Project Name:
Tag No:
Description:
Subsystem:
System:
1.06 Confirm all paint/surface coatings are free from damage. Ongoing
1.07 Desiccant bags is provided and checked for condition, quantity and replace as necessary. Ongoing
1.08 Ensure all holes for entry cable are plugged properly at terminal box. Ongoing
1.09 All flanged openings shall be provided with vinyl cap or metal closure with gasket or substantial Ongoing
wood closures (3/4” thickness minimum) and at least four full diameter bolts to protect the flanges
from damage and prevent the entry of dirt and moisture to the equipment interior. Wooden covers
should not directly in contact with flange surfaces. Plastic sheet, rubber sheet, or equal shall be
placed in between. Wooden cover shall not be used for extended outdoor storage more than 3
months.
1.10 Plastic wrapping shall be removed for outdoor storage. Ongoing
1.11 Stainless steel and other exotic materials shall be stored separately from carbon steel materials. Ongoing
1.12 Desiccant shall not be used to protect rubber and stainless-steel products. Ongoing
1.13 All stainless steel and other exotic materials fitting and flanges shall be stored indoor. Ongoing
1.14 Confirm that all necessary covers, end caps and plugs are in position and replace any that are Ongoing
missing.
1.15 Confirm all instruments on packages or skids are in good condition with no visible damage. Ongoing
1.16 Check all openings and hook up connections are closed/blinded. Ongoing
1.17 Confirm any seal gas panel systems are suitable protected. Ongoing
1.18 Confirm all cabinets, panels, junction box’s, enclosure doors and covers have not been damaged Ongoing
during the inspection checks. Confirm they are replaced / installed correctly.
1.19 All panel fronts, gauges and in line instrumentation adequately protected from construction activity. Ongoing
1.20 Ensure equipment that is installed is protected suitably from any ongoing construction activities to Ongoing
prevent any damage.
1.21 Confirm preservation tag or label is fitted & updated. Ongoing
2.02 Confirm compressor electrical & control panel enclosures are preserved with dessicant and Daily
completely sealed & where applicable anti condensation heater is powered and operating.
3 WEEKLY INSPECTION CHECK LIST
3.01 Confirm any Nitrogen blanket is at the correct pressure and re pressurize if required as per Weekly
supplier’s recommendations, and test for leaks. Nitrogen charge pressure shall be monitored
weekly and accountably recorded. Nitrogen pressure shall be checked and recharged weekly or as
required.
3.02 Weekly
All rotating equipment internally protected with a lubricating oil base rust preventative shall be
manually turned two or three revolutions at one week intervals. Care should be taken that the final
position of the shafts after turning is at least one quarter revolution from the point at which rotation
was started (to avoid Brinelling). Oil levels shall be checked at the time of rotation. A preservation
log shall be kept to record these actions.
3.03 Shipped loose items are stored as per manufacturers recommendation Weekly
12
PRESERVATION Inspection & Test Record
PRES-M-08 Rotating Equipment – Compressors Package
Project Name:
Tag No:
Description:
Subsystem:
System:
Comments:
Note: Tick all check item under OK - Satisfactory; N/A - Not Applicable; Punch items(s) are to be PL.
Contractor Company
Data Input
Performed By Checked By Checked By Accepted By Witnessed By
Construction
Company / Dept.: QC Inspector QC Inspector QC Lead Operation CCMS Coord./ Operator
Spv. / Pre-Comm.
Eng.
Name:
Signature:
Date: