - -
0 22 - -
23 - -
24 - -
0 25 - -
0 26 - -
0 27 - -
28 - -
29 - -
30 - -
31 - -
0 32 - - -
0 33 - -
0 34 - -
0 35 - -
36 - -
0 37 - - -
0 38 - -
0 39 - -
0 40 - -
41 - -
42 - -
43 - -
44 - -
0 45 - -
0 46 - -
0 47 - -
0 48 - (18.00)
18 49 8 4 6 18.00 #REF!
52 - -
53 - -
54 - -
55 - -
56 - -
0 57 - -
0 58 - -
0 59 - #REF!
61 - -
0 62 - #REF!
20 64 6.00 4 5 5 20.00 -
280 65 25.00 54 29 59 30 56 27 - 280.00 #REF!
67 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
68 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
69 - -
70 - -
71 - -
72 - -
0 73 - -
74 - -
0 75 - -
76 - -
0 77 - -
78 - -
0 79 - -
0 80 - -
0 81 - -
82 - -
0 83 - -
0 84 - -
0 85 - -
0 86 - -
0 87 - -
0 88 - -
0 89 - -
0 90 - -
91 - -
92 - -
93 - -
94 - -
0 95 - -
0 96 - -
0 97 - -
0 98 - -
0 99 - -
0 100 - -
0 101 - -
0 102 - -
0 103 - #REF!
105 - -
106 - -
107 - -
108 - -
0 109 - -
110 - -
111 - -
0 112 - -
0 113 2 2 4.00 -
0 114 5 5 10.00 -
0 115 - -
0 116 - -
117 - -
0 118 - -
0 119 - -
0 120 - -
0 121 - -
0 122 - -
123 - -
0 124 - -
0 125 - -
0 126 - -
0 127 - -
128 - -
129 - -
130 - -
0 131 - -
0 132 - -
0 133 - -
0 134 - -
0 135 - -
0 136 - -
137 - -
0 138 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Total PERIODE MINGGU KE -
139 - -
140 - -
0 141 - -
0 142 - -
0 143 - -
0 144 - -
0 145 - -
146 - -
147 - -
148 - -
149 - -
150 - -
151 - -
152 - -
153 - -
154 - -
155 - -
156 - -
157 - -
158 - -
159 - -
160 - -
161 - -
162 - -
163 - -
164 - -
165 - -
166 - -
167 - -
168 - -
169 - -
170 - -
171 - -
172 - -
173 - -
174 - -
175 - -
176 - -
177 - -
178 - -
179 - -
180 - -
181 - #REF!
183 - -
184 - -
- -
RINCIAN PROGRES MINGGUAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 7.00 84,000.00 0.00 5.97% - - - 0.00% 7.00 84,000.00 0.00
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 465.52 12,000.00 5,586,240.00 0.33 - - - 0.00% - - - 0.00% - - -
3 Pembongkaran Plafond Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 - - - 0.00% - - - 0.00% - - -
4 Pembongkaran Lisplank Atap Eksisting M² 570.57 20,000.00 11,411,400.00 0.68 - - - 0.00% - - - 0.00% - - -
Jumlah C 148,274,513.08 8.81 45,398,824.00 2.70 0.00% 21,978,746.00 1.31 67,377,570.00 4.00
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 84.00 211,490.00 17,765,160.00 1.06 - - - 0.00% - - - 0.00% - - -
2 Plafond Calciboard (3,5mm) M² 84.00 73,279.00 6,155,436.00 0.37 - - - 0.00% - - - 0.00% - - -
-
Jumlah D 23,920,596.00 1.42 - - 0.00% - - - -
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42
- Cat Tembok Interior M² 2,023.34 34,980.00 70,776,293.28 4.20 - - - 0.00% - - - 0.00% - - -
- Cat Plafond M² 1,406.75 34,980.00 49,208,115.00 2.92 - - - 0.00% - - - 0.00% - - -
- Cat list plafond gypsum & kaLsiboard (interior) M' 684.00 7,500.00 5,130,000.00 0.30 - - - 0.00% - - - 0.00% - - -
2 Lantai 2
- Cat Tembok Exterior Weather Shield M² 1364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11
- Cat Tembok Interior M² 2,075.30 34,980.00 72,593,854.08 4.31 - - - 0.00% - - - 0.00% - - -
- Cat Plafond M² 1,410.93 34,980.00 49,354,331.40 2.93 - - - 0.00% - - - 0.00% - - -
- Cat list plafond gypsum & kaLsiboard (interior) M' 579.20 7,500.00 4,344,000.00 0.26 - - - 0.00% - - - 0.00% - - -
J. PEKERJAAN SANITASI
Roof Tank Air Bersih Type: Silinder Kapasitas: 5m3 Unit 2.00 10,084,500.00 20,169,000.00 1.20 - - - 0.00% - - - 0.00% - - -
Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO bh 4.00 4,951,184.00 19,804,736.00 1.18 - - - 0.00% - - - 0.00% - - -
- Pemasangan Toilet Jongkok Setara TOTO bh 4.00 822,269.00 3,289,076.00 0.20 4.00 3,289,076.00 0.20 100.00% - - - 0.00% 4.00 3,289,076.00 0.20
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 10.00 4,664,240.00 0.28 50.00% - - - 0.00% 10.00 4,664,240.00 0.28
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - 0.00% - - - 0.00% - - -
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - -
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO bh 6.00 4,951,184.00 29,707,104.00 1.76 - - - 0.00% - - - 0.00% - - -
- Pemasangan Toilet Jongkok Setara TOTO bh 2.00 822,269.00 1,644,538.00 0.10 - - - 0.00% 4.00 3,289,076.00 0.20 200.00% 4.00 3,289,076.00 0.20
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 - - - 0.00% 10.00 4,664,240.00 0.28 50.00% 10.00 4,664,240.00 0.28
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 - - - 0.00% - - - 0.00% - - -
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - -
Instalasi Pemipaan Site
- GIP dia. 50 (Dari Gedung Utama ke Sumur Pompa) m 150.00 165,000.00 24,750,000.00 1.47 - - - 0.00% - - - 0.00% - - -
- Gate valve dia 50mm bh 2.00 470,000.00 940,000.00 0.06 - - - 0.00% - - - 0.00% - - -
- Gate valve dia 40mm bh 2.00 320,000.00 640,000.00 0.04 - - - 0.00% - - - 0.00% - - -
- Gate valve dia 32mm bh 2.00 250,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - -
Instalasi Air Bersih
Lantai 1
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - 0.00% - - - 0.00% - - -
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - -
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - -
- Dia .25 m 10.00 35,000.00 350,000.00 0.02 - - - 0.00% - - - 0.00% - - -
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 20.00 500,000.00 0.03 100.00% - - - 0.00% 20.00 500,000.00 0.03
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - 0.00% - - - 0.00% - - -
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - -
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME VOLUME thd pek. VOLUME thd pek. VOLUME
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%)
Lantai 2
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 - - - 0.00% - - - 0.00% - - -
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - -
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 - - - 0.00% - - - 0.00% - - -
- Dia .25 m 20.00 35,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - -
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 - - - 0.00% 20.00 500,000.00 0.03 100.00% 20.00 500,000.00 0.03
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 - - - 0.00% - - - 0.00% - - -
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - -
Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 250.00 105,000.00 26,250,000.00 1.56 - - - 0.00% - - 0.00% - - -
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - 0.00% - - -
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 70.00 105,000.00 7,350,000.00 0.44 - - - 0.00% - - 0.00% - - -
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - 0.00% - - -
Instalasi Air Bekas
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- dia. 80 m 160.00 65,000.00 10,400,000.00 0.62 - - - 0.00% - - 0.00% - - -
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - 0.00% - - -
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - -
Lantai 2
- dia. 80 m 30.00 65,000.00 1,950,000.00 0.12 - - - 0.00% - - 0.00% - - -
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - 0.00% - - -
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - -
Instalasi Pipa Ventilasi
Pipa PVC Kelas D (Incl. Fitting & Accessories)
Lantai 1
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - 0.00% - - 0.00% - - -
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - -
Lantai 2
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 - - - 0.00% - - 0.00% - - -
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 - - - 0.00% - - 0.00% - - -
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres Ls 1.00 18,000,000.00 18,000,000.00 1.07 - - - 0.00% - - 0.00% - - -
A. JUMLAH BIAYA 1,683,636,346.77 100.00 298,097,093.60 17.71 100,914,398.00 5.99 399,011,491.60 23.70
B. PPN 10 % ( A X 10 % ) 168,363,634.68 29,809,709.36 10,091,439.80 39,901,149.16
C. JUMLAH (A + B ) 1,851,999,981.45 327,906,802.96 111,005,837.80 438,912,640.76
D. DIBULATKAN 1,851,999,000.00 327,906,000.00 111,005,000.00 438,912,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
thd pek.
100.00%
0.00%
0.00%
0.00%
0.00%
5.97%
0.00%
0.00%
0.00%
0.00%
62.23%
0.00%
40.81%
0.00%
0.00%
100.00%
0.00%
0.00%
0.00%
100.00%
0.00%
0.00%
0.00%
0.00%
26.17%
0.00%
0.00%
0.00%
82.52%
47.15%
44.80%
0.00%
48.64%
53.75%
thd pek.
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
85.71%
0.00%
0.00%
0.00%
100.00%
50.00%
0.00%
0.00%
0.00%
200.00%
50.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
0.00%
0.00%
thd pek.
0.00%
0.00%
0.00%
0.00%
100.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
2
3 - - 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
0 9 - - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
0 10 - - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - (62.00) 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
62 12 10 10 8 8 8 9 9 62.00 #REF! 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
14 - - 12 : 09 NOVEMBER 2015 s/d 15 NOVEMBER 2015
15 - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
41 18 4 5 4 6 7 7 8 41.00 - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
0 19 0 - - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
42 20 0 7 5 6 8 8 8 42.00 - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - -
22 - -
23 - -
24 - -
0 25 - -
0 26 - -
0 27 - -
28 - -
29 - -
30 - -
31 - -
0 32 - - -
0 33 - -
0 34 - -
0 35 - -
36 - -
0 37 - - -
0 38 - -
0 39 - -
0 40 - -
41 - -
42 - -
43 - -
44 - -
0 45 - 3.00
43 46 4 5 7 5 6 6 7 40.00 -
0 47 - -
0 48 - (62.00)
62 49 10 10 8 8 8 9 9 62.00 #REF!
52 - -
53 - -
54 - -
55 - -
56 - -
0 57 - -
0 58 - -
0 59 - #REF!
61 - -
0 62 - #REF!
18 64 8.00 10 18.00 -
250 65 22.00 44 26 28 40.00 42 48 250.00 #REF!
67 - -
68 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
69 - -
70 - -
71 - -
72 - -
0 73 - -
74 - -
0 75 - -
76 - -
0 77 - -
78 - -
0 79 - -
0 80 - -
0 81 - -
82 - -
0 83 - -
0 84 - -
0 85 - -
0 86 - -
0 87 - -
0 88 - -
0 89 - -
0 90 - -
91 - -
92 - -
93 - -
94 - -
0 95 - -
0 96 - -
0 97 - -
0 98 - -
0 99 - -
0 100 - -
0 101 - -
0 102 - -
0 103 - #REF!
105 - -
106 - -
107 - -
108 - -
0 109 - -
110 - -
111 - -
0 112 - -
0 113 - -
0 114 - -
0 115 - -
0 116 - -
117 - -
0 118 - -
4 119 2 2 4.00 (10.00)
20 120 10 10 20.00 -
0 121 - -
0 122 - -
123 - -
0 124 - -
0 125 - -
0 126 - -
0 127 - -
128 - -
129 - -
130 - -
0 131 - -
0 132 - -
0 133 - -
0 134 - -
0 135 - -
0 136 - -
137 - -
0 138 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
139 - -
140 - -
0 141 - -
0 142 - -
0 143 - -
0 144 - -
20 145 20 20.00 -
0 146 - -
147 - -
148 - -
149 - -
150 - -
151 - -
152 - -
153 - -
154 - -
155 - -
156 - -
157 - -
158 - -
159 - -
160 - -
161 - -
162 - -
163 - -
164 - -
165 - -
166 - -
167 - -
168 - -
169 - -
170 - -
171 - -
172 - -
173 - -
174 - -
175 - -
176 - -
177 - -
178 - -
179 - -
180 - -
181 - #REF!
183 - -
184 - -
- -
RINCIAN PROGRES BULANAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 1.00 500,000.00 0.03 100.00%
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 7.00 84,000.00 0.00 5.97%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 465.52 12,000.00 5,586,240.00 0.33 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
3 Pembongkaran Plafond Eksisting Toilet M² 117.30 12,000.00 1,407,600.00 0.08 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
4 Pembongkaran Lisplank Atap Eksisting M² 570.57 20,000.00 11,411,400.00 0.68 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 84.00 211,490.00 17,765,160.00 1.06 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
2 Plafond Calciboard (3,5mm) M² 84.00 73,279.00 6,155,436.00 0.37 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 1,062.92 40,752,352.80 2.42 100.00%
- Cat Tembok Interior M² 2,023.34 34,980.00 70,776,293.28 4.20 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Cat Plafond M² 1,406.75 34,980.00 49,208,115.00 2.92 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Cat list plafond gypsum & kaLsiboard (interior) M' 684.00 7,500.00 5,130,000.00 0.30 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
2 Lantai 2 -
- Cat Tembok Exterior Weather Shield M² 1364.72 38,340.00 52,323,364.80 3.11 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 1,364.72 52,323,364.80 3.11 100.00%
- Cat Tembok Interior M² 2,075.30 34,980.00 72,593,854.08 4.31 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Cat Plafond M² 1,410.93 34,980.00 49,354,331.40 2.93 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Cat list plafond gypsum & kaLsiboard (interior) M' 579.20 7,500.00 4,344,000.00 0.26 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
J. PEKERJAAN SANITASI
Roof Tank Air Bersih Type: Silinder Kapasitas: 5m3 Unit 2.00 10,084,500.00 20,169,000.00 1.20 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO bh 4.00 4,951,184.00 19,804,736.00 1.18 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Pemasangan Toilet Jongkok Setara TOTO bh 4.00 822,269.00 3,289,076.00 0.20 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 4.00 3,289,076.00 0.20 100.00%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 10.00 4,664,240.00 0.28 50.00%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO bh 6.00 4,951,184.00 29,707,104.00 1.76 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Pemasangan Toilet Jongkok Setara TOTO bh 2.00 822,269.00 1,644,538.00 0.10 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 4.00 3,289,076.00 0.20 200.00%
- Floor drain bh 20.00 466,424.00 9,328,480.00 0.55 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 10.00 4,664,240.00 0.28 50.00%
- Kran bh 16.00 285,180.00 4,562,880.00 0.27 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Washtavel Toto bh 4.00 1,688,029.00 6,752,116.00 0.40 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
Instalasi Pemipaan Site
- GIP dia. 50 (Dari Gedung Utama ke Sumur Pompa) m 150.00 165,000.00 24,750,000.00 1.47 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Gate valve dia 50mm bh 2.00 470,000.00 940,000.00 0.06 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Gate valve dia 40mm bh 2.00 320,000.00 640,000.00 0.04 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Gate valve dia 32mm bh 2.00 250,000.00 500,000.00 0.03 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
Instalasi Air Bersih
Lantai 1
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Dia .25 m 10.00 35,000.00 350,000.00 0.02 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 20.00 500,000.00 0.03 100.00%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
KONTRAK S/d Bulan Lalu Bulan Ini S/d Bulan Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME VOLUME thd pek. VOLUME thd pek. VOLUME thd pek.
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%)
Lantai 2
- PPR PN 10
- Dia .50 m 10.00 115,000.00 1,150,000.00 0.07 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Dia .40 m 10.00 70,000.00 700,000.00 0.04 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Dia .32 m 10.00 50,000.00 500,000.00 0.03 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Dia .25 m 20.00 35,000.00 700,000.00 0.04 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- Dia .20 m 20.00 25,000.00 500,000.00 0.03 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 20.00 500,000.00 0.03 100.00%
- Dia .15 m 75.00 25,000.00 1,875,000.00 0.11 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
Peralatan Katup-katup
- Gate Valve dia. 32 bh 2.00 350,000.00 700,000.00 0.04 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 250.00 105,000.00 26,250,000.00 1.56 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - - 0.00% - - - 0.00%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) m 70.00 105,000.00 7,350,000.00 0.44 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- CO, dia. 100 bh 4.00 250,000.00 1,000,000.00 0.06 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
Instalasi Air Bekas
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- dia. 80 m 160.00 65,000.00 10,400,000.00 0.62 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
Lantai 2
- dia. 80 m 30.00 65,000.00 1,950,000.00 0.12 #REF! #REF! #REF! #REF! - - - 0.00% - - - 0.00%
- dia. 50 m 40.00 32,000.00 1,280,000.00 0.08 #REF! #REF! #REF! #REF! - - - 0.00% - - - 0.00%
- CO, dia. 80 bh 4.00 175,000.00 700,000.00 0.04 #REF! #REF! #REF! #REF! - - - 0.00% - - - 0.00%
Instalasi Pipa Ventilasi
Pipa PVC Kelas D (Incl. Fitting & Accessories)
Lantai 1
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
Lantai 2
- dia. 50 m 15.00 17,000.00 255,000.00 0.02 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
vent cup
- dia. 50 bh 2.00 350,000.00 700,000.00 0.04 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres Ls 1.00 18,000,000.00 18,000,000.00 1.07 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - 0.00%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 #REF! #REF! #REF! #REF! 399,011,491.60 23.70
B. PPN 10 % ( A X 10 % ) 168,363,634.68 #REF! #REF! 39,901,149.16
C. JUMLAH (A + B ) 1,851,999,981.45 #REF! #REF! 438,912,640.76
D. DIBULATKAN 1,851,999,000.00 #REF! #REF! 438,912,000.00
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100.00%
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 133.08 12,000.00 1,596,960.00 0.09 7.00 84,000.00 0.00 5.26% - - - 0.00% 7.00 84,000.00 0.00 5.26%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 368.20 12,000.00 4,418,400.00 0.26 - - - 0.00% 78.00 936,000.00 0.06 21.18% 78.00 936,000.00 0.06 21.18%
3 Pembongkaran Plafond Eksisting Toilet M² 118.08 12,000.00 1,416,960.00 0.08 - - - 0.00% 32.00 384,000.00 0.02 27.10% 32.00 384,000.00 0.02 27.10%
4 Pembongkaran Lisplank Atap Eksisting M² 820.00 20,000.00 16,400,000.00 0.97 - - - 0.00% 90.00 1,800,000.00 0.11 10.98% 90.00 1,800,000.00 0.11 10.98%
5 Pembongkaran Plafond Eksisting Drop off utama M² 88.00 12,000.00 1,056,000.00 0.06 - - - 0.00% 88.00 1,056,000.00 0.06 100.00% 88.00 1,056,000.00 0.06 100.00%
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 206.08 211,490.00 43,583,859.20 2.59 - - - 0.00% 120.00 25,378,800.00 1.51 58.23% 120.00 25,378,800.00 1.51 58.23%
2 Plafond Calciboard (3,5mm) M² 206.08 73,279.00 15,101,336.32 0.90 - - - 0.00% 120.00 8,793,480.00 0.52 58.23% 120.00 8,793,480.00 0.52 58.23%
3 Cat Plafond M² 206.08 34,979.00 7,208,472.32 0.43 - - - 0.00% - - - 0.00% - - - 0.00%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42 100.00%
2 Lantai 2 -
- Cat Tembok Exterior Weather Shield M² 1,364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11 100.00%
3 Cat Kusen & Daun Pintu Jendela (Exterior) M² 189.25 47,230.00 8,938,277.50 0.53 - - - - - - - 0.00% - - - 0.00%
J. PEKERJAAN SANITASI
1 Tandon Air Bersih Type: Silinder Kapasitas: 2.200 Liter Unit 2.00 4,962,459.43 9,924,918.86 0.59 - - - 0.00% - - - 0.00% - - - 0.00%
2 Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO Buah 1.00 4,951,184.00 4,951,184.00 0.29 - - - 0.00% - - - 0.00% - - - 0.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 7.00 822,269.00 5,755,883.00 0.34 4.00 3,289,076.00 0.20 57.14% - - - 0.00% 4.00 3,289,076.00 0.20 57.14%
- Floor drain Buah 10.00 466,424.00 4,664,240.00 0.28 10.00 4,664,240.00 0.28 100.00% - - - 0.00% 10.00 4,664,240.00 0.28 100.00%
- Kran Buah 14.00 285,180.00 3,992,520.00 0.24 - - - 0.00% 8.00 2,281,440.00 0.14 57.14% 8.00 2,281,440.00 0.14 57.14%
- Washtavel Toto Buah 2.00 1,688,029.00 3,376,058.00 0.20 - - - 0.00% 1.00 1,688,029.00 0.10 50.00% 1.00 1,688,029.00 0.10 50.00%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO Buah 3.00 4,951,184.00 14,853,552.00 0.88 - - - 0.00% - - - 0.00% - - - 0.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 5.00 822,269.00 4,111,345.00 0.24 4.00 3,289,076.00 0.20 80.00% - - - 0.00% 4.00 3,289,076.00 0.20 80.00%
- Floor drain Buah 12.00 466,424.00 5,597,088.00 0.33 10.00 4,664,240.00 0.28 83.33% - - - 0.00% 10.00 4,664,240.00 0.28 83.33%
- Kran Buah 18.00 285,180.00 5,133,240.00 0.30 - - - 0.00% - - - 0.00% - - - 0.00%
- Washtavel Toto Buah 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0.00%
2 Instalasi Air Bersih
Lantai 1
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .32 M' 80.00 50,000.00 4,000,000.00 0.24 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .20 M' 100.00 25,000.00 2,500,000.00 0.15 20.00 500,000.00 0.03 20.00% - - - 0.00% 20.00 500,000.00 0.03 20.00%
Lantai 2
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .20 M' 120.00 25,000.00 3,000,000.00 0.18 20.00 500,000.00 0.03 16.67% - - - 0.00% 20.00 500,000.00 0.03 16.67%
3 Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 70.00 105,000.00 7,350,000.00 0.44 - - - 0.00% - - - 0.00% - - - 0.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - - 0.00% - - - 0.00%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 130.00 105,000.00 13,650,000.00 0.81 - - - 0.00% - - - 0.00% - - - 0.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% - - - 0.00% - - - 0.00%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME VOLUME thd pek. VOLUME thd pek. VOLUME thd pek.
