You are on page 1of 62

B CONCRETE WORK

Rates for Concrete Work shall include for :


a. Mixing, depositing, handling, hoisting and plasing in position and
packing around reinforcement.

b. Vibrating, curing as directed.

BASIC PRICES

Materials

Cement Rs. 860.00 bag.


Sand Rs. 10,300.00 cube.
Metal 3/4 " Rs. 4,800.00 cube.
Metal 1 " Rs. 4,500.00 cube.
Metal 2 " Rs. 2,000.00 cube.
Water Rs. 0.50 gal.

Labour

Skilled Labour Rs. 1,200.00 per day


Un Skilled Labour Rs. 900.00 per day
Vibrator Operator Rs. 1,200.00 per day
Concrete Mixer
operator Rs. 1,200.00 per day

Plant and Equipment

Concrete Mixer Rs. 1,500.00 per day


Vibrator Rs. 900.00 per day

Overheads & Profit 25.00 %


B CONCRETE WORK

B. 01 Cement concrete 1 : 3 : 6 with 2" metal cube. Rs. 35,004.38


( grade 10 )

B. 02 Cement concrete 1 : 3 : 6 with 1" metal cube. Rs. 37,293.13


( grade 10 )

B. 03 Cement concrete 1 : 21/2 : 5 with 1" metal cube. Rs. 41,026.88


( grade 15 )

B. 04 Cement concrete 1 : 2 :4 ( 3/4" metal ) cube. Rs. 45,701.88


( grade 20 )

B. 05 Cement concrete 1 : 11/2 :3 ( 3/4" metal ) cube. Rs. 51,076.88


( grade 25 )

B. 06 2" thick blinding layer under column or


wall foundation in concrete 1:3:6 ( 2 " ) sqr. Rs. 6,745.20

B. 07 2" thick blinding layer under column or


wall foundation in concrete 1:3:6 ( 1 " ) sqr. Rs. 6,832.39

B. 08 3" thick blinding layer under column or


wall foundation in concrete 1:3:6 ( 1 " ) sqr. Rs. 9,306.45

B. 09 4" thick ground floor slab in concrete


1:3:6 ( 1 " ) sqr. Rs. 12,689.85

Cement concrete 1 : 2 : 4 - 3/4 " metal


( grade 20 )

B. 10 Cement concrete 1 : 2 : 4 : ( 3/4 " ) lintol


size 41/2" x 6" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 196.00

B. 11 Cement concrete 1 : 2 : 4 : ( 3/4 " ) lintol


size 6" x 9" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 286.19

B. 12 Cement concrete 1 : 2 : 4 : ( 3/4 " ) lintol


size 9" x9" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 452.08
B. 13 Cement concrete 1 : 2 : 4 : ( 3/4 " ) lintol
size 9" x 12" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 567.51

B. 14 Cement concrete 1 : 2 : 4 : ( 3/4 " ) lintol


size 6" x 13 1/2" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 476.54

B. 15 Cement concrete 1 : 2 : 4 : ( 3/4 " ) lintol


size 9" x 13 1/2" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 621.73

B. 16 Cement concrete 1 : 2 : 4 : ( 3/4 " ) lintol


size 12" x 13 1/2" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 706.64

B. 17 Cement concrete 1 : 2 : 4 : ( 3/4 " ) lintol


size 41/2" x 41/2" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 126.90

B. 18 9" x 9 " column in ground floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 47,943.73

B. 19 9" x 9 " column in first floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 49,068.73

B. 20 9" x 9 " column in second floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 49,631.23

B. 21 9" x 9 " column in thired floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 50,193.73

B. 22 12" x 12 " column in ground floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 46,984.28

B. 23 12" x 12 " column in first floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 48,109.28

B. 24 12" x 12 " column in second floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 48,671.78

B. 25 12" x 12 " column in thired floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 49,234.28

B. 26 9" x 9 " beam in ground floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 48,221.50

B. 27 9" x 9 " beam in first floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 49,346.50

B. 28 9" x 9 " beam in second floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 49,909.00

B. 29 9" x 9 " beam in thired floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 50,471.50

B. 30 9" x 12 " beam in ground floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 47,234.28

B. 31 9" x 12 " beam in first floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 48,359.28

B. 32 9" x 12 " beam in second floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 48,921.78

B. 33 9" x 12 " beam in thired floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 49,484.28

B. 34 12 " x 12 " beam in ground floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 47,234.28

B. 35 12 " x 12 " beam in first floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 48,359.28

B. 36 12 " x 12 " beam in second floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 48,921.78

B. 37 12 " x 12 " beam in thired floor in


concrete 1 : 2 : 4 ( 3/4 " ) cube Rs. 49,484.28

B. 38 4" thick slab in first floor ( 1: 2: 4 3/4 " ) sqr. Rs. 16,490.26

B. 39 4" thick slab in second floor ( 1: 2: 4 3/4 " ) sqr. Rs. 17,240.26

B. 40 4" thick slab in thired floor ( 1: 2: 4 3/4 " ) sqr. Rs. 18,177.76

B. 41 5" thick slab in first floor ( 1: 2: 4 3/4 " ) sqr. Rs. 21,608.37

B. 42 5" thick slab in second floor ( 1: 2: 4 3/4 " ) sqr. Rs. 22,733.37

B. 43 5" thick slab in thired floor ( 1: 2: 4 3/4 " ) sqr. Rs. 23,295.87

B. 44 6" thick slab in first floor ( 1: 2: 4 3/4 " ) sqr. Rs. 24,952.14
B. 45 6" thick slab in second floor ( 1: 2: 4 3/4 " ) sqr. Rs. 26,077.14

B. 46 6" thick slab in thired floor ( 1: 2: 4 3/4 " ) sqr. Rs. 26,639.64

Cement concrete 1 : 11/2 : 3 - 3/4 " metal


( grade 25 )

B. 47 Cement concrete 1 : 11/2 : 3 : ( 3/4 " ) lintol


size 41/2" x 6" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 205.95

B. 48 Cement concrete 1 : 11/2 : 3 : ( 3/4 " ) lintol


size 6" x 9" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 339.16

B. 49 Cement concrete 1 : 11/2 : 3 : ( 3/4 " ) lintol


size 9" x9" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 482.35

B. 50 Cement concrete 1 : 11/2 : 3 : ( 3/4 " ) lintol


size 9" x 12" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 542.20

B. 51 Cement concrete 1 : 11/2 : 3 : ( 3/4 " ) lintol


size 6" x 13 1/2" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 473.83

B. 52 Cement concrete 1 : 11/2 : 3 : ( 3/4 " ) lintol


size 9" x 13 1/2" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 666.88

B. 53 Cement concrete 1 : 11/2 : 3 : ( 3/4 " ) lintol


size 12" x 13 1/2" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 766.84

B. 54 Cement concrete 1 : 11/2 : 3 : ( 3/4 " ) lintol


size 41/2" x 41/2" with and including formwork.
( reinforcement paid separately. ) l.ft. Rs. 134.27

B. 55 9" x 9 " column in ground floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 53,587.48
B. 56 9" x 9 " column in first floor in
concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 54,712.48

B. 57 9" x 9 " column in second floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 55,274.98

B. 58 9" x 9 " column in thired floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 55,837.48

B. 59 12" x 12 " column in ground floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 52,628.03

B. 60 12" x 12 " column in first floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 53,753.03

B. 61 12" x 12 " column in second floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 54,315.53

B. 62 12" x 12 " column in thired floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 54,878.03

B. 63 9" x 9 " beam in ground floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 53,865.25

B. 64 9" x 9 " beam in first floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 54,990.25

B. 65 9" x 9 " beam in second floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 55,552.75

B. 66 9" x 9 " beam in thired floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 56,115.25

B. 67 9" x 12 " beam in ground floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 52,878.03

B. 68 9" x 12 " beam in first floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 54,003.03

B. 69 9" x 12 " beam in second floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 54,565.53

B. 70 9" x 12 " beam in thired floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 55,128.03
B. 71 12 " x 12 " beam in ground floor in
concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 52,878.03

