You are on page 1of 6

10 TheStructuralEngineer Feature
July 2014 FlexiArch system

FlexiArch: from concept


to practical applications
of speed of construction with prestressed
A. Long OBE FREng, PhD, DSc, FIStructE, FICE Queen’s University Belfast, Northern Ireland concrete/steel beam and slab systems which
rose to prominence in the 1950s and 1960s
D. McPolin BEng, MSc, PhD Queen’s University Belfast, Northern Ireland and are still widely used. However, many of
these beam and slab bridges, even though
J. Kirkpatrick BSc, PhD, CEng, FIStructE Independent Consultant their specified design lives were 120 years,
have deteriorated after only 20-30 years and
A. Gupta BTech, MTech, MPhil Macrete Ireland Ltd., Toomebridge, Northern Ireland indeed a significant number have already
had to be replaced. Where aesthetics were
D. Courtenay BEng Macrete Ireland Ltd., Toomebridge, Northern Ireland of paramount importance, the humble
masonry arch was overlooked as it could
not be built quickly. Instead, rigid precast
concrete arches, heavily reinforced so that
they could be safely lifted into position,
were adopted in some instances. However,
they do not answer the question raised by
Gordon Millington as they are difficult to
precast, store and transport to site. Also, like
beam and slab bridges, they are vulnerable
to reinforcement corrosion and they do not
have the high levels of durability associated
with unreinforced masonry arches. In
this context the UK Highways Agency
N Figure 1
Method of
construction: FlexiArch
recommends the use of the arch form where
ground conditions permit, and also states
that ‘consideration should be given to all
means of reducing or eliminating the use of
Introduction aesthetic, strong, durable, and require little corrodible reinforcement’3.
The attributes of strength, stiffness, durability maintenance?’ In summary, the basic challenge was to
and minimal maintenance of arch bridges This perceptive comment acted as a utilise our research expertise and practical
is acknowledged by structural engineers catalyst for research targeted at answering experience to develop an arch system with
throughout the world. In addition, their this question and (as described in greater all the attributes of an unreinforced masonry
aesthetic qualities are universally acclaimed; detail in the literature2) many of the arch, but that:
so much so that there are hundreds of stumbling blocks to the wider use of arches
thousands of arch bridges in the world (some were identified. For example, the need for • Can be installed as quickly as alternative
over 2000 years old) and in the UK alone over centring and accurate voussoirs for arches types of bridges
70 000 are in existence1. Thus in the early meant that they could not compete in terms • Eliminates the need for centring
1990s Gordon Millington (former Chairman (expensive to construct/install and often
of the Institution’s Northern Ireland Regional difficult to remove)
• Uses existing, well accepted methods of
Group) asked the first author the question:
‘Why is it that so few arch bridges have S Figure 2
Shienton Bridge, Shropshire
a) Lifting 13t FlexiArch unit
analysis/design for conventional masonry
been built since the early 1990s as they are b) Nearing completion arches
c) Finished bridge (October 2010)
MARCUS BRIERLEY/PLAINCOM.COM

a) b) c)