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%)
4 Instalasi Air Bekas
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- dia. 80 M' 30.00 65,000.00 1,950,000.00 0.12 - - - 0.00% - - - 0.00% - - - 0.00%
- dia. 50 M' 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- CO, dia. 80 Buah 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0.00%
Lantai 2
- dia. 80 M' 130.00 65,000.00 8,450,000.00 0.50 - - - 0.00% - - - 0.00% - - - 0.00%
- dia. 50 M' 40.00 32,000.00 1,280,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- CO, dia. 80 Buah 4.00 175,000.00 700,000.00 0.04 - - - 0.00% - - - 0.00% - - - 0.00%
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres (Halaman Depan) Ls 1.00 18,000,000.00 18,000,000.00 1.07 - - - 0.00% - - - 0.00% - - - 0.00%
2 Perbaikan Papan Nama Polres (Gedung Utama) Ls 1.00 36,000,000.00 36,000,000.00 2.14 - - - 0.00% - - - 0.00% - - - 0.00%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 399,011,491.60 23.70 258,372,680.78 15.35 657,384,172.38 39.05
B. PPN 10 % ( A X 10 % ) 168,363,634.68 39,901,149.16 25,837,268.08 65,738,417.24
C. JUMLAH (A + B ) 1,851,999,981.45 438,912,640.76 284,209,948.85 723,122,589.61
D. DIBULATKAN 1,851,999,000.00 438,912,000.00 284,209,000.00 723,122,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
:
1 Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
2
3 Err:522 Err:522 Err:522 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
0 9 - - - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
78 10 8.00 8 7 8.00 8 7 7 6 6 6 7.00 78.00 - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
32 11 32 - 32.00 - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
90 12 18 18 18 19 17 - 90.00 - 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
88 38 50 - 88.00 -
- - -
15 - - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
0 18 - - - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
6 19 3 3 - 6.00 - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
0 20 - - - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - - -
22 - - -
23 - - -
24 - - -
120 25 32 38 50 - 120.00 -
120 26 32 38 50 - 120.00 -
0 - - -
27 - - -
28 - - -
29 - - -
30 - - -
31 - - -
0 32 - - -
36 - - -
0 37 - - -
0 - - -
41 - - -
42 - - -
43 - - -
44 - - -
58 46 4 5 6 5 6 5 6 6 5 5 5.00 58.00 -
90 49 18 18 18 19 17.00 90.00 -
90 18 18 18 19 17.00 90.00 -
13 13 - 13.00 -
52 - - -
53 - - -
54 - - -
55 - - -
56 - - -
18.9896 57 18.99 - 18.99 -
5.644 58 5.644 - 5.64 -
0 59 - - -
0 - - -
61 - - -
0 62 - - -
54 64 26 28 - 54.00 -
8 65 8 - 8.00 -
116 16 17 15 18.00 16 17 17.00 116.00 -
0 67 - - -
- - -
1 Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
68 - - -
1 Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
69 - - -
70 - - -
71 - - -
72 - - -
6.75 73 3 2 1.75 6.75 -
74 - - -
0 75 - - -
78 - - -
0 79 - - -
0 80 - - -
0 81 - - -
82 - - -
0 83 - - -
0 84 - - -
0 85 - - -
0 86 - - -
0 87 - - -
0 88 - - -
0 90 - - -
91 - - -
92 - - -
93 - - -
94 - - -
0 95 - - -
0 97 - - -
0 98 - - -
0 99 - - -
0 101 - - -
2 102 2.00 2.00 -
0 103 - - -
105 - - -
106 - - -
107 - - -
108 - - -
0 109 - - -
110 - - -
111 - - -
0 112 - - -
0 113 - - -
0 114 - - -
8 115 8 - 8.00 -
1 116 1 - 1.00 -
117 - - -
0 118 - - -
0 119 - - -
0 120 - - -
0 121 - - -
0 122 - - -
128 - - -
129 - - -
130 - - -
0 133 - - -
0 134 - - -
0 135 - - -
139 - - -
140 - - -
0 144 - - -
0 145 - - -
149 - - -
150 - - -
151 - - -
0 152 - - -
0 153 - - -
154 - - -
0 155 - - -
0 156 - - -
1 Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
157 - - -
158 - - -
159 - - -
0 160 - - -
0 161 - - -
0 162 - - -
163 - - -
0 164 - - -
0 165 - - -
0 166 - - -
177 - - -
178 - - -
179 - - -
180 - - -
0 181 - - -
0 - - -
183 - - -
184 - - -
- - -
RINCIAN PROGRES MINGGUAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100.00%
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 133.08 12,000.00 1,596,960.00 0.09 7.00 84,000.00 0.00 5.26% 28.00 336,000.00 0.02 21.04% 35.00 420,000.00 0.02 26.30%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 368.20 12,000.00 4,418,400.00 0.26 78.00 936,000.00 0.06 21.18% 62.00 744,000.00 0.04 16.84% 140.00 1,680,000.00 0.10 38.02%
3 Pembongkaran Plafond Eksisting Toilet M² 118.08 12,000.00 1,416,960.00 0.08 32.00 384,000.00 0.02 27.10% 36.00 432,000.00 0.03 30.49% 68.00 816,000.00 0.05 57.59%
4 Pembongkaran Lisplank Atap Eksisting M² 820.00 20,000.00 16,400,000.00 0.97 90.00 1,800,000.00 0.11 10.98% 94.00 1,880,000.00 0.11 11.46% 184.00 3,680,000.00 0.22 22.44%
5 Pembongkaran Plafond Eksisting Drop off utama M² 88.00 12,000.00 1,056,000.00 0.06 88.00 1,056,000.00 0.06 100.00% - - - 0.00% 88.00 1,056,000.00 0.06 100.00%
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 206.08 211,490.00 43,583,859.20 2.59 120.00 25,378,800.00 1.51 58.23% 36.00 7,613,640.00 0.45 17.47% 156.00 32,992,440.00 1.96 75.70%
2 Plafond Calciboard (3,5mm) M² 206.08 73,279.00 15,101,336.32 0.90 120.00 8,793,480.00 0.52 58.23% 36.00 2,638,044.00 0.16 17.47% 156.00 11,431,524.00 0.68 75.70%
3 Cat Plafond M² 206.08 34,979.00 7,208,472.32 0.43 - - - 0.00% - - - 0.00% - - - 0.00%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42 100.00%
2 Lantai 2 -
- Cat Tembok Exterior Weather Shield M² 1,364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11 100.00%
3 Cat Kusen & Daun Pintu Jendela (Exterior) M² 189.25 47,230.00 8,938,277.50 0.53 - - - - - - - 0.00% - - - 0.00%
J. PEKERJAAN SANITASI
1 Tandon Air Bersih Type: Silinder Kapasitas: 2.200 Liter Unit 2.00 4,962,459.43 9,924,918.86 0.59 - - - 0.00% - - - 0.00% - - - 0.00%
2 Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO Buah 1.00 4,951,184.00 4,951,184.00 0.29 - - - 0.00% - - - 0.00% - - - 0.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 7.00 822,269.00 5,755,883.00 0.34 4.00 3,289,076.00 0.20 57.14% - - - 0.00% 4.00 3,289,076.00 0.20 57.14%
- Floor drain Buah 10.00 466,424.00 4,664,240.00 0.28 10.00 4,664,240.00 0.28 100.00% - - - 0.00% 10.00 4,664,240.00 0.28 100.00%
- Kran Buah 14.00 285,180.00 3,992,520.00 0.24 8.00 2,281,440.00 0.14 57.14% - - - 0.00% 8.00 2,281,440.00 0.14 57.14%
- Washtavel Toto Buah 2.00 1,688,029.00 3,376,058.00 0.20 1.00 1,688,029.00 0.10 50.00% - - - 0.00% 1.00 1,688,029.00 0.10 50.00%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO Buah 3.00 4,951,184.00 14,853,552.00 0.88 - - - 0.00% - - - 0.00% - - - 0.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 5.00 822,269.00 4,111,345.00 0.24 4.00 3,289,076.00 0.20 80.00% - - - 0.00% 4.00 3,289,076.00 0.20 80.00%
- Floor drain Buah 12.00 466,424.00 5,597,088.00 0.33 10.00 4,664,240.00 0.28 83.33% - - - 0.00% 10.00 4,664,240.00 0.28 83.33%
- Kran Buah 18.00 285,180.00 5,133,240.00 0.30 - - - 0.00% - - - 0.00% - - - 0.00%
- Washtavel Toto Buah 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0.00%
2 Instalasi Air Bersih
Lantai 1
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .32 M' 80.00 50,000.00 4,000,000.00 0.24 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .20 M' 100.00 25,000.00 2,500,000.00 0.15 20.00 500,000.00 0.03 20.00% - - - 0.00% 20.00 500,000.00 0.03 20.00%
Lantai 2
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .20 M' 120.00 25,000.00 3,000,000.00 0.18 20.00 500,000.00 0.03 16.67% - - - 0.00% 20.00 500,000.00 0.03 16.67%
3 Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 70.00 105,000.00 7,350,000.00 0.44 - - - 0.00% 35.00 3,675,000.00 0.22 50.00% 35.00 3,675,000.00 0.22 50.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% 2.00 500,000.00 0.03 50.00% 2.00 500,000.00 0.03 50.00%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 130.00 105,000.00 13,650,000.00 0.81 - - - 0.00% 65.00 6,825,000.00 0.41 50.00% 65.00 6,825,000.00 0.41 50.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% 2.00 500,000.00 0.03 50.00% 2.00 500,000.00 0.03 50.00%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME ( Rp. ) ( Rp. ) (%) VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek.
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres (Halaman Depan) Ls 1.00 18,000,000.00 18,000,000.00 1.07 - - - 0.00% 1.00 18,000,000.00 1.07 100.00% 1.00 18,000,000.00 1.07 100.00%
2 Perbaikan Papan Nama Polres (Gedung Utama) Ls 1.00 36,000,000.00 36,000,000.00 2.14 - - - 0.00% - - - 0.00% - - - 0.00%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 657,384,172.38 39.05 216,948,316.36 12.89 874,332,488.73 51.93
B. PPN 10 % ( A X 10 % ) 168,363,634.68 65,738,417.24 21,694,831.64 87,433,248.87
C. JUMLAH (A + B ) 1,851,999,981.45 723,122,589.61 238,643,147.99 961,765,737.61
D. DIBULATKAN 1,851,999,000.00 723,122,000.00 238,643,000.00 961,765,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
:
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
2
3 - - 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
28 9 8.00 9 11 - 28.00 - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
62 10 10.00 12 8 9.00 12 11 - 62.00 - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
36 11 16 20 - 36.00 - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
94 12 26 28 30 10.00 94.00 #REF! 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
0 -
-
15 - - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
0 18 - - - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
0 19 - - - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
72 20 14 12 13 10 12 11.00 72.00 - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - - -
22 - - -
23 - - -
24 - - -
36 25 16 20 - 36.00 -
36 26 16 20 - 36.00 -
0 -
27 - - -
28 - - -
29 - - -
30 - - -
31 - - -
0 32 - - #REF!
36 - - -
0 37 - - #REF!
0 -
41 - - -
42 - - -
43 - - -
44 - - #REF!
62 46 8 9 8 7 9 12 9.00 62.00 #REF!
94 49 26 28 30 10.00 94.00 #REF!
94 26 28 30 10.00
0 -
52 - - -
53 - - -
54 - - -
55 - - -
56 - - -
0 57 - - -
0 58 - - -
186 59 32 36 34 30 28 26 - 186.00 #REF!
0 -
61 - - -
0 62 - - #REF!
42.864 64 12.00 14 16.864 - 42.86 -
8 65 8 - 8.00 #REF!
122 16.00 16 18 19 20 16 17.00
0 67 - - -
-
68 - - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
69 - - -
70 - - -
71 - - -
72 - - -
0 73 - - -
74 - - -
0.225 75 0.225 - 0.23 #REF!
78 - - -
0.45 79 0.45 - 0.45 -
23.7353 80 23.73525 - 23.74 -
1.2 81 1.2 - 1.20 -
82 - - -
0.27 83 0.27 - 0.27 -
23.0571 84 23.0571 - 23.06 -
1.2 85 1.2 - 1.20 -
2.7 86 2.7 - 2.70 -
1 87 1 - 1.00 -
2 88 2 - 2.00 #REF!
1 90 1 - 1.00 -
91 - - -
92 - - -
93 - - -
94 - - -
0 95 - - #REF!
0 97 - - -
0 98 - - -
0 99 - - #REF!
0 101 - - -
0 102 - - -
0 103 - - #REF!
105 - - -
106 - - -
107 - - -
108 - - -
0 109 - - -
110 - - -
111 - - -
0 112 - - -
0 113 - - -
0 114 - - -
0 115 - - -
0 116 - - -
117 - - -
0 118 - - -
0 119 - - -
0 120 - - -
0 121 - - -
0 122 - - #REF!
128 - - -
129 - - -
130 - - #REF!
0 133 - - -
0 134 - - -
0 135 - - #REF!
139 - - -
140 - - #REF!
0 144 - - -
0 145 - - #REF!
149 - - -
150 - - -
151 - - -
35 152 35 - 35.00 -
2 153 2 - 2.00 -
154 - - -
65 155 65 - 65.00 -
2 156 2 - 2.00 -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
157 - - -
158 - - -
159 - - -
15 160 15 - 15.00 -
20 161 20 - 20.00 -
2 162 2 - 2.00 -
163 - - -
65 164 65 - 65.00 -
20 165 20 - 20.00 -
2 166 2 - 2.00 #REF!
177 - - -
178 - - -
179 - - -
180 - - -
1 181 1.00 1.00 #REF!
0 -
183 - - -
184 - - -
- -
RINCIAN PROGRES MINGGUAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100.00%
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 133.08 12,000.00 1,596,960.00 0.09 35.00 420,000.00 0.02 26.30% 32.00 384,000.00 0.02 24.05% 67.00 804,000.00 0.05 50.35%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 368.20 12,000.00 4,418,400.00 0.26 140.00 1,680,000.00 0.10 38.02% - - - 0.00% 140.00 1,680,000.00 0.10 38.02%
3 Pembongkaran Plafond Eksisting Toilet M² 118.08 12,000.00 1,416,960.00 0.08 68.00 816,000.00 0.05 57.59% - - - 0.00% 68.00 816,000.00 0.05 57.59%
4 Pembongkaran Lisplank Atap Eksisting M² 820.00 20,000.00 16,400,000.00 0.97 184.00 3,680,000.00 0.22 22.44% 98.00 1,960,000.00 0.12 11.95% 282.00 5,640,000.00 0.33 34.39%
5 Pembongkaran Plafond Eksisting Drop off utama M² 88.00 12,000.00 1,056,000.00 0.06 88.00 1,056,000.00 0.06 100.00% - - - 0.00% 88.00 1,056,000.00 0.06 100.00%
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 206.08 211,490.00 43,583,859.20 2.59 156.00 32,992,440.00 1.96 75.70% - - - 0.00% 156.00 32,992,440.00 1.96 75.70%
2 Plafond Calciboard (3,5mm) M² 206.08 73,279.00 15,101,336.32 0.90 156.00 11,431,524.00 0.68 75.70% - - - 0.00% 156.00 11,431,524.00 0.68 75.70%
3 Cat Plafond M² 206.08 34,979.00 7,208,472.32 0.43 - - - 0.00% - - - 0.00% - - - 0.00%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42 100.00%
2 Lantai 2
- Cat Tembok Exterior Weather Shield M² 1,364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11 100.00%
3 Cat Kusen & Daun Pintu Jendela (Exterior) M² 189.25 47,230.00 8,938,277.50 0.53 - - - - - - - 0.00% - - - 0.00%
J. PEKERJAAN SANITASI
1 Tandon Air Bersih Type: Silinder Kapasitas: 2.200 Liter Unit 2.00 4,962,459.43 9,924,918.86 0.59 - - - 0.00% - - - 0.00% - - - 0.00%
2 Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO Buah 1.00 4,951,184.00 4,951,184.00 0.29 - - - 0.00% - - - 0.00% - - - 0.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 7.00 822,269.00 5,755,883.00 0.34 4.00 3,289,076.00 0.20 57.14% - - - 0.00% 4.00 3,289,076.00 0.20 57.14%
- Floor drain Buah 10.00 466,424.00 4,664,240.00 0.28 10.00 4,664,240.00 0.28 100.00% - - - 0.00% 10.00 4,664,240.00 0.28 100.00%
- Kran Buah 14.00 285,180.00 3,992,520.00 0.24 8.00 2,281,440.00 0.14 57.14% - - - 0.00% 8.00 2,281,440.00 0.14 57.14%
- Washtavel Toto Buah 2.00 1,688,029.00 3,376,058.00 0.20 1.00 1,688,029.00 0.10 50.00% - - - 0.00% 1.00 1,688,029.00 0.10 50.00%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO Buah 3.00 4,951,184.00 14,853,552.00 0.88 - - - 0.00% - - - 0.00% - - - 0.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 5.00 822,269.00 4,111,345.00 0.24 4.00 3,289,076.00 0.20 80.00% - - - 0.00% 4.00 3,289,076.00 0.20 80.00%
- Floor drain Buah 12.00 466,424.00 5,597,088.00 0.33 10.00 4,664,240.00 0.28 83.33% - - - 0.00% 10.00 4,664,240.00 0.28 83.33%
- Kran Buah 18.00 285,180.00 5,133,240.00 0.30 - - - 0.00% - - - 0.00% - - - 0.00%
- Washtavel Toto Buah 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0.00%
2 Instalasi Air Bersih
Lantai 1
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .32 M' 80.00 50,000.00 4,000,000.00 0.24 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .20 M' 100.00 25,000.00 2,500,000.00 0.15 20.00 500,000.00 0.03 20.00% 30.00 750,000.00 0.04 30.00% 50.00 1,250,000.00 0.07 50.00%
Lantai 2
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .20 M' 120.00 25,000.00 3,000,000.00 0.18 20.00 500,000.00 0.03 16.67% 40.00 1,000,000.00 0.06 33.33% 60.00 1,500,000.00 0.09 50.00%
3 Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 70.00 105,000.00 7,350,000.00 0.44 35.00 3,675,000.00 0.22 50.00% 35.00 3,675,000.00 0.22 50.00% 70.00 7,350,000.00 0.44 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 2.00 500,000.00 0.03 50.00% 2.00 500,000.00 0.03 50.00% 4.00 1,000,000.00 0.06 100.00%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 130.00 105,000.00 13,650,000.00 0.81 65.00 6,825,000.00 0.41 50.00% 65.00 6,825,000.00 0.41 50.00% 130.00 13,650,000.00 0.81 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 2.00 500,000.00 0.03 50.00% 2.00 500,000.00 0.03 50.00% 4.00 1,000,000.00 0.06 100.00%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME ( Rp. ) ( Rp. ) (%) VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek.
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres (Halaman Depan) Ls 1.00 18,000,000.00 18,000,000.00 1.07 1.00 18,000,000.00 1.07 100.00% - - - 0.00% 1.00 18,000,000.00 1.07 100.00%
2 Perbaikan Papan Nama Polres (Gedung Utama) Ls 1.00 36,000,000.00 36,000,000.00 2.14 - - - 0.00% 1.00 36,000,000.00 2.14 100.00% 1.00 36,000,000.00 2.14 100.00%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 874,332,488.73 51.93 226,567,564.00 13.46 1,100,900,052.73 65.39
B. PPN 10 % ( A X 10 % ) 168,363,634.68 87,433,248.87 22,656,756.40 110,090,005.27
C. JUMLAH (A + B ) 1,851,999,981.45 961,765,737.61 249,224,320.40 1,210,990,058.01
D. DIBULATKAN 1,851,999,000.00 961,765,000.00 249,224,000.00 1,210,990,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
:
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
2
3 - - 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
32 9 12.00 9 11 - 32.00 - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
0 10 - - - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - - - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
98 12 28 30 32 8.00 98.00 - 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
0 - - -
- - -
15 - - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
22 18 8 8 6 - 22.00 - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
0 19 - - - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
46 20 12 14 10 10 - 46.00 - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - - -
22 - - -
23 - - -
24 - - -
0 25 - - -
0 26 - - -
0 - - -
27 - - -
28 - - -
29 - - -
30 - - -
31 - - -
0 32 - - -
36 - - -
0 37 - - -
0 - - -
41 - - -
42 - - -
43 - - -
44 - - -
62 46 8 10 9 8 7 12 8.00 62.00 -
98 49 28 30 32 8.00 98.00 -
98 28 30 32 8.00 98.00 -
0 - - -
52 - - -
53 - - -
54 - - -
55 - - -
56 - - -
0 57 - - -
0 58 - - -
184 59 32 28 30 26 28 20 20.00 184.00 -
0 - - -
61 - - -
0 62 - - -
0 64 - - -
8 65 8.00 - 8.00 -
128 22 20 24 20 22 20.00 128.00 -
0 67 - - -
- - -
68 - - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
69 - - -
70 - - -
71 - - -
72 - - -
6.75 73 2 2.25 2.5 - 6.75 -
74 - - -
0 75 - - -
78 - - -
0 79 - - -
0 80 - - -
0 81 - - -
82 - - -
0 83 - - -
0 84 - - -
0 85 - - -
0 86 - - -
0 87 - - -
0 88 - - -
0 90 - - -
91 - - -
92 - - -
93 - - -
94 - - -
32 95 12 14 6.00 32.00 -
1 97 0 1.00 1.00 -
1 98 1 - 1.00 -
32 99 12 14 6.00 32.00 -
0 101 - - -
0 102 - - -
0 103 - - -
105 - - -
106 - - -
107 - - -
108 - - -
0 109 - - -
110 - - -
111 - - -
0 112 - - -
0 113 - - -
0 114 - - -
0 115 - - -
0 116 - - -
117 - - -
0 118 - - -
0 119 - - -
0 120 - - -
0 121 - - -
0 122 - - -
128 - - -
129 - - -
130 - - -
0 133 - - -
0 134 - - -
30 135 12 18 - 30.00 -
139 - - -
140 - - -
0 144 - - -
40 145 14 12 14 - 40.00 -
149 - - -
150 - - -
151 - - -
35 152 35 - 35.00 -
2 153 2 - 2.00 -
154 - - -
65 155 65 - 65.00 -
2 156 2 - 2.00 -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
157 - - -
158 - - -
159 - - -
15 160 15 - 15.00 -
20 161 20 - 20.00 -
2 162 2 - 2.00 -
163 - - -
40 164 40 - 40.00 -
12 165 12 - 12.00 -
1 166 1 - 1.00 -
177 - - -
178 - - -
179 - - -
180 - - -
0 181 - - -
1 1.00 1.00 -
183 - - -
184 - -
- -
RINCIAN PROGRES MINGGUAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100.00%
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 133.08 12,000.00 1,596,960.00 0.09 67.00 804,000.00 0.05 50.35% - - - 0.00% 67.00 804,000.00 0.05 50.35%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 368.20 12,000.00 4,418,400.00 0.26 140.00 1,680,000.00 0.10 38.02% - - - 0.00% 140.00 1,680,000.00 0.10 38.02%
3 Pembongkaran Plafond Eksisting Toilet M² 118.08 12,000.00 1,416,960.00 0.08 68.00 816,000.00 0.05 57.59% - - - 0.00% 68.00 816,000.00 0.05 57.59%
4 Pembongkaran Lisplank Atap Eksisting M² 820.00 20,000.00 16,400,000.00 0.97 282.00 5,640,000.00 0.33 34.39% 94.00 1,880,000.00 0.11 11.46% 376.00 7,520,000.00 0.45 45.85%
5 Pembongkaran Plafond Eksisting Drop off utama M² 88.00 12,000.00 1,056,000.00 0.06 88.00 1,056,000.00 0.06 100.00% - - - 0.00% 88.00 1,056,000.00 0.06 100.00%
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 206.08 211,490.00 43,583,859.20 2.59 156.00 32,992,440.00 1.96 75.70% - - - 0.00% 156.00 32,992,440.00 1.96 75.70%
2 Plafond Calciboard (3,5mm) M² 206.08 73,279.00 15,101,336.32 0.90 156.00 11,431,524.00 0.68 75.70% - - - 0.00% 156.00 11,431,524.00 0.68 75.70%
3 Cat Plafond M² 206.08 34,979.00 7,208,472.32 0.43 - - - 0.00% - - - 0.00% - - - 0.00%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42 100.00%
2 Lantai 2
- Cat Tembok Exterior Weather Shield M² 1,364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11 100.00%
3 Cat Kusen & Daun Pintu Jendela (Exterior) M² 189.25 47,230.00 8,938,277.50 0.53 - - - - - - - 0.00% - - - 0.00%
J. PEKERJAAN SANITASI
1 Tandon Air Bersih Type: Silinder Kapasitas: 2.200 Liter Unit 2.00 4,962,459.43 9,924,918.86 0.59 - - - 0.00% - - - 0.00% - - - 0.00%
2 Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO Buah 1.00 4,951,184.00 4,951,184.00 0.29 - - - 0.00% 1.00 4,951,184.00 0.29 100.00% 1.00 4,951,184.00 0.29 100.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 7.00 822,269.00 5,755,883.00 0.34 4.00 3,289,076.00 0.20 57.14% 3.00 2,466,807.00 0.15 42.86% 7.00 5,755,883.00 0.34 100.00%
- Floor drain Buah 10.00 466,424.00 4,664,240.00 0.28 10.00 4,664,240.00 0.28 100.00% - - - 0.00% 10.00 4,664,240.00 0.28 100.00%
- Kran Buah 14.00 285,180.00 3,992,520.00 0.24 8.00 2,281,440.00 0.14 57.14% - - - 0.00% 8.00 2,281,440.00 0.14 57.14%
- Washtavel Toto Buah 2.00 1,688,029.00 3,376,058.00 0.20 1.00 1,688,029.00 0.10 50.00% - - - 0.00% 1.00 1,688,029.00 0.10 50.00%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO Buah 3.00 4,951,184.00 14,853,552.00 0.88 - - - 0.00% - - - 0.00% - - - 0.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 5.00 822,269.00 4,111,345.00 0.24 4.00 3,289,076.00 0.20 80.00% - - - 0.00% 4.00 3,289,076.00 0.20 80.00%
- Floor drain Buah 12.00 466,424.00 5,597,088.00 0.33 10.00 4,664,240.00 0.28 83.33% 2.00 932,848.00 0.06 16.67% 12.00 5,597,088.00 0.33 100.00%
- Kran Buah 18.00 285,180.00 5,133,240.00 0.30 - - - 0.00% - - - 0.00% - - - 0.00%
- Washtavel Toto Buah 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0.00%
2 Instalasi Air Bersih
Lantai 1
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .32 M' 80.00 50,000.00 4,000,000.00 0.24 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .20 M' 100.00 25,000.00 2,500,000.00 0.15 50.00 1,250,000.00 0.07 50.00% - - - 0.00% 50.00 1,250,000.00 0.07 50.00%
Lantai 2
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .20 M' 120.00 25,000.00 3,000,000.00 0.18 60.00 1,500,000.00 0.09 50.00% - - - 0.00% 60.00 1,500,000.00 0.09 50.00%
3 Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 70.00 105,000.00 7,350,000.00 0.44 70.00 7,350,000.00 0.44 100.00% - - - 0.00% 70.00 7,350,000.00 0.44 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 130.00 105,000.00 13,650,000.00 0.81 130.00 13,650,000.00 0.81 100.00% - - - 0.00% 130.00 13,650,000.00 0.81 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME ( Rp. ) ( Rp. ) (%) VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek.
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres (Halaman Depan) Ls 1.00 18,000,000.00 18,000,000.00 1.07 1.00 18,000,000.00 1.07 100.00% - - - 0.00% 1.00 18,000,000.00 1.07 100.00%
2 Perbaikan Papan Nama Polres (Gedung Utama) Ls 1.00 36,000,000.00 36,000,000.00 2.14 1.00 36,000,000.00 2.14 100.00% - - - 0.00% 1.00 36,000,000.00 2.14 100.00%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 1,100,900,052.73 65.39 157,296,774.75 9.34 1,258,196,827.48 74.73
B. PPN 10 % ( A X 10 % ) 168,363,634.68 110,090,005.27 15,729,677.47 125,819,682.75
C. JUMLAH (A + B ) 1,851,999,981.45 1,210,990,058.01 173,026,452.22 1,384,016,510.23
D. DIBULATKAN 1,851,999,000.00 1,210,990,000.00 173,026,000.00 1,384,016,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
:
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
2
3 - - 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
0 9 - - - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
0 10 - - - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - - - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
94 12 32 34 28 - 94.00 - 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
0 - - -
- - -
15 - - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
16 18 6 4 6.00 16.00 - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
4 19 2 2 - 4.00 - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
32 20 9 11 12 - 32.00 - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - - -
22 - - -
23 - - -
24 - - -
0 25 - - -
0 26 - - -
0 - - -
27 - - -
28 - - -
29 - - -
30 - - -
31 - - -
0 32 - - -
36 - - -
0 37 - - -
0 - - -
41 - - -
42 - - -
43 - - -
44 - - -
48 46 8 10 6 8 7 9.00 48.00 -
94 49 32 34 28.00 94.00 -
94 32 34 28.00 94.00 -
0 - - -
52 - - -
53 - - -
54 - - -
55 - - -
56 - - -
0 57 - - -
0 58 - - -
130.4 59 22 24 20 23 22 19.40 130.40 -
0 - - -
61 - - -
0 62 - - -
0 64 - - -
6.756 65 6.76 - 6.76 -
98.8 20 18 20 21 19.80 98.80 -
0 67 - - -
- - -
68 - - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
69 - - -
70 - - -
71 - - -
72 - - -
0 73 - - -
74 - - -
0.225 75 0.225 - 0.23 -
78 - - -
0.45 79 0.45 - 0.45 -
23.7353 80 23.73525 - 23.74 -
1.2 81 1.2 - 1.20 -
82 - - -
0.27 83 0.27 - 0.27 -
23.0571 84 23.0571 - 23.06 -
1.2 85 1.2 - 1.20 -
2.7 86 2.7 - 2.70 -
1 87 1 - 1.00 -
2 88 2 - 2.00 -
1 90 1 - 1.00 -
91 - - -
92 - - -
93 - - -
94 - - -
0 95 - - -
0 97 - - -
0 98 - - -
0 99 - - -
0 101 - - -
0 102 - - -
2 103 2 - 2.00 -
105 - - -
106 - - -
107 - - -
108 - - -
0 109 - - -
110 - - -
111 - - -
1 112 1 - 1.00 -
3 113 3 - 3.00 -
0 114 - - -
0 115 - - -
0 116 - - -
117 - - -
0 118 - - -
0 119 - - -
2 120 2 0 - 2.00 -
0 121 - - -
0 122 - - -
128 - - -
129 - - -
130 - - -
0 133 - - -
0 134 - - -
0 135 - - -
139 - - -
140 - - -
0 144 - - -
0 145 - - -
149 - - -
150 - - -
151 - - -
0 152 - - -
0 153 - - -
154 - - -
0 155 - - -
0 156 - - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
157 - - -
158 - - -
159 - - -
0 160 - - -
0 161 - - -
0 162 - - -
163 - - -
0 164 - - -
0 165 - - -
0 166 - - -
177 - - -
178 - - -
179 - - -
180 - - -
0 181 - - -
0 - - -
183 - - -
184 - - -
- -
RINCIAN PROGRES BULANAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100.00%
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 133.08 12,000.00 1,596,960.00 0.09 7.00 84,000.00 0.00 5.26% 60.00 720,000.00 0.04 45.09% 67.00 804,000.00 0.05 50.35%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 368.20 12,000.00 4,418,400.00 0.26 - - - 0.00% 140.00 1,680,000.00 0.10 38.02% 140.00 1,680,000.00 0.10 38.02%
3 Pembongkaran Plafond Eksisting Toilet M² 118.08 12,000.00 1,416,960.00 0.08 - - - 0.00% 68.00 816,000.00 0.05 57.59% 68.00 816,000.00 0.05 57.59%
4 Pembongkaran Lisplank Atap Eksisting M² 820.00 20,000.00 16,400,000.00 0.97 - - - 0.00% 376.00 7,520,000.00 0.45 45.85% 376.00 7,520,000.00 0.45 45.85%
5 Pembongkaran Plafond Eksisting Drop off utama M² 88.00 12,000.00 1,056,000.00 0.06 - - - 0.00% 88.00 1,056,000.00 0.06 100.00% 88.00 1,056,000.00 0.06 100.00%
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 206.08 211,490.00 43,583,859.20 2.59 - - - 0.00% 156.00 32,992,440.00 1.96 75.70% 156.00 32,992,440.00 1.96 75.70%
2 Plafond Calciboard (3,5mm) M² 206.08 73,279.00 15,101,336.32 0.90 - - - 0.00% 156.00 11,431,524.00 0.68 75.70% 156.00 11,431,524.00 0.68 75.70%
3 Cat Plafond M² 206.08 34,979.00 7,208,472.32 0.43 - - - 0.00% - - - 0.00% - - - 0.00%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42 100.00%
2 Lantai 2 -
- Cat Tembok Exterior Weather Shield M² 1,364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11 100.00%
3 Cat Kusen & Daun Pintu Jendela (Exterior) M² 189.25 47,230.00 8,938,277.50 0.53 - - - - - - - 0.00% - - - 0.00%
J. PEKERJAAN SANITASI
1 Tandon Air Bersih Type: Silinder Kapasitas: 2.200 Liter Unit 2.00 4,962,459.43 9,924,918.86 0.59 - - - 0.00% - - - 0.00% - - - 0.00%
2 Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO Buah 1.00 4,951,184.00 4,951,184.00 0.29 - - - 0.00% 1.00 4,951,184.00 0.29 100.00% 1.00 4,951,184.00 0.29 100.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 7.00 822,269.00 5,755,883.00 0.34 4.00 3,289,076.00 0.20 57.14% 3.00 2,466,807.00 0.15 42.86% 7.00 5,755,883.00 0.34 100.00%
- Floor drain Buah 10.00 466,424.00 4,664,240.00 0.28 10.00 4,664,240.00 0.28 100.00% - - - 0.00% 10.00 4,664,240.00 0.28 100.00%
- Kran Buah 14.00 285,180.00 3,992,520.00 0.24 - - - 0.00% 8.00 2,281,440.00 0.14 57.14% 8.00 2,281,440.00 0.14 57.14%
- Washtavel Toto Buah 2.00 1,688,029.00 3,376,058.00 0.20 - - - 0.00% 1.00 1,688,029.00 0.10 50.00% 1.00 1,688,029.00 0.10 50.00%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO Buah 3.00 4,951,184.00 14,853,552.00 0.88 - - - 0.00% - - - 0.00% - - - 0.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 5.00 822,269.00 4,111,345.00 0.24 4.00 3,289,076.00 0.20 80.00% - - - 0.00% 4.00 3,289,076.00 0.20 80.00%
- Floor drain Buah 12.00 466,424.00 5,597,088.00 0.33 10.00 4,664,240.00 0.28 83.33% 2.00 932,848.00 0.06 16.67% 12.00 5,597,088.00 0.33 100.00%
- Kran Buah 18.00 285,180.00 5,133,240.00 0.30 - - - 0.00% - - - 0.00% - - - 0.00%
- Washtavel Toto Buah 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% - - - 0.00% - - - 0.00%
2 Instalasi Air Bersih
Lantai 1
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .32 M' 80.00 50,000.00 4,000,000.00 0.24 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .20 M' 100.00 25,000.00 2,500,000.00 0.15 20.00 500,000.00 0.03 20.00% 30.00 750,000.00 0.04 30.00% 50.00 1,250,000.00 0.07 50.00%
Lantai 2
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .20 M' 120.00 25,000.00 3,000,000.00 0.18 20.00 500,000.00 0.03 16.67% 40.00 1,000,000.00 0.06 33.33% 60.00 1,500,000.00 0.09 50.00%
3 Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 70.00 105,000.00 7,350,000.00 0.44 - - - 0.00% 70.00 7,350,000.00 0.44 100.00% 70.00 7,350,000.00 0.44 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% 4.00 1,000,000.00 0.06 100.00% 4.00 1,000,000.00 0.06 100.00%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 130.00 105,000.00 13,650,000.00 0.81 - - - 0.00% 130.00 13,650,000.00 0.81 100.00% 130.00 13,650,000.00 0.81 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 - - - 0.00% 4.00 1,000,000.00 0.06 100.00% 4.00 1,000,000.00 0.06 100.00%
KONTRAK S/d Bulan Lalu Bulan Ini S/d Bulan Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME ( Rp. ) ( Rp. ) (%) VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek.
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres (Halaman Depan) Ls 1.00 18,000,000.00 18,000,000.00 1.07 - - - 0.00% 1.00 18,000,000.00 1.07 100.00% 1.00 18,000,000.00 1.07 100.00%
2 Perbaikan Papan Nama Polres (Gedung Utama) Ls 1.00 36,000,000.00 36,000,000.00 2.14 - - - 0.00% 1.00 36,000,000.00 2.14 100.00% 1.00 36,000,000.00 2.14 100.00%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 399,011,491.60 23.70 859,185,335.88 51.03 1,258,196,827.48 74.73
B. PPN 10 % ( A X 10 % ) 168,363,634.68 39,901,149.16 85,918,533.59 125,819,682.75
C. JUMLAH (A + B ) 1,851,999,981.45 438,912,640.76 945,103,869.47 1,384,016,510.23
D. DIBULATKAN 1,851,999,000.00 438,912,000.00 945,103,000.00 1,384,016,000.00
0 27 - -
28 - -
29 - -
30 - -
31 - -
0 32 - - #REF!
36 - -
0 37 - - #REF!
41 - -
42 - -
43 - -
44 - #REF!
43 46 4 5 7 5 6 6 7 40.00 #REF!
62 49 10 10 8 8 8 9 9 62.00 #REF!
52 - -
53 - -
54 - -
55 - -
56 - 18.99
0 57 - 5.64
0 58 - 500.40
0 59 - #REF!
61 - -
0 62 - #REF!
18 64 8.00 10 18.00 (219.24)
250 65 22.00 44 26 28 40.00 42 48 250.00 #REF!
67 - -
68 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
69 - -
70 - -
71 - -
72 - 13.50
0 73 - -
74 - 0.45
0 75 - #REF!
78 - 0.90
0 79 - 47.47
0 80 - 2.40
0 81 - -
82 - 0.54
0 83 - 46.11
0 84 - 2.40
0 85 - 5.40
0 86 - 2.00
0 87 - 4.00
0 88 - #REF!
0 90 - -
91 - -
92 - -
93 - -
94 - 32.00
0 95 - #REF!
0 97 - 1.00
0 98 - 32.00
0 99 - #REF!
0 101 - 2.00
0 102 - 2.00
0 103 - #REF!
105 - -
106 - -
107 - -
108 - -
0 109 - -
110 - -
111 - 1.00
0 112 - 3.00
0 113 - -
0 114 - 8.00
0 115 - 1.00
0 116 - -
117 - -
0 118 - (4.00)
4 119 2 2 4.00 (18.00)
20 120 10 10 20.00 -
0 121 - -
0 122 - #REF!
128 - -
129 - -
130 - #REF!
0 133 - -
0 134 - 30.00
0 135 - #REF!
139 - -
140 - #REF!
0 144 - 20.00
20 145 20 20.00 #REF!
149 - -
150 - -
151 - 70.00
152 - 4.00
153 - -
154 - 130.00
155 - 4.00
156 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
157 - -
158 - -
159 - 30.00
160 - 40.00
161 - 4.00
162 - -
163 - 105.00
164 - 32.00
165 - 3.00
166 - #REF!
177 - -
178 - -
179 - -
180 - 1.00
181 - #REF!
183 - -
184 - -
- -
RINCIAN PROGRES MINGGUAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100.00%
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 133.08 12,000.00 1,596,960.00 0.09 67.00 804,000.00 0.05 50.35% 21.08 252,960.00 0.02 15.84% 88.08 1,056,960.00 0.06 66.19%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 368.20 12,000.00 4,418,400.00 0.26 140.00 1,680,000.00 0.10 38.02% 56.20 674,400.00 0.04 15.26% 196.20 2,354,400.00 0.14 53.29%
3 Pembongkaran Plafond Eksisting Toilet M² 118.08 12,000.00 1,416,960.00 0.08 68.00 816,000.00 0.05 57.59% - - - 0.00% 68.00 816,000.00 0.05 57.59%
4 Pembongkaran Lisplank Atap Eksisting M² 820.00 20,000.00 16,400,000.00 0.97 376.00 7,520,000.00 0.45 45.85% 154.00 3,080,000.00 0.18 18.78% 530.00 10,600,000.00 0.63 64.63%
5 Pembongkaran Plafond Eksisting Drop off utama M² 88.00 12,000.00 1,056,000.00 0.06 88.00 1,056,000.00 0.06 100.00% - - - 0.00% 88.00 1,056,000.00 0.06 100.00%
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 206.08 211,490.00 43,583,859.20 2.59 156.00 32,992,440.00 1.96 75.70% - - - 0.00% 156.00 32,992,440.00 1.96 75.70%
2 Plafond Calciboard (3,5mm) M² 206.08 73,279.00 15,101,336.32 0.90 156.00 11,431,524.00 0.68 75.70% - - - 0.00% 156.00 11,431,524.00 0.68 75.70%
3 Cat Plafond M² 206.08 34,979.00 7,208,472.32 0.43 - - - 0.00% 88.00 3,078,152.00 0.18 42.70% 88.00 3,078,152.00 0.18 42.70%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42 100.00%
2 Lantai 2 -
- Cat Tembok Exterior Weather Shield M² 1,364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11 100.00%
3 Cat Kusen & Daun Pintu Jendela (Exterior) M² 189.25 47,230.00 8,938,277.50 0.53 - - - - 92.00 4,345,160.00 0.26 48.61% 92.00 4,345,160.00 0.26 48.61%
J. PEKERJAAN SANITASI
1 Tandon Air Bersih Type: Silinder Kapasitas: 2.200 Liter Unit 2.00 4,962,459.43 9,924,918.86 0.59 - - - 0.00% 2.00 9,924,918.86 0.59 100.00% 2.00 9,924,918.86 0.59 100.00%
2 Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO Buah 1.00 4,951,184.00 4,951,184.00 0.29 1.00 4,951,184.00 0.29 100.00% - - - 0.00% 1.00 4,951,184.00 0.29 100.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 7.00 822,269.00 5,755,883.00 0.34 7.00 5,755,883.00 0.34 100.00% - - - 0.00% 7.00 5,755,883.00 0.34 100.00%
- Floor drain Buah 10.00 466,424.00 4,664,240.00 0.28 10.00 4,664,240.00 0.28 100.00% - - - 0.00% 10.00 4,664,240.00 0.28 100.00%
- Kran Buah 14.00 285,180.00 3,992,520.00 0.24 8.00 2,281,440.00 0.14 57.14% 6.00 1,711,080.00 0.10 42.86% 14.00 3,992,520.00 0.24 100.00%
- Washtavel Toto Buah 2.00 1,688,029.00 3,376,058.00 0.20 1.00 1,688,029.00 0.10 50.00% 1.00 1,688,029.00 0.10 50.00% 2.00 3,376,058.00 0.20 100.00%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO Buah 3.00 4,951,184.00 14,853,552.00 0.88 - - - 0.00% 1.00 4,951,184.00 0.29 33.33% 1.00 4,951,184.00 0.29 33.33%
- Pemasangan Toilet Jongkok Setara TOTO Buah 5.00 822,269.00 4,111,345.00 0.24 4.00 3,289,076.00 0.20 80.00% - - - 0.00% 4.00 3,289,076.00 0.20 80.00%
- Floor drain Buah 12.00 466,424.00 5,597,088.00 0.33 12.00 5,597,088.00 0.33 100.00% - - - 0.00% 12.00 5,597,088.00 0.33 100.00%
- Kran Buah 18.00 285,180.00 5,133,240.00 0.30 - - - 0.00% 6.00 1,711,080.00 0.10 33.33% 6.00 1,711,080.00 0.10 33.33%
- Washtavel Toto Buah 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% 2.00 3,376,058.00 0.20 50.00% 2.00 3,376,058.00 0.20 50.00%
2 Instalasi Air Bersih
Lantai 1
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .32 M' 80.00 50,000.00 4,000,000.00 0.24 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% 20.00 700,000.00 0.04 50.00% 20.00 700,000.00 0.04 50.00%
- Dia .20 M' 100.00 25,000.00 2,500,000.00 0.15 50.00 1,250,000.00 0.07 50.00% 20.00 500,000.00 0.03 20.00% 70.00 1,750,000.00 0.10 70.00%
Lantai 2
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% 16.00 560,000.00 0.03 40.00% 16.00 560,000.00 0.03 40.00%
- Dia .20 M' 120.00 25,000.00 3,000,000.00 0.18 60.00 1,500,000.00 0.09 50.00% 28.00 700,000.00 0.04 23.33% 88.00 2,200,000.00 0.13 73.33%
3 Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 70.00 105,000.00 7,350,000.00 0.44 70.00 7,350,000.00 0.44 100.00% - - - 0.00% 70.00 7,350,000.00 0.44 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 130.00 105,000.00 13,650,000.00 0.81 130.00 13,650,000.00 0.81 100.00% - - - 0.00% 130.00 13,650,000.00 0.81 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME VOLUME thd pek. VOLUME thd pek. VOLUME thd pek.
( Rp. ) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%) ( Rp. ) (%)
4 Instalasi Air Bekas
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- dia. 80 M' 30.00 65,000.00 1,950,000.00 0.12 30.00 1,950,000.00 0.12 100.00% - - - 0.00% 30.00 1,950,000.00 0.12 100.00%
- dia. 50 M' 40.00 32,000.00 1,280,000.00 0.08 40.00 1,280,000.00 0.08 100.00% - - - 0.00% 40.00 1,280,000.00 0.08 100.00%
- CO, dia. 80 Buah 4.00 175,000.00 700,000.00 0.04 4.00 700,000.00 0.04 100.00% - - - 0.00% 4.00 700,000.00 0.04 100.00%
Lantai 2
- dia. 80 M' 130.00 65,000.00 8,450,000.00 0.50 105.00 6,825,000.00 0.41 80.77% - - - 0.00% 105.00 6,825,000.00 0.41 80.77%
- dia. 50 M' 40.00 32,000.00 1,280,000.00 0.08 32.00 1,024,000.00 0.06 80.00% - - - 0.00% 32.00 1,024,000.00 0.06 80.00%
- CO, dia. 80 Buah 4.00 175,000.00 700,000.00 0.04 3.00 525,000.00 0.03 75.00% - - - 0.00% 3.00 525,000.00 0.03 75.00%
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres (Halaman Depan) Ls 1.00 18,000,000.00 18,000,000.00 1.07 1.00 18,000,000.00 1.07 100.00% - - - 0.00% 1.00 18,000,000.00 1.07 100.00%
2 Perbaikan Papan Nama Polres (Gedung Utama) Ls 1.00 36,000,000.00 36,000,000.00 2.14 1.00 36,000,000.00 2.14 100.00% - - - 0.00% 1.00 36,000,000.00 2.14 100.00%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 1,258,196,827.48 74.73 163,849,423.86 9.73 1,422,046,251.35 84.46
B. PPN 10 % ( A X 10 % ) 168,363,634.68 125,819,682.75 16,384,942.39 142,204,625.13
C. JUMLAH (A + B ) 1,851,999,981.45 1,384,016,510.23 180,234,366.25 1,564,250,876.48
D. DIBULATKAN 1,851,999,000.00 1,384,016,000.00 180,234,000.00 1,564,250,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
:
1 Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
2
3 Err:522 Err:522 Err:522 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
21.08 9 10 11.08 - 21.08 - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
56.2 10 8 9 8 10 12 9.20 56.20 - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - - - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
154 12 18 19 21 17 18 20 22 19.00 154.00 - 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
0 - - -
- - -
15 - - - 13 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
16 - - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
0 18 - - - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
3 19 1 2 - 3.00 - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
24 20 6 8 6 4.00 24.00 - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - - -
22 - - -
23 - - -
24 - - -
0 25 - - -
0 26 - - -
88 88 - 88.00 -
27 - - -
28 - - -
29 - - -
30 - - -
31 - - -
0 32 - - -
36 - - -
0 37 - - -
92 12 14 12 9 10 11 12 12.00 92.00 -
41 - - -
42 - - -
43 - - -
44 - - -
46.66 46 8 10 14 9 5.66 - 46.66 -
154 49 18 19 21 17 18 20 22 19.00 154.00 -
154 18 19 21 17 18 20 22 19.00 154.00 -
0 - - -
52 - - -
53 - - -
54 - - -
55 - - -
56 - - -
0 57 - - -
0 58 - - -
0 59 - - -
0 - - -
61 - - -
77.5 62 16 20 16 16 9.5 - 77.50 -
0 64 - - -
0 65 - - -
0 - - -
0 67 - - -
- - -
1 Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
68 - - -
1 Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
69 - - -
70 - - -
71 - - -
72 - - -
0 73 - - -
74 - - -
0 75 - - -
78 - - -
0 79 - - -
0 80 - - -
0 81 - - -
82 - - -
0 83 - - -
0 84 - - -
0 85 - - -
0 86 - - -
0 87 - - -
0 88 - - -
0 90 - - -
91 - - -
92 - - -
93 - - -
94 - - -
0 95 - - -
0 97 - - -
0 98 - - -
0 99 - - -
0 101 - - -
0 102 - - -
0 103 - - -
105 - - -
106 - - -
107 - - -
108 - - -
2 109 2 - 2.00 -
110 - - -
111 - - -
0 112 - - -
0 113 - - -
0 114 - - -
6 115 6 - 6.00 -
1 116 1.00 1.00 -
117 - - -
1 118 1 - 1.00 -
0 119 - - -
0 120 - - -
6 121 6 - 6.00 -
2 122 1 1 - 2.00 -
128 - - -
129 - - -
130 - - -
0 133 - - -
20 134 10 10 - 20.00 -
20 135 20.00 20.00 -
139 - - -
140 - - -
16 144 16 - 16.00 -
28 145 12 16.00 28.00 -
149 - - -
150 - - -
151 - - -
0 152 - - -
0 153 - - -
154 - - -
0 155 - - -
0 156 - - -
1 Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Total PERIODE MINGGU KE -
157 - - -
158 - - -
159 - - -
0 160 - - -
0 161 - - -
0 162 - - -
163 - - -
0 164 - - -
0 165 - - -
0 166 - - -
177 - - -
178 - - -
179 - - -
180 - - -
0 181 - - -
0 - - -
183 - - -
184 - - -
- - -
RINCIAN PROGRES MINGGUAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100.00%
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 133.08 12,000.00 1,596,960.00 0.09 88.08 1,056,960.00 0.06 66.19% - - - 0.00% 88.08 1,056,960.00 0.06 66.19%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 368.20 12,000.00 4,418,400.00 0.26 196.20 2,354,400.00 0.14 53.29% - - - 0.00% 196.20 2,354,400.00 0.14 53.29%
3 Pembongkaran Plafond Eksisting Toilet M² 118.08 12,000.00 1,416,960.00 0.08 68.00 816,000.00 0.05 57.59% 50.08 600,960.00 0.04 42.41% 118.08 1,416,960.00 0.08 100.00%
4 Pembongkaran Lisplank Atap Eksisting M² 820.00 20,000.00 16,400,000.00 0.97 530.00 10,600,000.00 0.63 64.63% 160.00 3,200,000.00 0.19 19.51% 690.00 13,800,000.00 0.82 84.15%
5 Pembongkaran Plafond Eksisting Drop off utama M² 88.00 12,000.00 1,056,000.00 0.06 88.00 1,056,000.00 0.06 100.00% - - - 0.00% 88.00 1,056,000.00 0.06 100.00%
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 206.08 211,490.00 43,583,859.20 2.59 156.00 32,992,440.00 1.96 75.70% - - - 0.00% 156.00 32,992,440.00 1.96 75.70%
2 Plafond Calciboard (3,5mm) M² 206.08 73,279.00 15,101,336.32 0.90 156.00 11,431,524.00 0.68 75.70% - - - 0.00% 156.00 11,431,524.00 0.68 75.70%
3 Cat Plafond M² 206.08 34,979.00 7,208,472.32 0.43 88.00 3,078,152.00 0.18 42.70% 68.00 2,378,572.00 0.14 33.00% 156.00 5,456,724.00 0.32 75.70%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42 100.00%
2 Lantai 2 -
- Cat Tembok Exterior Weather Shield M² 1,364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11 100.00%
3 Cat Kusen & Daun Pintu Jendela (Exterior) M² 189.25 47,230.00 8,938,277.50 0.53 92.00 4,345,160.00 0.26 0.49 97.25 4,593,117.50 0.27 51.39% 189.25 8,938,277.50 0.53 100.00%
J. PEKERJAAN SANITASI
1 Tandon Air Bersih Type: Silinder Kapasitas: 2.200 Liter Unit 2.00 4,962,459.43 9,924,918.86 0.59 2.00 9,924,918.86 0.59 100.00% - - - 0.00% 2.00 9,924,918.86 0.59 100.00%
2 Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO Buah 1.00 4,951,184.00 4,951,184.00 0.29 1.00 4,951,184.00 0.29 100.00% - - - 0.00% 1.00 4,951,184.00 0.29 100.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 7.00 822,269.00 5,755,883.00 0.34 7.00 5,755,883.00 0.34 100.00% - - - 0.00% 7.00 5,755,883.00 0.34 100.00%
- Floor drain Buah 10.00 466,424.00 4,664,240.00 0.28 10.00 4,664,240.00 0.28 100.00% - - - 0.00% 10.00 4,664,240.00 0.28 100.00%
- Kran Buah 14.00 285,180.00 3,992,520.00 0.24 14.00 3,992,520.00 0.24 100.00% - - - 0.00% 14.00 3,992,520.00 0.24 100.00%
- Washtavel Toto Buah 2.00 1,688,029.00 3,376,058.00 0.20 2.00 3,376,058.00 0.20 100.00% - - - 0.00% 2.00 3,376,058.00 0.20 100.00%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO Buah 3.00 4,951,184.00 14,853,552.00 0.88 1.00 4,951,184.00 0.29 33.33% 2.00 9,902,368.00 0.59 66.67% 3.00 14,853,552.00 0.88 100.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 5.00 822,269.00 4,111,345.00 0.24 4.00 3,289,076.00 0.20 80.00% 1.00 822,269.00 0.05 20.00% 5.00 4,111,345.00 0.24 100.00%
- Floor drain Buah 12.00 466,424.00 5,597,088.00 0.33 12.00 5,597,088.00 0.33 100.00% - - - 0.00% 12.00 5,597,088.00 0.33 100.00%
- Kran Buah 18.00 285,180.00 5,133,240.00 0.30 6.00 1,711,080.00 0.10 33.33% 6.00 1,711,080.00 0.10 33.33% 12.00 3,422,160.00 0.20 66.67%
- Washtavel Toto Buah 4.00 1,688,029.00 6,752,116.00 0.40 2.00 3,376,058.00 0.20 50.00% 1.00 1,688,029.00 0.10 25.00% 3.00 5,064,087.00 0.30 75.00%
2 Instalasi Air Bersih
Lantai 1
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .32 M' 80.00 50,000.00 4,000,000.00 0.24 - - - 0.00% - - - 0.00% - - - 0.00%
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 20.00 700,000.00 0.04 50.00% 20.00 700,000.00 0.04 50.00% 40.00 1,400,000.00 0.08 100.00%
- Dia .20 M' 100.00 25,000.00 2,500,000.00 0.15 70.00 1,750,000.00 0.10 70.00% 30.00 750,000.00 0.04 30.00% 100.00 2,500,000.00 0.15 100.00%
Lantai 2
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 16.00 560,000.00 0.03 40.00% 24.00 840,000.00 0.05 60.00% 40.00 1,400,000.00 0.08 100.00%
- Dia .20 M' 120.00 25,000.00 3,000,000.00 0.18 88.00 2,200,000.00 0.13 73.33% 32.00 800,000.00 0.05 26.67% 120.00 3,000,000.00 0.18 100.00%
3 Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 70.00 105,000.00 7,350,000.00 0.44 70.00 7,350,000.00 0.44 100.00% - - - 0.00% 70.00 7,350,000.00 0.44 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 130.00 105,000.00 13,650,000.00 0.81 130.00 13,650,000.00 0.81 100.00% - - - 0.00% 130.00 13,650,000.00 0.81 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME ( Rp. ) ( Rp. ) (%) VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek.
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres (Halaman Depan) Ls 1.00 18,000,000.00 18,000,000.00 1.07 1.00 18,000,000.00 1.07 100.00% - - - 0.00% 1.00 18,000,000.00 1.07 100.00%
2 Perbaikan Papan Nama Polres (Gedung Utama) Ls 1.00 36,000,000.00 36,000,000.00 2.14 1.00 36,000,000.00 2.14 100.00% - - - 0.00% 1.00 36,000,000.00 2.14 100.00%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 1,422,046,251.35 84.46 136,811,815.08 8.13 1,558,858,066.43 92.59
B. PPN 10 % ( A X 10 % ) 168,363,634.68 142,204,625.13 13,681,181.51 155,885,806.64
C. JUMLAH (A + B ) 1,851,999,981.45 1,564,250,876.48 150,492,996.59 1,714,743,873.07
D. DIBULATKAN 1,851,999,000.00 1,564,250,000.00 150,492,000.00 1,714,743,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
:
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
2
3 Err:522 Err:522 - 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
0 9 - - - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
0 10 - - - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
50.08 11 24 26.08 50.08 - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
160 12 21 24 23 21 24 22 25.00 160.00 #REF! 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
0 - 11 : 09 NOVEMBER 2015 s/d 15 NOVEMBER 2015
- 12 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
15 - - - 13 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
16 - - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
0 18 - - - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
2 19 2 - 2.00 - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
39.968 20 12 14 13.968 - 39.97 - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - - -
22 - - -
23 - - -
24 - - -
0 25 - - -
0 26 - - -
68 68 -
27 - - -
28 - - -
29 - - -
30 - - -
31 - - -
0 32 - - #REF!
36 - - -
0 37 - - #REF!
97.25 15 16 13 12 15 14 12.25
41 - - -
42 - - -
43 - - -
44 - - #REF!
0 46 - - #REF!
160 49 21 24 23 21 24 22 25.00 160.00 #REF!
160 21 24 23 21 24 22 25.00
0 -
52 - - -
53 - - -
54 - - -
55 - - -
56 - - -
0 57 - - -
0 58 - - -
0 59 - - #REF!
42 6 7 5 7 8 5 4.00
61 - - -
0 62 - - #REF!
0 64 - - -
0 65 - - #REF!
0 -
520 67 74 78 72 75 68 82 71.00 520.00 -
-
68 - - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
69 - - -
70 - - -
71 - - -
72 - - -
0 73 - - -
74 - - -
0 75 - - #REF!
78 - - -
0 79 - - -
0 80 - - -
0 81 - - -
82 - - -
0 83 - - -
0 84 - - -
0 85 - - -
0 86 - - -
0 87 - - -
0 88 - - #REF!
0 90 - - -
91 - - -
92 - - -
93 - - -
94 - - -
0 95 - - #REF!
0 97 - - -
0 98 - - -
0 99 - - #REF!
0 101 - - -
0 102 - - -
0 103 - - #REF!
105 - - -
106 - - -
107 - - -
108 - - -
0 109 - - -
110 - - -
111 - - -
0 112 - - -
0 113 - - -
0 114 - - -
0 115 - - -
0 116 - - -
117 - - -
2 118 1 1 - 2.00 -
1 119 1 - 1.00 -
0 120 - - -
6 121 6 - 6.00 -
1 122 1 - 1.00 #REF!
128 - - -
129 - - -
130 - - #REF!
0 133 - - -
20 134 20 - 20.00 -
30 135 14 16 - 30.00 #REF!
139 - - -
140 - - #REF!
24 144 14 10 - 24.00 -
32 145 14 18.00 32.00 #REF!
149 - - -
150 - - -
151 - - -
0 152 - - -
0 153 - - -
154 - - -
0 155 - - -
0 156 - - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
157 - - -
158 - - -
159 - - -
0 160 - - -
0 161 - - -
0 162 - - -
163 - - -
25 164 15 10 - 25.00 -
8 165 8 - 8.00 -
1 166 1 - 1.00 #REF!
177 - - -
178 - - -
179 - - -
180 - - -
0 181 - - #REF!
0 -
183 - - -
184 - - -
- - -
RINCIAN PROGRES MINGGUAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100.00%
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 133.08 12,000.00 1,596,960.00 0.09 88.08 1,056,960.00 0.06 66.19% - - - 0.00% 88.08 1,056,960.00 0.06 66.19%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 368.20 12,000.00 4,418,400.00 0.26 196.20 2,354,400.00 0.14 53.29% - - - 0.00% 196.20 2,354,400.00 0.14 53.29%
3 Pembongkaran Plafond Eksisting Toilet M² 118.08 12,000.00 1,416,960.00 0.08 118.08 1,416,960.00 0.08 100.00% - - - 0.00% 118.08 1,416,960.00 0.08 100.00%
4 Pembongkaran Lisplank Atap Eksisting M² 820.00 20,000.00 16,400,000.00 0.97 690.00 13,800,000.00 0.82 84.15% 130.00 2,600,000.00 0.15 15.85% 820.00 16,400,000.00 0.97 100.00%
5 Pembongkaran Plafond Eksisting Drop off utama M² 88.00 12,000.00 1,056,000.00 0.06 88.00 1,056,000.00 0.06 100.00% - - - 0.00% 88.00 1,056,000.00 0.06 100.00%
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 206.08 211,490.00 43,583,859.20 2.59 156.00 32,992,440.00 1.96 75.70% 50.08 10,591,419.20 0.63 24.30% 206.08 43,583,859.20 2.59 100.00%
2 Plafond Calciboard (3,5mm) M² 206.08 73,279.00 15,101,336.32 0.90 156.00 11,431,524.00 0.68 75.70% 50.08 3,669,812.32 0.22 24.30% 206.08 15,101,336.32 0.90 100.00%
3 Cat Plafond M² 206.08 34,979.00 7,208,472.32 0.43 156.00 5,456,724.00 0.32 75.70% 50.08 1,751,748.32 0.10 24.30% 206.08 7,208,472.32 0.43 100.00%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42 100.00%
2 Lantai 2
- Cat Tembok Exterior Weather Shield M² 1,364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11 100.00%
3 Cat Kusen & Daun Pintu Jendela (Exterior) M² 189.25 47,230.00 8,938,277.50 0.53 189.25 8,938,277.50 0.53 1.00 - - - 0.00% 189.25 8,938,277.50 0.53 100.00%
J. PEKERJAAN SANITASI
1 Tandon Air Bersih Type: Silinder Kapasitas: 2.200 Liter Unit 2.00 4,962,459.43 9,924,918.86 0.59 2.00 9,924,918.86 0.59 100.00% - - - 0.00% 2.00 9,924,918.86 0.59 100.00%
2 Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO Buah 1.00 4,951,184.00 4,951,184.00 0.29 1.00 4,951,184.00 0.29 100.00% - - - 0.00% 1.00 4,951,184.00 0.29 100.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 7.00 822,269.00 5,755,883.00 0.34 7.00 5,755,883.00 0.34 100.00% - - - 0.00% 7.00 5,755,883.00 0.34 100.00%
- Floor drain Buah 10.00 466,424.00 4,664,240.00 0.28 10.00 4,664,240.00 0.28 100.00% - - - 0.00% 10.00 4,664,240.00 0.28 100.00%
- Kran Buah 14.00 285,180.00 3,992,520.00 0.24 14.00 3,992,520.00 0.24 100.00% - - - 0.00% 14.00 3,992,520.00 0.24 100.00%
- Washtavel Toto Buah 2.00 1,688,029.00 3,376,058.00 0.20 2.00 3,376,058.00 0.20 100.00% - - - 0.00% 2.00 3,376,058.00 0.20 100.00%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO Buah 3.00 4,951,184.00 14,853,552.00 0.88 3.00 14,853,552.00 0.88 100.00% - - - 0.00% 3.00 14,853,552.00 0.88 100.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 5.00 822,269.00 4,111,345.00 0.24 5.00 4,111,345.00 0.24 100.00% - - - 0.00% 5.00 4,111,345.00 0.24 100.00%
- Floor drain Buah 12.00 466,424.00 5,597,088.00 0.33 12.00 5,597,088.00 0.33 100.00% - - - 0.00% 12.00 5,597,088.00 0.33 100.00%
- Kran Buah 18.00 285,180.00 5,133,240.00 0.30 12.00 3,422,160.00 0.20 66.67% 6.00 1,711,080.00 0.10 33.33% 18.00 5,133,240.00 0.30 100.00%
- Washtavel Toto Buah 4.00 1,688,029.00 6,752,116.00 0.40 3.00 5,064,087.00 0.30 75.00% 1.00 1,688,029.00 0.10 25.00% 4.00 6,752,116.00 0.40 100.00%
2 Instalasi Air Bersih
Lantai 1
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .32 M' 80.00 50,000.00 4,000,000.00 0.24 - - - 0.00% 80.00 4,000,000.00 0.24 100.00% 80.00 4,000,000.00 0.24 100.00%
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 40.00 1,400,000.00 0.08 100.00% - - - 0.00% 40.00 1,400,000.00 0.08 100.00%
- Dia .20 M' 100.00 25,000.00 2,500,000.00 0.15 100.00 2,500,000.00 0.15 100.00% - - - 0.00% 100.00 2,500,000.00 0.15 100.00%
Lantai 2
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 40.00 1,400,000.00 0.08 100.00% - - - 0.00% 40.00 1,400,000.00 0.08 100.00%
- Dia .20 M' 120.00 25,000.00 3,000,000.00 0.18 120.00 3,000,000.00 0.18 100.00% - - - 0.00% 120.00 3,000,000.00 0.18 100.00%
3 Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 70.00 105,000.00 7,350,000.00 0.44 70.00 7,350,000.00 0.44 100.00% - - - 0.00% 70.00 7,350,000.00 0.44 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 130.00 105,000.00 13,650,000.00 0.81 130.00 13,650,000.00 0.81 100.00% - - - 0.00% 130.00 13,650,000.00 0.81 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME ( Rp. ) ( Rp. ) (%) VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek.
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres (Halaman Depan) Ls 1.00 18,000,000.00 18,000,000.00 1.07 1.00 18,000,000.00 1.07 100.00% - - - 0.00% 1.00 18,000,000.00 1.07 100.00%
2 Perbaikan Papan Nama Polres (Gedung Utama) Ls 1.00 36,000,000.00 36,000,000.00 2.14 1.00 36,000,000.00 2.14 100.00% - - - 0.00% 1.00 36,000,000.00 2.14 100.00%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 1,558,858,066.43 92.59 122,174,280.34 7.26 1,681,032,346.77 99.85
B. PPN 10 % ( A X 10 % ) 168,363,634.68 155,885,806.64 12,217,428.03 168,103,234.68
C. JUMLAH (A + B ) 1,851,999,981.45 1,714,743,873.07 134,391,708.38 1,849,135,581.45
D. DIBULATKAN 1,851,999,000.00 1,714,743,000.00 134,391,000.00 1,849,135,000.00
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
:
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
2
3 Err:522 Err:522 Err:522 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
0 9 - - - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
0 10 - - - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - - - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
130 12 26 24 27 27 26 - 130.00 - 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
0 - - - 11 : 09 NOVEMBER 2015 s/d 15 NOVEMBER 2015
- - - 12 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
15 - - - 13 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
16 - - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
22.08 18 10 12.08 - 22.08 - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
1.832 19 1.832 - 1.83 - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
0 20 - - - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - - -
22 - - -
23 - - -
24 - - -
50.08 25 12 14 14 10.08 - 50.08 -
50.08 26 12 14 14 10.08 - 50.08 -
50.08 24 26.08 - 50.08 -
27 - - -
28 - - -
29 - - -
30 - - -
31 - - -
0 32 - - -
36 - - -
0 37 - - -
0 - - -
41 - - -
42 - - -
43 - - -
44 - - -
0 46 - - -
130 49 26 24 27 27 26 - 130.00 -
130 26 24 27 27 26 - 130.00 -
0 - - -
52 - - -
53 - - -
54 - - -
55 - - -
56 - - -
0 57 - - -
0 58 - - -
0 59 - - -
54.656 11 10 13 10 10.656 0 - 54.66 -
61 - - -
0 62 - - -
0 64 - - -
0 65 - - -
0 - - -
690.8 67 142 138 129 147 134.8 - 690.80 -
- - -
68 - - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
69 - - -
70 - - -
71 - - -
72 - - -
0 73 - - -
74 - - -
0 75 - - -
78 - - -
0 79 - - -
0 80 - - -
0 81 - - -
82 - - -
0 83 - - -
0 84 - - -
0 85 - - -
0 86 - - -
0 87 - - -
0 88 - - -
0 90 - - -
91 - - -
92 - - -
93 - - -
94 - - -
0 95 - - -
0 97 - - -
0 98 - - -
0 99 - - -
0 101 - - -
0 102 - - -
0 103 - - -
105 - - -
106 - - -
107 - - -
108 - - -
0 109 - - -
110 - - -
111 - - -
0 112 - - -
0 113 - - -
0 114 - - -
0 115 - - -
0 116 - - -
117 - - -
0 118 - - -
0 119 - - -
0 120 - - -
6 121 6 - 6.00 -
1 122 1 - 1.00 -
128 - - -
129 - - -
130 - - -
80 133 20 40 20 - 80.00 -
0 134 - - -
0 135 - - -
139 - - -
140 - - -
0 144 - - -
0 145 - - -
149 - - -
150 - - -
151 - - -
0 152 - - -
0 153 - - -
154 - - -
0 155 - - -
0 156 - - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
157 - - -
158 - - -
159 - - -
0 160 - - -
0 161 - - -
0 162 - - -
163 - - -
0 164 - - -
0 165 - - -
0 166 - - -
177 - - -
178 - - -
179 - - -
180 - - -
0 181 - - -
0 - - -
183 - - -
184 - - -
- - -
RINCIAN PROGRES MINGGUAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100.00%
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 133.08 12,000.00 1,596,960.00 0.09 88.08 1,056,960.00 0.06 66.19% - - - 0.00% 88.08 1,056,960.00 0.06 66.19%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 368.20 12,000.00 4,418,400.00 0.26 196.20 2,354,400.00 0.14 53.29% - - - 0.00% 196.20 2,354,400.00 0.14 53.29%
3 Pembongkaran Plafond Eksisting Toilet M² 118.08 12,000.00 1,416,960.00 0.08 118.08 1,416,960.00 0.08 100.00% - - - 0.00% 118.08 1,416,960.00 0.08 100.00%
4 Pembongkaran Lisplank Atap Eksisting M² 820.00 20,000.00 16,400,000.00 0.97 820.00 16,400,000.00 0.97 100.00% - - - 0.00% 820.00 16,400,000.00 0.97 100.00%
5 Pembongkaran Plafond Eksisting Drop off utama M² 88.00 12,000.00 1,056,000.00 0.06 88.00 1,056,000.00 0.06 100.00% - - - 0.00% 88.00 1,056,000.00 0.06 100.00%
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 206.08 211,490.00 43,583,859.20 2.59 206.08 43,583,859.20 2.59 100.00% - - - 0.00% 206.08 43,583,859.20 2.59 100.00%
2 Plafond Calciboard (3,5mm) M² 206.08 73,279.00 15,101,336.32 0.90 206.08 15,101,336.32 0.90 100.00% - - - 0.00% 206.08 15,101,336.32 0.90 100.00%
3 Cat Plafond M² 206.08 34,979.00 7,208,472.32 0.43 206.08 7,208,472.32 0.43 100.00% - - - 0.00% 206.08 7,208,472.32 0.43 100.00%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42 100.00%
2 Lantai 2
- Cat Tembok Exterior Weather Shield M² 1,364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11 100.00%
3 Cat Kusen & Daun Pintu Jendela (Exterior) M² 189.25 47,230.00 8,938,277.50 0.53 189.25 8,938,277.50 0.53 1.00 - - - 0.00% 189.25 8,938,277.50 0.53 100.00%
J. PEKERJAAN SANITASI
1 Tandon Air Bersih Type: Silinder Kapasitas: 2.200 Liter Unit 2.00 4,962,459.43 9,924,918.86 0.59 2.00 9,924,918.86 0.59 100.00% - - - 0.00% 2.00 9,924,918.86 0.59 100.00%
2 Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO Buah 1.00 4,951,184.00 4,951,184.00 0.29 1.00 4,951,184.00 0.29 100.00% - - - 0.00% 1.00 4,951,184.00 0.29 100.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 7.00 822,269.00 5,755,883.00 0.34 7.00 5,755,883.00 0.34 100.00% - - - 0.00% 7.00 5,755,883.00 0.34 100.00%
- Floor drain Buah 10.00 466,424.00 4,664,240.00 0.28 10.00 4,664,240.00 0.28 100.00% - - - 0.00% 10.00 4,664,240.00 0.28 100.00%
- Kran Buah 14.00 285,180.00 3,992,520.00 0.24 14.00 3,992,520.00 0.24 100.00% - - - 0.00% 14.00 3,992,520.00 0.24 100.00%
- Washtavel Toto Buah 2.00 1,688,029.00 3,376,058.00 0.20 2.00 3,376,058.00 0.20 100.00% - - - 0.00% 2.00 3,376,058.00 0.20 100.00%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO Buah 3.00 4,951,184.00 14,853,552.00 0.88 3.00 14,853,552.00 0.88 100.00% - - - 0.00% 3.00 14,853,552.00 0.88 100.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 5.00 822,269.00 4,111,345.00 0.24 5.00 4,111,345.00 0.24 100.00% - - - 0.00% 5.00 4,111,345.00 0.24 100.00%
- Floor drain Buah 12.00 466,424.00 5,597,088.00 0.33 12.00 5,597,088.00 0.33 100.00% - - - 0.00% 12.00 5,597,088.00 0.33 100.00%
- Kran Buah 18.00 285,180.00 5,133,240.00 0.30 18.00 5,133,240.00 0.30 100.00% - - - 0.00% 18.00 5,133,240.00 0.30 100.00%
- Washtavel Toto Buah 4.00 1,688,029.00 6,752,116.00 0.40 4.00 6,752,116.00 0.40 100.00% - - - 0.00% 4.00 6,752,116.00 0.40 100.00%
2 Instalasi Air Bersih
Lantai 1
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .32 M' 80.00 50,000.00 4,000,000.00 0.24 80.00 4,000,000.00 0.24 100.00% - - - 0.00% 80.00 4,000,000.00 0.24 100.00%
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 40.00 1,400,000.00 0.08 100.00% - - - 0.00% 40.00 1,400,000.00 0.08 100.00%
- Dia .20 M' 100.00 25,000.00 2,500,000.00 0.15 100.00 2,500,000.00 0.15 100.00% - - - 0.00% 100.00 2,500,000.00 0.15 100.00%
Lantai 2
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 40.00 1,400,000.00 0.08 100.00% - - - 0.00% 40.00 1,400,000.00 0.08 100.00%
- Dia .20 M' 120.00 25,000.00 3,000,000.00 0.18 120.00 3,000,000.00 0.18 100.00% - - - 0.00% 120.00 3,000,000.00 0.18 100.00%
3 Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 70.00 105,000.00 7,350,000.00 0.44 70.00 7,350,000.00 0.44 100.00% - - - 0.00% 70.00 7,350,000.00 0.44 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 130.00 105,000.00 13,650,000.00 0.81 130.00 13,650,000.00 0.81 100.00% - - - 0.00% 130.00 13,650,000.00 0.81 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME ( Rp. ) ( Rp. ) (%) VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek.