B. 72 12 " x 12 " beam in first floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 54,003.03

B. 73 12 " x 12 " beam in second floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 54,565.53

B. 74 12 " x 12 " beam in thired floor in


concrete 1 : 11/2 : 3 ( 3/4 " ) cube Rs. 55,128.03

B. 75 4" thick slab in first floor ( 1: 11/2: 3 -3/4 " ) sqr. Rs. 17,625.20

B. 76 4" thick slab in second floor ( 1: 11/2: 3 -3/4 " ) sqr. Rs. 18,375.20

B. 77 4" thick slab in thired floor ( 1: 11/2: 3 - 3/4 " ) sqr. Rs. 18,750.20

B. 78 5" thick slab in first floor ( 1: 11/2: 3 - 3/4 " ) sqr. Rs. 24,134.62

B. 79 5" thick slab in second floor ( 1: 11/2: 3 3/4 " ) sqr. Rs. 24,884.62

B. 80 5" thick slab in thired floor ( 1: 11/2: 3 3/4 " ) sqr. Rs. 25,259.62

B. 81 6" thick slab in first floor ( 1: 11/2: 3 3/4 " ) sqr. Rs. 27,774.02

B. 82 6" thick slab in second floor ( 1: 11/2: 3 3/4 " ) sqr. Rs. 28,524.02

B. 83 6" thick slab in thired floor ( 1: 11/2: 3 3/4 " ) sqr. Rs. 28,899.02
B. 01 Concrete 1 : 3 : 6 ( 2 " ) grade 10 Per Cube

MIXING COST

Materials

13.00 bags Cement at. Rs. 860.00 Rs. 11,180.00


0.60 cube Sand at. Rs. 10,300.00 Rs. 6,180.00
1.00 cube Metal ( 2" ) at. Rs. 2,000.00 Rs. 2,000.00
125 gal. Water at. Rs. 0.50 Rs. 62.50
Rs. 19,422.50
Labour

1 Mixer operator 1/3 day at. Rs, 1,200.00 Rs. 396.00


6 Uunskilled labour 1/3 day at. Rs, 900.00 Rs. 1,800.00
Rs. 2,196.00
Plant and equipment

Concrete mixer 14/10 at. Rs, 1,500.00 Rs. 500.00


1/3 day

Cost for one cube ( mixing cost only ) Rs. 22,118.50

LAYING COST

Labour

0.75 day Mason at Rs. 1,200.00 Rs. 900.00


0.75 day Vibrator Operator at Rs. 1,200.00 Rs. 900.00
0.75 day 6 unskilled labour at Rs. 900.00 Rs. 2,700.00
Rs. 4,500.00
Plant and equipment
0.75 day Vibrator at Rs. 900.00 Rs. 675.00

Add
3 % of labour cost for tools Rs. 135.00
5 % of labour cost for scaffolding Rs. 225.00
Rs. 360.00
Curing
100 gal. Water at Rs. 0.50 Rs. 50.00
0.33 day Unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
28,003.50

Overheads & Profit 7,000.88

Cost for one cube with overheads & profits. 35,004.38

B. 02 Concrete 1 : 3 : 6 ( 1 " ) grade 10 Per Cube

MIXING COST

Materials

13.00 bags Cement at. Rs. 860.00 Rs. 11,180.00


0.60 cube Sand at. Rs. 7,200.00 Rs. 4,320.00
1.00 cube Metal ( 2" ) at. Rs. 4,000.00 Rs. 4,000.00
125 gal. Water at. Rs. 0.50 Rs. 62.50
Rs. 19,562.50

Labour

1 Mixer operator 1/3 day at. Rs, 1,300.00 Rs. 429.00


6 Unskilled labour 1/3 day at. Rs, 1,000.00 Rs. 2,000.00
Rs. 2,429.00

Plant and equipment

1/3 day
Concrete mixer 14/10 at. Rs, 1,500.00 Rs. 500.00

Cost for one cube ( mixing cost only ) Rs. 22,491.50

LAYING COST

Labour

0.75 day mason at Rs. 1,200.00 Rs. 900.00


0.75 day Vibrator Operator at Rs. 1,200.00 Rs. 900.00
0.75 day 6 unskilled labour at Rs. 900.00 Rs. 4,050.00
Rs. 5,850.00
Plant and equipment
0.75 day vibrator at Rs. 900.00 Rs. 675.00

Add

3 % of labour cost for tools Rs. 175.50


5 % of labour cost for scaffolding Rs. 292.50
Rs. 468.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 29,834.50
Overheads & Profit Rs. 7,458.63

Cost for one cube with overheads & profits. Rs. 37,293.13

B. 03 Concrete 1 : 21/2 : 5 ( 1 " ) grade 15 Per Cube

MIXING COST

Materials

14.00 bags Cement at. Rs. 860.00 Rs. 12,040.00


0.60 cube Sand at. Rs. 10,300.00 Rs. 6,180.00
1.00 cube Metal ( 2" ) at. Rs. 4,500.00 Rs. 4,500.00
125 gal. Water at. Rs. 0.50 Rs. 62.50
Rs. 22,782.50
Labour

1 Mixer operator 1/3 day at. Rs, 1,200.00 Rs. 396.00


6 unskilled labour 1/3 day at. Rs, 900.00 Rs. 1,800.00
Rs. 2,196.00
Plant and equipment

1/3 day concrete mixer 14/10 at. Rs, 1,500.00 Rs. 500.00

Cost for one cube ( mixing cost only ) Rs. 25,478.50

LAYING COST

Labour

0.75 day mason at Rs. 1,200.00 Rs. 900.00


0.75 day skilled labour for
vibrator at Rs. 1,200.00 Rs. 900.00
0.75 day 6 unskilled labour at Rs. 900.00 Rs. 4,050.00
Rs. 5,850.00
Plant and equipment
0.75 day vibrator at Rs. 900.00 Rs. 675.00

Add

3 % of labour cost for tools Rs. 175.50


5 % of labour cost for scaffolding Rs. 292.50
468.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
350.00 Rs. 350.00
Rs. 32,821.50
Overheads & Profit Rs. 8,205.38

Cost for one cube with overheads & profits. Rs. 41,026.88

B. 04 Concrete 1 : 2 : 4 ( 3/4 " ) grade 20 Per Cube

MIXING COST

Materials

18.00 bags Cement at. Rs. 860.00 Rs. 15,480.00


0.60 cube Sand at. Rs. 10,300.00 Rs. 6,180.00
1.00 cube Metal ( 2" ) at. Rs. 4,800.00 Rs. 4,800.00
125 gal. Water at. Rs. 0.50 Rs. 62.50
Rs. 26,522.50
Labour

1 mixer operator 1/3 day at. Rs, 1,200.00 Rs. 396.00


6 unskilled labour 1/3 day at. Rs, 900.00 Rs. 1,800.00
Rs. 2,196.00
Plant and equipment

concrete mixer 14/10 at. Rs, 1,500.00 Rs. 500.00


1/3 day
Cost for one cube ( mixing cost only ) Rs. 29,218.50

LAYING COST

Labour

0.75 day mason at Rs. 1,200.00 Rs. 900.00


0.75 day skilled labour for
vibrator at Rs. 1,200.00 Rs. 900.00
0.75 day 6 unskilled labour at Rs. 900.00 Rs. 4,050.00
Rs. 5,850.00
Plant and equipment
0.75 day vibrator at Rs. 900.00 Rs. 675.00

