OIL INDIA LIMITED 23-May-2022

Well Wise Daily Report for Workover Wells


Outfit R/up Date
Operations Carried out
Well Current Shift
RG-A 21-04-2022 [Resumed cement cleaning from 2898 m down to 2933 m. Pumped Hi vis pill & circulated out cement cu ngs.]
NHK084 (WA) 56 Next Well : NHK025(10)-R/NHK069(10000)-R/NHK650
[P/out OE tbg from 2428 m to surface. R/in bit upto 295 m. Surface tested mud-motor found ok. [Further operations couldn't be carried out from 1800
RG-B 15-02-2022
hrs due to bandh called by local people ci ng noise related issue.]]
NHK526 (CA) 148
Next Well : NHK037-R/NHK495-R/NHK148(5)-R/NHK164
[Resume POOH 2-7/8" tbg with TSA + GLV from 910 m to 423 m. Observed heavy spiral scrapping tool inside tubing and also small piece of piano wire.
RG-C 18-05-2022
Cumula ve recovery of dyform wire rope of approx 954 m. Shut the well.]
NHK443 (WA) 8
Next Well : NHK559(5)-R/HJN007 (sand screen)(5)-R/NHK304
[R/in O/E EUE tbg from 1700 m to 1898 m. Changed over the well fluid in to water.In between, instrumentation crew tried to rectify the gear shifting
RG-D 21-03-2022 problem of Ou it Engine no.1, but unable to solve the problem. POOH O/E EUE tbg from 1898 m. M/A & r/in 5-1/2" H/W PKR dn to 118 m.]
NHK591 (WA) 100 Next Well : NHK385(ABD) / NHK444(ABD)(S/Const)

[RIH TCR bit from 3561 m upto 3606 m . Clean down hole upto 3618 m ( BP top). Circulated well . P/out TCR bit with mud motor upto 1909 m and shut
RG-E 25-02-2022
well.]
KLN013 (CA) 132
Next Well : SLM014(WDC)-R/NHK011
[P/out tapered mill sgl by sgl from 2610 m to 1523 m [Shut in well at 18:00 hrs due to bandh called by local people ci ng noise related issue.]]
BHEL-A 22-07-2021
Next Well : NHK107(5)-R/NHK191(ABD)-R/NHK621(ABD)/JRN020(ABD)/NHK360 (ABD)/NHK440(ABD)/ NHK441(ABD)/JRN032(ABD)
MDK003(WI) (CA) 470
[POOH Rotovert + J nipple from 2253 m. RIH safety string and shut well. Well kept ready for wireline job for casing communica on iden fica on.]
BHEL-C 30-04-2022
Next well: JRN005(ABD)/ NHK239(ABD)-R/DRI001(ABD)/ JRN027/BGP007-R / NHK131(Ench-Statics)-R/ NHK232(ABD)/ NHK593/NHK150(ABD)-R
NHK576 (CA) 40
[R/in drill pipe with FBM. Started milling from the depth of 13.25 m and milled down to the 23.05 m with continuous circulation and rotary on.
M-1 27-04-2022
Cummula ve hole cleaned = 16.56 m. Shut in the well.]
NHK250 (CA) 24
Next Well : NHK143(ABD)R/JRN-12(5)
DM-1 23-11-2021 [P/out 9.5/8" Rotovert from 1681 m upto 124 m.]
NHK496 (CA) 201 Next Well : NHK235(5)/NHK296(15000)-R/NHK115(ABD)-R/NHK196(Approach)/ NHK087(ABD)
DM-2 [General rig down is in progress.]
NHK166 (WA) Next Well: NHK302(20)/NHK378(5)/NHK447(ABD)-R/ WDW(NHK192)
DM-3 [Rig up job in fwd loc NHK448 is in progress.]
NHK459 (CA) Next Well : NHK448 (ABD)-R/ NHK007(5000)/ WBT001-(ABD)
[WLD unit rigged up & Lowered 2-1/8" Dummy/GR/CCL upto 2880 m. Again, lowered 2-1/8" TTP/CCL & perforated in the range 2841-2847 m. No
DM-4 27-01-2022
immediate pressure built up observed. Shut in well.]
NHK246 (WA) 176
Next Well: NHK114(5)-R/DRI-4(ABD)/DRI003-R/ NHK247(ABD)-R/ NHK104(ABD)
Continued forward circulation with 2 % Nacl & found crude Oil mix solution in return. Pumped 155 bbl kill fluid & got same weight solution. Circulated
CH-1 15-05-2022 for 1 hr. Observed well for 30 mins. No activity seen. Attempted to clean down hole without success. POOH rotovert from 2362.33 m. RIH FBM+ mud
JRN039 (CA) 16 motor upto 960 m.
Next well: NHK553(10)/NHK195 (WI-Stk PKR)
R/in Impression Block from 498 m to 2224 m. Circulated prior to taking impression. Took impression by slacking 8000 lbs. P/out Impression block sgl by
CH-2 18-02-2022
sgl upto 629 m.
HJN054 (EA) 180
Next well: HJN039-R/NHK542-R
WLD made JB trip which got held-up at 3980.6 m and recorded CBL-VDL-CAST log in the range 3980-3850 m which showed channeling across the range
CH-3 23-04-2022
recorded. Interpreta on of pipe inspec on mode is in progress.
BRK011 (EA) 60
Next Well : HJN016(10)-R/HJN057-R/BRK013(ABD)-R /NHK253-R (WI)
CH-4 Rig up job is in progress. To carry out Pre WO safety audit today.
BHJ003 (EA) Next Well: BHJ002/KRJ001/ SCM003-R(SPF)
Continued milling fish top with concave mill from 1349 m down to 1349.45 m. Observed fine metal cuttings in returns. Tried to mill down further but
CH-5 02-05-2022 with no progress. Circulated out metal cuttings. POOH concave mill with junk- busket from 1349 m. R/in I/Block with D/pipe down to 214 m and is in
BGP006 (EA) 42 progress.
Next Well: NHK592(30,000)-R/HJN014-R(WI)/NHK563(LHDP)/BMR006-R(*DIQ)/BMR008(ABD)-R(*DIQ)
Baker Hughes rigged up logging gears & recorded Temp-GR-CCL log in the range 4000-4200 m. R/dn logging gears. Took injectivity in presence of M/S
SLB representa ve @ 2000 psi & recorded as Nil (400 psi decline in 15 min). P/out string with Re-entry guide up to 437 m from 3950 m & is in progress.
CH-6 16-05-2022
Next Well : BMR04(HF)/MRN024 (WI)-R / MRN108-R(ESP)/MRN025(15000)/DKP03(ABD)-
BMR003 (WA) 14
R/MRN089(ABD)/MRN074(ABD)/MRN08(ABD)/MRN06/MRN071

