SECTION - 7
SECTION - 7
CONTENTS
1.0 GENERAL 3
12.0 INSURANCE 6
FORMT9-P REV-B (MUM)
SECTION - 7
1.0 GENERAL
1.1 Contractor shall submit equipment / system erection, testing and commissioning wise
billing schedule inline with EPC tender specification along with cash flow statement.
1.2 Contractor shall strictly follow the above billing schedule and cash flow statement in
execution of contract.
All statutory clearance/approval for works are in Contractor’s scope except approval
of State Electricity Board (SEB) U/S 44, Pollution Control Board(PCB) and aviation
clearance, which are in owner’s scope. However, all supporting papers and desired
assistance are to be provided by Contractor.
4.1 The terms of payment for erection, testing and commissioning, Marine-cum-Storage-
cum-Erection Insurance are detailed herein.
4.2 For the Erection, testing & commissioning Services, Marine cum Storage cum
Erection Insurance till plant take over by the owner, terms of payment are as below:-
5.3 Defect Liability period / Warranty 10% of contract value will be submitted
Bank Guarantee before commissioning valid for 12
months from take over or 15 months
from commissioning whichever is earlier.
(10% Bank guarantee given for security
deposit under clause 5.1 can be
extended/converted into Bank Guarantee
for warranty)
(a) Liquidated Damages (LD) for delay ½ % of contract price per week’s delay
(or part thereof) with maximum of 5% of
contract value to be recovered from last
10% payment or Bank Guarantee for
performance.
The Contractor shall be entitled to use for the purposes of the Works such supplies of
electricity, water, if available with owner.
b) Rate of water at one point in Cement plant As per mutually agreed rates.
c) Note
Any tax, which Owner may be required to deduct by law/statute, shall be deducted at
source and shall be paid to the tax authorities on account of the Contractor. Owner
shall provide the Contractor a certificate for such deduction of tax.
The basic considerations shall be the strict adherence to the time schedule of
Erection, Testing & Commissioning of equipment.
The Erection, Testing & Commissioning of the equipment shall be completed as per
agreed project schedule. However, if there is delay in erection, testing and
commissioning beyond agreed date, Bank Guarantee or 10 % of contract value from
last payment will be considered for applying Liquidated Damages (LD) for delay.
After all the systems have been completely stabilized and proved safe, the Owner
shall offer the systems as a whole for continuous and safe operation as a "reliability
run" at rated design load for fifteen (15) days of uninterrupted operation to their
satisfaction. The Owner may decide to reduce the period of 15 days if he is satisfied
with running of equipment of plant during the intervening period.
After the satisfactory reliability run, the unit shall be considered operationally reliable
and be ready for Performance Testing. The results would be evaluated and shall be
accepted by Owner if found satisfactory and bank guarantee for technical
performance shall be released to Contractor.
B. Owner retains the option to reject the work wherever the workmanship is faulty
and affects the operation of power plant and Contractor shall carry out
necessary modifications / replacement to make good the defects within
reasonable time with no extra cost to the owner. However, the Liquidated
Damages (LD) for late completion will apply in case of delay in the project
completion.
FORMT9-P REV-B (MUM)
C. The cumulative sum of all Liquidated Damages (LD) for delay in completion of
work and shortfall in performance will not exceed 10% of the Contract value.
For all items under guarantee shortfall in performance is not acceptable more than the
permissible tolerance wherever specified and shall be guaranteed by the Contractor
as under compulsory correction. The performance shall be proved under worst grid
conditions as specified.
For the items indicated above the Contractor shall carry out modifications to obtain
the performance. As these are primary parameters, these must be corrected before
reliability run if it affects reliability run during the stabilisation period. And further, these
parameters must remain stable throughout the period of reliability run. All work related
to correction and subsequent reliability run to prove stability / reliability shall be
completed within the guarantee period with no extra cost to the Owner. All the
corrections required shall be carried out at site, as far as possible;
In the event of rejection of erection work, which is faulty, it is obvious that the overall
project schedule will be affected. To minimise the loss due to such an occurrence, the
Owner retains the right to use as best as possible, the faulty equipment until new
replacement arrives at site for erection. Note should be taken that as the faulty work if
it does not inhibit the operation of plant. During this period, the Contractor shall not
limit the use of the faulty equipment, except for reasons of safety during operation,
both of personnel and the equipment.
12.0 INSURANCE
The beneficiary of insurance policy shall be the owner. The Contractor will obtain
N.O.C. from Owner before receiving the claim from Insurance Companies.