Add
3 % of labour cost for tools Rs. 175.50
5 % of labour cost for scaffolding Rs. 292.50
468.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
36,561.50

Overheads & Profit 9,140.38

Cost for one cube with overheads & profits. 45,701.88

B. 05 Concrete 1 : 11/2 : 3 ( 3/4 " ) grade 25 Per Cube

MIXING COST

Materials

23.00 bags Cement at. Rs. 860.00 Rs. 19,780.00


0.60 cube Sand at. Rs. 10,300.00 Rs. 6,180.00
1.00 cube Metal ( 2" ) at. Rs. 4,800.00 Rs. 4,800.00
125 gal. Water at. Rs. 0.50 Rs. 62.50
Rs. 30,822.50
Labour

1 mixer operator 1/3 day at. Rs, 1,200.00 Rs. 396.00


6 unskilled labour 1/3 day at. Rs, 900.00 Rs. 1,800.00
Rs. 2,196.00
Plant and equipment

concrete mixer 14/10 at. Rs, 1,500.00 Rs. 500.00


1/3 day

Cost for one cube ( mixing cost only ) Rs. 33,518.50

LAYING COST

Labour

0.75 day mason at Rs. 1,200.00 Rs. 900.00


0.75 day Vibrator Operator at Rs. 1,200.00 Rs. 900.00
0.75 day 6 unskilled labour at Rs. 900.00 Rs. 4,050.00
Rs. 5,850.00
Plant and equipment
0.75 day vibrator at Rs. 900.00 Rs. 675.00

Add
3 % of labour cost for tools Rs. 175.50
5 % of labour cost for scaffolding Rs. 292.50
Rs. 468.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 40,861.50
Overheads & Profit Rs. 10,215.38

Cost for one cube with overheads & profits. Rs. 51,076.88

B. 05a Concrete 1 : 1 : 2 ( 3/4 " ) grade 30 Per Cube

MIXING COST

Materials

31.00 bags Cement at. Rs. 860.00 Rs. 26,660.00


0.60 cube Sand at. Rs. 10,300.00 Rs. 6,180.00
1.00 cube Metal ( 2" ) at. Rs. 4,800.00 Rs. 4,800.00
125 gal. Water at. Rs. 0.50 Rs. 62.50
Rs. 37,702.50
Labour

1 mixer operator 1/3 day at. Rs, 1,200.00 Rs. 396.00


6 unskilled labour 1/3 day at. Rs, 900.00 Rs. 1,800.00
Rs. 2,196.00
Plant and equipment
concrete mixer 14/10 at. Rs, 1,500.00 Rs. 500.00
1/3 day
Cost for one cube ( mixing cost only ) Rs. 40,398.50

LAYING COST

Labour

0.75 day mason at Rs. 1,200.00 Rs. 600.00


0.75 day skilled labour for
vibrator at Rs. 1,200.00 Rs. 600.00
0.75 day 6 unskilled labour at Rs. 900.00 Rs. 4,050.00
5,250.00 Rs. 5,250.00
Plant and equipment
0.75 day vibrator at Rs. 900.00 Rs. 675.00
Add

3 % of labour cost for tools Rs. 157.50


5 % of labour cost for scaffolding Rs. 262.50
Rs. 420.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 47,093.50
Overheads & Profit Rs. 11,773.38

Cost for one cube with overheads & profits. Rs. 58,866.88

B. 06 2" thick blinding layer under wall / column foundation ( 1 : 3 : 6 - 2 " )

Per sqr.

Materials

0.17 cube mixed concrete at. Rs. 22,118.50 Rs. 3,760.15


( as per item B. 01 )
Add 10 % for wastage Rs. 376.01 Rs. 4,136.16

Labour

1.00 Skilled labour 1/ 4 day at. Rs. 1,200.00 Rs. 300.00


4.00 Unskilled labour 1/ 4 day at. Rs. 900.00 Rs. 900.00 Rs. 1,200.00

Tools
5 % of labour cost Rs. 60.00
Rs. 5,396.16
Add
Overheads & Profit Rs. 1,349.04

Cost for one sqr. with overheads & profits. Rs. 6,745.20
B. 07 2" thick blinding layer under wall / column foundation ( 1 : 3 : 6 - 1 " )

Per sqr.

Materials

0.17 cube mixed concrete at. Rs. 22,491.50 Rs. 3,823.56


( as per item B. 02 )
Add 10 % for wastage Rs. 382.36 Rs. 4,205.91

Labour

1 Skilled labour 1/ 4 day at. Rs. 1,200.00 Rs. 300.00

4 Unskilled labour 1/ 4 day at. Rs. 900.00 Rs. 900.00 Rs. 1,200.00

Tools

5 % of labour cost Rs. 60.00


5,465.91
Add
Overheads & Profit Rs. 1,366.48

Cost for one sqr. with overheads & profits. Rs. 6,832.39
B. 08 3" thick blinding layer under wall / column foundation ( 1 : 3 : 6 - 1" )

Per sqr.

Materials
0.25 cube mixed concrete at. Rs. 22,491.50 Rs. 5,622.88
( as per item B. 02 )

Add 10 % for wastage Rs. 562.29


6,185.16 Rs. 6,185.16
Labour

1 skilled labour 1/4 day at. Rs. 1,200.00 Rs. 300.00


4 unskilled labour 1/4 day at. Rs. 900.00 Rs. 900.00
1,200.00 Rs. 1,200.00
Tools

5 % cost of labour cost Rs. 60.00


7,445.16
Add
Overheads & Profit Rs. 1,861.29

Cost for one sqr. with overheads & profits. Rs. 9,306.45
note
For laying concrete at depths more than 5 ' 0 " add 1/4 extra day unskilled labour
B. 09 4 " thick ground floor slab. ( 1 : 3 : 6 1 " )

Per sqr.

Materials
0.33 cube mixed concrete at. Rs. 22,491.50 Rs. 7,497.17
( as per item B. 02 )

Add 10 % for wastage Rs. 749.72


Rs. 8,246.88
Labour

1.00 skilled labour 1/3 day at. Rs. 1,200.00 Rs. 400.00
4.00 unskilled labour 1/3 day at. Rs. 900.00 Rs. 1,200.00
Rs. 1,600.00
Plant and equipment
0.25 day vibrator at. Rs. 900.00 Rs. 225.00

Add

Tools 5 % of of labour cost Rs. 80.00


10,151.88
Add
Overheads & Profit Rs. 2,537.97
Cost for one sqr. with overheads & profits. Rs. 12,689.85

B. 10 Cement concrete 1:2:4 ( 3/4 " ) lintol size 4 1/2" x 6"


with and including formwork ( reinforcement paid separately )

10 l. ft.

Materials

1.85 c. ft. Concrete ( B 04 ) at. Rs. 45,701.88 Rs. 845.48


13.7 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 786.43
Rs. 1,631.91
Add

Extra cost of labour

1/8 day Skilled labour at. Rs. 1,200.00 Rs. 150.00


1/8 day Un skilled labour at. Rs. 900.00 Rs. 112.50
262.50

Overheads & Profit Rs. 65.63


Rs. 328.13
cost for 10.0 l. ft. Rs. 1,960.04
Cost for one foot with preliminaries. Rs. 196.00

B. 11 Cement concrete 1:2:4 ( 3/4 " ) lintol size 6" x 9"


with and including formwork ( reinforcement paid separately )

10 l. ft.

