You are on page 1of 4

QUANTITY WAGES

FOREMAN 1 1,333.00/day
HELPER 4 600.00/day
PLUMBER 1 700.00/day
CARPENTER 3 700.00/day
MASON 4 816.00/day
WELDER 1 700.00/day
LABOR 1 500.00/day
STEEL MAN 1 700.00/day
PAINTER 3 700.00/day
ELECTRICIAN 1 700.00/day
TOTAL WAGES IN A YEAR 2,718,885.00

LIST OF MATERIALS

UNIT PRICE QUANTITY AMOUNT


SOLAR PANEL 9,000.00 3 27,000.00
SOLAR/CHARGE 5,500.00 1 5,500.00
CONTROLLER
SOLAR BATTERY 13,055.00 3 39,165.00
SOLAR INVERTER 55,000.00 1 55,000.00
SOCKET 164.00 19 3,280.00
SINK 8,000.00 3 24,000.00
SHOWER 1,248.00 2 2,496.00
FAUCET 1,000.00 5 5,000.00
s 230.00 4 920.00
100.00 7 700.00
EXHAUST FAN 1,500.00 1 1,500.00
ALAMBRE 1,300.00 p/roll 3 3,900.00
TOILET BOWL 3,000.00 2 6,000.00
BIDET 1,700.00 2 3,400.00
BASIN 1,900.00 2 3,800.00
LIGHT BULBS/CEILING 600.00 20 12,000.00
599.00 19 11,381.00
BULB HOUSE 30.00 19
STEEL BAR 175.00 35 6,125.00
10mm,12mm 220.00 70 15,400.00
WHITE SAND 3,200.00/elf 5 16,000.00
CEMENT 250.00 297 74,250.00
HOLLOW BLOCKS #4, 19.00 500 9,500.00
#5 20.00 1,500 30,000.00
WIRES
TYPE 2.0 2,580.00 3 7,740.00
3.5 5,235.00 BOX 3 15,705.00
8.0 8,300.00 1 8,300.00
Polyvinyl Chloride (PVC) 281.00 25 7,025.00
#2 #3 #4 10 2,810.00
12 3,372.00
ELBOW 15.00 10 150.00
NELTEX 1,200.00 2 2,400.00
Random Copolymer 1,300.00 10 13,000.00
Polypropylene(PPR) 1,600.00 4 6,400.00
½, ¾
COUPLING 18.00 10 180.00
TEE 35.00 10 350.00
ELBOW WITH A 20.00 9 180.00
THREAD
TEE WITH A THREAD 10.00 9 90.00
PLYWOOD size ¾ 2,340.00 27 63,180.00
GATE VALVE 1,020.00 2 1,040.00
SKIM COAT 550.00 20 11,000.00
FLAT LATEX 2,500.00 5 12,500.00
SEMI-GLOSS 2,500.00 3 7,500.00
ROLLER (BIG) 45.00 4 180.00
ROLLER (SMALL) 40.00 4 160.00
TILES 22x120 213.00 200 42,600.00
20x30 64.00 30 1,920.00
ADHESIVE 380.00 10 3,800.00
GROUT 120.00 4 480.00
METAL PARING 140.00 100 14,000.00
CHANNEL (C) 130.00 40 5,200.00
CLIP-W 5.00 400 2,000.00
HARDIE FLEX 1,852.00 70 129,640.00
GYPSUM BOARD 490.00 70 34,300.00
BLIND RIVET 290.00 10 2,900.00
METAL BIT 1/8 67.00 3 201.00
GASA 45.00 6 270.00
METAL SCREW 200.00 2 400.00
1 ½ ,2 200.00 2 400.00
PARLINS 499.00 40 19,960.00
LONG SPAN ROOF 1,300.00 14 18,200.00
ANGULAR 286.00 32 9,152.00
SCREW (TEX) 150.00 800 120,000.00
GUTTER 392.00 10 3,920.00
SANEPA 900.00 5 4,500.00
HOSE (FLEXIBLE) 12.00 71 852.00
SQUARE BOX 40.00 20 800.00
UTILITY BOX 25.00 20 500.00
BREAKER 370.00 6 2,220.00
PANEL BOX 1,000.00 1 1,100.00
SANDPAPER 75.00 40 3,000.00
FLAP DISC 50.00 20 1,000.00
CUTTING DISC 50.00 20 1,000.00
LEVEL HOSE 27.00 15 405.00
CONCRETE NAIL 100.00 5 500.00
X1,X2,X3 100.00 5 500.00
100.00 5 500.00
SEALANT 650.00 5 900.00
TUBULAR 650.00 10 6,500.00
THINNER 270.00 1 270.00
TOTAL 953,469 TOTAL INCLUDING THE 3,672,354.00
WAGES OF LABORS
INTRODUCTION

Good morning, everyone. I’d like to start off by thanking each of you for taking the time to
participate today. We’ll be here discussing our “green dream house planning”. But before that,
we will introduce ourselves. (Introduction tayo).
Now, let us propose the design we made in a 100 square meter house
First is the front view (script nyo kung pano nyo sya iexxplain,)
Next is the aerial view (script nyo kung pano nyo sya iexxplain,)
And the last is interior layout (script nyo kung pano nyo sya iexxplain,)
We also listed the materials we needed to build the house

Approximately a year is needed to complete the house.

HOUSE PRICE: 4,750,000.00

You might also like