BASIC PRICES
Materials
Labour
B. 38 4" thick slab in first floor ( 1: 2: 4 3/4 " ) sqr. Rs. 16,490.26
B. 39 4" thick slab in second floor ( 1: 2: 4 3/4 " ) sqr. Rs. 17,240.26
B. 40 4" thick slab in thired floor ( 1: 2: 4 3/4 " ) sqr. Rs. 18,177.76
B. 41 5" thick slab in first floor ( 1: 2: 4 3/4 " ) sqr. Rs. 21,608.37
B. 42 5" thick slab in second floor ( 1: 2: 4 3/4 " ) sqr. Rs. 22,733.37
B. 43 5" thick slab in thired floor ( 1: 2: 4 3/4 " ) sqr. Rs. 23,295.87
B. 44 6" thick slab in first floor ( 1: 2: 4 3/4 " ) sqr. Rs. 24,952.14
B. 45 6" thick slab in second floor ( 1: 2: 4 3/4 " ) sqr. Rs. 26,077.14
B. 46 6" thick slab in thired floor ( 1: 2: 4 3/4 " ) sqr. Rs. 26,639.64
B. 75 4" thick slab in first floor ( 1: 11/2: 3 -3/4 " ) sqr. Rs. 17,625.20
B. 76 4" thick slab in second floor ( 1: 11/2: 3 -3/4 " ) sqr. Rs. 18,375.20
B. 77 4" thick slab in thired floor ( 1: 11/2: 3 - 3/4 " ) sqr. Rs. 18,750.20
B. 78 5" thick slab in first floor ( 1: 11/2: 3 - 3/4 " ) sqr. Rs. 24,134.62
B. 79 5" thick slab in second floor ( 1: 11/2: 3 3/4 " ) sqr. Rs. 24,884.62
B. 80 5" thick slab in thired floor ( 1: 11/2: 3 3/4 " ) sqr. Rs. 25,259.62
B. 81 6" thick slab in first floor ( 1: 11/2: 3 3/4 " ) sqr. Rs. 27,774.02
B. 82 6" thick slab in second floor ( 1: 11/2: 3 3/4 " ) sqr. Rs. 28,524.02
B. 83 6" thick slab in thired floor ( 1: 11/2: 3 3/4 " ) sqr. Rs. 28,899.02
B. 01 Concrete 1 : 3 : 6 ( 2 " ) grade 10 Per Cube
MIXING COST
Materials
LAYING COST
Labour
Add
3 % of labour cost for tools Rs. 135.00
5 % of labour cost for scaffolding Rs. 225.00
Rs. 360.00
Curing
100 gal. Water at Rs. 0.50 Rs. 50.00
0.33 day Unskilled labour at Rs. 900.00 Rs. 300.00
Rs. 350.00
28,003.50
MIXING COST
Materials
Labour
1/3 day
Concrete mixer 14/10 at. Rs, 1,500.00 Rs. 500.00
LAYING COST
Labour
Add
Cost for one cube with overheads & profits. Rs. 37,293.13
MIXING COST
Materials
1/3 day concrete mixer 14/10 at. Rs, 1,500.00 Rs. 500.00
LAYING COST
Labour
Add
Cost for one cube with overheads & profits. Rs. 41,026.88
MIXING COST
Materials
LAYING COST
Labour
Add
3 % of labour cost for tools Rs. 175.50
5 % of labour cost for scaffolding Rs. 292.50
468.00
Curing
MIXING COST
Materials
LAYING COST
Labour
Add
3 % of labour cost for tools Rs. 175.50
5 % of labour cost for scaffolding Rs. 292.50
Rs. 468.00
Curing
Cost for one cube with overheads & profits. Rs. 51,076.88
MIXING COST
Materials
LAYING COST
Labour
Cost for one cube with overheads & profits. Rs. 58,866.88
Per sqr.
Materials
Labour
Tools
5 % of labour cost Rs. 60.00
Rs. 5,396.16
Add
Overheads & Profit Rs. 1,349.04
Cost for one sqr. with overheads & profits. Rs. 6,745.20
B. 07 2" thick blinding layer under wall / column foundation ( 1 : 3 : 6 - 1 " )
Per sqr.
Materials
Labour
4 Unskilled labour 1/ 4 day at. Rs. 900.00 Rs. 900.00 Rs. 1,200.00
Tools
Cost for one sqr. with overheads & profits. Rs. 6,832.39
B. 08 3" thick blinding layer under wall / column foundation ( 1 : 3 : 6 - 1" )
Per sqr.