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres (Halaman Depan) Ls 1.00 18,000,000.00 18,000,000.00 1.07 1.00 18,000,000.00 1.07 100.00% - - - 0.00% 1.00 18,000,000.00 1.07 100.00%
2 Perbaikan Papan Nama Polres (Gedung Utama) Ls 1.00 36,000,000.00 36,000,000.00 2.14 1.00 36,000,000.00 2.14 100.00% - - - 0.00% 1.00 36,000,000.00 2.14 100.00%
2. AHMAD IMAMUDDIN H, ST :
NIP. 1985 07202014 03 1 002
RISKA YULIYANTO, ST WAHYUDDIN, ST
Site Engineer Site Manager
3. JUPRIANSYAH :
:
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
2
3 Err:522 Err:522 Err:522 1 : 24 AGUSTUS 2015 s/d 31 AGUSTUS 2015
0 4 - - - 2 : 01 SEPTEMBER 2015 s/d 06 SEPTEMBER 2015
5 - - - 3 : 07 SEPTEMBER 2015 s/d 13 SEPTEMBER 2015
6 - - - 4 : 14 SEPTEMBER 2015 s/d 20 SEPTEMBER 2015
7 - - - 5 : 21 SEPTEMBER 2015 s/d 30 SEPTEMBER 2015
8 - - - 6 : 01 OKTOBER 2015 s/d 11 OKTOBER 2015
0 9 - - - 7 : 12 OKTOBER 2015 s/d 18 OKTOBER 2015
0 10 - - - 8 : 19 OKTOBER 2015 s/d 25 OKTOBER 2015
0 11 - - - 9 : 26 OKTOBER 2015 s/d 31 OKTOBER 2015
0 12 - - - 10 : 01 NOVEMBER 2015 s/d 08 NOVEMBER 2015
0 - - - 11 : 09 NOVEMBER 2015 s/d 15 NOVEMBER 2015
- - - 12 : 16 NOVEMBER 2015 s/d 22 NOVEMBER 2015
15 - - - 13 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
16 - - - 14 : 23 NOVEMBER 2015 s/d 30 NOVEMBER 2015
17 - - - 15 : 01 DESEMBER 2015 s/d 06 DESEMBER 2015
0 18 - - - 16 : 07 DESEMBER 2015 s/d 13 DESEMBER 2015
0 19 - - - 17 : 14 DESEMBER 2015 s/d 20 DESEMBER 2015
0 20 - - - 18 : 21 DESEMBER 2015 s/d 27 DESEMBER 2015
21 - - -
22 - - -
23 - - -
24 - - -
0 25 - - -
0 26 - - -
0 - - -
27 - - -
28 - - -
29 - - -
30 - - -
31 - - -
0 32 - - -
36 - - -
0 37 - - -
0 - - -
41 - - -
42 - - -
43 - - -
44 - - -
0 46 - - -
0 49 - - -
0 - - -
0 - - -
52 - - -
53 - - -
54 - - -
55 - - -
56 - - -
0 57 - - -
0 58 - - -
0 59 - - -
0 - - -
61 - - -
0 62 - - -
0 64 - - -
0 65 - - -
0 - - -
0 67 - - -
- - -
68 - - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
69 - - -
70 - - -
71 - - -
72 - - -
0 73 - - -
74 - - -
0 75 - - -
78 - - -
0 79 - - -
0 80 - - -
0 81 - - -
82 - - -
0 83 - - -
0 84 - - -
0 85 - - -
0 86 - - -
0 87 - - -
0 88 - - -
0 90 - - -
91 - - -
92 - - -
93 - - -
94 - - -
0 95 - - -
0 97 - - -
0 98 - - -
0 99 - - -
0 101 - - -
0 102 - - -
0 103 - - -
105 - - -
106 - - -
107 - - -
108 - - -
0 109 - - -
110 - - -
111 - - -
0 112 - - -
0 113 - - -
0 114 - - -
0 115 - - -
0 116 - - -
117 - - -
0 118 - - -
0 119 - - -
0 120 - - -
0 121 - - -
0 122 - - -
128 - - -
129 - - -
130 - - -
0 133 - - -
0 134 - - -
0 135 - - -
139 - - -
140 - - -
0 144 - - -
0 145 - - -
149 - - -
150 - - -
151 - - -
0 152 - - -
0 153 - - -
154 - - -
0 155 - - -
0 156 - - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
157 - - -
158 - - -
159 - - -
0 160 - - -
0 161 - - -
0 162 - - -
163 - - -
0 164 - - -
0 165 - - -
0 166 - - -
177 - - -
178 - - -
179 - - -
180 - - -
0 181 - - -
0 - - -
183 - - -
184 - - -
- - -
RINCIAN PROGRES BULANAN
A PEKERJAAN PERSIAPAN
1 Papan Proyek bh 1.00 500,000.00 500,000.00 0.03 1.00 500,000.00 0.03 100.00% - - - 0.00% 1.00 500,000.00 0.03 100.00%
B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik Eksisting Toilet M² 133.08 12,000.00 1,596,960.00 0.09 67.00 804,000.00 0.05 50.35% 21.08 252,960.00 0.02 15.84% 88.08 1,056,960.00 0.06 66.19%
2 Pembongkaran Dinding Keramik Eksisting Toilet M² 368.20 12,000.00 4,418,400.00 0.26 140.00 1,680,000.00 0.10 38.02% 56.20 674,400.00 0.04 15.26% 196.20 2,354,400.00 0.14 53.29%
3 Pembongkaran Plafond Eksisting Toilet M² 118.08 12,000.00 1,416,960.00 0.08 68.00 816,000.00 0.05 57.59% 50.08 600,960.00 0.04 42.41% 118.08 1,416,960.00 0.08 100.00%
4 Pembongkaran Lisplank Atap Eksisting M² 820.00 20,000.00 16,400,000.00 0.97 376.00 7,520,000.00 0.45 45.85% 444.00 8,880,000.00 0.53 54.15% 820.00 16,400,000.00 0.97 100.00%
5 Pembongkaran Plafond Eksisting Drop off utama M² 88.00 12,000.00 1,056,000.00 0.06 88.00 1,056,000.00 0.06 100.00% - - - 0.00% 88.00 1,056,000.00 0.06 100.00%
D PEKERJAAN PLAFOND
1 Pemasangan Rangka Hollow 40x40 M² 206.08 211,490.00 43,583,859.20 2.59 156.00 32,992,440.00 1.96 75.70% 50.08 10,591,419.20 0.63 24.30% 206.08 43,583,859.20 2.59 100.00%
2 Plafond Calciboard (3,5mm) M² 206.08 73,279.00 15,101,336.32 0.90 156.00 11,431,524.00 0.68 75.70% 50.08 3,669,812.32 0.22 24.30% 206.08 15,101,336.32 0.90 100.00%
3 Cat Plafond M² 206.08 34,979.00 7,208,472.32 0.43 - - - 0.00% 206.08 7,208,472.32 0.43 100.00% 206.08 7,208,472.32 0.43 100.00%
E PEKERJAAN PENGECATAN
1 Lantai 1
- Cat Tembok Exterior Weather Shield M² 1,062.92 38,340.00 40,752,352.80 2.42 1,062.92 40,752,352.80 2.42 100.00% - - - 0.00% 1,062.92 40,752,352.80 2.42 100.00%
2 Lantai 2 -
- Cat Tembok Exterior Weather Shield M² 1,364.72 38,340.00 52,323,364.80 3.11 1,364.72 52,323,364.80 3.11 100.00% - - - 0.00% 1,364.72 52,323,364.80 3.11 100.00%
3 Cat Kusen & Daun Pintu Jendela (Exterior) M² 189.25 47,230.00 8,938,277.50 0.53 - - - - 189.25 8,938,277.50 0.53 100.00% 189.25 8,938,277.50 0.53 100.00%
J. PEKERJAAN SANITASI
1 Tandon Air Bersih Type: Silinder Kapasitas: 2.200 Liter Unit 2.00 4,962,459.43 9,924,918.86 0.59 - - - 0.00% 2.00 9,924,918.86 0.59 100.00% 2.00 9,924,918.86 0.59 100.00%
2 Sanitair Fixture
Lantai 1
- Pemasangan Toilet Duduk Setara TOTO Buah 1.00 4,951,184.00 4,951,184.00 0.29 1.00 4,951,184.00 0.29 100.00% - - - 0.00% 1.00 4,951,184.00 0.29 100.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 7.00 822,269.00 5,755,883.00 0.34 7.00 5,755,883.00 0.34 100.00% - - - 0.00% 7.00 5,755,883.00 0.34 100.00%
- Floor drain Buah 10.00 466,424.00 4,664,240.00 0.28 10.00 4,664,240.00 0.28 100.00% - - - 0.00% 10.00 4,664,240.00 0.28 100.00%
- Kran Buah 14.00 285,180.00 3,992,520.00 0.24 8.00 2,281,440.00 0.14 57.14% 6.00 1,711,080.00 0.10 42.86% 14.00 3,992,520.00 0.24 100.00%
- Washtavel Toto Buah 2.00 1,688,029.00 3,376,058.00 0.20 1.00 1,688,029.00 0.10 50.00% 1.00 1,688,029.00 0.10 50.00% 2.00 3,376,058.00 0.20 100.00%
Lantai 2
- Pemasangan Toilet Duduk Setara TOTO Buah 3.00 4,951,184.00 14,853,552.00 0.88 - - - 0.00% 3.00 14,853,552.00 0.88 100.00% 3.00 14,853,552.00 0.88 100.00%
- Pemasangan Toilet Jongkok Setara TOTO Buah 5.00 822,269.00 4,111,345.00 0.24 4.00 3,289,076.00 0.20 80.00% 1.00 822,269.00 0.05 20.00% 5.00 4,111,345.00 0.24 100.00%
- Floor drain Buah 12.00 466,424.00 5,597,088.00 0.33 12.00 5,597,088.00 0.33 100.00% - - - 0.00% 12.00 5,597,088.00 0.33 100.00%
- Kran Buah 18.00 285,180.00 5,133,240.00 0.30 - - - 0.00% 18.00 5,133,240.00 0.30 100.00% 18.00 5,133,240.00 0.30 100.00%
- Washtavel Toto Buah 4.00 1,688,029.00 6,752,116.00 0.40 - - - 0.00% 4.00 6,752,116.00 0.40 100.00% 4.00 6,752,116.00 0.40 100.00%
2 Instalasi Air Bersih
Lantai 1
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .32 M' 80.00 50,000.00 4,000,000.00 0.24 - - - 0.00% 80.00 4,000,000.00 0.24 100.00% 80.00 4,000,000.00 0.24 100.00%
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% 40.00 1,400,000.00 0.08 100.00% 40.00 1,400,000.00 0.08 100.00%
- Dia .20 M' 100.00 25,000.00 2,500,000.00 0.15 50.00 1,250,000.00 0.07 50.00% 50.00 1,250,000.00 0.07 50.00% 100.00 2,500,000.00 0.15 100.00%
Lantai 2
- Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- Dia .25 M' 40.00 35,000.00 1,400,000.00 0.08 - - - 0.00% 40.00 1,400,000.00 0.08 100.00% 40.00 1,400,000.00 0.08 100.00%
- Dia .20 M' 120.00 25,000.00 3,000,000.00 0.18 60.00 1,500,000.00 0.09 50.00% 60.00 1,500,000.00 0.09 50.00% 120.00 3,000,000.00 0.18 100.00%
3 Instalasi Air Kotor
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
Lantai 1
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 70.00 105,000.00 7,350,000.00 0.44 70.00 7,350,000.00 0.44 100.00% - - - 0.00% 70.00 7,350,000.00 0.44 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
Lantai 2
- Pipa PVC AW dia 100 mm ( pipa air kotor) M' 130.00 105,000.00 13,650,000.00 0.81 130.00 13,650,000.00 0.81 100.00% - - - 0.00% 130.00 13,650,000.00 0.81 100.00%
- CO, dia. 100 Buah 4.00 250,000.00 1,000,000.00 0.06 4.00 1,000,000.00 0.06 100.00% - - - 0.00% 4.00 1,000,000.00 0.06 100.00%
KONTRAK S/d Bulan Lalu Bulan Ini S/d Bulan Ini
NO URAIAN HARGA SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
SAT VOLUME ( Rp. ) ( Rp. ) (%) VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek. VOLUME ( Rp. ) (%) thd pek.
K. PEKERJAAN LAINNYA
1 Perbaikan Papan Nama Polres (Halaman Depan) Ls 1.00 18,000,000.00 18,000,000.00 1.07 1.00 18,000,000.00 1.07 100.00% - - - 0.00% 1.00 18,000,000.00 1.07 100.00%
2 Perbaikan Papan Nama Polres (Gedung Utama) Ls 1.00 36,000,000.00 36,000,000.00 2.14 1.00 36,000,000.00 2.14 100.00% - - - 0.00% 1.00 36,000,000.00 2.14 100.00%
A. JUMLAH BIAYA 1,683,636,346.77 100.00 1,258,196,827.48 74.73 422,835,519.29 25.11 1,681,032,346.77 99.85
B. PPN 10 % ( A X 10 % ) 168,363,634.68 125,819,682.75 42,283,551.93 168,103,234.68
C. JUMLAH (A + B ) 1,851,999,981.45 1,384,016,510.23 465,119,071.22 1,849,135,581.45
D. DIBULATKAN 1,851,999,000.00 1,384,016,000.00 465,119,000.00 1,849,135,000.00
0 27 - -
28 - -
29 - -
30 - -
31 - -
0 32 - - #REF!
36 - -
0 37 - - #REF!
41 - -
42 - -
43 - -
44 - #REF!
43 46 4 5 7 5 6 6 7 40.00 #REF!
62 49 10 10 8 8 8 9 9 62.00 #REF!
52 - -
53 - -
54 - -
55 - -
56 - -
0 57 - -
0 58 - -
0 59 - #REF!
61 - 77.50
0 62 - #REF!
18 64 8.00 10 18.00 (250.00)
250 65 22.00 44 26 28 40.00 42 48 250.00 #REF!
67 - -
68 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
69 - -
70 - -
71 - -
72 - -
0 73 - -
74 - -
0 75 - #REF!
78 - -
0 79 - -
0 80 - -
0 81 - -
82 - -
0 83 - -
0 84 - -
0 85 - -
0 86 - -
0 87 - -
0 88 - #REF!
0 90 - -
91 - -
92 - -
93 - -
94 - -
0 95 - #REF!
0 97 - -
0 98 - -
0 99 - #REF!
0 101 - -
0 102 - -
0 103 - #REF!
105 - -
106 - -
107 - -
108 - 2.00
0 109 - -
110 - -
111 - -
0 112 - -
0 113 - -
0 114 - 6.00
0 115 - 1.00
0 116 - -
117 - 3.00
0 118 - (3.00)
4 119 2 2 4.00 (20.00)
20 120 10 10 20.00 18.00
0 121 - 4.00
0 122 - #REF!
128 - -
129 - -
130 - #REF!
0 133 - 40.00
0 134 - 50.00
0 135 - #REF!
139 - -
140 - #REF!
0 144 - 40.00
20 145 20 20.00 #REF!
149 - -
150 - -
151 - -
152 - -
153 - -
154 - -
155 - -
156 - -
1 Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Total PERIODE MINGGU KE -
157 - -
158 - -
159 - -
160 - -
161 - -
162 - -
163 - 25.00
164 - 8.00
165 - 1.00
166 - #REF!
177 - -
178 - -
179 - -
180 - -
181 - #REF!
183 - -
184 - -
- -
TIME SCHEDULE BULAN JUNI
PROGRESS
Minggu ke - (%)
NO. URAIAN PEKERJAAN HARGA ( Rp.) Bobot ( % )
I II III IV V VI VII VIII
Chart Title
II. PEKERJAAN GALIAN, PASIR DAN TANAH 10,693,620.00 6.05 2.02 2.02 2.02 50
III. PEKERJAAN BETON DAN PAVING BLOCK 159,880,149.48 90.52 18.10 18.10 18.10 18.10 18.10 0
PROGRESS
Minggu ke - (%)
NO. URAIAN PEKERJAAN HARGA ( Rp.) Bobot ( % )
I II III IV V VI VII VIII
Chart Title
I. PEKERJAAN PENDAHULUAN 6,050,000.00 3.43 3.43 100
II. PEKERJAAN GALIAN, PASIR DAN TANAH 10,693,620.00 6.05 2.02 2.02 2.02 50
III. PEKERJAAN BETON DAN PAVING BLOCK 159,880,149.48 90.52 18.10 18.10 18.10 18.10 18.10 0
PROGRESS
Minggu ke - (%)
NO. URAIAN PEKERJAAN HARGA ( Rp.) Bobot ( % )
I II III IV V VI VII VIII
II. PEKERJAAN GALIAN, PASIR DAN TANAH 10,693,620.00 6.05 2.02 2.02 2.02 50
III. PEKERJAAN BETON DAN PAVING BLOCK 159,880,149.48 90.52 18.10 18.10 18.10 18.10 18.10 0
WA ODE RAHMIN, ST
Direktris
RINCIAN PROGRES MINGGUAN
NAMA PROGRAM : PENINGKATAN SARANA DAN PASARANA PENDIDIKAN : 2 ( DUA )
MINGGU KE
KEGIATAN : PEMBANGUNAN PRASARANA SDN 014 PENAJAM PERIODE : 26 JUNI 2017 s/d 30 JUNI 2017
LOKASI : KECAMATAN PENAJAM TAHUN ANGGARAN : 2017
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
IV PEKERJAAN PASANGAN
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 - - 0% - - 0% - - - 0%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 - - 0% - - 0% - - - 0%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - 0% - - 0% - - - 0%
57,517,398.91 5.34 - - - - - -
V PEKERJAAN KAYU
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 - - 0% - - 0% - - - 0%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 - - 0% - - 0% - - - 0%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - 0% - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - 0% - - 0% - - - 0%
11,660,440.93 1.08 - - - - - -
VI. PEKERJAAN BETON
1 SLOOF 15/20
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% - - - 0% - - - 0%
2 KOLOM PRAKTIS
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 - - 0% - - 0% - - - 0%
5 CANOPY
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - 0% - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - 0% - - 0% - - - 0%
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% - - - 0% - - - 0%
36,932,777.55 3.43 - - - - - -
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
X. PEKERJAAN LANTAI
1 Pasang Lantai Keramik 40x40 cm M2 54.86 251,350.54 13,789,090.62 1.28 - - - 0% - - - 0% - - - 0%
2 Plint Keramik Ruangan M2 29.75 34,103.94 1,014,592.22 0.09 - - - 0% - - - 0% - - - 0%
3 Pasang Lantai Keramik Kasar 40x40 cm Teras M2 4.70 237,639.93 1,117,858.23 0.10 - - - 0% - - - 0% - - - 0%
15,921,541.07 1.48 - - - - - -
Disetujui Oleh,
DINAS PENDIDIKAN PEMUDA DAN Diperiksa Oleh, Dibuat Oleh,
OLAHRAGA Konsultan Pengawas Kontraktor Pelaksana
KAB. PENAJAM PASER UTARA CV. BUANA LESTARI CV. PRIMA EKA CIPTA
Pengawas Lapangan
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
IV PEKERJAAN PASANGAN
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 - - 0% - - 0% - - - 0%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 - - 0% - - 0% - - - 0%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - 0% - - 0% - - - 0%
57,517,398.91 5.34 - - - - - -
V PEKERJAAN KAYU
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 - - 0% - - 0% - - - 0%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 - - 0% - - 0% - - - 0%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - 0% - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - 0% - - 0% - - - 0%
11,660,440.93 1.08 - - - - - -
VI. PEKERJAAN BETON
1 SLOOF 15/20
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% - - - 0% - - - 0%
2 KOLOM PRAKTIS
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 - - 0% - - 0% - - - 0%
5 CANOPY
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - 0% - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - 0% - - 0% - - - 0%
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% - - - 0% - - - 0%
36,932,777.55 3.43 - - - - - -
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
X. PEKERJAAN LANTAI
1 Pasang Lantai Keramik 40x40 cm M2 54.86 251,350.54 13,789,090.62 1.28 - - - 0% - - - 0% - - - 0%
2 Plint Keramik Ruangan M2 29.75 34,103.94 1,014,592.22 0.09 - - - 0% - - - 0% - - - 0%
3 Pasang Lantai Keramik Kasar 40x40 cm Teras M2 4.70 237,639.93 1,117,858.23 0.10 - - - 0% - - - 0% - - - 0%
15,921,541.07 1.48 - - - - - -
Disetujui Oleh,
DINAS PENDIDIKAN PEMUDA DAN OLAHRAGA Diperiksa Oleh, Dibuat Oleh,
KAB. PENAJAM PASER UTARA Konsultan Pengawas Kontraktor Pelaksana
Pengawas Lapangan CV. BUANA LESTARI CV. PRIMA EKA CIPTA
TAHUN 2017
120(Seratus Dua Puluh) Hari Kalender
NO. JENIS PEKERJAAN BOBOT (%) BULAN /I MINGGU KE- KET
JUNI JULI AGUSTUS SEPTEMBER OKTOBER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
tgl 19-25 26-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-30 1-7 8-16
A PEMBANGUNAN RKB
I PEKERJAAN PERSIAPAN 0.28 0.28 100%
II PEKERJAAN TANAH 3.02 0.50 0.50 0.80 1.22
III PEKERJAAN PONDASI 7.84 1.00 1.00 2.00 3.84
IV PEKERJAAN PASANGAN 8.96 1.00 1.00 1.00 0.50 5.46
V PEKERJAAN KAYU 5.56 0.20 5.00 0.20 0.16
VI PEKERJAAN STRUKTUR 12.86 1.00 2.00 3.00 5.00 1.86 -
VII PEKERJAAN PENUTUP ATAP 11.20 6.00 4.00 1.20 -
VIII PEKERJAAN PLAFOND 8.59 1.00 4.50 3.09 - -
IX PEKERJAAN KUNCI DAN KACA 0.95 0.60 0.35
X PEKERJAAN LANTAI 6.41 1.00 5.00 0.41
XI PEKERJAAN CAT-CATAN 5.35 4.00 1.20 0.15 -
B PEMBANGUNAN PERPUSTAKAAN
I PEKERJAAN PERSIAPAN 0.19 0.19
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
IV PEKERJAAN PASANGAN
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 - - 0% - - 0% - - - 0%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 - - 0% - - 0% - - - 0%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - 0% - - 0% - - - 0%
57,517,398.91 5.34 - - - - - -
V PEKERJAAN KAYU
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 - - 0% - - 0% - - - 0%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 - - 0% - - 0% - - - 0%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - 0% - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - 0% - - 0% - - - 0%
11,660,440.93 1.08 - - - - - -
VI. PEKERJAAN BETON
1 SLOOF 15/20
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% - - - 0% - - - 0%
2 KOLOM PRAKTIS
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 - - 0% - - 0% - - - 0%
5 CANOPY
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - 0% - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - 0% - - 0% - - - 0%
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% - - - 0% - - - 0%
36,932,777.55 3.43 - - - - - -
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
X. PEKERJAAN LANTAI
1 Pasang Lantai Keramik 40x40 cm M2 54.86 251,350.54 13,789,090.62 1.28 - - - 0% - - - 0% - - - 0%
2 Plint Keramik Ruangan M2 29.75 34,103.94 1,014,592.22 0.09 - - - 0% - - - 0% - - - 0%
3 Pasang Lantai Keramik Kasar 40x40 cm Teras M2 4.70 237,639.93 1,117,858.23 0.10 - - - 0% - - - 0% - - - 0%
15,921,541.07 1.48 - - - - - -
Disetujui Oleh,
DINAS PENDIDIKAN PEMUDA DAN OLAHRAGA Diperiksa Oleh, Dibuat Oleh,