TSE31_10-15 Flexi art v4.indd 10 26/06/2014 10:45


www.thestructuralengineer.org

11

• Is cost competitive and suitable for • The voussoirs can be accurately, quickly,
construction off-site and consistently produced with the desired
• Uses precast concrete for the voussoirs taper in relatively simple shuttering
to avoid time/cost constraints and quality • High quality concrete can be utilised for
control limitations associated with the the individual precast voussoirs:
production of stone voussoirs • To enhance the durability of the arch
while in service
In this article, the concept of the patented • To greatly reduce the variability in the
‘FlexiArch’ system4 — developed to meet physical properties normally associated with
this challenge — will be described, along natural stonework
with brief details of relevant analysis/
design methods and the comprehensive Safe lifting and installation of
tests carried out to validate the system. In FlexiArch units
addition, case studies will be presented for The primary function of the polymeric
four specific applications of this versatile reinforcement is to provide sufficient tensile
a)
system – chosen as a representative sample strength so that the FlexiArch units can be
from the 40 FlexiArch bridges already in lifted safely; both from the flat casting bay
service in the UK and Ireland. on to a flatbed lorry and from the lorry in its
designated arch form into position on the
Innovative concept and method of precast sill beams at the bridge site.
manufacture With safe working being of primary
As has already been indicated, it is no importance, carefully designed tests,
longer appropriate to construct an arch which accurately simulated the boundary
in the traditional labour intensive way, due conditions, were carried out to ascertain the
to the excessive costs associated with strength of the polymeric reinforcement2.
construction/installation/removal of the Using these results and taking account of
centring and the preparation of precision creep effects, an appropriate load factor
voussoirs. Thus, a radically different approach was applied to ensure there was no risk
to the construction of arches was considered of failure during lifting. Note that great
necessary to convince practising structural care needs to be taken during installation
engineers of a viable, cost effective and (typically, a FlexiArch unit for a 15m span
sustainable solution. bridge can weigh around 15t) but provided
The FlexiArch is constructed and b) the recommended procedures are adopted,
transported to site in flat pack form using it has been found that a typical unit can be
polymeric reinforcement to carry the self- accurately located on site every 15 minutes.
weight of the arch unit during lifting. Once in As a consequence, most bridges can be
place it behaves as a conventional masonry installed in well under a day, thus affording
arch. The preferred method of construction the FlexiArch enormous benefits relative to a
of the arch unit is shown in Figure 1 (although conventionally constructed arch.
more detail is also available in the literature2).
For the manufacture of each arch unit the Strength and serviceability testing at
tapered voussoirs are precast individually and model and full scale
MARCUS BRIERLEY/PLAINCOM.COM

laid contiguously (with the top edge touching), A wide range of static loading tests
in a horizontal line with a layer of polymeric have been carried out to validate the
reinforcement placed on top. In situ screed, performance of the system. As indicated,
approximately 40mm thick, is placed on top these have included model tests in the
and allowed to harden so that the voussoirs laboratory (at fifth, quarter and third scale)
are interconnected. c)
with granular or concrete backfill where
The FlexiArch units can be cast in it was possible to achieve the ultimate
convenient widths to suit the design capacity2. However, model tests can give
requirements, site restrictions and available N Figure 3
Bridge widening: Bouthray, Cumbria
a) Lowering unit onto sill beams
rise to scale effects at ultimate, and as
lifting capacity. When lifted at the designated b) Prior to installation of lean mix concrete backfill
they are not considered to be reliable at
anchorage points, gravity forces cause the c) Finished bridge predicting behaviour at serviceability loads,
wedge shaped gaps to close. Concrete a number of full scale tests were carried
hinges form in the screed and the integrity out at Macrete where the FlexiArch units
of the unit is provided by tension in the are constructed. These included tests on
polymeric reinforcement and the shear weight then transferred from tension in the 5m span × 2m rise and 10m span × 2m rise
resistance of the screed. Note that the polymeric reinforcement to compression in FlexiArches with lean mix concrete backfill,
degree of taper of the voussoirs controls the the voussoirs, i.e. it acts in the same way as a and a test on a 15m span × 3m rise with
geometry of the arch – flatter arches require conventional masonry arch. lightweight concrete backfill.
less taper and vice versa. The arch shaped Experience of using this method has At full scale the strengths of the arches
units are then lifted and placed on precast shown that it has a number of advantages were significantly higher than the maximum
footings at the bridge site, with all the self- over traditional practices: capacity of the loading rigs. However,

TSE31_10-15 Flexi art v4.indd 11 26/06/2014 10:46



12 TheStructuralEngineer Feature
July 2014 FlexiArch system

a) b)

N Figure 4
Siddington -
avoiding disruption to
services
a) Lifting FlexiArch unit
b) Lowering unit into
position
c) Sliding FlexiArch units
under services
d) Finished bridge