CH-7 12-04-2022 Waiting for SLH-90 LH 2-7/8" d/pipe.


NHK230 (WA) 84 Next Well : NHK124-R/ NHK456-R/ NHK648-R / KMC013
POOH OE tbg from 189 m. M/up 5 1/2" casing rotovert + J/nipple with tbg down to 3850 m. Tagged C/top. Established circulation with water for 1
CH-8 01-03-2022 cycle. P/out rotovert upto 3647 m in sgls. Further p/out is in progress.
KJN008 (EA) 178 (126) Next Well : MRN094 -R(WI)/NHK652-R(LHDP)/MRN104-R/MRN080-R (WI) / MRN119 (ABD)-R/
MRN023(10)/MRN085(10)/MRN105/MRN040/MRN054/MRN020/MRN066/MRN090(ABD)
Carried out tubing puncture at depth 3608 m. Checked SITP=SICP= 1200 psi. B-Annulus= Nil. Kill line tested at 2500 psi. Found ok. Tubing pressure
released to 700 psi. Pumped 71 pcf Sodium Formate solution through tubing at 1500 psi (max) and diverted return through casing to DIAN QPS.
CH-9 01-04-2022
Received return of 70 pcf solution through casing after pumping 327 bbls through tubing. Shut in the well at 17:00 hrs and kept for over night
MTN006 (CA) 106
observa on. Final SITP=SICP=Nil. Morning SITP=SICP= Nil.
Next well: NHK506/BMR-2-R(HF) /DHL01(HF)(*DYE)/MTN07-R(ESP)
Applied 07 Nos of gas shots & unloaded 59 bbls. Cumulative unloaded= 695 bbls. Shut the well at 16:30 hrs. Sample analysis as on 22.05.2022 at 09.45
AM showed: Floating Oil- 57%, Water: 43%; ( pH: 8.5, Sal : 5700 ppm, CO3 : 120; HCO3 : 305 ppm), at 2.00 PM showed: Oil- Nil, Water: 100%; (pH: 7.5,
CH-10 12-04-2022
Sal : 4800 ppm, CO3 : Nil; HCO3 : 366 ppm) and at 4.10 PM showed: Oil-2%, Water: 98%; (pH: 7.5, Sal : 4700 ppm, CO3 : Nil; HCO3 : 366 ppm).
NHK438 (CA) 84
Next well : DKM017/DKM012(WI)/DKM025/DKM034/ DKM003-R/DKM022-R

CH-11 03-03-2022 Rig down CTU. General rig down is in progress for fowd loc BRK030.
NMK001 (EA) 160 Next well: BRK030/ STL002/NHK481(5) /NHK471(5)/NHK375(15000)
CH-12 Completed ILM from WDW150. General Rig up in progress.
CBA016 (CA) Next Well : CBA019(15) /CBA018(5)/CBA06(5)/ NHK 499(ABD)/NHK466-R/BGN004-R
Applied 03 nos gas shots and unloaded 01 bbls of well fluid . (Cum. unloaded =284 bbls.) CTU rigged up. Released casing pressure. Shut in well. Sample
CH-13 07-02-2022
analysis as on 22.05.2022 at 01.20 PM : Oil- Nil, Water: 100%; (pH: 7.5, Sal : 1400 ppm, CO3 : nil; HCO3 :2745 ppm).
TNL010 (WA) 204
Next Well: NHK128(5)-R/SLM013-R(*LHDP)/ BGP005-R (SRP)/NHK561-R
WLD Mast
() Next Well : EKJ01/MKM069/BGN026
[General rig-up of acid setup completed. Pressure tested surface lines and fittings upto 750 psi, found okay. R/circulated one (01) hole volume. Kept the
Prod Set-up 21-05-2022
well shut. To start backwashing job on Monday.]
WDW201 (WA) 1
Next well:
Hooked up of acid pumping unit to the well-head completed. Pressure tested S/lines and fittings up to 3000 psi & found ok. R/circulated one (01) hole
S.Mark Setup 22-05-2022
volume. Kept the well shut. To carry out tubing integrity test today.
KMT005 (CA) 1
Next Well : WDW122/WDW200/WDW149
Note: MMC crew deployed in RG-A , RG-B, RG-C, RG-D, RG-E, BHEL A, BHEL C & DM-4