KAB. PENAJAM PASER UTARA Konsultan Pengawas Kontraktor Pelaksana
Pengawas Lapangan CV. BUANA LESTARI CV. PRIMA EKA CIPTA
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
-
B. PEMBANGUNAN PERPUSTAKAAN SDN 014 PENAJAM -
I PEKERJAAN PERSIAPAN -
1 Pembongkaran Bh 1.00 550,000.00 550,000.00 0.05 1.00 550,000.00 0.05 100% - - 0% 1.00 550,000.00 0.05 100%
2 Pemasangan Bowplank ls 1.00 1,500,000.00 1,500,000.00 0.14 1.00 1,500,000.00 0.14 100% - - - 0% 1.00 1,500,000.00 0.14 100%
Jumlah 2,050,000.00 0.19 - 2,050,000.00 0.19 - - 2,050,000.00 0.19
II PEKERJAAN TANAH -
1 Galian Tanah Biasa M3 30.016 83,384.00 2,502,854.14 0.23 12.01 1,001,141.66 0.09 40% 18.01 1,501,712.49 0.14 60% 30.02 2,502,854.14 0.23 100%
2 Urugan Tanah Kembali M3 9.005 27,794.67 250,285.44 0.02 - - - 0% - - 0% - - - 0%
3 Urugan Tanah M3 25.300 193,101.44 4,885,389.19 0.45 - - - 0% - - - 0% - - - 0%
4 Urugan Pasir Bawah Lantai M3 4.229 147,839.55 625,250.42 0.06 - - - 0% - - 0% - - - 0%
5 Urugan Pasir Bawah Pondasi M3 1.876 147,839.55 277,347.00 0.03 0.75 110,938.80 0.01 40% 1.13 167,058.69 0.02 60% 1.88 277,997.49 0.03 100%
8,541,126.19 0.79 - 1,112,080.46 0.10 1,668,771.18 0.15 2,780,851.63 0.26
III PEKERJAAN PONDASI -
1 Pasangan Pondasi Batu Gunung Camp 1:4 M3 17.82 1,004,855.99 17,908,543.45 1.66 - - - 0% 5.35 5,372,563.04 0.50 30% 5.35 5,372,563.04 0.50 30%
2 Pasangan pondasi keliling bangunan M3 5.37 1,004,855.99 5,397,583.95 0.50 - - - 0% - - 0% - - - 0%
3 Pasangan Batu Kosong M3 7.50 576,800.40 4,328,310.20 0.40 - - - 0% 2.25 1,298,493.06 0.12 30% 2.25 1,298,493.06 0.12 30%
4 Pancang Ulin 8 / 8 x 100 jarak 100 cm Ttk 47.00 119,190.40 5,601,948.80 0.52 18.80 2,240,779.52 0.21 40% 18.80 2,240,779.52 0.21 40% 37.60 4,481,559.04 0.42 80%
33,236,386.41 3.08 - 2,240,779.52 0.21 8,911,835.62 0.83 11,152,615.14 1.04
-
IV PEKERJAAN PASANGAN -
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 - - - 0% - - 0% - - - 0%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 - - - 0% - - 0% - - - 0%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - - 0% - - 0% - - - 0%
57,517,398.91 5.34 - - - - - - -
V PEKERJAAN KAYU -
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 - - - 0% - - 0% - - - 0%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 - - - 0% - - 0% - - - 0%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - - 0% - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - - 0% - - 0% - - - 0%
11,660,440.93 1.08 - - - - - - -
VI. PEKERJAAN BETON -
1 SLOOF 15/20 -
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% - - - 0% - - - 0%
-
2 KOLOM PRAKTIS -
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 - - - 0% - - 0% - - - 0%
-
3 KOLOM (K1) 20/20 -
- Pasang Begesting M2 3.04 125,631.07 381,918.45 0.04 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 36.81 17,463.94 642,890.38 0.06 - - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 0.30 1,492,238.06 453,640.37 0.04 - - - 0% - - - 0% - - - 0%
-
4 RING BALOK 15/20 - - -
- Pasang Begesting M2 10.30 176,515.91 1,818,113.87 0.17 - - - 0% - - 0% - - - 0%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% - - - 0% - - - 0%
-
5 CANOPY -
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - - 0% - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - - 0% - - 0% - - - 0%
-
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% - - - 0% - - - 0%
36,932,777.55 3.43 - - - - - - -
-
VII. PEKERJAAN PENUTUP ATAP -
1 Pasang Rangka Baja Ringan & Atap Genteng Metal M2 106.90 301,461.19 32,224,693.91 2.99 - - - 0% - - 0% - - - 0%
2 Pasang Bubungan M1 40.13 101,624.96 4,078,209.64 0.38 - - - 0% - - 0% - - - 0%
36,302,903.55 3.37 - - - - - - -
-
VIII. PEKERJAAN PLAFOND -
1 List Plafond Gypsum Profil m1 92.80 49,997.64 4,639,780.99 0.43 - - - 0% - - 0% - - - 0%
2 Plafond Calsiboart t=4mm + Rangka Besi Hollow M2 100.99 233,251.77 23,556,679.38 2.19 - - - 0% - - - 0% - - - 0%
28,196,460.37 2.62 - - - - - - -
-
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
Disetujui Oleh,
DINAS PENDIDIKAN PEMUDA DAN OLAHRAGA Diperiksa Oleh, Dibuat Oleh,
KAB. PENAJAM PASER UTARA Konsultan Pengawas Kontraktor Pelaksana
Pengawas Lapangan CV. BUANA LESTARI CV. PRIMA EKA CIPTA
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
-
B. PEMBANGUNAN PERPUSTAKAAN SDN 014 PENAJAM -
I PEKERJAAN PERSIAPAN -
1 Pembongkaran Bh 1.00 550,000.00 550,000.00 0.05 1.00 550,000.00 0.05 100% - - - 0% 1.00 550,000.00 0.05 100%
2 Pemasangan Bowplank ls 1.00 1,500,000.00 1,500,000.00 0.14 1.00 1,500,000.00 0.14 100% - - - 0% 1.00 1,500,000.00 0.14 100%
Jumlah 2,050,000.00 0.19 - 2,050,000.00 0.19 - - 2,050,000.00 0.19
II PEKERJAAN TANAH -
1 Galian Tanah Biasa M3 30.016 83,384.00 2,502,854.14 0.23 30.02 2,502,854.14 0.23 100% - - 0% 30.02 2,502,854.14 0.23 100%
2 Urugan Tanah Kembali M3 9.005 27,794.67 250,285.44 0.02 - - - 0% - - 0% - - - 0%
3 Urugan Tanah M3 25.300 193,101.44 4,885,389.19 0.45 - - - 0% - - - 0% - - - 0%
4 Urugan Pasir Bawah Lantai M3 4.229 147,839.55 625,250.42 0.06 - - - 0% - - - 0% - - - 0%
5 Urugan Pasir Bawah Pondasi M3 1.876 147,839.55 277,347.00 0.03 1.88 277,997.49 0.03 100% - - - 0% 1.88 277,997.49 0.03 100%
8,541,126.19 0.79 - 2,780,851.63 0.26 - - 2,780,851.63 0.26
III PEKERJAAN PONDASI -
1 Pasangan Pondasi Batu Gunung Camp 1:4 M3 17.82 1,004,855.99 17,908,543.45 1.66 5.35 5,372,563.04 0.50 30% 5.35 5,372,563.04 0.50 30% 10.69 10,745,126.07 1.00 60%
2 Pasangan pondasi keliling bangunan M3 5.37 1,004,855.99 5,397,583.95 0.50 - - - 0% - - 0% - - - 0%
3 Pasangan Batu Kosong M3 7.50 576,800.40 4,328,310.20 0.40 2.25 1,298,493.06 0.12 30% 2.25 1,298,493.06 0.12 30% 4.50 2,596,986.12 0.24 60%
4 Pancang Ulin 8 / 8 x 100 jarak 100 cm Ttk 47.00 119,190.40 5,601,948.80 0.52 37.60 4,481,559.04 0.42 80% - - - 0% 37.60 4,481,559.04 0.42 80%
33,236,386.41 3.08 - 11,152,615.14 1.04 6,671,056.10 0.62 17,823,671.23 1.65
-
IV PEKERJAAN PASANGAN -
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 - - - 0% - - - 0% - - - 0%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 - - - 0% - - 0% - - - 0%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - - 0% - - 0% - - - 0%
57,517,398.91 5.34 - - - - - - -
V PEKERJAAN KAYU -
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 - - - 0% - - 0% - - - 0%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 - - - 0% - - 0% - - - 0%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - - 0% - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - - 0% - - 0% - - - 0%
11,660,440.93 1.08 - - - - - - -
VI. PEKERJAAN BETON -
1 SLOOF 15/20 -
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% 75.29 1,314,772.85 0.12 30% 75.29 1,314,772.85 0.12 30%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% - - - 0% - - - 0%
-
2 KOLOM PRAKTIS -
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 - - - 0% - - 0% - - - 0%
-
3 KOLOM (K1) 20/20 -
- Pasang Begesting M2 3.04 125,631.07 381,918.45 0.04 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 36.81 17,463.94 642,890.38 0.06 - - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 0.30 1,492,238.06 453,640.37 0.04 - - - 0% - - - 0% - - - 0%
-
4 RING BALOK 15/20 - - -
- Pasang Begesting M2 10.30 176,515.91 1,818,113.87 0.17 - - - 0% - - 0% - - - 0%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% - - - 0% - - - 0%
-
5 CANOPY -
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - - 0% - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - - 0% - - 0% - - - 0%
-
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% - - - 0% - - - 0%
36,932,777.55 3.43 - - - 1,314,772.85 0.12 1,314,772.85 0.12
-
VII. PEKERJAAN PENUTUP ATAP -
1 Pasang Rangka Baja Ringan & Atap Genteng Metal M2 106.90 301,461.19 32,224,693.91 2.99 - - - 0% - - 0% - - - 0%
2 Pasang Bubungan M1 40.13 101,624.96 4,078,209.64 0.38 - - - 0% - - 0% - - - 0%
36,302,903.55 3.37 - - - - - - -
-
VIII. PEKERJAAN PLAFOND -
1 List Plafond Gypsum Profil m1 92.80 49,997.64 4,639,780.99 0.43 - - - 0% - - 0% - - - 0%
2 Plafond Calsiboart t=4mm + Rangka Besi Hollow M2 100.99 233,251.77 23,556,679.38 2.19 - - - 0% - - - 0% - - - 0%
28,196,460.37 2.62 - - - - - - -
-
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
Disetujui Oleh,
DINAS PENDIDIKAN PEMUDA DAN OLAHRAGA Diperiksa Oleh, Dibuat Oleh,
KAB. PENAJAM PASER UTARA Konsultan Pengawas Kontraktor Pelaksana
Pengawas Lapangan CV. BUANA LESTARI CV. PRIMA EKA CIPTA
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
-
B. PEMBANGUNAN PERPUSTAKAAN SDN 014 PENAJAM -
I PEKERJAAN PERSIAPAN -
1 Pembongkaran Bh 1.00 550,000.00 550,000.00 0.05 1.00 550,000.00 0.05 100% - - 0% 1.00 550,000.00 0.05 100%
2 Pemasangan Bowplank ls 1.00 1,500,000.00 1,500,000.00 0.14 1.00 1,500,000.00 0.14 100% - - 0% 1.00 1,500,000.00 0.14 100%
Jumlah 2,050,000.00 0.19 - 2,050,000.00 0.19 - - 2,050,000.00 0.19
II PEKERJAAN TANAH -
1 Galian Tanah Biasa M3 30.016 83,384.00 2,502,854.14 0.23 30.02 2,502,854.14 0.23 100% - - 0% 30.02 2,502,854.14 0.23 100%
2 Urugan Tanah Kembali M3 9.005 27,794.67 250,285.44 0.02 - - - 0% - - 0% - - - 0%
3 Urugan Tanah M3 25.300 193,101.44 4,885,389.19 0.45 - - - 0% - - 0% - - - 0%
4 Urugan Pasir Bawah Lantai M3 4.229 147,839.55 625,250.42 0.06 - - - 0% - - 0% - - - 0%
5 Urugan Pasir Bawah Pondasi M3 1.876 147,839.55 277,347.00 0.03 1.88 277,997.49 0.03 100% - - 0% 1.88 277,997.49 0.03 100%
8,541,126.19 0.79 - 2,780,851.63 0.26 - - 2,780,851.63 0.26
III PEKERJAAN PONDASI -
1 Pasangan Pondasi Batu Gunung Camp 1:4 M3 17.82 1,004,855.99 17,908,543.45 1.66 10.69 10,745,126.07 1.00 60% 7.13 7,163,417.38 0.66 40% 17.82 17,908,543.45 1.66 100%
2 Pasangan pondasi keliling bangunan M3 5.37 1,004,855.99 5,397,583.95 0.50 - - - 0% - - 0% - - - 0%
3 Pasangan Batu Kosong M3 7.50 576,800.40 4,328,310.20 0.40 4.50 2,596,986.12 0.24 60% 3.00 1,731,324.08 0.16 40% 7.50 4,328,310.20 0.40 100%
4 Pancang Ulin 8 / 8 x 100 jarak 100 cm Ttk 47.00 119,190.40 5,601,948.80 0.52 37.60 4,481,559.04 0.42 80% 9.40 1,120,389.76 0.10 20% 47.00 5,601,948.80 0.52 100%
33,236,386.41 3.08 - 17,823,671.23 1.65 10,015,131.22 0.93 27,838,802.46 2.58
-
IV PEKERJAAN PASANGAN -
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 - - - 0% 33.06 4,854,601.31 0.45 20% 33.06 4,854,601.31 0.45 20%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 - - - 0% - - 0% - - - 0%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - - 0% - - 0% - - - 0%
57,517,398.91 5.34 - - - 4,854,601.31 0.45 4,854,601.31 0.45
V PEKERJAAN KAYU -
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 - - - 0% - - 0% - - - 0%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 - - - 0% - - 0% - - - 0%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - - 0% - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - - 0% - - 0% - - - 0%
11,660,440.93 1.08 - - - - - - -
VI. PEKERJAAN BETON -
1 SLOOF 15/20 -
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 - - - 0% 10.30 1,294,000.02 0.12 100% 10.30 1,294,000.02 0.12 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 75.29 1,314,772.85 0.12 30% 175.67 3,067,803.31 0.28 70% 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% 1.55 2,305,507.80 0.21 100% 1.55 2,305,507.80 0.21 100%
-
2 KOLOM PRAKTIS -
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 - - - 0% - - 0% - - - 0%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 - - - 0% 306.99 5,361,209.67 0.50 100% 306.99 5,361,209.67 0.50 100%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 - - - 0% - - 0% - - - 0%
-
3 KOLOM (K1) 20/20 -
- Pasang Begesting M2 3.04 125,631.07 381,918.45 0.04 - - - 0% - - 0% - - - 0%
- Pembesian Kg 36.81 17,463.94 642,890.38 0.06 - - - 0% 36.81 642,890.38 0.06 100% 36.81 642,890.38 0.06 100%
- Cor Beton Camp 1:2:3 M3 0.30 1,492,238.06 453,640.37 0.04 - - - 0% - - 0% - - - 0%
-
4 RING BALOK 15/20 - -
- Pasang Begesting M2 10.30 176,515.91 1,818,113.87 0.17 - - - 0% - - 0% - - - 0%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% - - - 0% - - - 0%
-
5 CANOPY -
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - - 0% - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - - 0% - - 0% - - - 0%
-
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% - - - 0% - - - 0%
36,932,777.55 3.43 - 1,314,772.85 0.12 12,671,411.19 1.18 13,986,184.04 1.30
-
VII. PEKERJAAN PENUTUP ATAP -
1 Pasang Rangka Baja Ringan & Atap Genteng Metal M2 106.90 301,461.19 32,224,693.91 2.99 - - - 0% - - 0% - - - 0%
2 Pasang Bubungan M1 40.13 101,624.96 4,078,209.64 0.38 - - - 0% - - 0% - - - 0%
36,302,903.55 3.37 - - - - - - -
-
VIII. PEKERJAAN PLAFOND -
1 List Plafond Gypsum Profil m1 92.80 49,997.64 4,639,780.99 0.43 - - - 0% - - 0% - - - 0%
2 Plafond Calsiboart t=4mm + Rangka Besi Hollow M2 100.99 233,251.77 23,556,679.38 2.19 - - - 0% - - - 0% - - - 0%
28,196,460.37 2.62 - - - - - - -
-
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
Disetujui Oleh,
DINAS PENDIDIKAN PEMUDA DAN OLAHRAGA Diperiksa Oleh, Dibuat Oleh,
KAB. PENAJAM PASER UTARA Konsultan Pengawas Kontraktor Pelaksana
Pengawas Lapangan CV. BUANA LESTARI CV. PRIMA EKA CIPTA
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
- -
B. PEMBANGUNAN PERPUSTAKAAN SDN 014 PENAJAM - -
I PEKERJAAN PERSIAPAN - -
1 Pembongkaran Bh 1.00 550,000.00 550,000.00 0.05 - - - 0% 1.00 550,000.00 0.05 100% 1.00 550,000.00 0.05 100%
2 Pemasangan Bowplank ls 1.00 1,500,000.00 1,500,000.00 0.14 - - - 0% 1.00 1,500,000.00 0.14 100% 1.00 1,500,000.00 0.14 100%
Jumlah 2,050,000.00 0.19 - - - - 2,050,000.00 0.19 2,050,000.00 0.19
II PEKERJAAN TANAH - -
1 Galian Tanah Biasa M3 30.016 83,384.00 2,502,854.14 0.23 - - - 0% 30.02 2,502,854.14 0.23 100% 30.02 2,502,854.14 0.23 100%
2 Urugan Tanah Kembali M3 9.005 27,794.67 250,285.44 0.02 - - - 0% - - - 0% - - - 0%
3 Urugan Tanah M3 25.300 193,101.44 4,885,389.19 0.45 - - - 0% - - - 0% - - - 0%
4 Urugan Pasir Bawah Pondasi M3 4.229 147,839.55 625,250.42 0.06 - - - 0% - - - 0% - - - 0%
5 Urugan Pasir Bawah Lantai M3 1.876 147,839.55 277,347.00 0.03 - - - 0% 1.88 277,997.49 0.03 100% 1.88 277,997.49 0.03 100%
8,541,126.19 0.79 - - - - 2,780,851.63 0.26 2,780,851.63 0.26
III PEKERJAAN PONDASI - -
1 Pasangan Pondasi Batu Gunung Camp 1:4 M3 17.82 1,004,855.99 17,908,543.45 1.66 - - - 0% 17.82 17,908,543.45 1.66 100% 17.82 17,908,543.45 1.66 100%
2 Pasangan pondasi keliling bangunan M3 5.37 1,004,855.99 5,397,583.95 0.50 - - - 0% - - - 0% - - - 0%
3 Pasangan Batu Kosong M3 7.50 576,800.40 4,328,310.20 0.40 - - - 0% 7.50 4,328,310.20 0.40 100% 7.50 4,328,310.20 0.40 100%
4 Pancang Ulin 8 / 8 x 100 jarak 100 cm Ttk 47.00 119,190.40 5,601,948.80 0.52 - - - 0% 47.00 5,601,948.80 0.52 100% 47.00 5,601,948.80 0.52 100%
33,236,386.41 3.08 - - - - 27,838,802.46 2.58 27,838,802.46 2.58
- -
IV PEKERJAAN PASANGAN - -
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 - - - 0% 33.06 4,854,601.31 0.45 20% 33.06 4,854,601.31 0.45 20%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 - - - 0% - - - 0% - - - 0%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - - 0% - - - 0% - - - 0%
57,517,398.91 5.34 - - - - 4,854,601.31 0.45 4,854,601.31 0.45
V PEKERJAAN KAYU - -
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 - - - 0% - - - 0% - - - 0%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 - - - 0% - - - 0% - - - 0%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - - 0% - - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - - 0% - - - 0% - - - 0%
11,660,440.93 1.08 - - - - - - - -
VI. PEKERJAAN BETON - -
1 SLOOF 15/20 - -
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 - - - 0% 10.30 1,294,000.02 0.12 100% 10.30 1,294,000.02 0.12 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% 250.95 4,382,576.16 0.41 100% 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% 1.55 2,305,507.80 0.21 100% 1.55 2,305,507.80 0.21 100%
- -
2 KOLOM PRAKTIS - -
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 - - - 0% 306.99 5,361,209.67 0.50 100% 306.99 5,361,209.67 0.50 100%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 - - - 0% - - - 0% - - - 0%
- -
3 KOLOM (K1) 20/20 - -
- Pasang Begesting M2 3.04 125,631.07 381,918.45 0.04 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 36.81 17,463.94 642,890.38 0.06 - - - 0% 36.81 642,890.38 0.06 100% 36.81 642,890.38 0.06 100%
- Cor Beton Camp 1:2:3 M3 0.30 1,492,238.06 453,640.37 0.04 - - - 0% - - - 0% - - - 0%
- -
4 RING BALOK 15/20 - - -
- Pasang Begesting M2 10.30 176,515.91 1,818,113.87 0.17 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% - - - 0% - - - 0%
- -
5 CANOPY - -
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - - 0% - - - 0% - - - 0%
- -
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% - - - 0% - - - 0%
36,932,777.55 3.43 - - - - 13,986,184.04 1.30 13,986,184.04 1.30
- -
VII. PEKERJAAN PENUTUP ATAP - -
1 Pasang Rangka Baja Ringan & Atap Genteng Metal M2 106.90 301,461.19 32,224,693.91 2.99 - - - 0% - - - 0% - - - 0%
2 Pasang Bubungan M1 40.13 101,624.96 4,078,209.64 0.38 - - - 0% - - - 0% - - - 0%
36,302,903.55 3.37 - - - - - - - -
- -
VIII. PEKERJAAN PLAFOND - -
1 List Plafond Gypsum Profil m1 92.80 49,997.64 4,639,780.99 0.43 - - - 0% - - - 0% - - - 0%
2 Plafond Calsiboart t=4mm + Rangka Besi Hollow M2 100.99 233,251.77 23,556,679.38 2.19 - - - 0% - - - 0% - - - 0%
28,196,460.37 2.62 - - - - - - - -
- -
KONTRAK S/d Bulan Lalu Bulan Ini S/d Bulan Ini
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) (Rp. ) %) pek.
