Professional Documents
Culture Documents
Sector: CONSTRUCTION
Qualification Title: CARPENTRY NC II
Unit of Competency: STAKE-OUT BUILDING LINES
Module Title: STAKING-OUT BUILDING LINES
ST. ISIDORE “THE FARMER’S” LEARNING CENTER INC.
HOW TO USE THIS COMPETENCY BASED
LEARNING MATERIAL
LEARNING OUTCOMES:
Upon completion of this module, the trainee/student must be able to:
ASSESSMENT CRITERIA
• Plans and details are correctly interpreted and identified according
to job requirements
• Materials, tools and equipment are identified consistent with job
requirements
• Materials and tools are properly stored and freed from defects.
• Appropriate PPE are selected according to job requirements.
CONDITIONS:
You must be provided with the
following:
1. WORKPLACE LOCATION
2. TOOLS AND EQUIPMENT Hand Saw
Hammer Chalk
Line
Marking Tools Water Hose Level
Measuring Tools Plumb Bob
Steel Square PPE
Try-square Circular Saw
3. TRAINING MATERIALS
Leaning Packages
Bond paper
Ball pens
Manuals
Related References
ASSESSMENT METHOD
Portfolio
Learning Experience
PREPARE MATERIALS FOR STAKE-OUT BUILDING LINES
LEARNING OBJECTIVE:
Upon completing this section, you should be able to RECOGNIZE
THE DIFFERENT TYPES OF DRAWINGS AND THEIR USES.
CONSTRUCTION DRAWINGS
A. Site Plan
A site plan shows the contours, boundaries, roads, utilities, trees,
structures, and any other significant physical features on or near the
construction site. The locations of proposed structures are shown in
outline.
Figure 3. Site plan
B. Plot Plan
The plot plan shows the
survey marks with the elevations
and the grading requirements. The
plot plan is used by the
Engineering Aids to set up the
corners and perimeter of the
building using batter boards and
line stakes, as shown in Figure 4.
Thus, the plot plan furnishes the
essential data for laying out the
building.
C. Foundation Plan
A foundation plan is a plane view of a structure. That is, it looks as if
it were projected onto a horizontal plane and passed through the
structure. In the case of the foundation plan, the plane is slightly below the
level of the top of the foundation wall.
Figure 5. Foundation plan
D. Floor Plan
An architectural or structural floor plan shows the structural
characteristics of the building at the level of the plane of projection. A
mechanical floor plan shows the plumbing and heating systems and any
other mechanical components other than those that are electrical. An
electrical floor plan shows the lighting system and any other electrical
systems.
Figure 6. Shows the way a floor plan is developed: from elevation, to cutting
plane, to floor plan
Figure 7 is a floor plan
showing the lengths,
thicknesses, and character
of the outside walls and
partitions at the particular
floor level. It also shows the
number, dimensions, and
arrangement of the rooms,
the widths and locations of
doors and windows, and the
locations and character of
bathroom, kitchen, and
other utility features.
E. Elevations
The front, rear, and sides of a structure, as they would appear
projected on vertical planes, are shown in elevations. Studying the
elevation drawing gives you a working idea of the appearance and layout
of the structure.
G. Sectional Views
Sectional views, or
sections, provide important
information about the height,
materials, fastening and
support systems, and
concealed features of a
structure.
H. Details
Details are large-scale drawings that
show the builders of a structure how its
various parts are to be connected and placed.
Detail drawings are used whenever the
information provided in elevations, plans, and
sections is not clear enough for the
constructors on the job.
The construction of doors, windows, and
eaves is customarily shown in detail drawings
of buildings. Typical door and window details
are shown in Figure 12.
Check your answer with the answer key below. If you fail to get it
right, refer back to corresponding resources until you make it perfect.
1. D
2. C
3. B
4. A
5. C
6. C
7. D
8. A
INFORMATION SHEET NO. 1.1-2
MATERIALS SPECIFICATIONS
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the
TYPES, STANDARD SIZES, and USES of LUMBER for
CONSTRUCTION CARPENTRY.
A. Lumber
Lumber varies greatly in structural characteristics. A carpenter must
learn about lumber so that he can choose the most suitable material for
each job.
2. Uses of Lumber
LEARNING OBJECTIVE:
Upon completing this section, you should be able to know the
METHODS OF MEASURING LUMBER QUANTITIES IN TERMS OF
BOARD FEET, which is the unit by which it is ordered.