MARCUS BRIERLEY/PLAINCOM.COM
c) d)

the maximum loads applied (equivalent backfill, but were found to give significantly material like concrete beyond its elastic limit.
wheel load of 320kN – or lane loading of lower (conservative) estimated strengths As anticipated, the predictions were very
over 1000kN) were still in excess of the than those measured in the relevant model much in line with the findings of the full scale
maximum for the factored loads imposed on tests in the laboratory (around three times tests at Macrete, which were still behaving
road bridges. Thus, the tests confirmed that stronger). As anticipated, the strengths of elastically at the maximum load which could
like conventional masonry arches, which FlexiArches with concrete backfill were be applied using the loading rigs. Despite the
have enormous reserves of strength, the very much higher than those estimated on loadings applied being well under the likely
FlexiArch system (as anticipated because of the basis of granulated backfill (around ten ultimate capacity, they were still significantly
the uniformly high strength voussoirs) more times stronger than predicted). It was also greater than any potential load which could
than satisfied the stringent requirements found that both methods give comparable be applied by a vehicle.
for highway bridges. Note that Macrete predictions for horizontal and vertical
and contractors using the FlexiArch have reactions, which proved useful for the design Observations on seismic
found that concrete backfill is preferred on of the footings. performance of FlexiArch
grounds of economy (as no compacting In order to get a better understanding of Relatively little research has been carried
is needed and it inhibits the ingress of the behaviour of the system with concrete out in the seismic behaviour of arches.
flood water) and it also allows the bridge backfill, FlexiArches with a range of Why? Could it be because experienced
to be used for traffic, just a few days after geometries were analysed using ABAQUS earthquake engineering researchers have
installation. finite element software7. Using a two found that the humble arch performs well
dimensional approach in conjunction with under seismic loading whereas other
Structural analysis/design of relevant material properties for the concrete structural forms do not? As a consequence,
FlexiArch bridges in the arch (50N/mm²) and the backfill have they focused their work on areas of
Once constructed, the FlexiArch behaves as (10N/mm²), it was found that the deflections greatest need?
a conventional arch and as a consequence predicted were in good agreement with Visiting seismically active areas in
standard design/analysis tools for arches those measured in the full scale tests8. For the Mediterranean region one can find
have been used in the design process example, under a wheel load of 32t the tests numerous arches, many dating back to
e.g. Archie-M software analysis system5 on the 15m span × 3m rise, FlexiArch gave Roman times, as well as other structural
and LimitState:RING software6. Both a deflection of 7.2mm while the numerical forms. By simply looking at the damage
approaches give comparable estimates model predicted 6.4mm. Note that no caused by earthquakes which have taken
of strength for the system with granular attempt was made to try to model a brittle place over the past 2000 years we can

TSE31_10-15 Flexi art v4.indd 12 26/06/2014 10:46


www.thestructuralengineer.org

13

a) b)

N Figure 5
Tameside bridge
strengthening
a) Installing FlexiArch unit
on extended sill beams
b) Hydraulic jacking
system
c) Sliding FlexiArch units
along sill beams
d) Finished bridge

MARCUS BRIERLEY/PLAINCOM.COM
c) d)

