You are on page 1of 10

THIS STANDARD IS: STD NO : 110-75-04

Updated INDEX : 4.9.2


DESIGN STANDARD DATE : 28 APR 2006
OWNER : 8157
PAGE : 1 OF 10

SUBJECT : HYDROSTATIC TESTING - NATURAL AND CONTROLLED CIRCULATION BOILERS

PURPOSE : To provide recommended hydrostatic test procedures.

REMARKS: This Standard to be effective immediately.

NOTES: 1. See Page 2 for Versions.


2. Standard No. 17-75, Index 4.9.2 has been incorporated into this Standard.

PROGRAM MANAGER
PREPARED BY: T. MISKELL STANDARDS ENGINEERING - 9390
MANAGER
APPROVED FOR CONTENT: D. CELLI FIELD OPERATIONS - 8157
PROGRAM MANAGER
APPROVED FOR PUBLICATION: T. MISKELL STANDARDS ENGINEERING - 9390

This document contains proprietary data and shall not be reproduced


or disclosed without the permission of ALSTOM Power Inc.
SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 2 of 10

UNITS: „ ENGLISH; † METRIC; † BOTH; † NONE


PRODUCT LINES: CHECK THE PRODUCT LINES THAT THE STANDARD IS APPLICABLE TO
† ALL; „ A = CONTROLLED CIRC. BOILERS † H = HEAT RECOVERY STEAM GENERATORS (HRSG)
† B = SUPERCRITICAL BOILERS † P = PULVERIZERS – MILLING SYSTEM
„ C = VU40 AND VU60 BOILERS „ R = CHEMICAL RECOVERY BOILERS
„ E = FLUIDIZED BED BOILERS (CFB) † S = SERVICES (AFTER MARKET USE)
„ F = NATURAL CIRC. BOILERS (UTILITY)

Versions

Ver. 2 - Updated Standard format; revised


Paragraphs 1.1, 1.2, 1.4, 1.5.1,1.5.1b, 1.5.1c,
1.5.2, 1.5.3, 2.1.4d, 2.1.5, 2.2.4, 3.1, 3.1.1,
3.1.2, 3.1.2a, 3.1.2b, 5.1.3, 5.4.1; added
Paragraphs 1.5.1d, 1.5.1e, 2.1.9, 2.8, 3.1.2b,
4.6; deleted Paragraphs 4.3.2.1, 5.4.2 and
Attachment "B".

Ver. 3 - Updated standard format; name


change to ALSTOM Power Inc. Revised Para.
1.5.1.c

Ver. 4 – Added paragraph 2.1.10 on Page 5


SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 3 of 10

1.0 General these other organizations their proper Code


certification covering such portions of work.
1.1 After installation of all pressure Regardless of any division of contractual
parts, Section I of the ASME Boiler and Pressure responsibilities, the Manufacturer has the duty of
Vessel Code requires that a boiler shall be compiling Code certification, covering all parts of
subjected to a hydrostatic pressure test. This will a field-assembled boiler and of preparing Master
be conducted at a test pressure of 1.5 times the Data Report Form P-3 or P-3A.
maximum allowable working pressure to be
stamped on the boiler. This is shown on the a. The completed boiler unit
Manufacturer's Data Report, Form P-3 or P-3A. includes all piping and piping components that
The limits of the ASME boundaries are shown on are covered by the ASME Boiler and Pressure
the Pressure Part piping and instrument drawing. Vessel Code, Section I, Fig. 58.3.1.

1.2 The exact hydrostatic test process will b. When ALSTOM Power designs
depend on local job site conditions. Since this and fabricates a boiler in accordance with the
procedure is general in nature, it shall be ASME Code, it is our responsibility to register it
followed as conditions allow, in conjunction with with the National Board.
the subject Contract Instruction Manual.
c. An ASME Master Code Data
1.3 The unit shall be hydrostatically Report is assembled for each project. The report
tested for conformance to ASME Code consists of: Form P3A, Form P7 and Form P4
requirements in two areas: from the Fabricators. This package will be sent
from Windsor to the Site Manager prior to
1.3.1 Primary Circuitry (Drums, hydrostatic testing. The Contractor who erected
Economizers, Water Walls, Steam Cooled Walls, the boiler must, after the successful site
Superheater). hydrostatic test, sign the back of the P3A or P3
Forms in the "Certificate of Field Assembly
1.3.2 Reheater(s). Compliance" block and have the site's Authorized
Inspector sign the "Certificate of Field Assembly
1.4 Upon request, the Project Engineer Inspection" block.
shall supply assistance or additional information
for hydrostatic testing. Note: To make it easier to identify the originals,
please sign in blue ink. The entire report is
1.5 Reports returned to:

1.5.1 Section I of the ASME Boiler and ALSTOM Power Inc.


Pressure Vessel Code states that the boiler 2000 Day Hill Road
Manufacturer has the responsibility of assuring, Windsor, CT 06095-0500
through proper certification, that all work ATT: Project Quality Manager
performed by him or others responsible to him
complies with all the code requirements including d. When the completed report has
design, construction, materials and been received in Windsor, it will be reviewed by
workmanship. When some portions of a our Authorized Inspector and the final signatures
completed boiler unit are supplied by or worked will be affixed to the report. The nameplate will
on by others not responsible to the Manufacturer, then be stamped and sent to the site for
the Manufacturer has the duty of obtaining from attachment to the boiler.
SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 4 of 10

e. The original ASME Master Code 2.1.3 All necessary valves, including
Data Report will be filed with the National Board drains, installed and closed.
and copies will be distributed, as required, by
QA. 2.1.4 All safety valves installed or
openings blanked off.
1.5.2 The following information about
leaks during hydro test is to be reported a. Safety valves shall not be
immediately to the Project Engineer in Windsor gagged at this time.
both by phone and by TIR (Technical Information
Request). b. Check that hydrostatic test plugs
were installed where necessary and gags are
a. Exact location of leak(s) - available and fit correctly.
component circuit, elevation, material, etc.
c. Detailed instructions are
b. Description of leak(s) - in straight provided by the Manufacturers for hydrostatic
tube, elbow, shop or field weld, torch cut where a testing safety valves. These instructions must be
lug was removed, attachment weld, etc. adhered to without change.

c. Magnitude of leak(s) - weep, d. Power actuated pressure


longitudinal crack, burn through, etc. relieving valves do not require gagging or
hydrostatic test plugs. However, special
The Project Engineer will advise precautions must be observed:
QA and Projects of this information.
The power actuated pressure
1.5.3 Upon completion, a written relieving isolation valve must be in the full open
Report of Inspection of the hydro test is to be sent position.
to the Project Engineer in Windsor. This report
shall include the leak information reported in The shut-off valve in the pressure
Paragraph 1.5.2. sending line from the header to the controller
must be closed to avoid damaging the controller.
1.5.4 Check List The drain and test valve in the pressure sensing
line must be open.
Attachment "A", Hydrostatic Test
Water Sample, is to be completed by the Site 2.1.5 All manhole closure plates and
Manager and retained in the site QA file. header handhole caps closed and bolted or
welded tight. If special closure plugs must be
2.0 Test Preparation designed, contact the Project Engineer for
assistance.
2.1 Prior to hydrostatic testing, the
following items shall be inspected: 2.1.6 All instrumentation isolated or
valved off.
2.1.1 All debris shall be removed from
all pressure parts including headers and drums. Water columns and gauge
glasses must not be hydrostatically tested with the
2.1.2 All necessary welds completed, boiler; they are designed for operating pressure
x-rayed and stress relieved. only. They must be valved off and the drain
valves opened.
SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 5 of 10

2.1.7 All vents necessary to prevent air 2.2.2 One gauge shall be located at
entrapment during filling opened (such as the hydrostatic test pump.
superheater link vents, economizer link vents,
drum vents, etc.). 2.2.3 One gauge shall be located
near the highest elevation of the boiler for test
2.1.8 All gamma ray or radiographic pressure.
openings have their plugs installed and seal
welded. 2.2.4 A connection shall be provided
for the Inspector's test gauge. A check with the
2.1.9 The blanking off plates for the local Inspector(s) can verify if this is a technique
circulating pumps, when used, are installed. to be used.

a. We do not recommend that 2.3 Air Testing Pressure Parts


the boiler water-circulating pump (BWCP)
be installed during the initial ASME Code 2.3.1 Testing the pressure parts with
hydrostatic test. If the pumps are air prior to filling may reduce filling time and
installed, contact the Project Engineer or water wastage. This will aid in locating any cuts
Standards Engineering for special or gouges not observed by visual inspection.
instructions.
2.3.2 Smaller leaks can be detected by
b. If the unit does not have using sonic testing devices.
suction valves, the BWCP's shall not be
installed until the ASME Code hydrostatic 2.3.3 The air pressure used for testing
test has been completed. shall not exceed 25 psi.