Materials
3.75 c. ft. Concrete ( B 04 ) at. Rs. 45,701.88 Rs. 1,713.82
20.00 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,148.07
Rs. 2,861.89
Add

Extra cost of labour


1/8 day Skilled labour at. Rs. 1,200.00 Rs. 150.00
1/8 day Un skilled labour at. Rs. 900.00 Rs. 112.50
262.50
Overheads & Profit 65.63
328.13
cost for 10.0 l. ft. 2,861.89

Cost for one foot with preliminaries. Rs. 286.19

B. 12 Cement concrete 1:2:4 ( 3/4 " ) lintol size 9" x 9 "


with and including formwork ( reinforcement paid separately )

10 l. ft.

Materials

5.63 c. ft. Concrete ( B 04 ) at. Rs. 45,701.88 Rs. 2,573.02


22.5 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,291.58
Rs. 3,864.59
Add

Extra cost of labour

1/4 day Skilled labour at. Rs. 1,200.00 Rs. 300.00


1/4 day Un skilled labour at. Rs. 900.00 Rs. 225.00
Rs. 525.00
Overheads & Profit Rs. 131.25
Rs. 656.25
cost for 10.0 l. ft. Rs. 4,520.84
Cost for one foot with preliminaries. Rs. 452.08

B. 13 Cement concrete 1:2:4 ( 3/4 " ) lintol size 9" x 12 "


with and including formwork ( reinforcement paid separately )

10 l. ft.

Materials

7.50 c. ft. Concrete ( B 04 ) at. Rs. 45,701.88 Rs. 3,427.64


27.72 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,591.23
Rs. 5,018.87
Add

Extra cost of labour

1/4 day Skilled labour at. Rs. 1,200.00 Rs. 300.00


1/4 day Un skilled labour at. Rs. 900.00 Rs. 225.00
Rs. 525.00
Overheads & Profit Rs. 131.25
Rs. 656.25
cost for 10.0 l. ft. Rs. 5,675.12

Cost for one foot with preliminaries. Rs. 567.51

B. 14 Cement concrete 1:2:4 ( 3/4 " ) lintol size 6" x 13 1/2 "
with and including formwork ( reinforcement paid separately )

10 l. ft.

Materials

5.6 c. ft. Concrete ( B 04 ) at. Rs. 45,701.88 Rs. 2,559.31


27 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,549.89
Rs. 4,109.20
Add

Extra cost of labour

1/4 day Skilled labour at. Rs. 1,200.00 Rs. 300.00


1/4 day Un skilled labour at. Rs. 900.00 Rs. 225.00
Rs. 525.00

Overheads & Profit Rs. 131.25


Rs. 656.25
cost for 10.0 l. ft. Rs. 4,765.45

Cost for one foot with preliminaries. Rs. 476.54

B. 15 Cement concrete 1:2:4 ( 3/4 " ) lintol size 9" x 131/2"


with and including formwork ( reinforcement paid separately )

10 l. ft.
Materials

8.4 c. ft. Concrete ( B 04 ) at. Rs. 45,701.88 Rs. 3,838.96


30 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,722.11
Rs. 5,561.06
Add

Extra cost of labour

1/4 day Skilled labour at. Rs. 1,200.00 Rs. 300.00


1/4 day Un skilled labour at. Rs. 900.00 Rs. 225.00
Rs. 525.00
Overheads & Profit Rs. 131.25
Rs. 656.25
cost for 10.0 l. ft. Rs. 6,217.31

Cost for one foot with preliminaries. Rs. 621.73

B. 16 Cement concrete 1:2:4 ( 3/4 " ) lintol size 12" x 13 1/2 "
with and including formwork ( reinforcement paid separately )

10 l. ft.

Materials

11.2 c. ft. Concrete ( B 04 ) at. Rs. 45,701.88 Rs. 5,118.61


22.5 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,291.58
Rs. 6,410.19
Add

Extra cost of labour

1/4 day Skilled labour at. Rs. 1,200.00 Rs. 300.00


1/4 day Un skilled labour at. Rs. 900.00 Rs. 225.00
Rs. 525.00
Overheads & Profit Rs. 131.25
Rs. 656.25
cost for 10.0 l. ft. Rs. 7,066.44

Cost for one foot with preliminaries. Rs. 706.64

B. 17 Cement concrete 1:2:4 ( 3/4 " ) lintol size 4 1/2" x 4 1/2 "
with and including formwork ( reinforcement paid separately )

10 l. ft.

Materials

1.37 c. ft. Concrete ( B 04 ) at. Rs. 45,701.88 Rs. 626.12


11.2 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 642.92
Rs. 1,269.03
Add

Extra cost of labour

1/8 day Skilled labour at. Rs. 1,200.00 Rs. 150.00


1/8 day Un skilled labour at. Rs. 900.00 Rs. 112.50
Rs. 262.50
Overheads & Profit Rs. 65.63
Rs. 328.13
cost for 10.0 l. ft. Rs. 1,269.03

Cost for one foot with preliminaries. Rs. 126.90

B. 18 Concrete columns in ground floor ( 1 : 2 : 4 3/4 " )

16 no 9 " X 9 " columns each 5 ' 0 " high

0.45 cube ( 80.00 l. ft. )

Materials
0.45 cube mixed concrete at Rs. 29,218.50 Rs. 13,148.33
( as per item B. 04 )

Add
5 % wastage Rs. 657.42
Rs. 13,805.74
LAYING COST

Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
1/2 day skilled labour for
vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. Rs. 450.00

Add
3 % of labour cost for tools Rs. 76.50
5 % of labour cost for scaffolding Rs. 127.50
Rs. 204.00
Curing

50 gal. water at Rs. 0.50 Rs. 25.00


1/4 day unskilled labour at Rs. 900.00 Rs. 225.00
Rs. 250.00
Cost for 0.45 cubes Rs. 17,259.74

Overheads & Profit 4,314.94

21,574.68

Cost for one cube with overheads & profits. 47,943.73


in 9" x 9" columns.

B. 19 9 " x 9" Concrete columns in first floor

Cost for 9 " X 9 " columns


in ground floor Rs. 47,943.73

Add

2 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00

Cost for one cube with overheads & profits. Rs. 49,068.73
in 9" x 9" columns.
B. 20 9 " x 9 " Concrete columns in second floor

Cost of 9 " X 9 " columns 47,943.73

Add

3 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,350.00


Overheads & Profit Rs. 337.50
Rs. 1,687.50

Cost for one cube with overheads & profits. 49,631.23


in 9" x 9" columns.

B. 21 9 " x 9 " Concrete columns in third floor

Cost of 9 " X 9 " columns 47,943.73

Add

4 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,800.00


Overheads & Profit Rs. 450.00
2,250.00

Cost for one cube with overheads & profits. 50,193.73


in 9" x 9" columns.

B. 22 Concrete columns in ground floor

10 no 12 " x 12 " columns each 5 ' 0 " high

0.50 cube ( 50.00 l. ft. )

Materials
0.50 cube mixed concrete at Rs. 29,218.50 Rs. 14,609.25
( as per item B. 04 )

Add
5 % wastage Rs. 730.46
Rs. 15,339.71
LAYING COST
Labour

0.50 day mason at Rs. 1,200.00 Rs. 600.00


day skilled labour for
0.50 vibrator at Rs. 1,200.00 Rs. 600.00
0.50 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
0.50 day vibrator at Rs. 900.00 Rs. 450.00

Add

3 % of labour cost for tools Rs. 76.50


5 % of labour cost for scaffolding Rs. 127.50
Rs. 204.00
Curing

50 gal. water at Rs. 0.50 Rs. 25.00


1/4 day unskilled labour at Rs. 900.00 Rs. 225.00
Rs. 250.00
Rs. 18,793.71
Overheads & Profit Rs. 4,698.43
cost for .50 cube coloumn Rs. 23,492.14

Cost for one cube with overheads & profits. 46,984.28


in 12" x 12" columns.