draw some conclusions. Commonly, in the precast spandrel walls are unlikely to be a arch to greatly reduce the risk of future
ruins of a typical Roman town, all beam and problem relative to masonry walls, and the flood damage. As they wished to reduce
column structures have collapsed, whereas presence of polymeric reinforcement and construction time and avoid the use of a
by contrast, masonry arch structures have interconnecting concrete screed should bridge with corrodible reinforcement, the
maintained their integrity. The only aspect of mean that the system will outperform a council selected a 13.7m span x 2.7m rise
arch bridges which appear to be vulnerable conventional arch under seismic loading. FlexiArch and ordered 8 x 1m wide units from
are the planar masonry spandrel walls9. This is precisely what has been found from Macrete Ireland, Ltd. Each unit (Figure 2a)
The internet provides a wealth of shaking table tests in California where the weighed 13t and was placed on the precast
documentation on the damage caused to FlexiArch performed exceptionally well12,13. sill beams in a matter of 10-15 minutes. Once
structures by major earthquakes. There is all the ‘FlexiArch’ units had been located
an enormous amount of information on the FlexiArch exemplars and the precast spandrel wall installed, the
Great Hanshin (Kobe) earthquake of 1995 More than 40 bridges have been bridge was ready for the lean mix concrete
(6.9-7.2 on the Richter scale), which caused constructed in the UK and Ireland over the backfill (Figure 2b). The spandrel walls were
over 6400 deaths and damage costing past eight years using FlexiArch. In this then finished in stonework (Figure 2c) to
in excess of $100 billion; 2.5% of Japan’s section, details of four different applications produce an aesthetically pleasing solution.
GDP at the time10. Looking at the graphic of the system are given. Relevant videos of The contractor, DEW Construction, worked
images of the spectacular collapse of the two of these bridges are available14,15 as well closely with Shropshire Council and Macrete
elevated Hanshin Expressway, highlights as photographs of all four projects16. Ireland Ltd, to complete the £450k contract
that bridge structures made from beam on time and within budget, in 2010.
elements resting on tall piers are vulnerable. FlexiArch replacement bridge: Sheinton,
In contrast, there is not a single image of an Shropshire Bridge widening: Bouthray, Cumbria
arch which has collapsed under the same In 2009, the old bridge in the small village In the devastating flooding experienced
seismic loading. of Sheinton, Shropshire was irreparably in Cumbria in 2009, severe damage was
Relatively recent research on the seismic damaged by flooding and a temporary caused to a two span arch bridge at
behaviour of arches has been carried Bailey Bridge was installed to restore Bouthray. After inspection, Cumbria County
out at MIT and it has been found that a communication across the tributary of the Council engineers decided to replace the
masonry arch is remarkably resilient11. River Severn. Engineers from Shropshire upstream face (over 2m wide) with an arch
How then will a FlexiArch perform? The Council decided to replace the three span system without corrodible reinforcement.
bridge with a much longer single span The main span (6.6m x 1.77m rise) and side

TSE31_10-15 Flexi art v4.indd 13 26/06/2014 10:46



14 TheStructuralEngineer Feature
July 2014 FlexiArch system

authors firmly believe that the system has yet


to achieve its full potential. For example:

