Professional Documents
Culture Documents
The Parties
The Antecedents
4. Sometime on 2015, as a contractor for infrastructure, I won in the bidding
involving two projects conducted by XXXXXXXXX which were for the
construction of (i) the Science and Technology R & D Building (Phase 3)
and (ii) the Engineering Building (Phase 14).
6. It was indicated therein that the contract price for the Science and
Technology Building was Nine Million, Nine Hundred Seventy-Five
Thousand, Two Hundred Fifty-Six and 87/100 (9,975,256,087.00) while
the contract price for the Engineering Building was Five Million Nine
Hundred Eighty Thousand Four Hundred Ninety Six Pesos & 26/100
(5,980,496,026.00).
(ii) Two Million One Hundred Nineteen Thousand, Seven Hundred Forty-
Two Pesos & 08/100 for the first 25% of the accomplishment, from
the contract price;
(iii) Two Million One Hundred Nineteen Thousand, Seven Hundred Forty-
Two Pesos & 08/100 for the first 50% of the accomplishment, from
the contract price;
(iv) Two Million One Hundred Nineteen Thousand, Seven Hundred Forty-
Two Pesos & 08/100 for the first 75% of the accomplishment, from
the contract price;
(ii) One Million Two Hundred Seventy Thousand, Eight Hundred Fifty-
Five Pesos & 46/100 for the first 25% of the accomplishment, from
the contract price;
(iii) One Million Two Hundred Seventy Thousand, Eight Hundred Fifty-
Five Pesos & 46/100 for the first 50% of the accomplishment, from
the contract price;
(iv) One Million Two Hundred Seventy Thousand, Eight Hundred Fifty-
Five Pesos & 46/100 for the first 75% of the accomplishment, from
the contract price;
(v) Seven Hundred Sixty-Two Thousand, Five Hundred Thirteen &
26/100, for the first 90% of the accomplishment, from the contract
price; and
(vi) Five Hundred Eight Thousand, Three Hundred Forty-Two & 18/100
to be paid at the time and in the manner provided in the Instruction to
Bidders for the Engineering Building.
15.Hence, on 20 October 2016, another request for site inspection and a 100%
billing was subsequently sent by the complainant to the respondents. Copies
of the request for site inspection including the request for 100% billing is
hereto attached and marked as ANNEXES “F” and series and form an
integral part hereof.
16.It was only then that Respondent President XXXX acted upon our request by
endorsing the same to Vice-President XXXXon 21 October 2016. A copy of
the 1st Endorsement for both projects are attached and marked as ANNEXES
“G” and series and form part hereof.
18.From the date of the 2nd endorsement, and instead of taking action on our
billing, respondent xxxxxxx employed all malicious means and maneuvers
to fabricate issues on delays perhaps wanting to free themselves from the
liability of paying their obligations. Such ploy were clearly manifested
through the following undertakings:
20.On 27 December 2016, respondent xxxxx attempted to hand over three (3)
letters dated: i) September 26, 2016; ii) October 28, 2016; and iii)
November 9, 2016 stating among others that construction work was delayed
for 172 calendar days, 204 calendar days and 236 calendar days,
respectively, to one of my office staff namely xxxxxx while she at the SSU
campus.
21.Respondent xxxxxx, in fact, instructed xxxxxxx, my office staff to write
down and indicate the dates of receipt to correspond to the respective dates
of the letters. However, my office staff refused to comply with said
instructions, and instead indicated the actual date of receipt on the said
letters.
22.Having failed in their malicious intent and with zealousness to further taint
and tarnish my reputation, respondent xxxxxx succeeded in furnishing me
another set of the same ante-dated letters in another occasion. Thus, on 31
December 2016, thru xxxxx , who once went on an OJT with my business
enterprise, using her position and influence in the said University,
respondent xxxxxxxx compelled xxxxxxxx to receive the letters, despite the
fact that xxxxxxxx has no authority to receive any communications or
documents for and in my behalf. xxxxxxx likewise instructed xxxxxxxx the
very same instructions she gave to xxxxxxxxxx. However, instead of filling
up the portion of the date of receipt, xxxxxxx, left the portion blank. The
blank portion were later filled up by xxxxxxx with dates that would make it
appear that I received said letters corresponding to the dates of the letters.