B. 23 12 " x 12 " Concrete columns in first floor

Cost of 12 " X 12 " columns Rs. 46,984.28

Add

2 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00
Cost for one cube with overheads & profits. Rs. 48,109.28
in 12" x 12" columns.

B. 24 12 " x 12 " Concrete columns in second floor

Cost of 12 " X 12 " columns Rs. 46,984.28

Add

3 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,350.00


Overheads & Profit Rs. 337.50
Rs. 1,687.50

Cost for one cube with overheads & profits. Rs. 48,671.78
in 12" x 12" columns.

B. 25 12 " x 12 " Concrete columns in third floor

Cost of 12 " X 12 " columns 46,984.28 46,984.28

Add

4 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,800.00


Overheads & Profit Rs. 450.00
2,250.00

Cost for one cube with overheads & profits. 49,234.28


in 12" x 12" columns.

B. 26 9 " x 9 " Concrete beams in ground floor level

8 no 9 " X 9 " beam 10' 0" ft long

0.45 cube ( 80.00 l. ft. )

Materials
0.45 cube mixed concrete at Rs. 29,218.50 Rs. 13,148.33
( as per item B. 04 )
Add
5 % wastage Rs. 657.42
Rs. 13,805.74
LAYING COST

Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00

Add

5 % of labour cost for scaffolding Rs. 127.50


3 % of labour cost for tools Rs. 76.50
Rs. 204.00
Curing
100 gal. water at Rs. 0.50 Rs. 50.00
1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 17,359.74
Overheads & Profit Rs. 4,339.94
Rs. 21,699.68

Cost for one cube with overheads & profits. Rs. 48,221.50
in 9" x 9" beam.

B. 27 9 " x 9" Concrete beam in first floor

1 cube

Cost of 9 " X 9 " beam Rs. 48,221.50

Add
2 Un skilled labour 1/2 day Rs. 900.00 Rs. 900.00
Preliminaries Rs. 225.00
Rs. 1,125.00

Cost for one cube with overheads & profits.


in 9" x 9" beam. Rs. 49,346.50

B. 28 9 " x 9 " Concrete beam in second floor

1 cube

Cost of 9 " X 9 " beam Rs. 48,221.50

Add
3 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,350.00
Overheads & Profit Rs. Rs. 337.50
Rs. 1,687.50

Cost for one cube with overheads & profits.


in 9" x 9" beam. Rs. 49,909.00

B. 29 9 " x 9 " Concrete beam in third floor

1 cube

Cost of 9 " X 9 " beam Rs. 48,221.50 Rs. 48,221.50

Add
4 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,800.00
Overheads & Profit Rs. 450.00

Rs. 2,250.00
Cost for one cube with overheads & profits.
in 9" x 9" beam. Rs. 50,471.50

B. 30 Concrete beams in ground floor level

6 no 9 " X 12 " beam 10' 0" ft long

0.50 cube ( 60.00 l. ft. )

Materials
0.5 cube mixed concrete at Rs. 29,218.50 Rs. 14,609.25
( as per item B. 04 )
Add
5 % wastage Rs. 730.46
Rs. 15,339.71
LAYING COST

Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00

Add

5 % of labour cost for scaffolding Rs. 127.50


3 % of labour cost for tools Rs. 76.50
Rs. 204.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 18,893.71
Overheads & Profit Rs. 4,723.43
Rs. 23,617.14

Cost for one cube with overheads & profits. 47,234.28


in 9" x 12" beam.

B. 31 Concrete beam in first floor

1 cube

Cost of 9 " X 12 " beam Rs. 47,234.28


Add
2 Un skilled labour 1/2 day Rs. 900.00 Rs. 900.00
Overheads & Profit Rs. 225.00
Rs. 1,125.00

Cost for one cube with overheads & profits. Rs. 48,359.28
in 9" x 12" beam.

B. 32 Concrete beam in second floor

1 cube

Cost of 9 " X 12 " beam Rs. 47,234.28

Add
3 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,350.00
Overheads & Profit Rs. 337.50
Rs. 1,687.50

Cost for one cube with overheads & profits. Rs. 48,921.78
in 9" x 12" beam.

B. 33 Concrete beam in third floor

1 cube

Cost of 9 " X 12 " beam Rs. 47,234.28

Add
4 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,800.00
Overheads & Profit Rs. 450.00
Rs. 2,250.00
Cost for one cube with overheads & profits. Rs. 49,484.28
in 9" x 12" beam.

B. 34 Concrete beams in ground floor level

5 no 12 " X 12 " beam 10' 0" ft long


0.50cube ( 50 l. ft. )

Materials
0.5 cube mixed concrete at Rs. 29,218.50 Rs. 14,609.25
( as per item B. 04 )
Add
5 % wastage Rs. 730.46
Rs. 15,339.71
LAYING COST

Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00

Add

5 % of labour cost for scaffolding Rs. 127.50


3 % of labour cost for tools Rs. 76.50
Rs. 204.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 18,893.71
Overheads & Profit Rs. 4,723.43
Rs. 23,617.14

Cost for one cube with overheads & profits. 47,234.28


in 12" x 12" beam.

B. 35 Concrete beam in first floor


1 cube

Cost of 12 " X 12 " beam Rs. 47,234.28

Add
2 Un skilled labour 1/2 day Rs. 900.00 Rs. 900.00
Overheads & Profit Rs. 225.00
Rs. 1,125.00

Cost for one cube with overheads & profits. Rs. 48,359.28
in 12" x 12" beam.

B. 36 Concrete beam in second floor

1 cube

Cost of 12 " X 12 " beam Rs. 47,234.28

Add
3 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,350.00
Overheads & Profit Rs. 337.50
Rs. 1,687.50

Cost for one cube with overheads & profits. Rs. 48,921.78
in 12" x 12" beam.

B. 37 Concrete beam in thired floor

1 cube

Cost of 12 " X 12 " beam Rs. 47,234.28

Add
4 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,800.00
Overheads & Profit Rs. 450.00
Rs. 2,250.00

Cost for one cube with overheads & profits. Rs. 49,484.28
in 12" x 12" beam.
B. 38 4 " thick concrete slab in first floor

Per sqr

0.33 cube ( 100.00 s. ft. )

Materials
0.33 cube mixed concrete at Rs. 29,218.50 Rs. 9,642.11
( as per item B. 04 )
Add
5 % wastage Rs. 482.11
Rs. 10,124.21

LAYING COST
Labour

1/2 day mason at Rs. 1,200.00 Rs. 600.00


day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 2 unskilled labour at Rs. 900.00 Rs. 900.00
Rs. 2,100.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. Rs. 450.00

Add

5 % of labour cost for scaffolding Rs. 105.00


3 % of labour cost for tools Rs. 63.00
Rs. 168.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
350.00 Rs. 350.00
Rs. 13,192.21
Overheads & Profit Rs. 3,298.05
Cost for one sqr. with overheads & profits. Rs. 16,490.26
B. 39 4 " thick concrete slab in second floor 1 sqr.