Materials
0.25 cube mixed concrete at. Rs. 22,491.50 Rs. 5,622.88
( as per item B. 02 )
Cost for one sqr. with overheads & profits. Rs. 9,306.45
note
For laying concrete at depths more than 5 ' 0 " add 1/4 extra day unskilled labour
B. 09 4 " thick ground floor slab. ( 1 : 3 : 6 1 " )
Per sqr.
Materials
0.33 cube mixed concrete at. Rs. 22,491.50 Rs. 7,497.17
( as per item B. 02 )
1.00 skilled labour 1/3 day at. Rs. 1,200.00 Rs. 400.00
4.00 unskilled labour 1/3 day at. Rs. 900.00 Rs. 1,200.00
Rs. 1,600.00
Plant and equipment
0.25 day vibrator at. Rs. 900.00 Rs. 225.00
Add
10 l. ft.
Materials
10 l. ft.
Materials
3.75 c. ft. Concrete ( B 04 ) at. Rs. 45,701.88 Rs. 1,713.82
20.00 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,148.07
Rs. 2,861.89
Add
10 l. ft.
Materials
10 l. ft.
Materials
B. 14 Cement concrete 1:2:4 ( 3/4 " ) lintol size 6" x 13 1/2 "
with and including formwork ( reinforcement paid separately )
10 l. ft.
Materials
10 l. ft.
Materials
B. 16 Cement concrete 1:2:4 ( 3/4 " ) lintol size 12" x 13 1/2 "
with and including formwork ( reinforcement paid separately )
10 l. ft.
Materials
B. 17 Cement concrete 1:2:4 ( 3/4 " ) lintol size 4 1/2" x 4 1/2 "
with and including formwork ( reinforcement paid separately )
10 l. ft.
Materials
Materials
0.45 cube mixed concrete at Rs. 29,218.50 Rs. 13,148.33
( as per item B. 04 )
Add
5 % wastage Rs. 657.42
Rs. 13,805.74
LAYING COST
Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
1/2 day skilled labour for
vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. Rs. 450.00
Add
3 % of labour cost for tools Rs. 76.50
5 % of labour cost for scaffolding Rs. 127.50
Rs. 204.00
Curing
21,574.68
Add
Cost for one cube with overheads & profits. Rs. 49,068.73
in 9" x 9" columns.
B. 20 9 " x 9 " Concrete columns in second floor
Add
Add
Materials
0.50 cube mixed concrete at Rs. 29,218.50 Rs. 14,609.25
( as per item B. 04 )
Add
5 % wastage Rs. 730.46
Rs. 15,339.71
LAYING COST
Labour
Add
Add
Add
Cost for one cube with overheads & profits. Rs. 48,671.78
in 12" x 12" columns.
Add
Materials
0.45 cube mixed concrete at Rs. 29,218.50 Rs. 13,148.33
( as per item B. 04 )
Add
5 % wastage Rs. 657.42
Rs. 13,805.74
LAYING COST
Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00
Add
Cost for one cube with overheads & profits. Rs. 48,221.50
in 9" x 9" beam.
1 cube
Add
2 Un skilled labour 1/2 day Rs. 900.00 Rs. 900.00
Preliminaries Rs. 225.00
Rs. 1,125.00
1 cube
Add
3 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,350.00
Overheads & Profit Rs. Rs. 337.50
Rs. 1,687.50
1 cube
Add
4 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,800.00
Overheads & Profit Rs. 450.00
Rs. 2,250.00
Cost for one cube with overheads & profits.
in 9" x 9" beam. Rs. 50,471.50
Materials
0.5 cube mixed concrete at Rs. 29,218.50 Rs. 14,609.25
( as per item B. 04 )
Add
5 % wastage Rs. 730.46
Rs. 15,339.71
LAYING COST
Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00
Add
1 cube
Cost for one cube with overheads & profits. Rs. 48,359.28
in 9" x 12" beam.
1 cube
Add
3 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,350.00
Overheads & Profit Rs. 337.50
Rs. 1,687.50
Cost for one cube with overheads & profits. Rs. 48,921.78
in 9" x 12" beam.
1 cube
Add
4 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,800.00
Overheads & Profit Rs. 450.00
Rs. 2,250.00
Cost for one cube with overheads & profits. Rs. 49,484.28
in 9" x 12" beam.
