Summery Sheet / Brief Note
Sr. No. Description of Work Deficiency Recommendation Remarks
Total Connected Load is 420 KW whereas the senction Sectioned Load should be increase upto 420 KW
1 Present Electrical Load load of hospital 120 KW. Top Priority.

Future Proposed Electrical


2 No Electrical load will be consider for future Sectioned Load should be increase upto 420 KW Top Priority.
Load
Transformer installed of 160 KVA is installed having no New Transformer is required of 400KVA.
3a Transformer deficiency. Top Priority.

3b DG Set DG set of 125 KVA, 82.5KVA, 50KVA, 15KVA is available. New DG set of capacity of 125KVA, 62.5 KVA is
required Top Priority.

3c HT Panel Not availible HT pannel with VCB as per desired rating is required. Top Priority.

1. Nody Earthing not available 1.Body Earthings should be connect with DB's
2. Blanking plate and DB dressing not proper done. 2. Blanking plate required and DB dressing with tie and Top Priority.
3d DB's 3. DB ferruling is required. 3. DB
Enclosure not available Enclosure is required.

More LT Panel need to be install with 250 Amp


3e LT Panel LT Panel Installed Breakers Top Priority.

Minimum Six more Chemical Earthing with 3 mtr Rod


4 Earthing & Neutral Earthings are available need to be insall Top Priority.

5 Air Conditioning & Heating AC AMC is not available AMC Services are required Top Priority.
System
AS PER NBC 2016 INSTITUTIONAL BUILDING-C
6 Fire Fighting System & Fire Fighting System and Fire Extinguisher are not (a)-1 CATEGORY,FIRE FIGHTING TERRACE FLOOR Top Priority.
Functioning available PUMP(450 LPM) IS REQUIRED WITH 5000 LTR.
FIRE WATER TANK

Ventilation System Installed & Not Requied


7 Functioning
Not Requied

UPS, Inverter, Servo Voltage


8 Stabilizer
Inverter Batteries are in good condition Service and AMC is required for UPS system Top Priority.

One more Main Incomer Cable of 3.5 CX120sqmm


9 HT/ LT Cables, Wires, etc. Size of Main incomer Cable is undergauge
XLPE Cable
Top Priority.

10 Power Factor Correction Panel Availible but not sufficient. Require to install upto 25KVAR Top Priority.

Scrutiny of the Bills and LT-CT HTCT Metering is not availible as per system. HTCT Metering panel required maintinence and
11 Meter/HT-CT Meter proper earthings
Top Priority.

Analysis of the Solar PV Solar PV System feasibility is available but solar PV


12 Feasibility and Capacity system 75KW installed
More Solar PV system need to be install Top Priority.

13 AMC and MEP Services AMC and MEP Services are not Available
AMC Services are required for UPS, AC and medical Top Priority.
available or not equipments

Technical Manpower
14 availability for Supervision & Technical Manpower is available Not Requied Top Priority.
Monitoring
Signature of Auditor