Cost for 4 " thick concrete slab in ground floor Rs. 16,490.26

1/3 day 2 un skilled labour Rs. 900.00 Rs. 600.00


Overheads & Profit Rs. 150.00
Rs. 750.00

Cost for one sqr. with overheads & profits. Rs. 17,240.26

B. 40 4 " thick concrete slab in third floor

Cost for 4 " thick concrete slab in ground floor Rs. 16,490.26

1/2 day 3 un skilled labour Rs. 900.00 Rs. 1,350.00


Overheads & Profit Rs. 337.50
Rs. 1,687.50

Cost for one sqr. with overheads & profits. Rs. 18,177.76
B. 41 5 " thick concrete slab in first floor Per sqr

MIXING COST

0.42 cube ( 100.00 s. ft. )

Materials
0.42 cube mixed concrete at Rs. 29,218.50 Rs. 12,271.77
( as per item B. 04 )
Add
5 % wastage Rs. 1,460.93
Rs. 13,732.70

LAYING COST

Labour

1/2 day mason at Rs. 1,200.00 Rs. 600.00


day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00

Add

5 % of labour cost for scaffolding Rs. 127.50


3 % of labour cost for tools Rs. 76.50
Rs. 204.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 17,286.70
Overheads & Profit Rs. 4,321.67
Cost for one sqr. with overheads & profits. Rs. 21,608.37
B. 42 5 " thick concrete slab in second floor

Cost for 5 " thick concrete slab in ground floor Rs. 21,608.37

1/2 day 2 un skilled labour Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00

Cost for one sqr. with overheads & profits. Rs. 22,733.37

B. 43 5 " thick concrete slab in third floor

Cost for 5" thick concrete slab in ground floor Rs. 21,608.37

1/2 day 3un skilled labour Rs. 900.00 Rs. 1,350.00


Overheads & Profit Rs. 337.50
Rs. 1,687.50

Cost for one sqr. with overheads & profits. Rs. 23,295.87
B. 44 6 " thick concrete slab in first floor Per sqr

MIXING COST

0.50 cube ( 100.00 s. ft. )

Materials
0.5 cube mixed concrete at Rs. 29,218.50 Rs. 14,609.25
( as per item B. 04 )
Add
5 % wastage Rs. 730.46
Rs. 15,339.71

LAYING COST
Labour

2/3 day mason at Rs. 1,200.00 Rs. 800.00


2/3 day Vibrator Operator at Rs. 1,200.00 Rs. 800.00
2/3 day 3 unskilled labour at Rs. 900.00 Rs. 1,800.00
Rs. 3,400.00
Plant and equipment
2/3 day vibrator at Rs. 900.00 Rs. 600.00

5 % of labour cost for scaffolding Rs. 170.00


3 % of labour cost for tools Rs. 102.00
Rs. 272.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 19,961.71
Overheads & Profit Rs. 4,990.43
Cost for one sqr. with overheads & profits. Rs. 24,952.14
B. 45 6 " thick concrete slab in second floor

Cost for 6 " thick concrete slab in first floor Rs. 24,952.14

1/2 day 2 un skilled labour Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00

Cost for one sqr. with overheads & profits. Rs. 26,077.14

B. 46 6 " thick concrete slab in third floor Rs. 24,952.14

1/2 day 3un skilled labour Rs. 900.00 Rs. 1,350.00


Overheads & Profit Rs. 337.50
Rs. 1,687.50

Cost for one sqr. with overheads & profits. Rs. 26,639.64
Cement concrete 1 : 11/2 : 3 - ( 3/4 )
( grade 25 )

B. 47 Cement concrete 1:11/2:3 ( 3/4 " ) lintol size 4 1/2" x 6"


with and including formwork ( reinforcement paid separately )

10 l. ft.

Materials

1.85 c. ft. Concrete ( B 05 ) at. Rs. 51,076.88 Rs. 944.92


13.7 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 786.43
Rs. 1,731.35
Add

Extra cost of labour

1/8 day Skilled labour at. Rs. 1,200.00 Rs. 150.00


1/8 day Un skilled labour at. Rs. 900.00 Rs. 112.50
262.50

Overheads & Profit Rs. 65.63


Rs. 328.13
cost for 10.0 l. ft. Rs. 2,059.48

Cost for one foot with preliminaries. Rs. 205.95


B. 48 Cement concrete 1:11/2:3 ( 3/4 " ) lintol size 6" x 9"
with and including formwork ( reinforcement paid separately )

10 l. ft.

Materials
3.75 c. ft. Concrete ( B 05 ) at. Rs. 51,076.88 Rs. 1,915.38
20.00 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,148.07
Rs. 3,063.45
Add

Extra cost of labour

1/8 day Skilled labour at. Rs. 1,200.00 Rs. 150.00


1/8 day Un skilled labour at. Rs. 900.00 Rs. 112.50
262.50
Overheads & Profit 65.63
328.13
cost for 10.0 l. ft. 3,391.58

Cost for one foot with preliminaries. Rs. 339.16

B. 49 Cement concrete 1:11/2:3 ( 3/4 " ) lintol size 9" x 9 "


with and including formwork ( reinforcement paid separately )

10 l. ft.
Materials

5.63 c. ft. Concrete ( B 05 ) at. Rs. 51,076.88 Rs. 2,875.63


22.5 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,291.58
Rs. 4,167.21
Add
Extra cost of labour

1/4 day Skilled labour at. Rs. 1,200.00 Rs. 300.00


1/4 day Un skilled labour at. Rs. 900.00 Rs. 225.00
Rs. 525.00
Overheads & Profit Rs. 131.25
Rs. 656.25
cost for 10.0 l. ft. Rs. 4,823.46

Cost for one foot with preliminaries. Rs. 482.35

B. 50 Cement concrete 1:11/2:3 ( 3/4 " ) lintol size 9" x 12 "


with and including formwork ( reinforcement paid separately )

10 l. ft.
Materials

7.50 c. ft. Concrete ( B 05 ) at. Rs. 51,076.88 Rs. 3,830.77


27.72 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,591.23
Rs. 5,421.99
Add

Extra cost of labour

1/4 day Skilled labour at. Rs. 1,200.00 Rs. 300.00


1/4 day Un skilled labour at. Rs. 900.00 Rs. 225.00
Rs. 525.00
Overheads & Profit Rs. 131.25
Rs. 656.25
cost for 10.0 l. ft. Rs. 5,421.99

Cost for one foot with preliminaries. Rs. 542.20

B. 51 Cement concrete 1:11/2:3 ( 3/4 " ) lintol size 6" x 13 1/2 "
with and including formwork ( reinforcement paid separately )

10 l. ft.

Materials

5.6 c. ft. Concrete ( B 05 ) at. Rs. 51,076.88 Rs. 2,860.31


27 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,549.89
Rs. 4,410.20
Add

Extra cost of labour

1/4 day Skilled labour at. Rs. 1,200.00 Rs. 150.00


1/4 day Un skilled labour at. Rs. 900.00 Rs. 112.50
Rs. 262.50
Overheads & Profit Rs. 65.63
Rs. 328.13
cost for 10.0 l. ft. Rs. 4,738.32

Cost for one foot with preliminaries. Rs. 473.83

B. 52 Cement concrete 1:11/2:3 ( 3/4 " ) lintol size 9" x 131/2"


with and including formwork ( reinforcement paid separately )

10 l. ft.
Materials

8.4 c. ft. Concrete ( B 05 ) at. Rs. 51,076.88 Rs. 4,290.46


30 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,722.11
Rs. 6,012.56
Add

Extra cost of labour

1/4 day Skilled labour at. Rs. 1,200.00 Rs. 300.00


1/4 day Un skilled labour at. Rs. 900.00 Rs. 225.00
Rs. 525.00
Overheads & Profit Rs. 131.25
Rs. 656.25
cost for 10.0 l. ft. Rs. 6,668.81

Cost for one foot with preliminaries. Rs. 666.88

B. 53 Cement concrete 1:11/2:3 ( 3/4 " ) lintol size 12" x 13 1/2 "
with and including formwork ( reinforcement paid separately )

10 l. ft.
Materials
11.2 c. ft. Concrete ( B 05 ) at. Rs. 51,076.88 Rs. 5,720.61
22.5 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,291.58
Rs. 7,012.19
Add
Extra cost of labour

1/4 day Skilled labour at. Rs. 1,200.00 Rs. 300.00


1/4 day Un skilled labour at. Rs. 900.00 Rs. 225.00
Rs. 525.00
Overheads & Profit Rs. 131.25
Rs. 656.25
cost for 10.0 l. ft. Rs. 7,668.44

Cost for one foot with preliminaries. Rs. 766.84

B. 54 Cement concrete 1:11/2:3 ( 3/4 " ) lintol size 4 1/2" x 4 1/2 "
with and including formwork ( reinforcement paid separately )

10 l. ft.