Materials
0.5 cube mixed concrete at Rs. 29,218.50 Rs. 14,609.25
( as per item B. 04 )
Add
5 % wastage Rs. 730.46
Rs. 15,339.71
LAYING COST
Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00
Add
Add
2 Un skilled labour 1/2 day Rs. 900.00 Rs. 900.00
Overheads & Profit Rs. 225.00
Rs. 1,125.00
Cost for one cube with overheads & profits. Rs. 48,359.28
in 12" x 12" beam.
1 cube
Add
3 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,350.00
Overheads & Profit Rs. 337.50
Rs. 1,687.50
Cost for one cube with overheads & profits. Rs. 48,921.78
in 12" x 12" beam.
1 cube
Add
4 Un skilled labour 1/2 day Rs. 900.00 Rs. 1,800.00
Overheads & Profit Rs. 450.00
Rs. 2,250.00
Cost for one cube with overheads & profits. Rs. 49,484.28
in 12" x 12" beam.
B. 38 4 " thick concrete slab in first floor
Per sqr
Materials
0.33 cube mixed concrete at Rs. 29,218.50 Rs. 9,642.11
( as per item B. 04 )
Add
5 % wastage Rs. 482.11
Rs. 10,124.21
LAYING COST
Labour
Add
Cost for 4 " thick concrete slab in ground floor Rs. 16,490.26
Cost for one sqr. with overheads & profits. Rs. 17,240.26
Cost for 4 " thick concrete slab in ground floor Rs. 16,490.26
Cost for one sqr. with overheads & profits. Rs. 18,177.76
B. 41 5 " thick concrete slab in first floor Per sqr
MIXING COST
Materials
0.42 cube mixed concrete at Rs. 29,218.50 Rs. 12,271.77
( as per item B. 04 )
Add
5 % wastage Rs. 1,460.93
Rs. 13,732.70
LAYING COST
Labour
Add
Cost for 5 " thick concrete slab in ground floor Rs. 21,608.37
Cost for one sqr. with overheads & profits. Rs. 22,733.37
Cost for 5" thick concrete slab in ground floor Rs. 21,608.37
Cost for one sqr. with overheads & profits. Rs. 23,295.87
B. 44 6 " thick concrete slab in first floor Per sqr
MIXING COST
Materials
0.5 cube mixed concrete at Rs. 29,218.50 Rs. 14,609.25
( as per item B. 04 )
Add
5 % wastage Rs. 730.46
Rs. 15,339.71
LAYING COST
Labour
Cost for 6 " thick concrete slab in first floor Rs. 24,952.14
Cost for one sqr. with overheads & profits. Rs. 26,077.14
Cost for one sqr. with overheads & profits. Rs. 26,639.64
Cement concrete 1 : 11/2 : 3 - ( 3/4 )
( grade 25 )
10 l. ft.
Materials
10 l. ft.
Materials
3.75 c. ft. Concrete ( B 05 ) at. Rs. 51,076.88 Rs. 1,915.38
20.00 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,148.07
Rs. 3,063.45
Add
10 l. ft.
Materials
10 l. ft.
Materials
B. 51 Cement concrete 1:11/2:3 ( 3/4 " ) lintol size 6" x 13 1/2 "
with and including formwork ( reinforcement paid separately )
10 l. ft.
Materials
10 l. ft.
Materials
B. 53 Cement concrete 1:11/2:3 ( 3/4 " ) lintol size 12" x 13 1/2 "
with and including formwork ( reinforcement paid separately )
10 l. ft.
Materials
11.2 c. ft. Concrete ( B 05 ) at. Rs. 51,076.88 Rs. 5,720.61
22.5 s. ft. Sawn formwork at. Rs. 5,740.35 Rs. 1,291.58
Rs. 7,012.19
Add
Extra cost of labour
B. 54 Cement concrete 1:11/2:3 ( 3/4 " ) lintol size 4 1/2" x 4 1/2 "
with and including formwork ( reinforcement paid separately )
10 l. ft.
Materials
Materials
0.45 cube mixed concrete at Rs. 33,518.50 Rs. 15,083.33
( as per item B. 05 )
Add
5 % wastage Rs. 754.17
Rs. 15,837.49
LAYING COST
Labour
Add
3 % of labour cost for tools Rs. 76.50
5 % of labour cost for scaffolding Rs. 127.50
Rs. 204.00
Curing
24,114.36
Add
Cost for one cube with overheads & profits. Rs. 54,712.48
in 9" x 9" columns.