A. Methods of computing BF
Example: Under the 8-inch mark on the guideline, moving left from
14, the numbers 9 and 4 appear (9 and 4 should be on the same line
as 14). The number to the left of the vertical line represents feet; the
number to the right represents inches.
Check your answer with the answer key below. If you fail to get it
right, refer back to corresponding resources until you make it perfect.
1. 2 sq.feet
2. 8 sq.feet
3. 6.67 or 7 sq.feet
4. 48 sq.feet
5. 10.67 or 11 sq.feet
6. 18 sq.feet
7. 8 sq.feet
8. 6 sq.feet
9. 4 sq.feet
10. 11.67 or 12 sq.feet
11. 16 sq.feet
12. 48 sq.feet
INFORMATION SHEET NO. 1.1-4
TOOLS, MATERIALS AND EQUIPMENT FOR STAKING-OUT
BUILDING LINES
LEARNING OBJECTIVE:
Upon completing this section, you should be able to know the
DIFFERENT TYPES of TOOLS and MATERIALS USED in STAKING-OUT
BUILDING LINES.
It is very important to know that the name and proper use of each of
the various tools we need in our works. In addition, application on their
proper care and maintenance will give you the following advantages:
efficiency of the work, quality speed and accomplishment and accuracy.
Pencils
For more accurate marking and a longer-lasting point, they can
easily be sharpened to a chisel-point.
Claw Hammer
Although this tool is basically for nailing
and extracting nails, it has also been
widely used over the years by using the
side of the head as an alternative to the
wooden mallet. The claw is also used for a
limited amount of leverage work, such as
separating nailed boards, etc.
Plumb bob
It is a cone shaped metal suspended on a string used to check the
verticalness of a particular object.
Nylon string
It is used to indicate the sides of the building.
Ripping/Wrecking bar
This is used to pull out long nails. This may be straight or gooseneck.
It has a nail slot for pulling out spikes and wedging apart nailed boards.
Figure 23. Ripping/wrecking bar
Ax or Hatchet
An ax or hatchet is used during the staking out operation to sharpen
the ends of batter board posts and corner stakes.
Crosscut Saw
This is for cutting timber across the
grain. When crosscutting, the saw should
be at an approximate angle of 45° to the
timber.
Directions: Identify the tool materials asked for. Write your answer on
the space provided before the number.
Check your answer with the answer key below. if you fail to get it
right, refer back to corresponding resources until you make it perfect.
1. SLEDGE HAMMER
2. PLUMB BOB
3. TRY SQUARE
4. PULL PUSH RULE
5. CLAW HAMMER
6. LEVEL BAR
7. RIP SAW
8. NYLON STRING
9. BOLO
10. CROSS CUT SAW
INFORMATION SHEET NO. 1.1-5
COMPANY RULES AND REGULATIONS
LEARNING OBJECTIVE:
Upon completing this section, you should be able to know the
COMPANY RULES AND REGULATIONS.
1) Building permit
2) Electrical permit
4) Zoning clearance
5) Fencing permit
9) Enclosure permit
1) Engineering office
2) Electric company
3) Engineering office
4) Registry of Deeds
5) DENR
6) Water district
7) Engineering office
8) Engineering office
9) Engineering office
10) Engineering office
11) Engineering office
12) Engineering office
LEARNING OUTCOME NO. 2 Stake-out and set batter boards
CONTENT/S:
• Setting Batter Boards
ASSESSMENT CRITERIA
• Stakes are set out from pre-determined building lines
• Batter board materials are measured, laid out and cut according to
specification
• Stakes are set 0.75-1.00 meter away from the pre-determined
building lines
• Batter boards are properly secured with tolerance for dimensions
at +- 5 mm, and levelness of +- 3 mm.
• Appropriate PPE is used according to job requirements
CONDITIONS:
You must be provided with the
following:
1. WORKPLACE LOCATION
2. TOOLS AND EQUIPMENT Hand Saw
Hammer Chalk
Line
Marking Tools Water Hose Level
Measuring Tools Plumb Bob
Steel Square PPE
Try-square Circular Saw
3. TRAINING MATERIALS
Leaning Packages
Bond paper
Ball pens
Manuals
Related References
ASSESSMENT METHOD
Portfolio
Learning Experience
STAKE-OUT AND SET BATTER BOARDS
LEARNING OBJECTIVE:
Upon completing this section, you should be able to STAKE BATTER
BOARD.