Materials

1.37 c. ft. Concrete ( B 05 ) at. Rs. 51,076.88 Rs. 699.75


11.2 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 642.92
Rs. 1,342.67
Add

Extra cost of labour

1/8 day Skilled labour at. Rs. 1,200.00 Rs. 150.00


1/8 day Un skilled labour at. Rs. 900.00 Rs. 112.50
Rs. 262.50
Overheads & Profit Rs. 65.63
Rs. 328.13
cost for 10.0 l. ft. Rs. 1,342.67

Cost for one foot with preliminaries. Rs. 134.27


B. 55 Concrete columns in ground floor ( 1 : 11/2 : 3 3/4 " )

16 no 9 " X 9 " columns each 5 ' 0 " high

0.45 cube ( 80.00 l. ft. )

Materials
0.45 cube mixed concrete at Rs. 33,518.50 Rs. 15,083.33
( as per item B. 05 )

Add
5 % wastage Rs. 754.17
Rs. 15,837.49

LAYING COST
Labour

1/2 day mason at Rs. 1,200.00 Rs. 600.00


1/2 day skilled labour for
vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. Rs. 450.00

Add
3 % of labour cost for tools Rs. 76.50
5 % of labour cost for scaffolding Rs. 127.50
Rs. 204.00
Curing

50 gal. water at Rs. 0.50 Rs. 25.00


1/4 day unskilled labour at Rs. 900.00 Rs. 225.00
Rs. 250.00
Cost for 0.45 cubes Rs. 19,291.49

Overheads & Profit 4,822.87

24,114.36

Cost for one cube with overheads & profits. 53,587.48


in 9" x 9" columns.

B. 56 9 " x 9" Concrete columns in first floor

Cost for one cube 9 " X 9 " columns


in ground floor Rs. 53,587.48

Add

2 Un skilled labour 1/2day at. Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00

Cost for one cube with overheads & profits. Rs. 54,712.48
in 9" x 9" columns.

B. 57 9 " x 9 " Concrete columns in second floor

Cost for one cube 9 " X 9 " columns 53,587.48

Add

3 Un skilled labour 1/2day at. Rs. 900.00 Rs. 1,350.00


Overheads & Profit Rs. 337.50
Rs. 1,687.50

Cost for one cube with overheads & profits. 55,274.98


in 9" x 9" columns.

B. 58 9 " x 9 " Concrete columns in third floor

Cost for one cube 9 " X 9 " columns 53,587.48

Add

4 Un skilled labour 1/2day at. Rs. 900.00 Rs. 1,800.00


Overheads & Profit Rs. 450.00
2,250.00

Cost for one cube with overheads & profits. 55,837.48


in 9" x 9" columns.

B. 59 Concrete columns in ground floor

10 no 12 " x 12 " columns each 5 ' 0 " high

0.50 cube ( 50.00 l. ft. )

Materials
0.50 cube Mixed concrete at Rs. 33,518.50 Rs. 16,759.25
( as per item B. 05 )

Add
5 % wastage Rs. 837.96
Rs. 17,597.21

LAYING COST
Labour

0.50 day Mason at Rs. 1,200.00 Rs. 600.00


day Skilled labour for
0.50 vibrator at Rs. 1,200.00 Rs. 600.00
0.50 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
0.50 day vibrator at Rs. 900.00 Rs. 450.00
Add

3 % of labour cost for tools Rs. 76.50


5 % of labour cost for scaffolding Rs. 127.50
Rs. 204.00
Curing

50 gal. water at Rs. 0.50 Rs. 25.00


1/4 day unskilled labour at Rs. 900.00 Rs. 225.00
Rs. 250.00
Rs. 21,051.21
Overheads & Profit Rs. 5,262.80
cost for .50 cube coloumn Rs. 26,314.02

Cost for one cube with overheads & profits. 52,628.03


in 12" x 12" columns.

B. 60 12 " x 12 " Concrete columns in first floor

Cost for one cube 12 " X 12 " columns Rs. 52,628.03

Add

2 Un skilled labour 1/2day at. Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00

Cost for one cube with overheads & profits. Rs. 53,753.03
in 12" x 12" columns.

B. 61 12 " x 12 " Concrete columns in second floor

Cost for one cube 12 " X 12 " columns Rs. 52,628.03

Add
3 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,350.00
Overheads & Profit Rs. 337.50
Rs. 1,687.50

Cost for one cube with overheads & profits. Rs. 54,315.53
in 12" x 12" columns.

B. 62 12 " x 12 " Concrete columns in third floor

Cost for one cube 12 " X 12 " columns 52,628.03 52,628.03

Add

4 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,800.00


Overheads & Profit Rs. 450.00
2,250.00

Cost for one cube with overheads & profits. 54,878.03


in 12" x 12" columns.

B. 63 9 " x 9 " Concrete beams in ground floor level

8 no 9 " X 9 " beam 10' 0" ft long

0.45 cube ( 80.00 l. ft. )

Materials
0.45 cube mixed concrete at Rs. 33,518.50 Rs. 15,083.33
( as per item B. 05 )
Add
5 % wastage Rs. 754.17
Rs. 15,837.49

LAYING COST
Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00
Add

5 % of labour cost for scaffolding Rs. 127.50


3 % of labour cost for tools Rs. 76.50
Rs. 204.00
Curing
100 gal. water at Rs. 0.50 Rs. 50.00
1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 19,391.49
Overheads & Profit Rs. 4,847.87
Rs. 24,239.36

Cost for one cube with overheads & profits. Rs. 53,865.25
in 9" x 9" beam.

B. 64 9 " x 9" Concrete beam in first floor

1 cube

Cost of one cube in 9 " X 9 " beam in ground floor. Rs. 53,865.25

Add

2 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00
Cost for one cube with overheads & profits.
in 9" x 9" beam. Rs. 54,990.25

B. 65 9 " x 9 " Concrete beam in second floor

Cost of one cube in 9 " X 9 " beam in ground floor. Rs. 53,865.25

Add
3 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,350.00
Overheads & Profit Rs. 337.50
Rs. 1,687.50

Cost for one cube with overheads & profits.


in 9" x 9" beam. Rs. 55,552.75

B. 66 9 " x 9 " Concrete beam in third floor

Cost of one cube in 9 " X 9 " beam in ground floor. Rs. 53,865.25

Add

4 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,800.00


Overheads & Profit Rs. 450.00
Rs. 2,250.00

Cost for one cube with overheads & profits.


in 9" x 9" beam. Rs. 56,115.25

B. 67 Concrete beams in ground floor level 9" x 12"

6 no 9 " X 12 " beam 10' 0" ft long

0.50 cube ( 60.00 l. ft. )

Materials
0.50 cube mixed concrete at Rs. 33,518.50 Rs. 16,759.25
( as per item B. 04 )
Add
5 % wastage Rs. 837.96
Rs. 17,597.21

LAYING COST
Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00

Add

5 % of labour cost for scaffolding Rs. 127.50


3 % of labour cost for tools Rs. 76.50
Rs. 204.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 21,151.21
Overheads & Profit Rs. 5,287.80
Rs. 26,439.02

Cost for one cube with overheads & profits. 52,878.03


in 9" x 12" beam.