2.1.10 All spring and constant support 2.3.4 The air should be filtered and
hangers and supports must be blocked to avoid free of oil prior to entering the unit.
overextending and potential damage due to the
additional water weight from pressure parts 3.0 Filling
being completely filled for the hydrostatic tests.
Refer to Standard 76-75 and Drawing B-983-0300. 3.1 The Contract Documents will state
This applies to all Pressure Part Constant and who has the responsibility to provide the properly
Variable supports as well as Boiler and Non- treated water at the specified temperature for the
Boiler external Piping. hydrostatic test.

For all non- pressure part 3.1.1 Type of Water


constant and variable supports, the stops are to
be released This applies to components such as Refer to Contract Instruction
coal piping and ductwork. Manual for details. If water of the following
quality is not available, contact the Project
2.2 Test Gauges Engineer who will obtain assistance in
determining what quality is acceptable.
2.2.1 Two calibrated pressure gauges,
with current calibration tags, shall be used for the a. All Non-Drainable Areas
hydrostatic test.
Fill with condensate or
Pressure gauges used for the test demineralized water, containing 10 PPM of
shall be checked for calibration at the job site. ammonia and 200 PPM of hydrazine, with a
Do not rely on any calibration performed before solution of pH value of approximately 10.0.
shipment.
SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 6 of 10

b. Drainable Superheater and 3.2.2 Proceed filling the unit through


Reheater the normal filling connections. The unit can be
filled either through the economizer feedline or
Fill with condensate or through the water wall lower drums. Filling the
demineralized water containing 10 PPM of unit simultaneously from top and bottom is not
ammonia and 200 PPM of hydrazine, with a recommended, since this will greatly increase air
solution of pH value of approximately 10.0. If entrapment. If the unit is filled through the
not available, fill with water specified in economizer, the economizer recirculating line
Paragraph 3.1.1.c, except that no chlorine may valve should be in the wide-open position which
be present in this water. will facilitate filling and minimize air entrapment.

c. Remainder of Boiler Unit 3.3 The use of a vacuum pump can help
substantially in speeding up the filling time for a
Fill with condensate type water boiler.
or, if not available, with a clean source of filtered
water containing 10 PPM of ammonia and 200 3.3.1 A vacuum pump will also help to
PPM of hydrazine, with a solution of pH value of partially evacuate air from many areas where it
approximately 10.0. might be trapped when using normal filling
procedures.
3.1.2 The water temperature during
hydro testing shall be no less than 70o F per 3.3.2 The following general
Section I of the ASME Boiler and Pressure Vessel procedures shall be incorporated when using
Code. vacuum assist filling.

a. Following the intent of the Code, a. All boiler vents must be


the steam drum metal temperature shall be not connected to a common manifold to pull a
less than 70o F prior to or during the hydrostatic vacuum on all circuits of the boiler at the same
test. time.

b. For safety purposes during b. In order to minimize the amount


inspection, the metal temperature should not of water pulled into the vacuum, the manifold
exceed 120o F. must be connected to an inverted "J" pipe of
sufficient height to cause the water to go to
3.1.3 Responsibility for furnishing saturation. The vacuum pump should be
temporary connections for filling and draining connected to the end of the inverted "J" pipe.
the boiler will be dictated by the Contract
Documents. c. Open all valves in the vent
manifold system.
3.2 The Erecting Contractor will decide
the best location for filling and pressurizing the d. Close all other valves not
unit. necessary for filling the unit.

