UFA 2003

PROJECT MANAGEMENT

TITLE:
CASE STUDY

DATE:
12th JUNE 2022

LECTURER:
EN. WAN ZAMRI WAN HASSAN

NAME MATRIC NUMBER


WONG LI MIN UFA200092
Question 1
What are the needs that have been identified? (2 marks)

In order to increase sales, Matt and Grace believe putting their grocery store online would be beneficial.

Question 2
Based on the article above, explain how project and process relate to each other? (3 marks)
In order for the website to function properly, Matt and Grace need to determine what they want it to
accomplish. In order to build a website that will be able to sell products or provide information, they must
decide if it will have an online store or not. The website's features should also be tailored to the effects
they want. Budget is also an important factor that Matt and Grace will have to consider when developing
a website. It will be helpful for them to plan and thoughtfully consider the needs of the business if they do
all of this beforehand.

Question 3
You and your team need to prepare a project plan to present to Matt and Grace that includes:
a) The project triple constraints. (3 marks)
Scope: E-commerce website
Time: 3 months
Cost: RM50,000
b) A work breakdown structure. (5 marks)

Page | 1
c) A network diagram showing the interrelationships of all the activities. (5 marks)

d) Develop a cost estimate for each activity and determine the total budget for the project. (2 marks)

Activity April May June Total by activity

Website RM 5,000 RM 5,000 RM 5,000 RM 15,000


Design
Website - - RM 3,000 RM 3,000
Improvement
Insurance RM 2,000 RM 2,000 RM 2,000 RM 6,000
Labor Cost RM 4,000 RM 4,500 RM 4,500 RM 12,000
Equipment RM 3,000 RM 3,000 RM 3,500 RM 9,500
Cost
Miscellaneous RM 1,500 RM 1,500 RM 1,500 RM 4,500
Total RM 50,000