BAKTIAR, S. Pd
NIP. 1980102172006041009 RISKA YULIYANTO, ST ZAINUDDIN SIAR, ST
Site Enginer Site Manager
TIME SCHEDULE
NAMA PROGRAM : PENINGKATAN SARANA DAN PRASARANA PENDIDIKAN BULAN KE : III ( TIGA )
PEKERJAAN : PEMBANGUNAN PRASARANA SDN 014 PENAJAM PERIODE : AGUSTUS
NOMOR KONTRAK : 027/011/SPK/Disdikpora/2017 LOKASI : KEC. PENAJAM
TANGGAL : 19 JUNI 2017 TAHUN ANGGARAN : 2017
TAHUN 2017
120(Seratus Dua Puluh) Hari Kalender
NO. JENIS PEKERJAAN BOBOT (%) BULAN /I MINGGU KE- KET
JUNI JULI AGUSTUS SEPTEMBER OKTOBER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
tgl 19-25 26-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-30 1-7 8-16
A PEMBANGUNAN RKB
I PEKERJAAN PERSIAPAN 0.28 0.28 100%
II PEKERJAAN TANAH 3.02 0.50 0.50 0.80 1.22
III PEKERJAAN PONDASI 7.84 1.00 1.00 2.00 3.84
IV PEKERJAAN PASANGAN 8.96 1.00 1.00 1.00 0.50 5.46
V PEKERJAAN KAYU 5.56 0.20 5.00 0.20 0.16
VI PEKERJAAN STRUKTUR 12.86 1.00 2.00 3.00 5.00 1.86 -
VII PEKERJAAN PENUTUP ATAP 11.20 6.00 4.00 1.20 -
VIII PEKERJAAN PLAFOND 8.59 1.00 4.50 3.09 - -
IX PEKERJAAN KUNCI DAN KACA 0.95 0.60 0.35
X PEKERJAAN LANTAI 6.41 1.00 5.00 0.41
XI PEKERJAAN CAT-CATAN 5.35 4.00 1.20 0.15 -
B PEMBANGUNAN PERPUSTAKAAN
I PEKERJAAN PERSIAPAN 0.19 0.19
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
-
B. PEMBANGUNAN PERPUSTAKAAN SDN 014 PENAJAM -
I PEKERJAAN PERSIAPAN -
1 Pembongkaran Bh 1.00 550,000.00 550,000.00 0.05 1.00 550,000.00 0.05 100% - - 0% 1.00 550,000.00 0.05 100%
2 Pemasangan Bowplank ls 1.00 1,500,000.00 1,500,000.00 0.14 1.00 1,500,000.00 0.14 100% - - - 0% 1.00 1,500,000.00 0.14 100%
Jumlah 2,050,000.00 0.19 - 2,050,000.00 0.19 - - 2,050,000.00 0.19
II PEKERJAAN TANAH -
1 Galian Tanah Biasa M3 30.016 83,384.00 2,502,854.14 0.23 30.02 2,502,854.14 0.23 100% - - - 0% 30.02 2,502,854.14 0.23 100%
2 Urugan Tanah Kembali M3 9.005 27,794.67 250,285.44 0.02 - - - 0% - - - 0% - - - 0%
3 Urugan Tanah M3 25.300 193,101.44 4,885,389.19 0.45 - - - 0% - - - 0% - - - 0%
4 Urugan Pasir Bawah Lantai M3 4.229 147,839.55 625,250.42 0.06 - - - 0% - - - 0% - - - 0%
5 Urugan Pasir Bawah Pondasi M3 1.876 147,839.55 277,347.00 0.03 1.88 277,997.49 0.03 100% - - - 0% 1.88 277,997.49 0.03 100%
8,541,126.19 0.79 - 2,780,851.63 0.26 - - 2,780,851.63 0.26
III PEKERJAAN PONDASI -
1 Pasangan Pondasi Batu Gunung Camp 1:4 M3 17.82 1,004,855.99 17,908,543.45 1.66 17.82 17,908,543.45 1.66 100% - - - 0% 17.82 17,908,543.45 1.66 100%
2 Pasangan pondasi keliling bangunan M3 5.37 1,004,855.99 5,397,583.95 0.50 - - - 0% - - - 0% - - - 0%
3 Pasangan Batu Kosong M3 7.50 576,800.40 4,328,310.20 0.40 7.50 4,328,310.20 0.40 100% - - - 0% 7.50 4,328,310.20 0.40 100%
4 Pancang Ulin 8 / 8 x 100 jarak 100 cm Ttk 47.00 119,190.40 5,601,948.80 0.52 47.00 5,601,948.80 0.52 100% - - - 0% 47.00 5,601,948.80 0.52 100%
33,236,386.41 3.08 - 27,838,802.46 2.58 - - 27,838,802.46 2.58
-
IV PEKERJAAN PASANGAN -
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 33.06 4,854,601.31 0.45 20% 82.65 12,136,503.28 1.13 50% 115.71 16,991,104.59 1.58 70%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 - - - 0% - - - 0% - - - 0%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - - 0% - - 0% - - - 0%
57,517,398.91 5.34 - 4,854,601.31 0.45 12,136,503.28 1.13 16,991,104.59 1.58
V PEKERJAAN KAYU -
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 - - - 0% - - - 0% - - - 0%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 - - - 0% 15.00 1,125,000.00 0.10 100% 15.00 1,125,000.00 0.10 100%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - - 0% - - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - - 0% - - 0% - - - 0%
11,660,440.93 1.08 - - - 1,125,000.00 0.10 1,125,000.00 0.10
VI. PEKERJAAN BETON -
1 SLOOF 15/20 -
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 10.30 1,294,000.02 0.12 100% - - - 0% 10.30 1,294,000.02 0.12 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 250.95 4,382,576.16 0.41 100% - - - 0% 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 1.55 2,305,507.80 0.21 100% - - - 0% 1.55 2,305,507.80 0.21 100%
-
2 KOLOM PRAKTIS
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 - - - 0% 5.93 1,046,386.31 0.10 40% 5.93 1,046,386.31 0.10 40%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 306.99 5,361,209.67 0.50 100% - - - 0% 306.99 5,361,209.67 0.50 100%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 - - - 0% 0.39 574,989.17 0.05 40% 0.39 574,989.17 0.05 40%
-
3 KOLOM (K1) 20/20 -
- Pasang Begesting M2 3.04 125,631.07 381,918.45 0.04 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 36.81 17,463.94 642,890.38 0.06 36.81 642,890.38 0.06 100% - - - 0% 36.81 642,890.38 0.06 100%
- Cor Beton Camp 1:2:3 M3 0.30 1,492,238.06 453,640.37 0.04 - - - 0% - - - 0% - - - 0%
-
4 RING BALOK 15/20 - -
- Pasang Begesting M2 10.30 176,515.91 1,818,113.87 0.17 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% - - - 0% - - - 0%
-
5 CANOPY -
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - - 0% - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - - 0% - - 0% - - - 0%
-
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% - - - 0% - - - 0%
36,932,777.55 3.43 - 13,986,184.04 1.30 1,621,375.48 0.15 15,607,559.53 1.45
-
VII. PEKERJAAN PENUTUP ATAP -
1 Pasang Rangka Baja Ringan & Atap Genteng Metal M2 106.90 301,461.19 32,224,693.91 2.99 - - - 0% - - 0% - - - 0%
2 Pasang Bubungan M1 40.13 101,624.96 4,078,209.64 0.38 - - - 0% - - 0% - - - 0%
36,302,903.55 3.37 - - - - - - -
-
VIII. PEKERJAAN PLAFOND -
1 List Plafond Gypsum Profil m1 92.80 49,997.64 4,639,780.99 0.43 - - - 0% - - 0% - - - 0%
2 Plafond Calsiboart t=4mm + Rangka Besi Hollow M2 100.99 233,251.77 23,556,679.38 2.19 - - - 0% - - - 0% - - - 0%
28,196,460.37 2.62 - - - - - - -
-
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
Disetujui Oleh,
DINAS PENDIDIKAN PEMUDA DAN OLAHRAGA Diperiksa Oleh, Dibuat Oleh,
KAB. PENAJAM PASER UTARA Konsultan Pengawas Kontraktor Pelaksana
Pengawas Lapangan CV. BUANA LESTARI CV. PRIMA EKA CIPTA
RONNY HAMDANI
NIP. 1981 091 92 006 04 1019
RISKA YULIYANTO, ST ZAINUDDIN SIAR, ST
Site Enginer Site Manager
RINCIAN PROGRES MINGGUAN
NAMA PROGRAM : PENINGKATAN SARANA DAN PASARANA PENDIDIKAN : 8 ( DELAPAN )
MINGGU KE
KEGIATAN : PEMBANGUNAN PRASARANA SDN 014 PENAJAM PERIODE : 08 AGUSTUS S/D 14 AGUSTUS 2017
LOKASI : KECAMATAN PENAJAM TAHUN ANGGARAN : 2017
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) BOBOT
)
(% VOLUME JUMLAH HARGA
( Rp. )
BOBOT
(%)
thd
pek. VOLUME JUMLAH HARGA
(Rp. )
BOBOT thd pek. VOLUME
(%)
JUMLAH HARGA
(Rp. )
BOBOT (
%)
thd
pek.
NO URAIAN
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) BOBOT (% VOLUME JUMLAH HARGA BOBOT thd VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) BOBOT (% VOLUME JUMLAH HARGA BOBOT thd VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
-
B. PEMBANGUNAN PERPUSTAKAAN SDN 014 PENAJAM -
I PEKERJAAN PERSIAPAN -
1 Pembongkaran Bh 1.00 550,000.00 550,000.00 0.05 1.00 550,000.00 0.05 100% - - 0% 1.00 550,000.00 0.05 100%
2 Pemasangan Bowplank ls 1.00 1,500,000.00 1,500,000.00 0.14 1.00 1,500,000.00 0.14 100% - - 0% 1.00 1,500,000.00 0.14 100%
Jumlah 2,050,000.00 0.19 - 2,050,000.00 0.19 - - 2,050,000.00 0.19
II PEKERJAAN TANAH -
1 Galian Tanah Biasa M3 30.016 83,384.00 2,502,854.14 0.23 30.02 2,502,854.14 0.23 100% - - 0% 30.02 2,502,854.14 0.23 100%
2 Urugan Tanah Kembali M3 9.005 27,794.67 250,285.44 0.02 - - - 0% - - 0% - - - 0%
3 Urugan Tanah M3 25.300 193,101.44 4,885,389.19 0.45 - - - 0% - - 0% - - - 0%
4 Urugan Pasir Bawah Lantai M3 4.229 147,839.55 625,250.42 0.06 - - - 0% - - 0% - - - 0%
5 Urugan Pasir Bawah Pondasi M3 1.876 147,839.55 277,347.00 0.03 1.88 277,997.49 0.03 100% - - 0% 1.88 277,997.49 0.03 100%
8,541,126.19 0.79 - 2,780,851.63 0.26 - - 2,780,851.63 0.26
III PEKERJAAN PONDASI -
1 Pasangan Pondasi Batu Gunung Camp 1:4 M3 17.82 1,004,855.99 17,908,543.45 1.66 17.82 17,908,543.45 1.66 100% - - 0% 17.82 17,908,543.45 1.66 100%
2 Pasangan pondasi keliling bangunan M3 5.37 1,004,855.99 5,397,583.95 0.50 - - - 0% - - 0% - - - 0%
3 Pasangan Batu Kosong M3 7.50 576,800.40 4,328,310.20 0.40 7.50 4,328,310.20 0.40 100% - - 0% 7.50 4,328,310.20 0.40 100%
4 Pancang Ulin 8 / 8 x 100 jarak 100 cm Ttk 47.00 119,190.40 5,601,948.80 0.52 47.00 5,601,948.80 0.52 100% - - 0% 47.00 5,601,948.80 0.52 100%
33,236,386.41 3.08 - 27,838,802.46 2.58 - - 27,838,802.46 2.58
-
IV PEKERJAAN PASANGAN -
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 115.71 16,991,104.59 1.58 70% 49.59 7,281,901.97 0.68 30% 165.30 24,273,006.56 2.25 100%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 - - - 0% 32.64 2,290,902.71 0.21 10% 32.64 2,290,902.71 0.21 10%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - - 0% - - 0% - - - 0%
57,517,398.91 5.34 - 16,991,104.59 1.58 9,572,804.68 0.89 26,563,909.27 2.47
V PEKERJAAN KAYU -
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 - - - 0% 0.26 2,560,165.61 0.24 100% 0.26 2,560,165.61 0.24 100%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 15.00 1,125,000.00 0.10 100% - - 0% 15.00 1,125,000.00 0.10 100%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - - 0% - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - - 0% - - 0% - - - 0%
11,660,440.93 1.08 - 1,125,000.00 0.10 2,560,165.61 0.24 3,685,165.61 0.34
VI. PEKERJAAN BETON -
1 SLOOF 15/20 -
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 10.30 1,294,000.02 0.12 100% - - 0% 10.30 1,294,000.02 0.12 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 250.95 4,382,576.16 0.41 100% - - 0% 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 1.55 2,305,507.80 0.21 100% - - 0% 1.55 2,305,507.80 0.21 100%
-
2 KOLOM PRAKTIS -
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 5.93 1,046,386.31 0.10 40% 5.93 1,046,386.31 0.10 40% 11.86 2,092,772.63 0.19 80%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 306.99 5,361,209.67 0.50 100% - - - 0% 306.99 5,361,209.67 0.50 100%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 0.39 574,989.17 0.05 40% 0.39 574,989.17 0.05 40% 0.77 1,149,978.34 0.11 80%
-
3 KOLOM (K1) 20/20 -
- Pasang Begesting M2 3.04 125,631.07 381,918.45 0.04 - - - 0% 3.04 381,918.45 0.04 100% 3.04 381,918.45 0.04 100%
- Pembesian Kg 36.81 17,463.94 642,890.38 0.06 36.81 642,890.38 0.06 100% - - - 0% 36.81 642,890.38 0.06 100%
- Cor Beton Camp 1:2:3 M3 0.30 1,492,238.06 453,640.37 0.04 - - - 0% 0.30 453,640.37 0.04 100% 0.30 453,640.37 0.04 100%
-
4 RING BALOK 15/20 - -
- Pasang Begesting M2 10.30 176,515.91 1,818,113.87 0.17 - - - 0% 8.24 1,454,491.10 0.13 80% 8.24 1,454,491.10 0.13 80%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% 200.76 3,506,060.93 0.33 80% 200.76 3,506,060.93 0.33 80%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% 1.24 1,844,406.24 0.17 80% 1.24 1,844,406.24 0.17 80%
-
5 CANOPY -
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - - 0% - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - - 0% - - 0% - - - 0%
-
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% - - 0% - - - 0%
36,932,777.55 3.43 - 15,607,559.53 1.45 9,261,892.58 0.86 24,869,452.10 2.31
-
VII. PEKERJAAN PENUTUP ATAP -
1 Pasang Rangka Baja Ringan & Atap Genteng Metal M2 106.90 301,461.19 32,224,693.91 2.99 - - - 0% - - 0% - - - 0%
2 Pasang Bubungan M1 40.13 101,624.96 4,078,209.64 0.38 - - - 0% - - 0% - - - 0%
36,302,903.55 3.37 - - - - - - -
-
VIII. PEKERJAAN PLAFOND -
1 List Plafond Gypsum Profil m1 92.80 49,997.64 4,639,780.99 0.43 - - - 0% - - 0% - - - 0%
2 Plafond Calsiboart t=4mm + Rangka Besi Hollow M2 100.99 233,251.77 23,556,679.38 2.19 - - - 0% - - 0% - - - 0%
28,196,460.37 2.62 - - - - - - -
-
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) BOBOT (% VOLUME JUMLAH HARGA BOBOT thd VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
Disetujui Oleh,
Pengawas Lapangan Diperiksa Oleh, Dibuat Oleh,
DINAS PENDIDIKAN PEMUDA DAN OLAHRAGA Konsultan Pengawas Kontraktor Pelaksana
CV. BUANA LESTARI CV. PRIMA EKA CIPTA
KAB. PENAJAM PASER UTARA
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) BOBOT (% VOLUME JUMLAH HARGA BOBOT thd VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
-
B. PEMBANGUNAN PERPUSTAKAAN SDN 014 PENAJAM -
I PEKERJAAN PERSIAPAN -
1 Pembongkaran Bh 1.00 550,000.00 550,000.00 0.05 1.00 550,000.00 0.05 100% - - 0% 1.00 550,000.00 0.05 100%
2 Pemasangan Bowplank ls 1.00 1,500,000.00 1,500,000.00 0.14 1.00 1,500,000.00 0.14 100% - - 0% 1.00 1,500,000.00 0.14 100%
Jumlah 2,050,000.00 0.19 - 2,050,000.00 0.19 - - 2,050,000.00 0.19
II PEKERJAAN TANAH -
1 Galian Tanah Biasa M3 30.016 83,384.00 2,502,854.14 0.23 30.02 2,502,854.14 0.23 100% - - 0% 30.02 2,502,854.14 0.23 100%
2 Urugan Tanah Kembali M3 9.005 27,794.67 250,285.44 0.02 - - - 0% 9.00 250,285.44 0.02 100% 9.00 250,285.44 0.02 100%
3 Urugan Tanah M3 25.300 193,101.44 4,885,389.19 0.45 - - - 0% - - 0% - - - 0%
4 Urugan Pasir Bawah Lantai M3 4.229 147,839.55 625,250.42 0.06 - - - 0% - - 0% - - - 0%
5 Urugan Pasir Bawah Pondasi M3 1.876 147,839.55 277,347.00 0.03 1.88 277,997.49 0.03 100% - - 0% 1.88 277,997.49 0.03 100%
8,541,126.19 0.79 - 2,780,851.63 0.26 250,285.44 0.02 3,031,137.08 0.28
III PEKERJAAN PONDASI -
1 Pasangan Pondasi Batu Gunung Camp 1:4 M3 17.82 1,004,855.99 17,908,543.45 1.66 17.82 17,908,543.45 1.66 100% - - 0% 17.82 17,908,543.45 1.66 100%
2 Pasangan pondasi keliling bangunan M3 5.37 1,004,855.99 5,397,583.95 0.50 - - - 0% - - 0% - - - 0%
3 Pasangan Batu Kosong M3 7.50 576,800.40 4,328,310.20 0.40 7.50 4,328,310.20 0.40 100% - - 0% 7.50 4,328,310.20 0.40 100%
4 Pancang Ulin 8 / 8 x 100 jarak 100 cm Ttk 47.00 119,190.40 5,601,948.80 0.52 47.00 5,601,948.80 0.52 100% - - 0% 47.00 5,601,948.80 0.52 100%
33,236,386.41 3.08 - 27,838,802.46 2.58 - - 27,838,802.46 2.58
-
IV PEKERJAAN PASANGAN -
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 165.30 24,273,006.56 2.25 100% - - 0% 165.30 24,273,006.56 2.25 100%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 32.64 2,290,902.71 0.21 10% 179.52 12,599,964.89 1.17 55% 212.16 14,890,867.59 1.38 65%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - - 0% - - 0% - - - 0%
57,517,398.91 5.34 - 26,563,909.27 2.47 12,599,964.89 1.17 39,163,874.16 3.63
V PEKERJAAN KAYU -
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 0.26 2,560,165.61 0.24 100% - - 0% 0.26 2,560,165.61 0.24 100%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 15.00 1,125,000.00 0.10 100% - - 0% 15.00 1,125,000.00 0.10 100%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - - 0% - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - - 0% - - 0% - - - 0%
11,660,440.93 1.08 - 3,685,165.61 0.34 - - 3,685,165.61 0.34
VI. PEKERJAAN BETON -
1 SLOOF 15/20 -
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 10.30 1,294,000.02 0.12 100% - - 0% 10.30 1,294,000.02 0.12 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 250.95 4,382,576.16 0.41 100% - - 0% 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 1.55 2,305,507.80 0.21 100% - - 0% 1.55 2,305,507.80 0.21 100%
-
2 KOLOM PRAKTIS -
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 11.86 2,092,772.63 0.19 80% 2.96 523,193.16 0.05 20% 14.82 2,615,965.79 0.24 100%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 306.99 5,361,209.67 0.50 100% - - - 0% 306.99 5,361,209.67 0.50 100%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 0.77 1,149,978.34 0.11 80% 0.19 287,494.58 0.03 20% 0.96 1,437,472.92 0.13 100%
-
3 KOLOM (K1) 20/20 -
- Pasang Begesting M2 3.04 125,631.07 381,918.45 0.04 3.04 381,918.45 0.04 100% - - - 0% 3.04 381,918.45 0.04 100%
- Pembesian Kg 36.81 17,463.94 642,890.38 0.06 36.81 642,890.38 0.06 100% - - - 0% 36.81 642,890.38 0.06 100%
- Cor Beton Camp 1:2:3 M3 0.30 1,492,238.06 453,640.37 0.04 0.30 453,640.37 0.04 100% - - - 0% 0.30 453,640.37 0.04 100%
-
4 RING BALOK 15/20 - -
- Pasang Begesting M2 10.30 176,515.91 1,818,113.87 0.17 8.24 1,454,491.10 0.13 80% 2.06 363,622.77 0.03 20% 10.30 1,818,113.87 0.17 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 200.76 3,506,060.93 0.33 80% 50.19 876,515.23 0.08 20% 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 1.24 1,844,406.24 0.17 80% 0.31 461,101.56 0.04 20% 1.55 2,305,507.80 0.21 100%
-
5 CANOPY -
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - - 0% - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - - 0% - - 0% - - - 0%
-
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% - - 0% - - - 0%
36,932,777.55 3.43 - 24,869,452.10 2.31 2,511,927.31 0.23 27,381,379.41 2.54
-
VII. PEKERJAAN PENUTUP ATAP -
1 Pasang Rangka Baja Ringan & Atap Genteng Metal M2 106.90 301,461.19 32,224,693.91 2.99 - - - 0% 85.52 25,779,755.12 2.39 80% 85.52 25,779,755.12 2.39 80%
2 Pasang Bubungan M1 40.13 101,624.96 4,078,209.64 0.38 - - - 0% - - 0% - - - 0%
36,302,903.55 3.37 - - - 25,779,755.12 2.39 25,779,755.12 2.39
-
VIII. PEKERJAAN PLAFOND -
1 List Plafond Gypsum Profil m1 92.80 49,997.64 4,639,780.99 0.43 - - - 0% - - 0% - - - 0%
2 Plafond Calsiboart t=4mm + Rangka Besi Hollow M2 100.99 233,251.77 23,556,679.38 2.19 - - - 0% - - 0% - - - 0%
28,196,460.37 2.62 - - - - - - -
-
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
Disetujui Oleh,
Pengawas Lapangan Diperiksa Oleh, Dibuat Oleh,
DINAS PENDIDIKAN PEMUDA DAN OLAHRAGA Konsultan Pengawas Kontraktor Pelaksana
KAB. PENAJAM PASER UTARA CV. BUANA LESTARI CV. PRIMA EKA CIPTA
RONNY HAMDANI
NIP. 1981 091 92 006 04 1019 RISKA YULIYANTO, ST ZAINUDDIN SIAR, ST
Site Enginer Site Manager
RINCIAN PROGRES MINGGUAN
NAMA PROGRAM : PENINGKATAN SARANA DAN PASARANA PENDIDIKAN : 10 ( SEPULUH )
MINGGU KE
KEGIATAN : PEMBANGUNAN PRASARANA SDN 014 PENAJAM PERIODE : 22 AGUSTUS S/D 31 AGUSTUS 2017
LOKASI : KECAMATAN PENAJAM TAHUN ANGGARAN : 2017
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) BOBOT (% VOLUME JUMLAH HARGA BOBOT thd VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
-
B. PEMBANGUNAN PERPUSTAKAAN SDN 014 PENAJAM -
I PEKERJAAN PERSIAPAN -
1 Pembongkaran Bh 1.00 550,000.00 550,000.00 0.05 1.00 550,000.00 0.05 100% - - 0% 1.00 550,000.00 0.05 100%
2 Pemasangan Bowplank ls 1.00 1,500,000.00 1,500,000.00 0.14 1.00 1,500,000.00 0.14 100% - - 0% 1.00 1,500,000.00 0.14 100%
Jumlah 2,050,000.00 0.19 - 2,050,000.00 0.19 - - 2,050,000.00 0.19
II PEKERJAAN TANAH -
1 Galian Tanah Biasa M3 30.016 83,384.00 2,502,854.14 0.23 30.02 2,502,854.14 0.23 100% - - - 0% 30.02 2,502,854.14 0.23 100%
