Cooling Tower Equipment

Checklist
This checklist should be used and completed throughout the project and its
different stages, delivery, storage, installation & pre-commissioning , prior to the
functional testing taking place.

Project Name:

Date:

Equipment ID.

Contents
Contents ..................................................................................................... 1

Delivery Inspection ...................................................................................... 3

Storage Inspect ion ....................................................................................... 6

Storage Area ............................................................................................ 6

Storage of Cooling Tower .......................................................................... 7

Pre-Installation Inspection ............................................................................ 8

Maintenance/Access .................................................................................. 10

Pre-Commissioning I nspect ion .................................................................... 11

General .................................................................................................. 11

Electrical General ................................................................................... 12

Variable Speed Drive ............................................................................... 13

Controls System/Valves & Inter locks ......................................................... 13

Ambient Air Intake & Fill Pack .................................................................. 14

Pond/ Cold Water Basin ............................................................................ 14

Electric Heater ........................................................................................ 15

1 Co o l in g To w er Ch ec k l i s t
Sweeper System ..................................................................................... 16

Makeup Water Connection ....................................................................... 16

Bleed-Off/Blow Down Connect ion .............................................................. 16

Side Stream Filtration Connect ion ............................................................. 17

Overflow Pipework .................................................................................. 17

Drift Elim inat or ....................................................................................... 17

Fan & Motor ........................................................................................... 17

Ductwork ................................................................................................ 18

Access ................................................................................................... 19

Pipework to Nozzles ................................................................................ 19

Pipework from Tower ............................................................................... 21

Balance Pipework ................................................................................... 22

Controls ................................................................................................. 23

2 Co o l in g To w er Ch ec k l i s t
Delivery Inspection
Once the Cooling Tower arrives at site, usually delivered by a transport
company, and befor e being accepted into storage, or placed into posit ion , the
following should be checked with the dr iver .

Any damage that is noted should be reported to the manufacturer/supplier within


1 day in wr iting supported with photographs.

Ref Inspection/Task Yes/No Notes


/[n/a]

1 Supplier's consolidat ed delivery


ticket is available, showing all
equipment and ancillaries for
inspect ion and being used to
check against.

2 A copy of the order t hat was sent


to the supplier is available for
reference and is being used to
check against

3 Equipment is packaged and cr ated


in separate boxes, f or maximum
protection

4 The cooling tower nameplate and


details match the purchase order

5 Delivery protect ion is dry

6 The co oling tower is dry internally

7 The exter nal casing of the cooling


tower is undamaged

8 Access door opens/closes and


undamaged

3 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

9 Basin Guard Filter [if purchased


as option] included and
undamaged

10 Basin Sweeper System [if


purchased as option] included and
undamaged.

11 Basin Heater System [if


purchased as option] included and
undamaged.

12 Air Inlet Screens [ if purchased as


option] included and undamaged.

13 Portable Cr ane [ if purchased as


option] included and undamaged.

14 Ladder Safety Cage [if purchased


as option] included and
undamaged for access to the
roof/fan deck of the tower.

15 Guard Rail System [if purchased


as option] included and
undamaged for access around the
roof/fan deck of the tower.

16 Access door platfor m [if


purchased as option] included and
undamaged for access to the door
of the tower if installed on a high
steelwork frame.

17 Maintenance platfor m [if


purchased as option] included and
undamaged for access around the
tower and to any mot ors / parts

4 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

mounted on the external of the


tower.

18 Internal Plenum Walkway [ if


purchased as option] included and
undamaged. This is f or access
inside the tower.

19 Attenuat ion [if purchased as


option] included and undamaged.

20 All pipework connections are the


correct size

21 Pipework connect ions are


undamaged

22 All pipework handing’s and


positions are correct

23 All nozzles are installed on the


pipework and undam aged

24 All duct ing connect ions are


correct size

25 All ancillaries [valves, actuators,


fill pack, filters etc.] are included
in delivery as per the order and
delivery note

26 Spin the fan to ensur e not


damaged and out of line

27 Check all fill pack for damage


externally and inter nally

28 Replace and protect ion that has


been removed

5 Co o l in g To w er Ch ec k l i s t
Storage Inspection
Storage Area
If the equipment is t o be placed into stor age on site pr ior to installat ion there will
be an inspection completed checking the following.