• The maximum span could be increased to


25-30m for highway loading and even more
for pedestrian bridges if necessary. In the
W Figure 6
Stress ribbon/
FlexiArch pedestrian
latter case the FlexiArch could be transported
to site in two lengths for interconnection prior
bridge concept
to installation
• The system could be adapted for skew arch
bridges over railway lines where speed of
construction is of paramount importance. For
angles of skew of around 30o slightly modified
voussoirs could be beneficially deployed
• Utilise the FlexiArch in conjunction with
stress ribbon decks17 for very graceful
pedestrian bridges over motorways (Figure
6). Note that concrete arches utilised to
date have been cast in situ, whereas with
span (3.72m x 1.2m rise) FlexiArch units extensive reinforcement corrosion and FlexiArch both would be based on precast
selected, were supplied by Macrete and spalling. Replacement was unacceptable due units and hence the speed of construction
transported to site by lorry before being to the disruption to both services and a key could be greatly enhanced. Added to this, the
lifted (Figure 3a). Precast concrete spandrel transportation corridor. Repair by applying self anchoring characteristics identified by
walls were then located (Figure 3b). Finally, sprayed concrete to the deck soffit had been Strasky17 would allow the combined system
local stone was utilised to face the spandrel used in 1974, but it was clearly not a long term to be used where ground conditions did not
walls (Figure 3c). The finished bridge is solution nor was it considered aesthetically provide sufficient lateral restraint (normally
not only aesthetically pleasing but should pleasing. Wilde Consulting Engineers, a requirement for arch and stress ribbon
have a design life of over 120 years. The aware of other arch bridges over the linear bridges)
contractor was IT Shaw and Sons and the cycleway, then suggested using the Macrete • In the construction of new (or in the
client Cumbria County Council (contract FlexiArch. In December 2012, 14 x 1m wide replacement of existing) multi-span bridges
value £150k). units (Figure 5a) were installed by the main where the lateral forces could be minimised
contractor AE Yates. It was the system's first so that very slender intermediate piers could
Locating FlexiArch units under services: ever application for bridge strengthening. be utilised. In plan view (Figure 7) the ends of
Siddington, Gloucestershire The 7.4m span units were manufactured the first three FlexiArch units to be installed
In 2011, engineers in Gloucester were faced in NI and shipped to site before being could be tied together (as in the Jubilee
with having to replace a deteriorated arch individually lifted by crane and placed on Bridge) but once in place, the remaining units
bridge in Siddington, Gloucestershire. lightly greased, laterally extended sill beams could be installed without ties
Unfortunately the bridge incorporated a along each abutment. They were then pushed
number of vital services which could not be horizontally in pairs beneath the bridge using Concluding remarks
disrupted. The engineers sought a system two hydraulic jacks (Figure 5b and c). When The experience gained from constructing
which had all the characteristics of a masonry all 14 units had been located, spandrel walls more than 40 FlexiArch bridges in the UK
arch (including no corrodible reinforcement). were constructed and the gap between the and Ireland, and from the extensive tests at
Thus, 7 x 1m wide FlexiArch units (4m FlexiArch unit and the original deck soffit both full and model scale, have allowed the
span x 1.5m rise) were ordered. These units was filled with foamed concrete. The £420k following conclusions to be drawn:
were delivered in flat pack form. When contract was completed on time and within
lifted, gravity forces transformed them into budget and Tameside Council now have an • By manufacturing the voussoirs using
the required arch shape (Figure 4a and aesthetically pleasing bridge with a design life accurate moulds, interconnecting them via a
b). After a FlexiArch unit had been placed of 120 years (Figure 5d). screed and polymeric reinforcement, arches
on the extended sill beam it was jacked can be produced to the precision required by
horizontally under the services. Figure 4c Future developments designers without the need for centring
shows that minimal clearance was necessary. The four exemplars give an indication of the • Lifting the FlexiArch units onto flat bed
The final bridge (Figure 4d) satisfied all the versatility of the FlexiArch. However, the lorries, stacking them in their flat pack form,
site constraints and the client (Gloucester
Highways) and the contractor, ENVEX, found
it to be a user friendly system which could
be rapidly installed on site (contract value
£200k).

Bridge strengthening: Tameside,


Manchester W Figure 7
Multispan
bridges with
Tameside’s 78 year old Jubilee Bridge, slender piers
which spans National Cycle Route 66
in Manchester, had been weakened by

TSE31_10-15 Flexi art v4.indd 14 26/06/2014 10:46


www.thestructuralengineer.org

15

E4 Long A. E. (2004) Concrete arch and method of


manufacture, International Patent, Publication 27
May, No. WO 2004/044332A1, Queen’s University
Belfast

E5 Obvis Ltd. (2014) Archie-M [Online] Available at:


www.obvis.com/archie-m/ (Accessed: June 2014)

E6 LimitState (2014) About LimitState:RING [Online]:


Available at: www.limitstate.com/ring/details
(Accessed: June 2014)