3.2.1 The sequence of filling the non- e. Turn on the vacuum source and
drainable areas will be dictated by the design of start filling the boiler with water. Care must be
the boiler. Generally, fill the superheater exercised to minimize the amount of water
through a suitable outlet connection (such as getting into the vacuum pump.
final superheater outlet header drain or vent)
until all elements are filled and the water 3.4 As the unit fills, periodically check for
overflows into the steam drum. Close leaks.
superheater fill connection.
SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 7 of 10

3.5 Vents shall be closed after a steady


stream of water overflows from the vents. Close visual inspection is not
required during this stage.
Note: When valves are in tandem (double
valved), both valves must be closed for the hydro c. The hydrostatic test pressure is
test. then reduced to not less than the maximum
allowable working pressure, after the maximum
4.0 Hydrostatic Testing pressure has been noted and agreed to by the
Inspector.
4.1 Start hydro pump and raise pressure
to 80% of the pressure stamped on the lowest 4.5 Hydro Testing the Reheater(s)
safety valve setting. Hand tighten safety valve
gags per the Manufacturer's recommendations. 4.5.1 The reheater(s) shall be
pressurized at 1.5 times the maximum allowable
4.2 Pressure readings during the test will working pressure of the reheat sections.
be taken from the pressure gauge at the high
point of the boiler. a. Paragraphs 1.0 through 4.0 are
applicable for preparing to hydro test the
4.3 The Erecting Contractor will decide reheater.
on the equipment to be used for the hydrostatic
testing of the unit. b. For the actual hydro, follow the
procedures listed in Paragraphs 4.4.1a, 4.4.1b
4.3.1 When the boiler feed pump has and 4.4.1c.
been used for filling, the operating pressure of
the pump may be used to partially pressurize the 4.6 Inspection
boiler.
4.6.1 Reduce the hydrostatic pressure
4.3.2 High pressure pumps shall then to the agreed upon specific working pressure for
be used to obtain the test pressure. the boiler or the reheater respectively.

4.4 Hydro Testing the Primary Circuitry 4.6.2 Ensure that all personnel doing
the inspection are equipped with appropriate
4.4.1 The primary circuitry will be illumination devices, safety equipment, clothing
tested at 1.5 times the maximum allowable and safety goggles. High pressure water jets and
working pressure. chemicals can cause injury.

a. Start hydro pump and raise the 4.6.3 It is recommended that the
pressure to 80% of the pressure stamped on the inspection teams work in pairs especially in
lowest safety valve setting. Hand-tighten safety conditions where inspections are not visible from
valve gags per the Manufacturer's boiler walkways or inside of the boiler walls.
recommendations.
4.6.4 The areas of the boiler pressure
b. Raise the pressure to the parts to be inspected should be divided up to the
hydrostatic test pressure. respective inspection teams. It is suggested that
the Field Weld Data Summary sheets be given to
The pressure shall be under each inspection team so that all welds inspected
proper control at all times so that the required can be noted.
test pressure is never exceeded by more than 6%.
SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 8 of 10

4.6.5 Unless there are significantly 4.7.3 Make the required repair(s).
large leaks during the test, complete an entire
inspection of the unit, noting all areas of actual 4.7.4 Refill the unit per Paragraph 3.2.
and suspected leakage. Suspected tube leaks
should be marked using a non-water soluble 4.7.5 Re-hydro per Paragraph 4.0.
marker such as a paint stick.
5.0 Post Hydrostatic Test Procedure
4.6.6 If repairs are to be required,
shut down the hydrostatic pump, release the 5.1 The local job conditions and contract
pressure, remove the safety valve gags an drain specifications will dictate what laying-up
down the boiler to an elevation below the procedures are necessary for the boiler.
indicated repair location if possible.
5.1.1 This may include protection of
4.6.7 When repairs have been non-drainable areas from freezing and a
completed, the entire unit should be re-tested possible nitrogen blanket on the drainable areas
using the test procedure until no leaks are found. of the boiler.
At this time, the test pump should be isolated.
The boiler should be re-inspected for any leaks. Caution: When nitrogen is used, thorough
There may be some pressure variation due to ventilation is essential before entering boiler
temperature changes or leaking valves. When drums.
the Authorized Inspector is satisfied with the
results, release the test pressure and drain the 5.1.2 When the boiler is laid up with
boiler. water in it, the water must meet the criteria in
Paragraph 3.1.1
4.7 Releasing Test Pressure
5.1.3 Laying-up is normally the
4.7.1 Upon completion of either the Customer's responsibility. When the Contractor
primary circuitry or reheater test, or if leaks are is responsible, it is a joint Projects and Field
found, it will be necessary to release the Operations responsibility.
pressure.
5.2 Draining the Boiler
a. When valves are in tandem
(double valved), test pressure should be released 5.2.1 Open the boiler vent valves and
at a moderate rate with the outboard valve, while drain all drainable sections of the boiler.
the inboard valve is opened wide. This is to
prevent the valve seat of the pressure side valve 5.2.2 If wet lay-up is to be used, fill the
from being damaged. unit with hydrazine and ammonia treated water
per the Contract Instruction Manual to
b. Gag pressure on safety valves overflowing at the drum vents. Introduce
should be released when hydrostatic test pressure nitrogen through the drum vent to pressurize the
is 85-90% of the pressure on the lowest set valve unit approximately 3-5 psi.
per the Manufacturer's recommendations.
5.2.3 Since there is generally some
4.7.2 Drain the areas necessary to time delay between the hydrostatic test and the
make the repairs. initial boiling out and acid cleaning of the unit,
the water level should not be allowed to remain
at operating level.
SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 9 of 10