Ref Inspection/Task Yes/No Notes


/[n/a]

1 The area is internal and will not


be affected by weather .

[if the unit is not rated for external use]

2 The surface where t he equipment


is to be placed is flat .

3 The equipment will be raised from


the floor to allow airf low and stop
risk of wat er ingress .

4 The area is well covered and


protected.

[if the unit is not rated for external use]

5 The area is well vent ilated and no


risk of high humidity .

6 The area is clean & dust free.

6 Co o l in g To w er Ch ec k l i s t
Storage of Cooling Tower
Prior to the cooling t ower being placed into storage the following should be
checked.

Ref Inspection/Task Yes/No Notes


/[n/a]

1 Cooling tower will not have


materials stacked on it.

2 All ancillaries will be placed in a


safe and secure location so items
do not go m issing or get
damaged.

3 All or iginal packaging is intact and


not removed.

4 Pipework caps are not removed .

5 Cooling tower and all components


placed on a flat surf ace .

6 Barriers placed around the cooling


tower to protect against any
damage

7 Co o l in g To w er Ch ec k l i s t
Pre-Installation Inspection
Prior to the cooling t ower being installed the following should be checked.

Ref Inspection/Task Yes/No Notes


/[n/a]

1 The steelwork/ plinth/ base is


ready, flat and level & can bare
the weight of the installation.

2 Area being installed is not prone


to flooding or ponding of water .

3 The area the cooling tower will be


installed into is clean and dust
free.

If there is dust/const ruction work,


then the cooling tower should be
protected.

4 Ensure the cooling t ower can be


fixed to the st eelwor k/plinth/base ,
check for mount ing requirements
with the manufactur er.

5 If there is a buildup of snow within


the location of the cooling tower ,
it will not affect its operation or
maintenance requirements.

6 The installation of the cooling


tower will not impede the
installat ion of the pipewor k ,
cables etc.

7 All connect ions,


pipework/duct work etc., can be
independently supported and not
supported by the cooling tower .

8 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

Best pract ice is to install self -


support ing brackets prior to the
connection of the cooling tower .

8 Ensure that all access doors are


clear and not blocked from
brackets or other ser vices.

9 Check to ensur e that all


connection kits cont aining -
gaskets, bolts, cleat s, screws are
available to allow bolting up of the
cooling tower .

10 Remove all transport feet and


bolts.

11 Check that all requir ed cabling


can be run through the cooling
tower and on appropriate
containment.

12 Ensure there is enough space


under the cooling tower to allow
connecting of pipework etc.

9 Co o l in g To w er Ch ec k l i s t
Maintenance/Access
Ref Inspection/Task Yes/No Notes
/[n/a]

1 There is enough space allowed


around and above the cooling
tower once installed to perform
maintenance and remove
components.

[check the manufacturers maintenance


instructions for requirements]

2 All doors can be fully opened to


gain access to the cooling t ower
internal ar ea .

3 Check that there is enough space


for fill pack and fans to be
removed and replaced .

4 If the cooling tower is mounted on


a steel/ high platform , confirm that
there is a safe manner to gain
access, remove the parts and
components.

10 Co o l in g To w er Ch ec k l i s t
Pre-Commissioning Inspection
Once the equipment has been installed and prior to functional testing and
commissioning phase taking place the following will be checked.

General
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Document the information of the


cooling tower from its name plates
and cross ref erence with the
specified information to ensure
correct.

2 Ensure cooling tower is level.

3 Ensure all gaskets are installed


and sealed.

4 Ensure that all cleat s and fixings


are inst alled as per
manufacturer ’s instr uctions.

5 All access doors can be open and


closed with no gaps or leakage.

6 Check that all transport bolts and


feet are removed.

7 Fan housing ducting , if being


used, is installed and fixed.

8 All vibrat ion mounts installed

9 Seismic restraints, where


required, installed.

10 No leaks from the tower base and


all joints sealed

11 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

11 Cooling tower and all components


including valves and controls are
labeled in line with the project
naming convent ion.