B. 68 Concrete beam in first floor 9" x 12"

1 cube

For one cube 9 " x 12 " beam in ground floor Rs. 52,878.03

2 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00
Cost for one cube with overheads & profits.
in 9" x 12" beam. Rs. 54,003.03

B. 69 Concrete beam in second floor 9" x 12"


1 cube

For one cube 9 " x 12 " beam in ground floor 52,878.03

3 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,350.00


Overheads & Profit Rs. 337.50
Rs. 1,687.50
Cost for one cube with overheads & profits.
in 9" x 12" beam. Rs. 54,565.53

B. 70 Concrete beam in third floor 9" x 12"

1 cube

6 no 9 " X 12 " beam each 10 ' 0 " long Rs. 52,878.03

4 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,800.00


Overheads & Profit Rs. 450.00
Rs. 2,250.00
Cost for one cube with overheads & profits.
in 9" x 12" beam. Rs. 55,128.03

B. 71 Concrete beams in ground floor level 12" x 12"

5 no 12 " X 12 " beam 10' 0" ft long

0.50cube ( 50 l. ft. )

Materials
0.5 cube mixed concrete at Rs. 33,518.50 Rs. 16,759.25
( as per item B. 05 )
Add
5 % wastage Rs. 837.96
Rs. 17,597.21

LAYING COST
Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00

Add

5 % of labour cost for scaffolding Rs. 127.50


3 % of labour cost for tools Rs. 76.50
Rs. 204.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 21,151.21
Overheads & Profit Rs. 5,287.80
Rs. 26,439.02
Cost for one cube with preliminaeies
in 12" x 12" beam. Rs. 52,878.03

B. 72 Concrete beam in first floor 12" x 12"

For one cube 12 " x 12 " beam in ground floor Rs. 52,878.03

2 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00
Cost for one cube with overheads & profits.
in 12" x 12" beam. Rs. 54,003.03
B. 73 Concrete beam in second floor 12" x 12" 1 cube

For one cube 12 " x 12 " beam in ground floor Rs. 52,878.03

3 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,350.00


Overheads & Profit Rs. 337.50
Rs. 1,687.50
Cost for one cube with overheads & profits.
in 12" x 12" beam. Rs. 54,565.53

B. 74 Concrete beam in thired floor 12" x 12" 1 cube

For one cube 12 " x 12 " beam in ground floor 52,878.03

4 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,800.00


Overheads & Profit Rs. 450.00
Rs. 2,250.00
Cost for one cube with overheads & profits.
in 12" x 12" beam. Rs. 55,128.03

B. 75 4 " thick concrete slab in first floor Per 1 sqr

0.33 cube ( 100.00 s. ft. )

Materials
0.33 cube mixed concrete at Rs. 33,518.50 Rs. 11,061.11
( as per item B. 05 )
Add
5 % wastage Rs. 553.06
Rs. 11,614.16

LAYING COST
Labour
1/3 day mason at Rs. 1,200.00 Rs. 400.00
day skilled labour for
1/3 vibrator at Rs. 1,200.00 Rs. 400.00
1/3 day 3 unskilled labour at Rs. 900.00 Rs. 900.00
Rs. 1,700.00
Plant and equipment
1/3 day vibrator at Rs. 900.00 Rs. Rs. 300.00

Add

5 % of labour cost for scaffolding Rs. 85.00


3 % of labour cost for tools Rs. 51.00
Rs. 136.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
350.00 Rs. 350.00
Rs. 14,100.16

Overheads & Profit Rs. 3,525.04

Cost for one sqr. with overheads & profits. Rs. 17,625.20

B. 76 4 " thick concrete slab in second floor Per 1 sqr

Cost for 4 " thick concrete slab in ground floor Rs. 17,625.20

1/3 day 2 un skilled labour Rs. 900.00 Rs. 600.00


Overheads & Profit Rs. 150.00
Rs. 750.00

Cost for one sqr. with overheads & profits. Rs. 18,375.20
B. 77 4 " thick concrete slab in third floor Per 1 sqr

Cost for 4 " thick concrete slab in ground floor Rs. 17,625.20

1/3 day 3 un skilled labour Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00

Cost for one sqr. with overheads & profits. Rs. 18,750.20

B. 78 5 " thick concrete slab in first floor Per 1 sqr

MIXING COST

0.42 cube ( 100.00 s. ft. )

Materials
0.42 cube mixed concrete at Rs. 33,518.50 Rs. 14,077.77
( as per item B. 05 )
Add
5 % wastage Rs. 1,675.93
Rs. 15,753.70

LAYING COST

Labour

1/2 day mason at Rs. 1,200.00 Rs. 600.00


day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00

Add

5 % of labour cost for scaffolding Rs. 127.50


3 % of labour cost for tools Rs. 76.50
Rs. 204.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 19,307.70

Overheads & Profit Rs. 4,826.92

Cost for one sqr. with overheads & profits. Rs. 24,134.62

B. 79 5 " thick concrete slab in second floor Per 1 sqr

Cost for 5 " thick concrete slab in ground floor Rs. 24,134.62

1/3 day 2 un skilled labour Rs. 900.00 Rs. 600.00


Overheads & Profit Rs. 150.00
Rs. 750.00
Cost for one sqr. with overheads & profits. Rs. 24,884.62

B. 80 5 " thick concrete slab in third floor Per 1 sqr

Cost for 5" thick concrete slab in ground floor Rs. 24,134.62

1/3 day 3 un skilled labour Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00

Cost for one sqr. with overheads & profits. Rs. 25,259.62

B. 81 6 " thick concrete slab in first floor Per 1 sqr

MIXING COST

0.50 cube ( 100.00 s. ft. )


Materials
0.5 cube mixed concrete at Rs. 33,518.50 Rs. 16,759.25
( as per item B. 05 )
Add
5 % wastage Rs. 837.96
Rs. 17,597.21

LAYING COST
Labour

2/3 day mason at Rs. 1,200.00 Rs. 800.00


2/3 day Vibrator Operator at Rs. 1,200.00 Rs. 800.00
2/3 day 3 unskilled labour at Rs. 900.00 Rs. 1,800.00
Rs. 3,400.00
Plant and equipment
2/3 day vibrator at Rs. 900.00 Rs. 600.00

5 % of labour cost for scaffolding Rs. 170.00


3 % of labour cost for tools Rs. 102.00
Rs. 272.00
Curing

100 gal. water at Rs. 0.50 Rs. 50.00


1/3 day unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
Rs. 22,219.21

Overheads & Profit Rs. 5,554.80

Cost for one sqr. with overheads & profits. Rs. 27,774.02

B. 82 6 " thick concrete slab in second floor Per 1 sqr

Cost for 6 " thick concrete slab in ground floor Rs. 27,774.02

1/3 day 2 un skilled labour Rs. 900.00 Rs. 600.00


Preliminaries Rs. 150.00
Rs. 750.00

Cost for one sqr. with overheads & profits. Rs. 28,524.02

B. 83 6 " thick concrete slab in third floor Per 1 sqr

Cost for 6 " thick concrete slab in ground floor Rs. 27,774.02

1/3 day 3 un skilled labour Rs. 900.00 Rs. 900.00


Overheads & Profit Rs. 225.00
Rs. 1,125.00

Cost for one sqr. with overheads & profits. Rs. 28,899.02
12369 m3
8,546.00