5.2.4 Units not equipped with e. Samples should be sent to the


superheater or reheater outlet stop valves should Project Engineer in Windsor with a memo stating
have these outlets isolated by means of blank the sources of the hydrostatic test water used in
flanges so that a small positive nitrogen pressure filling the superheater and any chemical
can be applied. additions made to it.

5.3 Freeze Protection 5.5 Flexitallic Gaskets

5.3.1 If there is a chance of freezing, ALSTOM Power normally supplies,


the water in the drainable circuits in the boiler as contract material, 3 complete sets of drum
must be displaced with nitrogen and the unit can manholes.
be laid up under nitrogen pressure.

Temporary heating equipment


should be provided to keep the non-drainable
(superheater, reheater) sections above freezing
temperature. When external heating is being
applied, the unit should never be left unattended.

5.4 Water Sample

5.4.1 The ALSTOM Power Site


Manager has the responsibility of obtaining a
sample of the hydrostatic test water. See
Attachment "A".

a. The sample should be taken


from some portion of the non-drainable sections
of the superheater and reheater.

b. Suitable locations include the


superheater or reheater header drains or vents.

c. The sample of at least 1/2


gallon should be taken in a clean plastic bottle
which has been rinsed 3 times in the water being
sampled.

d. Precautions should be taken


against contamination from external sources.
Samples will be analyzed from external sources.
Samples will be analyzed for chlorides, so
particular care should be taken to prevent
contamination from the skin.
SUBJECT: Hydrostatic Testing - Natural and Controlled Circulation STD NO : 110-75-04
Boilers INDEX : 4.9.2
DATE : 28 APR 2006
OWNER : 8157
PAGE : 10 of 10

Attachment "A"
Hydrostatic Test Water Sample

Customer ______________________________ Contract No. _____________________

Location _______________________________ Unit No. _________________________

*Source of Hydrostatic ____________________ Date of Hydro ____________________


Fill Water Date of Boil-Out __________________

Chemical Added to Fill Water Quantity Added

1. ____________________________ _______ppm or_____________lbs/103lbs H2O________

2. ____________________________ _______ppm or_____________lbs/103lbs H2O________

3. ____________________________ _______ppm or_____________lbs/103lbs H2O________

Method of Chemical Addition: 1. _________________________________________

2. _________________________________________

3. _________________________________________

**Source of Sample
____________________________________________________________________________________

Nitrogen Pressure Maintained between Hydro and Boil-Out _____ Yes _____ No

Same Taken By _________________________________ Date ________________

* Complete Description of Source - Example: City of Albany, zeolite softened; well water, demineralized;
station condensate; e-c.

** Source of Sample - Example: Superheater outlet header drain, superheater intermediate pendant inlet
header drain, horizontal superheater inlet header drain, etc.

Precaution: If sampling water from horizontal superheater, make certain that the same water is used to fill
this section as was used in the pendant sections. If not, take the sample from the location representative of
the water in non-drainable pendant sections.

You might also like