B. Staking Procedures
Corner stakes are driven to mark the exact
corners of the project. Excavating for a foundation will
disturb the stakes, so batter boards are set up outside
the boundary established by the stakes to preserve
definite and accurate building lines. Heavy cord or fine
wire is stretched from one batter board to another to
mark these lines.
Figure 23. Right-angle batter boards
E. EXTENDING LINES
The following procedure applies to a simple layout as shown below,
and must be amended to apply to different or more complex layout
problems:
Step 1. After locating and sinking stakes A and B. erect batter boards 1, 2,
3, and 4. Extend a chalk line (X) from batter board 1 to batter board 3,
over stakes A and B.
Step 2. After locating and sinking stake C, erect batter boards 5 and 6.
Extend chalk line Y from batter board 2 over stakes A and C to batter
board 6.
Step 3. After locating and sinking stake D, erect batter boards 7 and
8. Extend chalk line Z from batter board 5 to batter board 7, over
stakes C and D.
Step 4. Extend line O from batter board 8 to batter board 4, over stakes D
and B.
Figure 26. Laying out building line
Where foundation walls are wide at the bottom and extend beyond
the outside dimensions of the building, the excavation must be larger
than the laid-out size. To lay out dimensions of this excavation, measure
out as far as required from the building line on each batter board and
stretch lines between these points, outside the first layout.
The lines may be at a right angle where they cross the corner
layout stakes, found by holding a plumb bob over the corner layout
stakes and adjusting the lines until they touch the plumb-bob line. All
lines should be checked with a line level or a carpenter's level.
JOB SHEET NO. 1.2-1
Title: Install Batter Boards
a. Lay out the site (refer to Operation Sheet No. 1.2-1a on Laying
out the Site)
1. Establish the maximum outer perimeter.
2. Establish the desired distance at which the project will parallel the
established front line.
3. Establish the rear line.
4. Establish the sidelines.
b. Set and stake batter boards. Drive the corner stakes to mark
the exact corners of the project (refer to Operation Sheet No.
1.2-1b on Setting and Staking Batter Board)
Assessment Method:
Portfolio
Demonstration
PERFORMANCE CRITERIA CHECKLIST
JOB SHEET NO. 1.2-1
CRITERIA YES NO
1. Are the stakes set out from the pre-determined
building lines?
2. Measure away from the front line (AB) along the side lines (AC
and
BD) the distances (AO and BO) to the desired dimensions of the
project that is to run parallel to the front line.
3. Stretch a line from point O on the left-side dimension to point O on
the right-side dimension. This marks the frontage of the project.
4. Measure in from lines AC and BD along line OO one half the
difference between the length of line OO and the actual dimension
of the project parallel to lines AB. This will designate the
measurement for points X. Both points X represent the two front
corners of the project.
Assessment Method:
Performance Criteria Checklist
PERFORMANCE CRITERIA CHECKLIST
OPERATION SHEET NO. 1.2-1a
CRITERIA YES NO
1. Are the plans and details correctly interpreted
and identified according to job requirements?
Assessment Method:
Performance Criteria Checklist
PERFORMANCE CRITERIA CHECKLIST
OPERATION SHEET NO. 1.2-1b
CRITERIA YES NO
Assessment Method:
Performance Criteria Checklist
PERFORMANCE CRITERIA CHECKLIST
OPERATION SHEET NO. 1.2-1c
CRITERIA YES NO
1. Have I determined the correct location of the
batter boards?
ASSESSMENT CRITERIA
• Stake-out building lines are properly secured for reference in
excavating building foundation.
• Marking lines are squared and plumbed from the batter board
lines with tolerance of + 3mm on all measurements.
• Worksite is cleaned and kept in safe state according to OSHC
regulations.
• Daily work report is accomplished in accordance with company
rules and regulationss
CONDITIONS:
You must be provided with the
following:
1. WORKPLACE LOCATION
2. TOOLS AND EQUIPMENT Hand Saw
Hammer Chalk
Line
Marking Tools Water Hose Level
Measuring Tools Plumb Bob
Steel Square PPE
Try-square Circular Saw
3. TRAINING MATERIALS
Leaning Packages
Bond paper
Ball pens
Manuals
Related References
ASSESSMENT METHOD
Portfolio
Learning Experience
Fix Building Lines
LEARNING OBJECTIVE:
Upon completing this section, you should be able to SQUARE LINES
Assessment Method:
Performance Criteria Checklist
PERFORMANCE CRITERIA CHECKLIST
OPERATION SHEET NO. 1.3-1
CRITERIA YES NO
1. Did I ensure that lines are at right angle with
each other using the two method?