Professional Documents
Culture Documents
PROGRAM MANAGER
PREPARED BY: T. MISKELL STANDARDS ENGINEERING - 9390
MANAGER
APPROVED FOR CONTENT: D. CELLI FIELD OPERATIONS - 8157
PROGRAM MANAGER
APPROVED FOR PUBLICATION: T. MISKELL STANDARDS ENGINEERING - 9390
Versions
1.2 The exact hydrostatic test process will b. When ALSTOM Power designs
depend on local job site conditions. Since this and fabricates a boiler in accordance with the
procedure is general in nature, it shall be ASME Code, it is our responsibility to register it
followed as conditions allow, in conjunction with with the National Board.
the subject Contract Instruction Manual.
c. An ASME Master Code Data
1.3 The unit shall be hydrostatically Report is assembled for each project. The report
tested for conformance to ASME Code consists of: Form P3A, Form P7 and Form P4
requirements in two areas: from the Fabricators. This package will be sent
from Windsor to the Site Manager prior to
1.3.1 Primary Circuitry (Drums, hydrostatic testing. The Contractor who erected
Economizers, Water Walls, Steam Cooled Walls, the boiler must, after the successful site
Superheater). hydrostatic test, sign the back of the P3A or P3
Forms in the "Certificate of Field Assembly
1.3.2 Reheater(s). Compliance" block and have the site's Authorized
Inspector sign the "Certificate of Field Assembly
1.4 Upon request, the Project Engineer Inspection" block.
shall supply assistance or additional information
for hydrostatic testing. Note: To make it easier to identify the originals,
please sign in blue ink. The entire report is
1.5 Reports returned to:
e. The original ASME Master Code 2.1.3 All necessary valves, including
Data Report will be filed with the National Board drains, installed and closed.
and copies will be distributed, as required, by
QA. 2.1.4 All safety valves installed or
openings blanked off.
1.5.2 The following information about
leaks during hydro test is to be reported a. Safety valves shall not be
immediately to the Project Engineer in Windsor gagged at this time.
both by phone and by TIR (Technical Information
Request). b. Check that hydrostatic test plugs
were installed where necessary and gags are
a. Exact location of leak(s) - available and fit correctly.
component circuit, elevation, material, etc.
c. Detailed instructions are
b. Description of leak(s) - in straight provided by the Manufacturers for hydrostatic
tube, elbow, shop or field weld, torch cut where a testing safety valves. These instructions must be
lug was removed, attachment weld, etc. adhered to without change.
2.1.7 All vents necessary to prevent air 2.2.2 One gauge shall be located at
entrapment during filling opened (such as the hydrostatic test pump.
superheater link vents, economizer link vents,
drum vents, etc.). 2.2.3 One gauge shall be located
near the highest elevation of the boiler for test
2.1.8 All gamma ray or radiographic pressure.
openings have their plugs installed and seal
welded. 2.2.4 A connection shall be provided
for the Inspector's test gauge. A check with the
2.1.9 The blanking off plates for the local Inspector(s) can verify if this is a technique
circulating pumps, when used, are installed. to be used.
2.1.10 All spring and constant support 2.3.4 The air should be filtered and
hangers and supports must be blocked to avoid free of oil prior to entering the unit.
overextending and potential damage due to the
additional water weight from pressure parts 3.0 Filling
being completely filled for the hydrostatic tests.
Refer to Standard 76-75 and Drawing B-983-0300. 3.1 The Contract Documents will state
This applies to all Pressure Part Constant and who has the responsibility to provide the properly
Variable supports as well as Boiler and Non- treated water at the specified temperature for the
Boiler external Piping. hydrostatic test.
c. Remainder of Boiler Unit 3.3 The use of a vacuum pump can help
substantially in speeding up the filling time for a
Fill with condensate type water boiler.
or, if not available, with a clean source of filtered
water containing 10 PPM of ammonia and 200 3.3.1 A vacuum pump will also help to
PPM of hydrazine, with a solution of pH value of partially evacuate air from many areas where it
approximately 10.0. might be trapped when using normal filling
procedures.
3.1.2 The water temperature during
hydro testing shall be no less than 70o F per 3.3.2 The following general
Section I of the ASME Boiler and Pressure Vessel procedures shall be incorporated when using
Code. vacuum assist filling.
3.2.1 The sequence of filling the non- e. Turn on the vacuum source and
drainable areas will be dictated by the design of start filling the boiler with water. Care must be
the boiler. Generally, fill the superheater exercised to minimize the amount of water
through a suitable outlet connection (such as getting into the vacuum pump.
final superheater outlet header drain or vent)
until all elements are filled and the water 3.4 As the unit fills, periodically check for
overflows into the steam drum. Close leaks.
superheater fill connection.
SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 7 of 10
4.4 Hydro Testing the Primary Circuitry 4.6.2 Ensure that all personnel doing
the inspection are equipped with appropriate
4.4.1 The primary circuitry will be illumination devices, safety equipment, clothing
tested at 1.5 times the maximum allowable and safety goggles. High pressure water jets and
working pressure. chemicals can cause injury.
a. Start hydro pump and raise the 4.6.3 It is recommended that the
pressure to 80% of the pressure stamped on the inspection teams work in pairs especially in
lowest safety valve setting. Hand-tighten safety conditions where inspections are not visible from
valve gags per the Manufacturer's boiler walkways or inside of the boiler walls.
recommendations.
4.6.4 The areas of the boiler pressure
b. Raise the pressure to the parts to be inspected should be divided up to the
hydrostatic test pressure. respective inspection teams. It is suggested that
the Field Weld Data Summary sheets be given to
The pressure shall be under each inspection team so that all welds inspected
proper control at all times so that the required can be noted.
test pressure is never exceeded by more than 6%.
SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 8 of 10
4.6.5 Unless there are significantly 4.7.3 Make the required repair(s).
large leaks during the test, complete an entire
inspection of the unit, noting all areas of actual 4.7.4 Refill the unit per Paragraph 3.2.
and suspected leakage. Suspected tube leaks
should be marked using a non-water soluble 4.7.5 Re-hydro per Paragraph 4.0.
marker such as a paint stick.
5.0 Post Hydrostatic Test Procedure
4.6.6 If repairs are to be required,
shut down the hydrostatic pump, release the 5.1 The local job conditions and contract
pressure, remove the safety valve gags an drain specifications will dictate what laying-up
down the boiler to an elevation below the procedures are necessary for the boiler.
indicated repair location if possible.
5.1.1 This may include protection of
4.6.7 When repairs have been non-drainable areas from freezing and a
completed, the entire unit should be re-tested possible nitrogen blanket on the drainable areas
using the test procedure until no leaks are found. of the boiler.
At this time, the test pump should be isolated.
The boiler should be re-inspected for any leaks. Caution: When nitrogen is used, thorough
There may be some pressure variation due to ventilation is essential before entering boiler
temperature changes or leaking valves. When drums.
the Authorized Inspector is satisfied with the
results, release the test pressure and drain the 5.1.2 When the boiler is laid up with
boiler. water in it, the water must meet the criteria in
Paragraph 3.1.1
4.7 Releasing Test Pressure
5.1.3 Laying-up is normally the
4.7.1 Upon completion of either the Customer's responsibility. When the Contractor
primary circuitry or reheater test, or if leaks are is responsible, it is a joint Projects and Field
found, it will be necessary to release the Operations responsibility.
pressure.
5.2 Draining the Boiler
a. When valves are in tandem
(double valved), test pressure should be released 5.2.1 Open the boiler vent valves and
at a moderate rate with the outboard valve, while drain all drainable sections of the boiler.
the inboard valve is opened wide. This is to
prevent the valve seat of the pressure side valve 5.2.2 If wet lay-up is to be used, fill the
from being damaged. unit with hydrazine and ammonia treated water
per the Contract Instruction Manual to
b. Gag pressure on safety valves overflowing at the drum vents. Introduce
should be released when hydrostatic test pressure nitrogen through the drum vent to pressurize the
is 85-90% of the pressure on the lowest set valve unit approximately 3-5 psi.
per the Manufacturer's recommendations.
5.2.3 Since there is generally some
4.7.2 Drain the areas necessary to time delay between the hydrostatic test and the
make the repairs. initial boiling out and acid cleaning of the unit,
the water level should not be allowed to remain
at operating level.
SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 9 of 10
Attachment "A"
Hydrostatic Test Water Sample
2. _________________________________________
3. _________________________________________
**Source of Sample
____________________________________________________________________________________
Nitrogen Pressure Maintained between Hydro and Boil-Out _____ Yes _____ No
* Complete Description of Source - Example: City of Albany, zeolite softened; well water, demineralized;
station condensate; e-c.
** Source of Sample - Example: Superheater outlet header drain, superheater intermediate pendant inlet
header drain, horizontal superheater inlet header drain, etc.
Precaution: If sampling water from horizontal superheater, make certain that the same water is used to fill
this section as was used in the pendant sections. If not, take the sample from the location representative of
the water in non-drainable pendant sections.