STALLION INFRASTRUCTURE

RATE ANALYSIS ABSTRACT FOR PLASTER WORK


S.NO DESCRIPTION UOM RATE REMARKS
1 20MM External Wall SQM 402.475
2 12MM Internal Wall SQM 294.403
3 6MM Celling SQM 222.693
Rate Analysis for Plaster Work (For Sale Order)
S.No Description Unit QTY Rate Amount Remarks
A 20 mm Plaster Work (External) Sqm 1
1 Man Power
Mason & Labour /Sqm 1.0 230.00 230.00 21-22/Sqft
Sub Total (i) INR/Sqm 230.00
2 Material
Cement (1:6) Kgs/Sqm 5.7 8.00 45.9
Sand (1:6) Cft/Sqm 0.845 50.00 42.3

Sub Total (ii) INR/Sqm 88.16

Total (A) 318.16


Overheds (15%) 47.7
Contractor Profit (10%) 36.6
Total 402.5 Rate/Sqm
S.No Description Unit QTY Rate Amount Remarks
A 12 mm Plaster Work (Internal) Sqm 1
1 Man Power
Mason & Labour /Sqm 1.0 180.00 180.00 16-17/Sqft
Sub Total (i) INR/Sqm 180.00
2 Material
Cement (1:6) Kgs/Sqm 3.4 8.00 27.5
Sand (1:6) Cft/Sqm 0.505 50.00 25.3

Sub Total (ii) INR/Sqm 52.73

Total (A) 232.73


Overheds (15%) 34.9
Contractor Profit (10%) 26.8
Total 294.4 Rate/Sqm
S.No Description Unit QTY Rate Amount Remarks
A 6 mm Plaster Work (Celling) Sqm 1
1 Man Power
Mason & Labour /Sqm 1.0 140.00 140.00 16-17/Sqft
Sub Total (i) INR/Sqm 140.00
2 Material
Cement (1:4) Kgs/Sqm 3.0 8.00 24.2
Sand (1:4) Cft/Sqm 0.237 50.00 11.9

Sub Total (ii) INR/Sqm 36.04

Total (A) 176.04


Overheds (15%) 26.4
Contractor Profit (10%) 20.2
Total 222.7 Rate/Sqm