12 Operation and startup manual for


the cooling tower available.

Electrical General
Ref Inspection/Task Yes/No/[n/a] Notes

1 Cooling tower and


components are fully
earthed in line with t he
manufacturer ’s
instruct ions.

2 Earthing has been tested

3 Emergency disconnect
installed for each
component in line with
NFPA/local code
requirements

4 Electrical voltage from site


matches the cooling tower
motor requir ed voltages.

5 All cabling is installed and


connected on the cor rect
conta inment/raceways and
not damaged.

6 All cabling has been


tested/torque tested.

12 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No/[n/a] Notes

7 Local motor control panel


[LMCP] has been installed

8 Local motor control panel


has been electr ically tested

9 All electr ical cabling is


labelled in line wit h project
naming convent ion.

10 Cooling tower ready for


energizat ion

Variable Speed Drive


Ref Inspection/Task Yes/No/[n/a] Notes

1 Variable speed dr ive has


been installed.

2 Variable Speed Drive


[VSD] has been electrically
tested

3 Variable speed dr ive has


been functionally tested

Controls System/Valves & Interlocks


Ref Inspection/Task Yes/No/[n/a] Notes

1 Motorized valves installed


as per the drawings and
open/close freely.

2 All controls and panels


have been installed t o

13 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No/[n/a] Notes

operate the valves, f ans,


and interlocks.

3 Freez ing safety inter locks


installed as per the design.

4 Pressur e differential
measuring devices are
installed across all
strainer s

Ambient Air Intake & Fill Pack


Ref Inspection/Task Yes/No Notes
/[n/a]

1 Position of ambient air intake is


in line with the design and
manufacturer requir ements and
positioned so as will not be
affected by space restrictions or
any recirculat ion of surrounding
exhaust ducts.

2 All attenuators are installed as


shown on the dr awings.

3 Fill Pack is installed correctly,


with correct fixings, in line with
manufacturer ’s instr uctions.

4 Fill pack is clean

5 Fill pack can be rem oved for


cleaning and maintenance easily

Pond/Cold Water Basin

14 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Access door opens/closes and


undamaged

2 Basin is correct size

3 Basin is clean and fr ee of debr is

4 Water level is correct and float


valve set in line wit h the
design/manufacturer ’s
instruct ions.

5 Access platform inst alled, clean


and undamaged.

6 Basin guard is fitted, clean and


undamaged

7 Vortex preventor is installed,


clean and undamaged.

Electric Heater
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Electric heater installed for


freeze protect ion, clean and
undamaged

3 Heater elements are not


obstructed by debr is

4 All electr ical testing completed


including torque test s of
connections.

5 All safety component s are


connected and operational

15 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

including all thermostats to cut


power to heater if needed.

6 All controls cabling is connected


and installed in line with the
manufacturers/design drawings.

7 Power is available to the electric


heater/control panel for
operat ion.

Sweeper System
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Cooling Tower sweeper system


installed in line with
manufacturers requirements ,
clean and undamaged.

2 Sweeper syst em pipework and


nozzles clean and undamaged

Makeup Water Connection


Ref Inspection/Task Yes/No Notes
/[n/a]

1 Make up water connected and


correct size with float/level valve
correctly set.

2 Float valve undamaged.

Bleed-Off/Blow Down Connection

16 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Bleed-Off/Blowdown water
connected, correct size, clean
and undamaged.

Side Stream Filtration Connection


Ref Inspection/Task Yes/No Notes
/[n/a]

1 Side stream filter connected,


correct size, clean and
undamaged.

Overflow Pipework
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Overflow pipework connect ed,


correct size, clean and
undamaged.

Drift Eliminator
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Drift elim inators inst alled as per


manufacturers requirements,
correct size, fixed, clean, and
undamaged.

Fan & Motor

17 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Electrical connections and


cables are complete, fully tested
and torqued in line with
project/manufactur er
requirements

2 Motor protections installed and


operat ing [Over load]

3 Motor protections calibrated

4 Volt age from electrical systems


is correct for the cooling tower
requirements [within +/ -10%]

5 Fan housing clean and dust free

6 Fan, blades, and motors are


clean and dust free.