E7 Dassault Systèmes (2014) Abaqus Unified FEA


[Online]: Available at: www.3ds.com/products-
N Figure 8
Initial/whole life cycle costs
of alternative systems
services/simulia/portfolio/abaqus/latest-release/
(Accessed: June 2014)

together with their transportation to (and installation on) site, has E8 McGovern N. (2010) ‘Analysis of ‘FlexiArch’
proven to be simple — with no unforeseen problems occuring using Abaqus Computer Software’, MEng Project,
• As a typical FlexiArch unit can be lifted into position in 15 minutes (or Queen’s University Belfast
less), the speed of installation is comparable with precast concrete/
steel beams. As such, it can be used for road bridges over railway lines E9 De Felice G. and Giannini R. (2001) ‘Out of
where construction windows are restrictive plane seismic resistance of masonry walls’,
• The FlexiArch should have exceptional durability as it is made of Journal of Earthquake Engineering, 5 (2), pp. 253-
high quality precast concrete. As there is no corrodible reinforcement, 271
minimal maintenance is required. Total life cycle costs therefore, are
also minimal (Figure 8) E 10 BBC News (2014) On this day 1950-2005 (17
• Standard methods of design for conventional arches can be used to January 2005) Earthquake devastates Kobe
give safe but very conservative estimates of the strength of FlexiArch [Online] Available at: news.bbc.
bridges. Actual failure loads (from the model tests) with concrete co.uk/onthisday/hi/dates/stories/january/17/
backfill were c. 9-10 times higher, while the full scale tests showed little newsid_3375000/3375733.stm (Accessed: June
sign of distress at 5 times this load 2014)
• In general, after contractors, designers and clients have been
involved in the installation of a FlexiArch bridge they have become E 11 DeJong M. J. (2009) ‘Seismic Assessment
much more favourably disposed to the system. When this experience Strategies for Masonry Structures’, PhD Thesis,
is combined with competitive cost, aesthetics, sustainability and Massachusetts Institute of Technology
durability, its potential for use in the construction industry is immense
E 12 YouTube (2013) Seismic FlexiArch Test: Arch
Acknowledgements ring only [Online] Available at: www.youtube.
The financial support provided by the ICE R&D Enabling Fund, KTP com/watch?v=S8dBU6O2-ko (Accessed: June
Scheme, Invest Northern Ireland, DRD Roads Service (NI) and the 2014)
Leverhulme Trust is gratefully acknowledged. Input by K. McDonald,
B. Rankin, J. Kirkpatrick, S. Taylor, D. Robb and I. Hogg is also E 13 YouTube (2013) Seismic FlexiArch Test: With
acknowledged. backfill [Online] Available at: www.youtube.
com/watch?v=N5DRbeJ83-Y (Accessed: June
2014)

References E 14 Macrete (2010) Sheinton FlexiArch [Online]


Available at: www.macrete.com/flexiarch/
E1 HMSO Department of Transport (1993) Masonry flexiarch-projects/sheinton-flexiarch (Accessed:
Arch Bridges (Page J. Ed.) Transport Research June 2014)
Laboratory, London, UK
E 15 YouTube (2012) AshtonBridgemoviewithsound
E2 Long A., Kirkpatrick J., Gupta A., Nanukuttan S. and [Online] Available at: www.youtube.com/
McPolin D. (2013) ‘Rapid construction of arch watch?v=W5mBL7O7mIY (Accessed: June 2014)
bridges using the innovative FlexiArch’, Proc. ICE,
Bridge Engineering, 166 (BE3), pp. 143-153 E 16 Macrete (2013) FlexiArch [Online] Available
at: www.macrete.com/flexiarch/flexiarch-
E3 HMSO Department of Transport (2004) Design projects (Accessed: June 2014)
Manual for Roads and Bridges (BD 91/04: Un-
reinforced masonry arch bridges) [Online] Available E 17 Strasky J. (2005) Stress ribbon and cable-
at: www.dft.gov.uk/ha/standards/dmrb/vol2/ supported pedestrian bridges, London: Thomas
section2/bd9104.pdf (Accessed: June 2014) Telford Publishing

TSE31_10-15 Flexi art v4.indd 15 26/06/2014 10:46

You might also like