XXXXXXXXX, however, indicated later that he actually received such
documents only on December 31, 2016.
(i) 93% accomplishment and a delay of 278 days for the Science &
Technology building;
(ii) 90% accomplishment and a delay of 303 days for the Engineering
Building
26.The 3rd endorsement submitted by respondent xxxxxxxxx likewise
recommended for Contract Termination citing R.A 9184 as their legal basis.
Copies of the 3rd endorsements and the inspection reports dated 16 January
and 17 January 2017 are hereto attached, marked as ANNEXES “J” and
series and form as integral part hereof.
(a) Act promptly on letters and requests. - All public officials and
employees shall, within fifteen (15) working days from receipt thereof,
respond to letters, telegrams or other means of communications sent
by the public. The reply must contain the action taken on the request.”
31.As stated supra, it took respondents more than almost four months from 10
August 2016, or until 31 January 2017, before my request was acted upon by
them.
34.Assuming, arguendo, that there was delay, the same could be imputed
against the respondent as it was due to their neglect and failure to take action
on our requests for inspections and evaluation of the projects. The Notices of
Termination, alleging the incurred delay and the negative slippage are purely
without basis. In truth and in fact, the construction works had both a 100%
accomplishment, hence, no more contracts to be terminated.
35.If indeed, there was failure to faithfully comply with my obligations under
the two contracts, respondents should have made the appropriate demand, so
as to afford me the opportunity to properly address any issue laid and to
avoid financial losses and reverses from both parties. In this regard,
respondent failed to do so.
37.For failure of respondents to comply with their obligations under the two
contracts, complainant made a final demand from the respondents for
settlement of the following amounts:
38.A copy of the final demand letter is hereto attached, marked as Annex “M”
and forms an integral part hereof.
40.With the foregoing circumstances, herein Complainant had not only incurred
financial reverses and but also suffered sleepless nights, metal anxiety,
wounded feelings, besmirched reputation and social humiliation within the
community of contractors and suppliers of materials.
41.The two projects subject of this controversy are not the only projects
undergone by my business enterprise with XXXXXXXXX. A previous
project, which was the Construction of Food Technology and Research
Training Center endured an almost similar situation and may be considered
as a precedent on the ploy undertaken by respondent XXXX. The Food Tech
project, and after 75% work accomplishment, respondent XXX employed all
means to disapprove the disbursement in payment of the corresponding work
accomplishment, such as submitting an inspection report without the
concurrence and in disregard of the other members of the monitoring and
evaluation committee. A copy of the said monitoring and evaluation report is
hereto attached and marked as Annex “N” and forms part hereof.
44.Faithful with his obligations under the contract despite non-payment of the
75% billing as scheduled, complainant still continued the construction
works for this particular project until the same was 100% work
accomplished and fully completed.
45.When the construction work was 100% and fully completed in the Food
Tech Project, and after incurring delay attributable to respondents,
complainant was able to collect for the 100% billing which respondents paid
after arbitrarily and whimsically deducting liquidated damages and which
liquidated damages was in the amount of ONE HUNDRED SIXTY-
SEVEN THOUSAND, EIGHT HUNDRED TWENTY-SIX & 79/100 (P
167,826.79) PESOS. A copy of the said payment is hereto attached and
marked as Annex “P” and forms part hereof.
XXXXXXX
Complainant
2. Except for the civil case that I have filed with the Regional Trial Court
against the respondents for collection of sum of money with damages, I have
not commenced any other action or proceeding involving the same issues in
the Supreme Court, the Court of Appeals, or any other tribunal or agency;
4. If I should thereafter learn that a similar action or proceeding has been filed
or is pending before the Supreme Court, the Court of Appeals, or any other
tribunal or agency, I undertake to report that fact within five (5) days
therefrom to this Honorable Court.
XXXXXXXXXXXXXXX
Complainant