7 Ensure the fan wheel is centered


on the intake section

8 Check tight ness of fixings


[torque]

9 Impeller is balanced

10 Fan/motor rotates in correct


direct ion with no obstructions [by
hand]

11 Fan/motor rotates in correct


direct ion with no obstructions
[electr ically bump unit on ]

Ductwork
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Fan housing cowl/ducting


installed wit h relevant mesh and
is unobstructed.
18 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

2 Mesh free area meet s the design


requirements

Access
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Portable Cr ane installed in line


with the manufactur er’s
instruct ions and undamaged.

Ladder Safety Cage installed,


and undamaged for access to the
roof/fan deck of the tower.

Guard Rail System installed, and


undamaged for access around
the roof/fan deck of the tower.

Access door platfor m installed,


and undamaged for access to the
door of the tower if installed on a
high steelwork frame.

Maintenance platfor m installed,


and undamaged for access
around the tower and to any
motors / parts mounted on the
external of the tower .

Internal Plenum Walkway


installed, and undam aged. This
is for access inside t he tower.

Pipework to Nozzles

19 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Ensure that the pipework and


connections are the correct size
and in line with the drawing.

2 Ensure the installation of the


pipework will not put stress on the
cooling tower connections or
create vibrations.

3 The materials used between the


cooling towers and t he condenser
water system will not cause
Electrolysis.

4 Pipework that is to connect to the


cooling tower has been weld
tested.

5 Pipework that is connected to the


cooling tower has been pressure
tested.

6 Pipework that is connected to the


cooling tower has been cleaned
and flushed.

7 Pipework is insulated and vapor


sealed where required

8 Insulation is labelled

9 All pressure gauges installed, and


display scale as per design
requirements.

10 All valves/control valves are


installed and in corr ect direct ion

11 All commissioning devices are


installed in line with

20 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

manufacturer ’s instr uctions,


including expected diameters from
turbulence.

12 All Strainer s are inst alled and


inspected to ensure the mesh is
clean.

13 All expansion / rubber bellows are


installed.

Pipework from Tower


Ref Inspection/Task Yes/No Notes
/[n/a]

1 Ensure that the pipework and


connections are the correct size
and in line with the drawing.

2 Ensure the installation of the


pipework will not put stress on the
cooling tower connections or
create vibrations.

3 The materials used between the


cooling towers and t he condenser
water system will not cause
Electrolysis.

4 Pipework that is to connect to the


cooling tower has been weld
tested.

5 Pipework that is connected to the


cooling tower has been pressure
tested.

21 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

6 Pipework that is connected to the


cooling tower has been cleaned
and flushed.

7 Pipework is insulated and vapor


sealed where required

8 Insulation is labelled

9 All pressure gauges installed, and


display scale as per design
requirements.

10 All valves/control valves are


installed and in corr ect direct ion

11 All commissioning devices are


installed in line with
manufacturer ’s instr uctions,
including expected diameters from
turbulence.

12 All Strainer s are inst alled and


inspected to ensure the mesh is
clean.

13 All expansion / rubber bellows are


installed.

Balance Pipework
Ref Inspection/Task Yes/No Notes
/[n/a]

1 Ensure that the pipework and


connections are the correct size
and in line with the drawing.

22 Co o l in g To w er Ch ec k l i s t
Ref Inspection/Task Yes/No Notes
/[n/a]

2 Ensure the installation of the


pipework will not put stress on the
cooling tower connections or
create vibrations.

3 The materials used between the


cooling towers and t he pipework
system will not cause Electrolysis.

4 Pipework that is to connect to the


cooling tower has been weld
tested.

5 Pipework that is connected to the


cooling tower has been pressure
tested.

6 Pipework that is connected to the


cooling tower has been cleaned
and flushed.

7 All expansion / rubber bellows are


installed.

Controls
Ref Inspection/Task Yes/No/[n/a] Notes

1 Ensure all sensors and


instruments are inst alled
as per the control
logic/manufacturers wir ing
drawings

2 All sensors are calibrated

23 Co o l in g To w er Ch ec k l i s t