Add
Add
Materials
0.50 cube Mixed concrete at Rs. 33,518.50 Rs. 16,759.25
( as per item B. 05 )
Add
5 % wastage Rs. 837.96
Rs. 17,597.21
LAYING COST
Labour
Add
Cost for one cube with overheads & profits. Rs. 53,753.03
in 12" x 12" columns.
Add
3 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,350.00
Overheads & Profit Rs. 337.50
Rs. 1,687.50
Cost for one cube with overheads & profits. Rs. 54,315.53
in 12" x 12" columns.
Add
Materials
0.45 cube mixed concrete at Rs. 33,518.50 Rs. 15,083.33
( as per item B. 05 )
Add
5 % wastage Rs. 754.17
Rs. 15,837.49
LAYING COST
Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00
Add
Cost for one cube with overheads & profits. Rs. 53,865.25
in 9" x 9" beam.
1 cube
Cost of one cube in 9 " X 9 " beam in ground floor. Rs. 53,865.25
Add
Cost of one cube in 9 " X 9 " beam in ground floor. Rs. 53,865.25
Add
3 Un skilled labour 1/2 day at. Rs. 900.00 Rs. 1,350.00
Overheads & Profit Rs. 337.50
Rs. 1,687.50
Cost of one cube in 9 " X 9 " beam in ground floor. Rs. 53,865.25
Add
Materials
0.50 cube mixed concrete at Rs. 33,518.50 Rs. 16,759.25
( as per item B. 04 )
Add
5 % wastage Rs. 837.96
Rs. 17,597.21
LAYING COST
Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00
Add
1 cube
For one cube 9 " x 12 " beam in ground floor Rs. 52,878.03
1 cube
0.50cube ( 50 l. ft. )
Materials
0.5 cube mixed concrete at Rs. 33,518.50 Rs. 16,759.25
( as per item B. 05 )
Add
5 % wastage Rs. 837.96
Rs. 17,597.21
LAYING COST
Labour
1/2 day mason at Rs. 1,200.00 Rs. 600.00
day skilled labour for
1/2 vibrator at Rs. 1,200.00 Rs. 600.00
1/2 day 3 unskilled labour at Rs. 900.00 Rs. 1,350.00
Rs. 2,550.00
Plant and equipment
1/2 day vibrator at Rs. 900.00 Rs. 450.00
Add
For one cube 12 " x 12 " beam in ground floor Rs. 52,878.03
For one cube 12 " x 12 " beam in ground floor Rs. 52,878.03
Materials
0.33 cube mixed concrete at Rs. 33,518.50 Rs. 11,061.11
( as per item B. 05 )
Add
5 % wastage Rs. 553.06
Rs. 11,614.16
LAYING COST
Labour
1/3 day mason at Rs. 1,200.00 Rs. 400.00
day skilled labour for
1/3 vibrator at Rs. 1,200.00 Rs. 400.00
1/3 day 3 unskilled labour at Rs. 900.00 Rs. 900.00
Rs. 1,700.00
Plant and equipment
1/3 day vibrator at Rs. 900.00 Rs. Rs. 300.00
Add
Cost for one sqr. with overheads & profits. Rs. 17,625.20
Cost for 4 " thick concrete slab in ground floor Rs. 17,625.20
Cost for one sqr. with overheads & profits. Rs. 18,375.20
B. 77 4 " thick concrete slab in third floor Per 1 sqr
Cost for 4 " thick concrete slab in ground floor Rs. 17,625.20
Cost for one sqr. with overheads & profits. Rs. 18,750.20
MIXING COST
Materials
0.42 cube mixed concrete at Rs. 33,518.50 Rs. 14,077.77
( as per item B. 05 )
Add
5 % wastage Rs. 1,675.93
Rs. 15,753.70
LAYING COST
Labour
Add
Cost for one sqr. with overheads & profits. Rs. 24,134.62
Cost for 5 " thick concrete slab in ground floor Rs. 24,134.62
Cost for 5" thick concrete slab in ground floor Rs. 24,134.62
Cost for one sqr. with overheads & profits. Rs. 25,259.62
MIXING COST
LAYING COST
Labour
Cost for one sqr. with overheads & profits. Rs. 27,774.02
Cost for 6 " thick concrete slab in ground floor Rs. 27,774.02
Cost for one sqr. with overheads & profits. Rs. 28,524.02
Cost for 6 " thick concrete slab in ground floor Rs. 27,774.02
Cost for one sqr. with overheads & profits. Rs. 28,899.02
12369 m3
8,546.00