2 Urugan Tanah Kembali M3 9.005 27,794.67 250,285.44 0.02 9.00 250,285.44 0.02 100% - - - 0% 9.00 250,285.44 0.02 100%
3 Urugan Tanah M3 25.300 193,101.44 4,885,389.19 0.45 - - - 0% 25.30 4,885,389.19 0.45 100% 25.30 4,885,389.19 0.45 100%
4 Urugan Pasir Bawah Lantai M3 4.229 147,839.55 625,250.42 0.06 - - - 0% 4.23 625,250.42 0.06 100% 4.23 625,250.42 0.06 100%
5 Urugan Pasir Bawah Pondasi M3 1.876 147,839.55 277,347.00 0.03 1.88 277,997.49 0.03 100% - - 0% 1.88 277,997.49 0.03 100%
8,541,126.19 0.79 - 3,031,137.08 0.28 5,510,639.61 0.51 8,541,776.69 0.79
III PEKERJAAN PONDASI -
1 Pasangan Pondasi Batu Gunung Camp 1:4 M3 17.82 1,004,855.99 17,908,543.45 1.66 17.82 17,908,543.45 1.66 100% - - - 0% 17.82 17,908,543.45 1.66 100%
2 Pasangan pondasi keliling bangunan M3 5.37 1,004,855.99 5,397,583.95 0.50 - - - 0% 5.37 5,397,583.95 0.50 100% 5.37 5,397,583.95 0.50 100%
3 Pasangan Batu Kosong M3 7.50 576,800.40 4,328,310.20 0.40 7.50 4,328,310.20 0.40 100% - - - 0% 7.50 4,328,310.20 0.40 100%
4 Pancang Ulin 8 / 8 x 100 jarak 100 cm Ttk 47.00 119,190.40 5,601,948.80 0.52 47.00 5,601,948.80 0.52 100% - - - 0% 47.00 5,601,948.80 0.52 100%
33,236,386.41 3.08 - 27,838,802.46 2.58 5,397,583.95 0.50 33,236,386.41 3.08
-
IV PEKERJAAN PASANGAN -
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 165.30 24,273,006.56 2.25 100% - - - 0% 165.30 24,273,006.56 2.25 100%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 212.16 14,890,867.59 1.38 65% 114.24 8,018,159.47 0.74 35% 326.41 22,909,027.07 2.13 100%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - - 0% 65.28 2,067,073.06 0.19 20% 65.28 2,067,073.06 0.19 20%
57,517,398.91 5.34 - 39,163,874.16 3.63 10,085,232.53 0.94 49,249,106.68 4.57
V PEKERJAAN KAYU -
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 0.26 2,560,165.61 0.24 100% - - 0% 0.26 2,560,165.61 0.24 100%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 15.00 1,125,000.00 0.10 100% - - 0% 15.00 1,125,000.00 0.10 100%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - - 0% - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - - 0% - - 0% - - - 0%
11,660,440.93 1.08 - 3,685,165.61 0.34 - - 3,685,165.61 0.34
VI. PEKERJAAN BETON -
1 SLOOF 15/20 -
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 10.30 1,294,000.02 0.12 100% - - 0% 10.30 1,294,000.02 0.12 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 250.95 4,382,576.16 0.41 100% - - 0% 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 1.55 2,305,507.80 0.21 100% - - 0% 1.55 2,305,507.80 0.21 100%
-
2 KOLOM PRAKTIS -
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 14.82 2,615,965.79 0.24 100% - - 0% 14.82 2,615,965.79 0.24 100%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 306.99 5,361,209.67 0.50 100% - - 0% 306.99 5,361,209.67 0.50 100%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 0.96 1,437,472.92 0.13 100% - - 0% 0.96 1,437,472.92 0.13 100%
-
3 KOLOM (K1) 20/20 -
- Pasang Begesting M2 3.04 125,631.07 381,918.45 0.04 3.04 381,918.45 0.04 100% - - 0% 3.04 381,918.45 0.04 100%
- Pembesian Kg 36.81 17,463.94 642,890.38 0.06 36.81 642,890.38 0.06 100% - - 0% 36.81 642,890.38 0.06 100%
- Cor Beton Camp 1:2:3 M3 0.30 1,492,238.06 453,640.37 0.04 0.30 453,640.37 0.04 100% - - 0% 0.30 453,640.37 0.04 100%
-
4 RING BALOK 15/20 - -
- Pasang Begesting M2 10.30 176,515.91 1,818,113.87 0.17 10.30 1,818,113.87 0.17 100% - - 0% 10.30 1,818,113.87 0.17 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 250.95 4,382,576.16 0.41 100% - - 0% 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 1.55 2,305,507.80 0.21 100% - - 0% 1.55 2,305,507.80 0.21 100%
-
5 CANOPY -
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - - 0% - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - - 0% - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - - 0% - - 0% - - - 0%
-
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% 6.93 8,377,403.85 0.78 100% 6.93 8,377,403.85 0.78 100%
36,932,777.55 3.43 - 27,381,379.41 2.54 8,377,403.85 0.78 35,758,783.27 3.32
-
VII. PEKERJAAN PENUTUP ATAP -
1 Pasang Rangka Baja Ringan & Atap Genteng Metal M2 106.90 301,461.19 32,224,693.91 2.99 85.52 25,779,755.12 2.39 80% 21.38 6,444,938.78 0.60 20% 106.90 32,224,693.91 2.99 100%
2 Pasang Bubungan M1 40.13 101,624.96 4,078,209.64 0.38 - - - 0% - - - 0% - - - 0%
36,302,903.55 3.37 - 25,779,755.12 2.39 6,444,938.78 0.60 32,224,693.91 2.99
-
VIII. PEKERJAAN PLAFOND -
1 List Plafond Gypsum Profil m1 92.80 49,997.64 4,639,780.99 0.43 - - - 0% - - 0% - - - 0%
2 Plafond Calsiboart t=4mm + Rangka Besi Hollow M2 100.99 233,251.77 23,556,679.38 2.19 - - - 0% - - 0% - - - 0%
28,196,460.37 2.62 - - - - - - -
-
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
Disetujui Oleh,
Pengawas Lapangan Diperiksa Oleh, Dibuat Oleh,
DINAS PENDIDIKAN PEMUDA DAN OLAHRAGA Konsultan Pengawas Kontraktor Pelaksana
CV. BUANA LESTARI CV. PRIMA EKA CIPTA
KAB. PENAJAM PASER UTARA
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) BOBOT (% VOLUME JUMLAH HARGA BOBOT thd VOLUME JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
- -
B. PEMBANGUNAN PERPUSTAKAAN SDN 014 PENAJAM - -
I PEKERJAAN PERSIAPAN - -
1 Pembongkaran Bh 1.00 550,000.00 550,000.00 0.05 1.00 550,000.00 0.05 100% - - - 0% 1.00 550,000.00 0.05 100%
2 Pemasangan Bowplank ls 1.00 1,500,000.00 1,500,000.00 0.14 1.00 1,500,000.00 0.14 100% - - - 0% 1.00 1,500,000.00 0.14 100%
Jumlah 2,050,000.00 0.19 - 2,050,000.00 0.19 - - - 2,050,000.00 0.19
II PEKERJAAN TANAH - -
1 Galian Tanah Biasa M3 30.016 83,384.00 2,502,854.14 0.23 30.02 2,502,854.14 0.23 100% - - - 0% 30.02 2,502,854.14 0.23 100%
2 Urugan Tanah Kembali M3 9.005 27,794.67 250,285.44 0.02 - - - 0% 9.00 250,285.44 0.02 100% 9.00 250,285.44 0.02 100%
3 Urugan Tanah M3 25.300 193,101.44 4,885,389.19 0.45 - - - 0% 25.30 4,885,389.19 0.45 100% 25.30 4,885,389.19 0.45 100%
4 Urugan Pasir Bawah Pondasi M3 4.229 147,839.55 625,250.42 0.06 - - - 0% 4.23 625,250.42 0.06 100% 4.23 625,250.42 0.06 100%
5 Urugan Pasir Bawah Lantai M3 1.876 147,839.55 277,347.00 0.03 1.88 277,997.49 0.03 100% - - - 0% 1.88 277,997.49 0.03 100%
8,541,126.19 0.79 - 2,780,851.63 0.26 - 5,760,925.05 0.53 8,541,776.69 0.79
III PEKERJAAN PONDASI - -
1 Pasangan Pondasi Batu Gunung Camp 1:4 M3 17.82 1,004,855.99 17,908,543.45 1.66 17.82 17,908,543.45 1.66 100% - - - 0% 17.82 17,908,543.45 1.66 100%
2 Pasangan pondasi keliling bangunan M3 5.37 1,004,855.99 5,397,583.95 0.50 - - - 0% 5.37 5,397,583.95 0.50 100% 5.37 5,397,583.95 0.50 100%
3 Pasangan Batu Kosong M3 7.50 576,800.40 4,328,310.20 0.40 7.50 4,328,310.20 0.40 100% - - - 0% 7.50 4,328,310.20 0.40 100%
4 Pancang Ulin 8 / 8 x 100 jarak 100 cm Ttk 47.00 119,190.40 5,601,948.80 0.52 47.00 5,601,948.80 0.52 100% - - - 0% 47.00 5,601,948.80 0.52 100%
33,236,386.41 3.08 - 27,838,802.46 2.58 - 5,397,583.95 0.50 33,236,386.41 3.08
- -
IV PEKERJAAN PASANGAN - -
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 33.06 4,854,601.31 0.45 20% 132.24 19,418,405.25 1.80 80% 165.30 24,273,006.56 2.25 100%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 - - - 0% 326.41 22,909,027.07 2.13 100% 326.41 22,909,027.07 2.13 100%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 - - - 0% 65.28 2,067,073.06 0.19 20% 65.28 2,067,073.06 0.19 20%
57,517,398.91 5.34 - 4,854,601.31 0.45 - 44,394,505.37 4.12 49,249,106.68 4.57
V PEKERJAAN KAYU - -
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 - - - 0% 0.26 2,560,165.61 0.24 100% 0.26 2,560,165.61 0.24 100%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 - - - 0% 15.00 1,125,000.00 0.10 100% 15.00 1,125,000.00 0.10 100%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - 0% - - - 0% - - - 0%
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - - 0% - - - 0% - - - 0%
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - - 0% - - - 0% - - - 0%
11,660,440.93 1.08 - - - - 3,685,165.61 0.34 3,685,165.61 0.34
VI. PEKERJAAN BETON - -
1 SLOOF 15/20 - -
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 10.30 1,294,000.02 0.12 100% - - - 0% 10.30 1,294,000.02 0.12 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 250.95 4,382,576.16 0.41 100% - - - 0% 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 1.55 2,305,507.80 0.21 100% - - - 0% 1.55 2,305,507.80 0.21 100%
- -
2 KOLOM PRAKTIS - -
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 - - - 0% 14.82 2,615,965.79 0.24 100% 14.82 2,615,965.79 0.24 100%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 306.99 5,361,209.67 0.50 100% - - - 0% 306.99 5,361,209.67 0.50 100%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 - - - 0% 0.96 1,437,472.92 0.13 100% 0.96 1,437,472.92 0.13 100%
- -
3 KOLOM (K1) 20/20 - -
- Pasang Begesting M2 3.04 125,631.07 381,918.45 0.04 - - - 0% 3.04 381,918.45 0.04 100% 3.04 381,918.45 0.04 100%
- Pembesian Kg 36.81 17,463.94 642,890.38 0.06 36.81 642,890.38 0.06 100% - - - 0% 36.81 642,890.38 0.06 100%
- Cor Beton Camp 1:2:3 M3 0.30 1,492,238.06 453,640.37 0.04 - - - 0% 0.30 453,640.37 0.04 100% 0.30 453,640.37 0.04 100%
- -
4 RING BALOK 15/20 - - -
- Pasang Begesting M2 10.30 176,515.91 1,818,113.87 0.17 - - - 0% 10.30 1,818,113.87 0.17 100% 10.30 1,818,113.87 0.17 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 - - - 0% 250.95 4,382,576.16 0.41 100% 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 - - - 0% 1.55 2,305,507.80 0.21 100% 1.55 2,305,507.80 0.21 100%
- -
5 CANOPY - -
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - - 0% - - - 0% - - - 0%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - - 0% - - - 0% - - - 0%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - - 0% - - - 0% - - - 0%
- -
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 - - - 0% 6.93 8,377,403.85 0.78 100% 6.93 8,377,403.85 0.78 100%
36,932,777.55 3.43 - 13,986,184.04 1.30 - 21,772,599.22 2.02 35,758,783.27 3.32
- -
VII. PEKERJAAN PENUTUP ATAP - -
1 Pasang Rangka Baja Ringan & Atap Genteng Metal M2 106.90 301,461.19 32,224,693.91 2.99 - - - 0% 106.90 32,224,693.91 2.99 100% 106.90 32,224,693.91 2.99 100%
2 Pasang Bubungan M1 40.13 101,624.96 4,078,209.64 0.38 - - - 0% - - - 0% - - - 0%
36,302,903.55 3.37 - - - - 32,224,693.91 2.99 32,224,693.91 2.99
- -
VIII. PEKERJAAN PLAFOND - -
1 List Plafond Gypsum Profil m1 92.80 49,997.64 4,639,780.99 0.43 - - - 0% - - - 0% - - - 0%
2 Plafond Calsiboart t=4mm + Rangka Besi Hollow M2 100.99 233,251.77 23,556,679.38 2.19 - - - 0% - - - 0% - - - 0%
28,196,460.37 2.62 - - - - - - - -
- -
KONTRAK S/d Bulan Lalu Bulan Ini S/d Bulan Ini
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
BAKTIAR, S. Pd
NIP. 1980102172006041009 RISKA YULIYANTO, ST ZAINUDDIN SIAR, ST
Site Enginer Site Manager
TIME SCHEDULE
NAMA PROGRAM : PENINGKATAN SARANA DAN PRASARANA PENDIDIKAN BULAN KE : IV ( EMPAT )
PEKERJAAN : PEMBANGUNAN PRASARANA SDN 014 PENAJAM PERIODE : SEPTEMBER
NOMOR KONTRAK : 027/011/SPK/Disdikpora/2017 LOKASI : KEC. PENAJAM
TANGGAL : 19 JUNI 2017 TAHUN ANGGARAN : 2017
TAHUN 2017
120(Seratus Dua Puluh) Hari Kalender
NO. JENIS PEKERJAAN BOBOT (%) BULAN /I MINGGU KE- KET
JUNI JULI AGUSTUS SEPTEMBER OKTOBER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
tgl 19-25 26-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-30 1-7 8-16
A PEMBANGUNAN RKB
I PEKERJAAN PERSIAPAN 0.28 0.28 100%
II PEKERJAAN TANAH 3.02 0.50 0.50 0.80 1.22
III PEKERJAAN PONDASI 7.84 1.00 1.00 2.00 3.84
IV PEKERJAAN PASANGAN 8.96 1.00 1.00 1.00 0.50 5.46
V PEKERJAAN KAYU 5.56 0.20 5.00 0.20 0.16
VI PEKERJAAN STRUKTUR 12.86 1.00 2.00 3.00 5.00 1.86 -
VII PEKERJAAN PENUTUP ATAP 11.20 6.00 4.00 1.20 -
VIII PEKERJAAN PLAFOND 8.59 1.00 4.50 3.09 - -
IX PEKERJAAN KUNCI DAN KACA 0.95 0.60 0.35
X PEKERJAAN LANTAI 6.41 1.00 5.00 0.41
XI PEKERJAAN CAT-CATAN 5.35 4.00 1.20 0.15 -
B PEMBANGUNAN PERPUSTAKAAN
I PEKERJAAN PERSIAPAN 0.19 0.19
KONTRAKTOR : CV. PRIMA EKA CIPTA KONSULTAN PENGAWAS : CV. BUANA LESTARI
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT thd pek. VOLUME JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) VOLUME VOLUME
) ( Rp. ) (%) pek. (Rp. ) (%) (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
-
B. PEMBANGUNAN PERPUSTAKAAN SDN 014 PENAJAM -
I PEKERJAAN PERSIAPAN -
1 Pembongkaran Bh 1.00 550,000.00 550,000.00 0.05 1.00 550,000.00 0.05 100% - - 1.00 550,000.00 0.05 100%
2 Pemasangan Bowplank ls 1.00 1,500,000.00 1,500,000.00 0.14 1.00 1,500,000.00 0.14 100% - - 1.00 1,500,000.00 0.14 100%
Jumlah 2,050,000.00 0.19 - 2,050,000.00 0.19 - - 2,050,000.00 0.19
II PEKERJAAN TANAH -
1 Galian Tanah Biasa M3 30.016 83,384.00 2,502,854.14 0.23 30.02 2,502,854.14 0.23 100% - - - 30.02 2,502,854.14 0.23 100%
2 Urugan Tanah Kembali M3 9.005 27,794.67 250,285.44 0.02 9.00 250,285.44 0.02 100% - - - 9.00 250,285.44 0.02 100%
3 Urugan Tanah M3 25.300 193,101.44 4,885,389.19 0.45 25.30 4,885,389.19 0.45 100% - - 25.30 4,885,389.19 0.45 100%
4 Urugan Pasir Bawah Lantai M3 4.229 147,839.55 625,250.42 0.06 4.23 625,250.42 0.06 100% - - 4.23 625,250.42 0.06 100%
5 Urugan Pasir Bawah Pondasi M3 1.876 147,839.55 277,347.00 0.03 1.88 277,997.49 0.03 100% - - 1.88 277,997.49 0.03 100%
8,541,126.19 0.79 - 8,541,776.69 0.79 - - 8,541,776.69 0.79
III PEKERJAAN PONDASI -
1 Pasangan Pondasi Batu Gunung Camp 1:4 M3 17.82 1,004,855.99 17,908,543.45 1.66 17.82 17,908,543.45 1.66 100% - - - 17.82 17,908,543.45 1.66 100%
2 Pasangan pondasi keliling bangunan M3 5.37 1,004,855.99 5,397,583.95 0.50 5.37 5,397,583.95 0.50 100% - - 5.37 5,397,583.95 0.50 100%
3 Pasangan Batu Kosong M3 7.50 576,800.40 4,328,310.20 0.40 7.50 4,328,310.20 0.40 100% - - - 7.50 4,328,310.20 0.40 100%
4 Pancang Ulin 8 / 8 x 100 jarak 100 cm Ttk 47.00 119,190.40 5,601,948.80 0.52 47.00 5,601,948.80 0.52 100% - - - 47.00 5,601,948.80 0.52 100%
33,236,386.41 3.08 - 33,236,386.41 3.08 - - 33,236,386.41 3.08
-
IV PEKERJAAN PASANGAN -
1 Pasangan Bata Merah Tebal 1/2 Bata camp 1:4 M2 165.30 146,839.48 24,273,006.56 2.25 165.30 24,273,006.56 2.25 100% - - - 165.30 24,273,006.56 2.25 100%
2 Plesteran Camp 1:4 M2 326.41 70,185.68 22,909,027.07 2.13 326.41 22,909,027.07 2.13 100% - - 326.41 22,909,027.07 2.13 100%
3 Acian m2 326.41 31,664.14 10,335,365.28 0.96 65.28 2,067,073.06 0.19 20% 195.84 6,201,219.17 0.58 60% 261.12 8,268,292.22 0.77 80%
57,517,398.91 5.34 - 49,249,106.68 4.57 6,201,219.17 0.58 55,450,325.85 5.15
V PEKERJAAN KAYU -
1 Pasang Kusen Pintu Dan Jendela Kayu klas 1 M3 0.256 9,992,840.00 2,560,165.61 0.24 0.26 2,560,165.61 0.24 100% - - 0.26 2,560,165.61 0.24 100%
2 Pasang Angin - Angin Kayu (10x30) Bh 15.000 75,000.00 1,125,000.00 0.10 15.00 1,125,000.00 0.10 100% - - 15.00 1,125,000.00 0.10 100%
3 Pasang Daun Pintu Bh 4.000 693,350.00 2,773,400.00 0.26 - - - - - - - -
4 Pasang Daun Jendela Bh 10.000 240,691.50 2,406,915.00 0.22 - - - - - - - -
5 Pasang Lisplank 2x20 (Woodplank Type) M1 43.560 64,163.46 2,794,960.32 0.26 - - - 43.56 2,794,960.32 0.26 100% 43.56 2,794,960.32 0.26 100%
11,660,440.93 1.08 - 3,685,165.61 0.34 2,794,960.32 0.26 6,480,125.93 0.60
VI. PEKERJAAN BETON -
1 SLOOF 15/20 -
- Pasang Begesting M2 10.30 125,631.07 1,294,000.02 0.12 10.30 1,294,000.02 0.12 100% - - 10.30 1,294,000.02 0.12 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 250.95 4,382,576.16 0.41 100% - - 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 1.55 2,305,507.80 0.21 100% - - 1.55 2,305,507.80 0.21 100%
-
2 KOLOM PRAKTIS -
- Pasang Begesting M2 14.82 176,515.91 2,615,965.79 0.24 14.82 2,615,965.79 0.24 100% - - 14.82 2,615,965.79 0.24 100%
- Pembesian Kg 306.99 17,463.94 5,361,209.67 0.50 306.99 5,361,209.67 0.50 100% - - 306.99 5,361,209.67 0.50 100%
- Cor Beton Camp 1:2:3 M3 0.96 1,492,238.06 1,437,472.92 0.13 0.96 1,437,472.92 0.13 100% - - 0.96 1,437,472.92 0.13 100%
-
3 KOLOM (K1) 20/20 -
- Pasang Begesting M2 3.04 125,631.07 381,918.45 0.04 3.04 381,918.45 0.04 100% - - 3.04 381,918.45 0.04 100%
- Pembesian Kg 36.81 17,463.94 642,890.38 0.06 36.81 642,890.38 0.06 100% - - 36.81 642,890.38 0.06 100%
- Cor Beton Camp 1:2:3 M3 0.30 1,492,238.06 453,640.37 0.04 0.30 453,640.37 0.04 100% - - 0.30 453,640.37 0.04 100%
-
4 RING BALOK 15/20 - -
- Pasang Begesting M2 10.30 176,515.91 1,818,113.87 0.17 10.30 1,818,113.87 0.17 100% - - 10.30 1,818,113.87 0.17 100%
- Pembesian Kg 250.95 17,463.94 4,382,576.16 0.41 250.95 4,382,576.16 0.41 100% - - 250.95 4,382,576.16 0.41 100%
- Cor Beton Camp 1:2:3 M3 1.55 1,492,238.06 2,305,507.80 0.21 1.55 2,305,507.80 0.21 100% - - 1.55 2,305,507.80 0.21 100%
-
5 CANOPY -
- Pasang Begesting M2 2.56 176,515.91 450,998.15 0.04 - - - 2.56 450,998.15 0.04 100% 2.56 450,998.15 0.04 100%
- Pembesian Kg 19.57 17,463.94 341,729.31 0.03 - - - 19.57 341,729.31 0.03 100% 19.57 341,729.31 0.03 100%
- Cor Beton Camp 1:2:3 T= 10 CM M3 0.26 1,492,238.06 381,266.82 0.04 - - - 0.26 381,266.82 0.04 100% 0.26 381,266.82 0.04 100%
-
6 Cor Rabat Bawah Lantai camp 1:3:5 T=7 cm M3 6.93 1,208,616.42 8,377,403.85 0.78 6.93 8,377,403.85 0.78 100% - - 6.93 8,377,403.85 0.78 100%
36,932,777.55 3.43 - 35,758,783.27 3.32 1,173,994.29 0.11 36,932,777.55 3.43
-
VII. PEKERJAAN PENUTUP ATAP -
1 Pasang Rangka Baja Ringan & Atap Genteng Metal M2 106.90 301,461.19 32,224,693.91 2.99 106.90 32,224,693.91 2.99 100% - - 106.90 32,224,693.91 2.99 100%
2 Pasang Bubungan M1 40.13 101,624.96 4,078,209.64 0.38 - - - 40.13 4,078,209.64 0.38 100% 40.13 4,078,209.64 0.38 100%
36,302,903.55 3.37 - 32,224,693.91 2.99 4,078,209.64 0.38 36,302,903.55 3.37
-
VIII. PEKERJAAN PLAFOND -
1 List Plafond Gypsum Profil m1 92.80 49,997.64 4,639,780.99 0.43 - - - 83.52 4,175,802.89 0.39 90% 83.52 4,175,802.89 0.39 90%
2 Plafond Calsiboart t=4mm + Rangka Besi Hollow M2 100.99 233,251.77 23,556,679.38 2.19 - - - 90.89 21,201,011.44 1.97 90% 90.89 21,201,011.44 1.97 90%
28,196,460.37 2.62 - - - 25,376,814.34 2.36 25,376,814.34 2.36
-
KONTRAK S/d Minggu Lalu Minggu Ini S/d Minggu Ini
NO URAIAN BOBOT (% JUMLAH HARGA BOBOT thd JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT ( thd
SAT VOLUME HARGA SAT ( Rp. ) JUMLAH HARGA ( Rp. ) ) VOLUME ( Rp. ) (%) pek. VOLUME (Rp. ) (%) thd pek. VOLUME (Rp. ) %) pek.
Disetujui Oleh,
Pengawas Lapangan Diperiksa Oleh, Dibuat Oleh,
DINAS PENDIDIKAN PEMUDA DAN OLAHRAGA Konsultan Pengawas Kontraktor Pelaksana
CV. BUANA LESTARI CV. PRIMA EKA CIPTA
KAB. PENAJAM PASER UTARA