SECTION - 5
SECTION - 5
CONTENTS
1.0 GENERAL 3
SECTION - 5
1.0 GENERAL
1.1 Contractor shall submit item, building / structure wise billing schedule inline with EPC
tender specification along with cash flow statement.
1.2 Contractor shall strictly follow the above billing schedule and cash flow statement in
execution of contract.
4.1 The terms of payment for the civil works are detailed herein.
The Contractor shall be entitled to use for the purposes of the Works such supplies of
electricity, water if available with client.
b) Rate of water at one point in Cement Plant as per mutually agreed rate.
c) Note
FORMT9-P REV-B (MUM)
Measuring meter of the above items will be in the scope of Contractor. Contractor
has to submit meter test certification from authorised agency.
6.1 Contract Price is inclusive of work contract tax and all other taxes, duties and levies
including, Insurance, excise duty, Sales Tax, but excluding local Entry Tax/Octroi if
applicable. The Contractor will apply for availing of Concessional rate of Works
Contract Tax to the State Govt. of Meghalaya.
Any tax, which Owner may be required to deduct by law/statute, shall be deducted at
source and shall be paid to the tax authorities on account of the Contractor. Owner
shall provide the Contractor a certificate for such deduction of tax.
The basic considerations shall be the strict adherence to the time schedule for
performing the specified `Works'.
The time for completion of civil & construction shall not be more than 15 (Fifteen)
months from the date of commencement, since the time for completion for
commissioning is 18 months from the date of commencement. However, if there is
delay in construction leading to a delay in commissioning beyond 18 months or if due
to faulty construction of structure commissioning is delayed, Bank Guarantee or 10 %
of contract value from last payment will be considered for applying LIQUIDATED
DAMAGES (LD) for delay. The LIQUIDATED DAMAGES (LD) will be 0.5% of contract
price per week or part thereof subject to a ceiling of 10% contract value.
After all the construction work have been completed and proved safe for performance
testing of systems or power plant, the Owner shall conduct "reliability run" of Power
Plant and associated system at rated / available load for fifteen (15) days of
uninterrupted operation to their satisfaction. The Owner may decide to reduce the
After the satisfactory reliability run, the unit (buildings/structures) shall be considered
operationally reliable.
A. For any defect in Civil / Architectural / Structural work, which may lead to power
plant not being able to deliver guaranteed performance (guaranteed by the
equipment supplier), the Contractor shall have to pay Liquidated Damages (LD)
at the rates in proportion to the LIQUIDATED DAMAGES (LD) of equipment
performance, with the ceiling of 10% of Contract Price.
B. Owner retains the option to reject the work wherever the workmanship affects
the operation of power plant and Contractor shall carry out necessary
modifications / replacement to make good the defects within reasonable time
with no extra cost to the owner. However, the L.D. for late completion will apply
in case of delay in the project completion.
C. The cumulative sum of all Liquidated Damages (LD) for delay in completion of
work and shortfall in performance will not exceed 15% of the Contract value.
FORMT9-P REV-B (MUM)